construction update report #2
TRANSCRIPT
World Children’s Fund Mama Kevina Comprehensive Secondary School
Construction Update Report #2
UGANDA
February, 2014
Real Medicine Foundation 11700 National Blvd, Suite 234 Los Angeles, CA 90064 (310) 820-4502
2
New Construction Project funded by World Children’s Fund:
We were very excited to announce in mid-2013, that World Children’s Fund agreed to fund the construction of four new buildings, which will substantially increase the capacity of the school to attract more paying students to help subsidize the non-paying students and move closer to becoming a sustainable school. The funds will go towards the construction of new girls’ and boys’ dormitory buildings, a dining hall, and finishing the ground floor of a new office/classroom block. Construction began in December 2013. This brings the partnership between WCF, RMF and Mama Kevina to a new level, and promises to make the school a model program for the area.
Construction Project Works/ Scope:
Completion of the Classroom block using part of existing building
Construction of a new Dining Hall
Construction of a new Dormitory block for Girls
Construction of new Dormitory block for Boys Contractor MMK Engineering Limited, P.O. Box 508 Kampala- Uganda. Update as of February 12, 2014
Real Medicine Foundation hired a Building/Structural Engineer, Odongo Richard Sikola, as an Independent Consultant to monitor the progress and quality of the work completed by MMK Engineering. Each release of funds to the Construction company is contingent upon the approval of RMF’s Engineering Consultant.
Status of the Contract Time:
Date of Contract Signing 17th October 2013 Date of site possession 27th December 2013 Contract Duration Four Months Commencement date 02nd January 2014 Expected Completion 03rd May 2014 Defect Liability period Six weeks Date of Final Hand over 17th July 2014
Progress
Equipment and Tools.
The following equipment/ tools have been mobilized by the contractor to site for the works execution
S/no Item Description Quantity Remarks
1 Tipper trucks 01 27.12.2013
2 Concrete Mixer .75m3 01 27.12.2013
3 Concrete Vibration 01 27.12.2013
3
4 Water pump 01 04.01.2014
5 Jumping Compactor 01 06.01.2014
6 Hand Tools Assorted 03.01.2014
Personnel
The following personnel have been mobilized to site.
S/no Title No Remarks
1 Project Director 01 Owor Mike A
2 Site Manager 01 Magara Bernard
3 Site Engineer 01 Oporu Paul P.
4 Site Foremen 04
5 Masons 35
6 Carpenters 07
7 Steel benders 05
8 Unskilled 65
Material mobilization
S/No Description Unit Quantity
Last month
This month Total
1 Concrete blocks No 480 1820 2300
2 Clay Bricks No 12,000 75,800 87,500
3 Coarse Sand trips 33 24 57
4 Aggregates Tons 125 105 230
5 Hard core Trips 15 19 34
6 Eucalyptus poles Pcs 970 970
4
7 Timber
(100*50)
(150*50)
(230*25)
(300*25)
Pcs
Pce
Pcs
pcs
824
40
10
732
824
40
10
732
8 Cement Bags 600 1035 1635
9 Steel
Y16
Y12
R8
Pcs
Pcs
Pcs
343
514
86
343
514
86
10 Max pan No 2370 2370
Construction Completion Percentages as of February 12th, 2013:
S/NO Description Physical Progress Achievement %
3.4..1 Class room block Roof Slab level 55%
3.4.2 Multipurpose Dining hall Over site Concrete 25%
3.4.3 Dormitory for boys Ready for roofing 60%
3.4.4 Dormitory for Girls Ready for roofing 60%
Current Engineering/Construction Activities per building:
Classroom Block
Demolitions and alterations Concrete works on columns and beams Concrete works on slab Building of Plinth walls Rendering of Plinth walls Fabrication / shuttering of form work Construction of the walls using concrete blocks Steel fixing and laying of Max-pan for the Slab.
Dining hall
5
Site clearance, setting out and excavation of foundations Concrete works on strip foundations Construction of Plinth walls Concrete works on slab Rendering of Plinth walls Fabrication / shuttering of form work Walling on going
Dormitory block for Girls
Site clearance, setting out and excavation of foundations Concrete works on strip foundations Construction of plinth walls Fixing of steel works for beams and columns Concrete works on beams and columns Concrete works on slab Fabrication / shuttering of form work Walling on going Fabrication of Roof Trusses on going
Dormitory block for Boys
Site clearance, setting out and excavation of foundations Concrete works on strip foundations Construction of plinth walls Fixing of steel works for beams and columns Concrete works on beams and columns Concrete works on slab Fabrication / shuttering of form work Walling ongoing Fabrication of Roof trusses ongoing.
Quality Control
All materials used on site for permanent works comply with the contract specification per the Independent
Engineer Consultant hired by RMF.
Construction Challenges encountered and addressed:
Description Action Taken
Classroom block
The plinth walls, columns and some sections of the slab on the old/original building had developed major cracks a sign of structural failures
Contractor instructed to demolish all failed sections and make good. A
new ground beam was introduced where the plinth wall had shown
structural failures
Multipurpose Dining Hall
According to the Site plan the structures crosses over the
Relocated in an orientation line with the existing laboratory block
6
football pitch and walkway to the boys dormitory
Boys Dormitory
Formally L Shaped
Gable roof type
Ground level matching with existing block
No provision for future upgrading
Shape changed to straight and increased the room by 12.8m2
Single hip and double gable to match
High headroom and above the existing structure
Reinforced beam and column introduced in preparation for future development into stored structures.
Girls Dormitory
Gable roof type
Ground level matching with existing block.
No provision for future upgrading
Single hip and double gable to match
High headroom and above the existing structure
Reinforced beam and column introduced in preparation for future development into stored structures.
February Project Photos:
7
Above laying of the foundation for the dining hall (casting slab concrete).
Above some of the raw materials being used at the site.
8
Above construction of boys dormtry in progress (fixing of colums).
Abov: Consultant Odongo (in lime green jacket), Sr.clare, RMF staff Achieng and Juliet, representantive
of little sisters of St Francis and Engineers inspecting the construction progress.
10
Above girls dormitory under construction (slab, plinth wall and wall set construction in progress).
Above construction construction of boys dormitry in progress.
Above prepping sub foundation on compacted gravel layer for the dining hall(on the left Engineer Mike
supervising work on at the site).