community meeting – construction update presentation october 21, 2015
Post on 08-Feb-2017
525 Views
Preview:
TRANSCRIPT
Construction Update Meeting
October 21, 2015
2
• Doug Nelson – Executive Director of Development & Construction, UCSF Benioff Children’s Hospital Oakland
• Richard West and Tony Solano – JLL
• Darrel Graef – Project Superintendent, Turner Construction Company
• Elena Anaya – NorCal Community Affairs Director, Turner Construction Company
• Ed Walsh and Abhishek Gupta – Turner Construction Company
Welcome
3
UCSF Benioff Children’s Hospital / Turner – General Discussion
Project Communication
Upcoming Construction Activities
Local Business Utilization
Agenda
4
• Project Communication• Project Communication
– Darrel Graef (Turner Supt) 510-764-3059– Flyers and Project Website
• notifications of change to site conditions as it pertains to the neighborhood
• http://chonext100.org
• Concerns/Issue Reporting—Contact information are posted on Site Signage and Project
Website
Communication & Reporting
5
• Relocation of bus stop on MLK between 52nd/53rd will take place next week )Week of October 26th). It will now to be located south of 52nd street.
• Installation of utilities on MLK will take place on weekdays between the hours of 9:00 am and 4:00; starting right after Thanksgiving weekend (beginning of December)
• Saw cutting the new entrance of the garage, and paving the street will take place towards the end of November. (Paving MLK will take place on a Saturday daytime operation to minimize impact to traffic).
Upcoming Major Construction Activities
6
• Project Communication
• Middle of December is anticipated start for excavation of the OPC2 site and start working on foundations/drill piers.
• December 15th we are expecting to reroute pedestrian traffic to the east side of OPC1, and begin work inside the lobby.
Upcoming Major Construction Activities (contd;)
9
• Project Communication• Publicized separate bid packages in Small Business Exchange,
Oakland Post & Daily Pacific Builder• Emailed copy of each advertisement above to over 150 community
based organizations, 300+ Turner School graduates, City of Oakland and Alameda County Contract Compliance Divisions.
Project’s Subcontractor Outreach
10
Project’s Local Business Participation• Local is defined as businesses located within the East Bay Green
Corridor:—Alameda—Albany—Berkeley—El Cerrito—Emeryville—Hayward—Oakland—Richmond—San Leandro
11
Project’s Bidding ResultsTotal of 247 prime contractors responded to this project as follows:
Total Local Oakland MBE WBE SBE OtherSubmitted bids 123 20 25 12 6 12 48Declined 124 19 22 9 4 13 57
12
Project’s Projected Business Participation*
• Local Goal = 35% Projected = 45%• Oakland Contractors = 15%
• Small Contractors = 35%• Minority Contractors = 7%• Women Contractors = 1%
*based on prime contracts only
13
Project’s Contract Awards• Approximately 33 prime contractors will be awarded contracts• Once all contracts are awarded, project goals will be assessed.
14
Questions/Discussion?
15
15Proposed RPP Boundary
RPP Boundary Map
16
Councilmember Kalb – Olga Bolotina obolotina@oaklandnet.com 510-238-7240
City of Oakland – Darien Avelino ddavelino@oaklandnet.com 510-238-6602
City of Oakland – Heather Klein hklein@oaklandnet.com 510-238-3659
RPP Contact Information
top related