a6marr - logistics plan - rev 5 - mar 2016.xlsx
Post on 04-Jan-2017
223 Views
Preview:
TRANSCRIPT
5 15/03/2016
4 24/02/2016
3 16/03/2015
2 19/02/2015
1 07/10/2014
Rev Date
Date Drawn Rev
Mar-16 RAS 5Appendidx H - Logitstics Plan
Comments
Drawing Description
A6 TO MANCHESTER AIRPORT RELIEF ROAD
LOGISTICS PLAN
Updated photos
Added Poynton notes
Added notes, structure details
Updated photos and office areas
Added one way access route for structures B007 and B008
Title
Buxton Line
Woodford Rd - Bramhall
Woodford Road
West Coast Mainline
Styal Rd
A555/B5358 Wlmslow Rd
A34 / Stanley Rd
B001
B002
B004
B012
B013
B004A
R010
B010A
B008
B007
B006
B005
TR1A
TR1B
R002A
R003
R004
R009
TR1F
TR1G
R011
TR1 12
TR1 11
TR1 1
TR1 2
TR1 3
CHESTER ROAD
OFFICES AND
COMPOUND
B001
OFFICES AND
COMPOUND
B002
OFFICES AND
A6 TO MANCHESTER
AIRPORT RELIEF ROAD
LOGISTICS PLAN
B014
B015
RO16
TR1M
B003
STYAL ROAD
OFFICES AND
COMPOUND
M56 West and M6
M60 North and West
M60 North and West
South (via Wilmslow)
M60 East
Derbyshire quarries
and South East
Chester Rd Link
Notes
Compounds
Storage compound areas are shown on the plan in strategic locations to assist with the transfer of materials throughout the job with adequate provision for loading, unloading and storage of
materials and equipment within these areas. Three main site compounds (for storage, office, parking, etc.) will be set up near Styal road, Chester Road and Buxton Road. Detailed views of
these can be seen on the drawings Appendix H – Styal Road Compound, Appendix H – Chester Road Compound, and Appendix H – Buxton Road Compound.
Offices and welfare facilities
Site offices are to be set up within the three main compound areas with a pedestrian crossing facility to be provided close to the Buxton Road compound for safe access to construction works.
Each office will provide both working space and welfare amenities. Further facilities will also be provided for fuel storage, laboratory testing, first aid, and changing rooms in the main
compound at Chester Road. In more remote areas of the construction works portable welfare facilities will be provided as required.
Parking
Car parking locations are indicatively shown on the plan with main parking areas to be found at the three main office site compounds. Additional parking areas have been identified to provide
for access to structures during construction along the route which can be found near Wilmslow Road/A555 junction, Dairy House Lane, Woodford Road Bramhall/A555 junction, Woodford
Road Poynton, and Macclesfield Road. Parking facilities have been identified within close proximity of the construction works wherever possible, with any pedestrian routes from the parking
to work sites being identified on the drawing. Where parking is not available close to the new structures it is proposed that transportation (works bus) from identified parking sites will be
provided for contractors to access the works.
Haul routes
Haul routes for construction and delivery vehicles are shown for both non-public and public roads with additional vehicular access to structures also shown. At any intersection between a haul
route on a non-public road and a public road there will be a wheel wash provided to minimise the deposit of extraneous matter onto the public road. Controlled crossings for plant will be
provided at Styal Road and Macclesfield Road.
