AQUATOR VERSION 2
MODELING AT CAD
ITEM STEP
1. Clean The Drawing
a.
Faster analysis in the
software
b.
Prevent bad/error
entities
c.
More accurate result
d.
Smoother modeling
experience
i.
Ensure the drawing does not contain 3D element /entities.
ii.
To ensure higher quality of clean drawing, copy necessary layers and
paste to a new drawing.
2. Scale
a.
To prevent error or
entities
i.
The best scale to import to the Aquator is 1:1.
3. Add New Layers
a.
CSSS-USERWATER
i.
Select LAYERS icon
ii.
Select NEW icon to add new layers.
iii.
Type for new layer (make sure in capital letter and spell with right )
and change any colour user want;
a.
CSSS-USERWATER
Select NEW layer icon
Insert both layer names
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 2/13
Page 2 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
ITEM STEP
4. Draw water
reticulation lines.
a.
Need to use single line
to draw.
b.
Make sure stop at
intersection.
a) CSSS-USERWATER
i.
Make sure change the current layer to CSSS-USERWATER
ii.
Select single line and start to draw the water reticulation line.
iii.
Make sure draw the single line and stop at every intersection.
iv.
Node will be created based the mouse click.
5. Save project
a.
Project need to be
close before import the
drawing into the
INFRAVERA software
i.
Select FILE.
ii.
Select SAVE AS to save the project.
iii.
Save the project
iv.
Close/Exit the project before import into the software
SELECT FILE
SELECT SAVE AS
WATEREC LINE
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 3/13
Page 3 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
SOFTWARE
1. IMPORT DRAWING
STEP
1.
Select the CAD IMPORT button.
2.
Located the CAD drawing.
3.
Drawing Scale will pop up after select the CAD drawing.4.
Select ACCEPT for drawing scale.
5.
Water Supply Guideline will pop up, select the design guide based the project.
6.
For example, select SYABAS.
7.
The layout CAD will appear.
SELECT CAD IMPORT
SELECT ACCEPT
i. SELECT SYABAS
ii. SELECT OK
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 4/13
Page 4 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
2. WATER TAB
STEP
1. Select WATER tab to start design water reticulation
2. To show the water reticulation line only, press space bar at keyboard
SELECT WATER TAB
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 5/13
Page 5 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
3. ADD TAPPING POINT & PRESSURE HEAD
STEP
1. Select first node as tapping point. In yellow colour, the node is selected.
2. Go to properties tab , at left hand side software.
3. At properties tab, Input term, change tapping point to TRUE.
4. Indicate the value for tapping pressure head by insert the number.
4. WATER DEMAND (Q)
i)
Have two method’s to key in;
a.
By Table
b.
By Properties
STEP
a.
By table
1.
Select last nodes, for example, node number 5.
2.
By right click mouse at nodes, the mouse properties will pop up.
3.
Select for table.
CHANGE TO TRUE
KEY IN THE PRESSURE
HEAD VALUE
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 6/13
Page 6 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
4.
Table for water demand will pop up.
5.
Select ADD button to add the table.
6.
Select CALC button to calculate the sub total Q.7.
Item for type of house, unit of house and water demand unit can be choosing based user.
8.
Select OK if satisfied with the data.
9.
Done water demand for that node.
b.
By Properties1.
Select the nodes, and go to properties.
2.
Indicate the level for that water demand manually.
3.
For example, 0.52.
i. SELECT THE NODES
ii. SELECT TABLE
ii.
SELECT CALC
BUTTON
iii. SELECT OK BUTTON
i. SELECT ADD
BUTTON
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 7/13
Page 7 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
4.
Press ENTER button at keyboard.
5. HYDRANT
STEP
1.
Select the nodes.
2.
Go to properties, select for Hydrant.
3.
Change the hydrant to TRUE.
4.
Hydrant will pop up at layout.
SELECT THE NODES
KEY IN THE WATER
DEMAND
SELECT THE NODES
CHANGE HYDRANT
TO TRUE
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 8/13
Page 8 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
6. FITTING/PUMP
STEP
1.
By select the pipe, right click mouse at that pipe.
2.
Select for fitting or pump. If select for fitting, choose the types of fitting to add on.
3.
For example, select for air valve fitting.
4.
Air valve fitting icon will appear at layout.
5. Key in the head loss for air valve, by select component at properties.
i. SELECT FITTING
ii. SELECT AIR VALVE
i. SELECT THE
COMPONENT
ii. KEY IN THE HEAD
LOSS
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 9/13
Page 9 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
7. RUN RESULT
STEP
1.
Select INTEGRITY icon before run.
2.
INTEGRITY PASS information will pop up.3.
Select OK button
4. The output data can be check at information tab (below tab)
8. SECTIONS
STEP
1.
Select SECTIONS icon.
2.
Section Data will be appearing at left side. Tick all the section.
3.
Select BUILD button to generate section.
SELECT OK
SELECT SECTIONS
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 10/13
Page 10 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
STEP
4.
Section will appear at section layout.
5.
To change the datum of slope, select SETUP button.
6.
Setup for CAD section will pop up, search for DATUM, and change the value. For example 80.
7.
Done change the datum value, select OK button.
8.
The data need to be change by re-select BUILD button.
9.
The section with new datum will be pop up again at layout section too.
TICK ALL THE SECTION
SELECT BUILD
CHANGE THE
DATUM VALUE
SELECT OK
BUTTON
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 11/13
Page 11 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
10. 3D VIEW
i) To view data input in 3D environment.
STEP
1.
Select 3D View icon.
2.
3D image will appear.
11. CALCULATION
i) Break down water reticulation calculation.
STEP
. Select Calculation icon.
2. The data calculation table will be pop up.
3. Click Select All button, and then Select show button.
4. The calculation will be appear.
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 12/13
Page 12 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
STEP
12. SAVE PROJECT
STEP
1.
Select file icon.
2.
Select save as to save the project.
3. Make sure save the project in one’s folder.
SELECT ALL
BUTTON
SELECT SHOW
SELECT SAVE AS
7/27/2019 Aquator Manual Training
http://slidepdf.com/reader/full/aquator-manual-training 13/13
Page 13 of 13
Infravera Sdn. Bhd.(920487-X) No 6-3, JalanPuteri 2/4, Bandar PuteriPuchong, 47100 Puchong, Selangor.Website : www.infravera.com
Tel: 03-8063 5733 Fax: 03-8051 4637 Email: sales@infravera.com (Sales) support@infravera.com (Tech. Support)
13. GENERATE REPORT
STEP
1.
Select REPORT tab.
2. Select WATER iconto generate the report.
3. The report will be pop up.
4. To change the format of report,select file and select EXPORT DOCUMENT and choose the format.
5. Or user also can select Export Document icon to change the format.
SELECT REPORTS