back to basics - earned value management for beginners webinar

Post on 07-Jul-2015

2.545 Views

Category:

Business

5 Downloads

Preview:

Click to see full reader

DESCRIPTION

This webinar was presented by Stephen Jones, Chair of the APM Planning, Monitoring and Control SIG and Simon Taylor, Vice-Chair of the same SIG on Thursday 11th December 2014. Earned value management is a project control process based on a structured approach to planning, cost collection and performance measurement. Earned value helps us manage a project by: providing data to enable objective measurement of project status; providing a basis for estimating final cost; predicting when the project will be complete; supporting the effective management of resources; providing a means of managing and controlling change. Earned value provides information which enables effective decision making by knowing: what has been achieved of the plan; what it has cost to achieve the planned work; if the work achieved is costing more or less than was planned; if the project is ahead of or behind the planned schedule. Good planning leads to good project execution and good management information.

TRANSCRIPT

Earned Value

Back to Basics

Stephen Jones

SPER Programme Lead

Chairman of APM PMC SIG

Simon Taylor

Head of Planning

Introductions

What is Earned Value?

Earned Value Management

– Establishing and managing goals throughout

the life of a project

– Provides indication of Project efficiency

Three pieces of Information

– Earned Value

– Actual Cost

– Planned Value

Earned Value

Budget Cost of Work Performed (BCWP)

The value of the work actually done at a

given point in time

How do you decided on the Value of

work done?

It’s the portion of the budget which

should have been spent to achieve the

work done.

Actual Cost

The Actual Cost of Work

Performed(ACWP) is the cost of the

work done.

It is the amount reported as actually

expended in completing the work

accomplished within a given time period

Planned Value

Budgeted Cost of Work Scheduled

(BCWS)

It is the value of the work that should

have been done at a given point in time.

It indicates the budget at a given point.

Example

A builder estimates to build a wall will require

100 bricks at £1 each. The builder can lay 10

bricks per hour. The builder charges £10 per

hour

Example

After 4 hours the builder has laid 50

bricks

Earned Value = £100, Actual = £90

Schedule Performance Index

SPI measures progress against the plan.

Greater than 1.0 is good (ahead of plan)

Less than 1.0 is bad (behind plan)

Equals 1.0 when we are on plan

SPI = BCWP / BCWS

Schedule Variance = BCWP – BCWS

Example

In our example

Earned Value (BCWP) = £100

Planned value (BCWS) = £80

SPI = BCWP / BCWS

SPI = 1.25

The builder is ahead of schedule

SV = 100 – 80 = +20

Cost Performance Index

CPI is a ratio of the value of work to

actual cost incurred.

Greater than 1.0 is good (under budget)

Less than 1.0 is bad (over budget)

Equals 1.0 when we are on budget

CPI = BCWP / ACWP

Cost Variance = BCWP – ACWP

Example

In our example, after 4 hours the cost will be £40 for labour plus £50 for brick = £90

Earned Value (BCWP) = £100

Actual cost (ACWP) = £90

CPI = BCWP / ACWP

CPI = 1.11

The cost is under budget

CV = 100 – 90 = +10

EAC

Estimate at Completion

A forecast of the cost required to

complete the project based on current

progress

EAC = Budget at Completion / CPI

EAC = £200 / 1.11

EAC = £180 (should finish under budget)

Estimated Duration

A forecast of the time required to

complete the project based on current

progress

Estimated Duration = Planned Duration /

SPI

In our example = 10 hours / 1.25

Estimated Duration = 8 hours

Should finish ahead of schedule

Summary

BAC = budget at Completion

Earned Value EV = %complete x BAC

Cost Variance CV = BCWP – ACWP

Schedule Variance SV = BCWP – BCWS

Cost Performance Index CPI = BCWP/ ACWP

Schedule Performance Index SPI = BCWP/ BCWS

EAC = Total Budget / CPI

Est. time at completion = Planned duration / SPI

Benefits of Earned Value Analysis

Measures work done against expenditure

Control is achieved by calculating variances

Positive: good, negative: Bad

Indices give a summary of project health

>1.0: good, < 1.0: bad

Generates forecast to completion based on current trends

SPI and CPI can be used as a measure of efficiency

Good News or Bad News

Good News or Bad News

Ahead of Schedule / Under Budget

Scheduled Variance

Cost

Variance

Incorrect

Good News or Bad News

Pole Results

Ahead of Schedule / Ahead of Budget

Ahead of Schedule / Over Budget

Behind Schedule / Ahead of Budget

Behind Schedule / Over Budget

On Schedule / On Budget

Good News or Bad News

Behind Schedule / Over Budget

Scheduled Variance

Cost

Variance

Bulls-eye Chart

EVM in projects

Where is the industry?

24

PWC 2014

Where is the industry?

25

PWC 2014

What is Earned Value Management?

Earned Value Management (EVM) is a project

management system that combines schedule

performance and cost performance to answer the

question,

“What did we get for the money we spent?”

To summarise....the basics:

How will you do the job? – Plan

How much will it cost? – Cost Loaded

How much have you achieved? - % Complete

26

Why use EVM?

It enables project teams to ask the questions

“have I spent too much money achieving too

little?”

“is the project behind or ahead of schedule?”

