City of San Mateo

Flood Control Efforts & Needs

Preliminary FIRM (2008)

Completed Capital Projects ($22.7M)

• SM Creek South Levee Wall – ($1.2M) Completed 2001

• Raising of Norfolk Bridge – ($1.9M) Completed 2002

• Caltrans Culvert – US101/3rd Ave– ($10M) Completed 2004

• SM Creek North Levee Wall – ($730k) Completed 2005

• O’Neill Slough Tide Gate & Levee – ($1.5M) Completed 2007

• South Bayfront Levee Project– ($7.4M) Completed 2011

South Levee Project Creek Floodwall and Railing

Seal Slough hydro-seeding/erosion control

Resultant FIRM (2012)

Remaining Capital Projects ($22.35M)

Raise North Levee at Coyote Point Beach ($7.35M)

Rehabilitate Pump Stations at

Poplar Avenue($7.5M)

Coyote Point($7.5M)

If areas were re-mapped to reflect rising sea level…..

City of San Mateo

Flood Control Efforts & Needs