September, 2012

Construction Update– Rio Canoas

Energia

2

Concession Overview

Garibaldi Power Plant

Installed capacity - 177.9 MW

Physical Guarantee - 83.3 average MWh

70% of energy sold

Concession rights: 35 years

Triunfo won the concession in July 2010

Capex to date R$452 million

Located at Abdon Batista and Cerro Negro, Santa

Catarina state, Southern Brazil.

3

February 2011 September 2012

Rapid Transformation of Greenfield Site

4

Rio Canoas Energia – Garibaldi Power Plant

GENERATION CIRCUIT

5

Rio Canoas Energia – Garibaldi Power Plant

THE POWER HOUSE ASSEMBLY

6

Rio Canoas Energia – Garibaldi Power Plant

THE RIGHT BANK OF THE DAM

7

Rio Canoas Energia – Garibaldi Power Plant

THE RIGHT BANK OF THE DAM

8

Rio Canoas Energia – Garibaldi Power Plant

THE RIGHT BANK OF THE DAM