Allows efficient and effective use of time and

deployment of resource

Requires discipline and rigour to operate

successfully (i.e. Robust baseline & proactive

change control)

27

Managing Multiple Contracts

28

Week 1 Week 2 Week 4 Week 5

This is a proven way to measure performance

Contract 2

Contract 3

Contract 4

Contract 5

Contract 1

SPI: 0.95 – CPI: 0.98

Week 3

SPI: 0.99 – CPI: 1.01

SPI: 0.89 – CPI: 0.76

SPI: 0.98 – CPI: 1.10

SPI: 0.98 – CPI: 1.15

If can you only

make 1 phone

call today who

should it be

too?

Managing Multiple Contracts

29

Week 1 Week 2 Week 4 Week 5

An integrated WBS & CBS will really help

here!

Contract 2

Contract 3

Contract 4

Contract 5

Contract 1

SPI: 0.95 – CPI: 0.98

Week 3

SPI: 0.99 – CPI: 1.01

SPI: 0.89 – CPI: 0.76

SPI: 0.98 – CPI: 1.10

SPI: 0.98 – CPI: 1.15

Trending EV Graphs

30

EVM Metric shows

underachievement

and overspend.

In a programme with

complex plans and

multiple contracts

EVM quickly shows

areas that need

further analysis.

£-

£10

£20

£30

£40

£50

£60

£70

£80

Week 1 Week 2 Week 3 Week 4 Week 5

Work P ac kag e 1

P lanned V alue E arned V alue Actual C os t

0.69

0.61

S P I:

C P I:

P otential Overs pend

P otential D elay

Trend

Week 6 Week 7

Project will need to over

perform in order to

recover

EVM and progress

% complete examples for

– Software (closing logs or validated

functionality)

– Design, 25% across task, 75% on FDR

– Units, RWI’s etc.

– No persistent 99% crawl

EVM in Contracts

NEC WI T&C’s as measuring in working

schedule is preferred

– Agree structure

– Agree % complete for work type

– Agree data format and align with systems

– Separate EVM baseline outside of

accepted schedule

EVM & Risk

Risk monies not held in baseline plan as

there is not 100% chance of occurrence

and subsequent earn

EV baseline budget = Project authority –

Risk & Contingency

Risk events are time phased activities

EVM & Risk

EVM & Risk

As risk occurs the baseline is updated

with the allocated funds maintaining

historic performance measures and

validity of baseline going forward

As project proceeds EFC stays the same

but baseline budget increases

Using Banana Curves for EVM

EV baseline is based on early CPM logic

Initial early plan know as P0

Not much hope of positive SPI

Too much red hides real issues

Generating a mid curve for EVM

37

£20

£20

£20

Early Finish

£20

£20

Generating a mid curve for EVM

38

£-

£20

£40

£60

£80

£100

£120

Da

y1

Da

y3

Da

y5

Da

y7

Da

y9

Da

y11

Da

y1

3

Da

y1

5

Da

y1

7

Da

y1

9

Da

y2

1

Da

y2

3

Da

y2

5

Da

y2

7

Da

y2

9

Co

st

Time

Early Finish

Early Finish

Generating a mid curve for EVM

39

£20

£20

£20

£20

£20

Late Finish

£-

£20

£40

£60

£80

£100

£120

Da

y1

Da

y3

Da

y5

Da

y7

Da

y9

Da

y11

Da

y1

3

Da

y1

5

Da

y1

7

Da

y1

9

Da

y2

1

Da

y2

3

Da

y2

5

Da

y2

7

Da

y2

9

Da

y3

1

Da

y3

3

Da

y3

5

Co

st

Time

Early & Late Finish

Early Finish

Late Finish

Generating a mid curve for EVM

40

Terminal Float

Generating a mid curve for EVM

41

£-

£20

£40

£60

£80

£100

£120

Da

y1

Da

y3

Day5

Da

y7

Da

y9

Da

y11

Da

y1

3

Day15

Da

y1

7

Da

y1

9

Da

y2

1

Day23

Da

y2

5

Da

y2

7

Da

y2

9

Da

y3

1

Da

y3

3

Da

y3

5

Co

st

Time

Mid Curve (Baseline Cost Forecast)

Early Finish

Late Finish

Baseline

Terminal Float

Using Banana Curves for EVM

Done outside planning tool

Requires some skill

Is totally worth doing

Key Points

Used to measure performance only at contract / project level by

the project team (not summarised)

Baseline midpoint generated from the approved working

schedule

Costs associated with non productivity based tasks will not be

included in baseline (PM costs, Materials, Risk, Contingency

etc.)

Budgets and progress will be quantified using an agreed

method of measuring progress (agreed units of measurement

shall be identified and standardised wherever possible)

EV based progress analysis and reporting should be part of any

regular progress meetings

Application for payment can be based on earned value

achieved 43

Common Issues around using EV

Senior management reaction to low SPI & CPI

Non effort based costs skewing EV figures

Schedule quality and baseline control

No standardised way of EV implementation

across supply chain

Varied levels of cost information from others

Non standardised, scientific progress

quantification to inform physical % complete

Summarisation of EV at programme and

portfolio level clouded real performance issues 44

Publications www.apm.org.uk/publications

Join the PMC SIG

Register at your email address at

http://www.apm.org.uk/

It’s Free!!!

You don’t have to be a member of

APM.

This presentation was

delivered for an APM webinar

To find out more about

upcoming events please visit our

website www.apm.org.uk/events

top related