Summer 2009 Capital Projects

Elementary Debt Exclusion Work Summer 2009

Presentation for Town Meeting April 2010

Capital Projects Summer 2009

Elementary Debt Exclusion • Hardy • Hunnewell• Schofield• Fiske• Upham

• Time Frame for summer work– Last day of school for teachers was Thursday, June 24,

2009. Work began immediately after that.– The 42 work days between June 30 and August 27

described the time frame for all the moving and work.

Summer 2008 • Roof replacement• Master Clock and Bell System

Summer 2008 • Roof replacement• Master Clock and Bell System

Summer 2009 • Flooring abatement and replacement in selected rooms• Gymnasium ceiling abatement / plaster / paint• Boiler replacement (in process)

Old flooring was abateddown to a wood subfloor.

Old flooring was abateddown to a wood subfloor.

A new wood subfloor was installed in preparation for the new tile.

Joints were patched

Joints were patched

and new tile installed.

Classroom and entry way tile

Ceiling tiles were removed. A new ceiling with new lights and new acoustical panels were installed.

Ceiling tiles were removed. A new ceiling with new lights and new acoustical panels were installed.

New boiler installation

The DPW completed work on a redesigned Hardy Road with increased parent drop off and pick up area.

Summer 2008 • Master Clock and Bell System• Exterior lights and interior carpet

Summer 2008 • Master Clock and Bell System• Exterior lights and interior carpet

Summer 2009 • Flooring abatement and replacement• New air exchange units in gymnasium ceiling• Roof replacement

New flooring was installed in 5 elementary schools.

New flooring was installed in 5 elementary schools.

Point distressed masonry

Point distressed masonry

Replace wood gutters

Point distressed masonry

Replace wood gutters

New roof on the flat section

Summer 2008 • Roof replacement• Master Clock and Bell System

Summer 2008 • Roof replacement• Master Clock and Bell System

Summer 2009 - Phase I (required packing and moving of all rooms in the work area)• Ceiling abatement and replacement

• New fire protection• New lighting

• Flooring abatement and replacement• Enlarge two student bathrooms on cafeteria level• Gymnasium ceiling abatement / plaster / paint• Boiler replacement (in process)

Summer 2008 • Roof replacement• Master Clock and Bell System

Summer 2009 - Phase I• Ceiling abatement and replacement

• New fire protection• New lighting

• Flooring abatement and replacement• Enlarge two student bathrooms on cafeteria level• Gymnasium ceiling abatement / plaster / paint• Boiler replacement (in process)

Summer 2010 - Phase II• Window replacements for both wings• Continued floor and ceiling abatement and replacement

An area of old ceiling previously abated as a result of water damage

The old ceiling was removed in preparation for the installation of fire protection (sprinkler system), new lights and a new suspended ceiling.

New smoke and acoustical stops were installed above the new suspended ceiling in walls separating classrooms.

New ceiling tile and new lighting

New ceiling tile and new lightingbrightened the hallways.

Floor preparation and new tile in the cafeteria

New tile in the cafeteria

New tile in the cafeteria

Two student bathrooms on the cafeteria level were renovated and are now ADA compliant.

Old carpet flooring

New tile flooring

In the process of replacing the gym ceiling the gym floor was damaged.

The floor was sanded, lines repainted and new coats of sealant applied.

Excavation and extensive new piping was required to add the new sprinkler system.

Fiske’s old boilers removed and ready for disposal.

New boilers ready for installation.

Summer 2008 • Master Clock and Bell System• New roof with improved roof drainage

Summer 2008 • Master Clock and Bell System• New roof with improved roof drainage

Summer 2009 • Flooring abatement and replacement in front hallway and entryway• Boiler replacement (in process)

Schofield’s entrance hallway rug was replaced with tile.

Entrance to the Schofield boiler room

Entrance to the Schofield boiler room

Entrance to the Schofield boiler room

New Boilers

Summer 2008 • Master Clock and Bell System

Summer 2008 • Master Clock and Bell System

Summer 2009 (required packing and moving of classrooms to complete the work)• New Roof• Flooring abatement and replacement• Gymnasium ceiling abatement / plaster / paint • Boiler replacement (in process)

Roofing work was completed more quickly than last summer.

Roofing work was completed more quickly than last summer.

On site demolition of the old boiler was required in preparation for installation of the new heating system.

On site demolition of the old boiler was required in preparation for installation of the new heating system.

Gym ceilings at

Upham, Hardy and Fiske

were abated and replaced

this summer.

Gym ceilings at

Upham, Hardy and Fiske

were abated and replaced

this summer.

Gym ceilings at

Upham, Hardy and Fiske

were abated and replaced

this summer.

New classroom tile

New classroom tile

New stair and landing tread

New classroom tile

New stair and landing tread

New hallway tile