@ G type apartments 173,172 & 171 primer works are in

progress.

@ G type apartments priority flats painting works are

completed.

@ A-54 Apartment External single coat paint completed.

Latest View of Apartment Block A54

@ A-54 Apartment Lift cladding works are in progress.

@ A 54 Apartment 302 Unit Putty works are completed.

@ A-54 Apartment 401 Unit Putty works are completed.

@ A 62 Villa External painting works are in progress.

@ A-63 Villa Internal putty works in progress. Staircase granite & Hand railing

works are completed.

@ A-110 villa Toilets tiling works are in progress.

@ A-113 villa Internal plastering works are in progress at first floor.

@ A-129 & A-130 Villa’s Tapper slab concreting works and roof tiles works are

completed.

@ A-117 Villa External plot development works are in progress.

.

@ A-118 Villa Staircase granite & Hand railing works completed, Internal putty works & External Plot development works are in progress..

@ A-121 Villa External and Internal putty works are completed.

@ A-124 villa External plastering works are in progress. Taper slab slopped roof

tiling works are completed.

.

@ A-125 Villa External putty works are in progress.

@ A-127 Villa Tapper slab concreting works, slopped roof tiles works

completed. Brick work are in progress.

@ A-150 villa External plastering works are in progress.

@ A-144 villa External primer works are completed, compound wall plastering works are in progress.