Page 1: Construction update   rio canoas energia

December 2012

Rio Canoas Energia – Works Status

Page 2: Construction update   rio canoas energia

2

Rio Canoas Energia – Garibaldi HPP

CANAIS QUE CONTROLAM A VAZÃO DA ÁGUA.

Page 3: Construction update   rio canoas energia

3

Beginning of tunnel

excavation in MAY 2012

Rio Canoas Energia – May 2012

Page 4: Construction update   rio canoas energia

4

Rio Canoas Energia – December 2012

Conclusion of tunnel

excavation in DECEMBER 2012

Page 5: Construction update   rio canoas energia

5

Rio Canoas Energia – Works Status

Page 6: Construction update   rio canoas energia

6

Rio Canoas Energia – Works Status

Page 7: Construction update   rio canoas energia

7

Rio Canoas Energia - Concession

Garibaldi HPP (SC)

Installed capacity –192 MW;

Current assured energy – 83.1 MWh;

70% of energy sold in ANEEL auction;

Bid in July 2010;

Location – Abdon Batista (SC) and Cerro Negro (SC)

Concession period: 35 years

Capex of R$565 million through September 2012

Rio Canoas

Page 8: Construction update   rio canoas energia