Cranes
Indicative details of cranes to be used at the structures throughout the site can be seen on in the structures key opposite. In addition, it will also be necessary for an 80 tonne mobile support
crane to be used at each of the bridge structures. Suggested positions of the main cranes for structures B001, B002, B005, B007, B010A, B014, and B015 are available in more detailed
drawings
Code Description Crane(s) required
B001 A6 bus overbridge Liebher LTM 1160 - 160 tonne mobile
B002 Hazel Grove to Buxton railway overbridgeLiebher LTM 1080 - 80 tonne mobile (East side)
Demag AC200 - 200 tonne mobile (West side)
B003 Old Mill Lane accommodation bridge Demag AC200 - 200 tonne mobile
B004 Prow bridge over Norbury Brook Liebher LTM 1080 - 80 tonne mobile
B004A Macclesfield Road bridge extension Liebher LTM 1080 - 80 tonne mobile
B005 Mill Hill hollow bridge Liebher LTM 1400 - 400 tonne mobile
B006 Hill Green accommodation bridge Demag AC200 - 200 tonne mobile
B007 Woodford Road, Poynton bridge Demag AC200 - 200 tonne mobile
B008 Westcoast main line bridge Liebher LTM 1400 - 400 tonne mobile
B010A Woodford Road bridge Liebher LTM 1400 - 400 tonne mobile
B012 Yew Tree accommodation bridge Liebher LTM 1080 - 80 tonne mobile
B013 Styal railway bridge Liebher LTM 1800 - 800 tonne mobile
B014 Styal Road - east bridge structureDemag AC200 - 200 tonne mobile
Liebher LTM 1400 - 400 tonne mobile
B015 Styal Road - west bridge structureDemag AC200 - 200 tonne mobile
Liebher LTM 1400 - 400 tonne mobile
R002A Retaining wall Liebher LTM 1080 - 80 tonne mobile
R003 Retaining wall Liebher LTM 1080 - 80 tonne mobile
R004 Retaining wall Liebher LTM 1080 - 80 tonne mobile
R009 Retaining wall Liebher LTM 1080 - 80 tonne mobile
R010 Retaining wall Liebher LTM 1080 - 80 tonne mobile
R011 Retaining wall Liebher LTM 1080 - 80 tonne mobile
R016 Retaining wall Liebher LTM 1080 - 80 tonne mobile
TR1 1 Gantry Liebher LTM 1080 - 80 tonne mobile
TR1 11 Dairy House Lane culvert Liebher LTM 1080 - 80 tonne mobile
TR1 12 Spath Brook culvert extension Liebher LTM 1080 - 80 tonne mobile
TR1 2 Gantry Liebher LTM 1080 - 80 tonne mobile
TR1 3 Gantry Liebher LTM 1080 - 80 tonne mobile
TR1A Retaining wall Liebher LTM 1080 - 80 tonne mobile
TR1B Retaining wall Liebher LTM 1080 - 80 tonne mobile
TR1F Retaining wall Liebher LTM 1080 - 80 tonne mobile
TR1G Retaining wall Liebher LTM 1080 - 80 tonne mobile
TR1M Retaining structure Liebher LTM 1080 - 80 tonne mobile
Structures Key
Dairyhouse Lane
KEY
TOPSOIL STOCKPILE AREAS
COMPOUND / LAYDOWN AREAS
STRUCTURE
OFFICE / WELFARE ACCOMMODATION AREA(DETAILED VIEW AVAILABLE)
PLANT CROSSING
GANTRY
HAUL ROUTES ON NON-PUBLIC ROADSHAUL ROUTES ON PUBLIC ROADS
ONE WAY ROUTE FOR ACCESS TO STRUCTURES ON PUBLIC ROADS
CAR PARKING All works will be carried out in accordance with
A6 to MARR
Code of Construction PracticePEDESTRIAN ACCESS TO WORKS
21916m3
Topsoil
BRIDGE CONSTRUCTION CRANE POSITION(DETAILED VIEW AVAILABLE)
WOODFORD REC
SATELLITE OFFICES
AND COMPOUND
Permitted route for secondary construction traffic.Generally light vehicles, but occasional HGVs.
SHENTONS
OFFICES AND
COMPOUND
Woodford Road Offices
Styal Road Offices
Shentons Offices
A523 Macclesfield Rd
A6 Buxton Rd
Access to structures B007 and B008 is gained through a one way system as shown. Entering from the A5143
and exiting onto the A5149 Chester Road.During movements of abnormal loads temporary mobile
traffic lights will be used to control the narrowing at Norbury Brook