MONTHLY PROGRESS MEETING NO. 15
(ENDING AUGUST 2015) – 03 SEPTEMBER 2015
THE CONSTRUCTION AND COMPLETION OF PROPOSED AMPANG-KUALALUMPUR ELEVATED HIGHWAY (AKLEH) PHASE 2 EAST BOUND FROM
JALAN JELATEK INTERCHANGE (KM 4.6) TO ULU KELANG INTERCHANGE (KM 6.0) FOR PROJEK LINTASAN KOTA SDN BHD
CONTENTS
1. EXECUTIVE SUMMARY
2. PROJECT OVERALL LAYOUT
3. SUMMARY OF PHYSICAL PROGRESS FOR MONTH OF AUGUST 2015
4. WORK DONE IN MONTH OF AUGUST 2015
5. QA / QC SUBMISSIONS
PROJECT: AKLEH PHASE 2
6. WORKS PROGRESS PHOTOS
7. STATUS OF PROGRESS CLAIM
8. MONTHLY LOOKAHEAD (1 SEPT 2015 ~ 30 SEPT 2015)
9. MAIN CONTRACTOR’S CONCLUSION
2
PROJECT: AKLEH PHASE 2
1. EXECUTIVE SUMMARY
Day Lapsed = 378 / 443 scheduled workdays
Weeks Lapsed = 67 / 79
Physical Progress (Planned) = 92.35 %
Physical Progress (Actual) = 92.74 %
Physical Variance = + 0.39 % (2.98 % in July 2015)
Financial Progress (Planned) = 90.67 %
3
Financial Progress (Planned) = 90.67 %
Financial Progress (Actual) = 89.05 %
Financial Variance = - 1.62 %
Average Manpower on Site = 106 nos.
Total Mandays Worked = 398 days
Total Manhours Worked = 398,360 manhoursCumulative
PROJECT: AKLEH PHASE 2
1. EXECUTIVE SUMMARY
120
140
160
180
200
4
0
20
40
60
80
100
Planned
Actual
PROJECT: AKLEH PHASE 2
2. PROJECT OVERALL LAYOUT
JELATEKINTERCHANGE
KM4.6
SECTION 1 (P1 ~ P19)
SECTION 2 (P20 ~ P31)
SECTION 3 (P32 ~ P44)
AMPANG INTERCHANGE
KM6.0
5
PROJECT: AKLEH PHASE 2
3. SUMMARY OF PHYSICAL PROGRESS FOR AUGUST 2015
6
PROJECT: AKLEH PHASE 2
3. WORK DONE IN MONTH OF AUGUST 2015
Component Activity / Description%
CompletionStatus
A. Design 1) Construction drawings currently issued up to designof Parapet.
Info
B. Physical Works
2) Bridge Structure Works
7
Worksa) Casting of Deck Slab – 45 spans out of 45 spans
completed.
b) Fabrication of Precast Parapet Panels in SPCIndustries – 1,822 nos. out of 1,857 nos.completed.
c) Installation of Precast Parapet Panels – 1,658nos. out of 1,857 nos. completed.
d) Casting of Road Kerbs – 39 nos. out of 45 spanscompleted.
100.00 %
98.1 %
89.3 %
86.7 %
2 nos. (July)4 nos. (August)
389 nos. (July)835 nos. (August)
11 nos. (July)22 nos. (August)
PROJECT: AKLEH PHASE 2
3. WORK DONE IN MONTH OF AUGUST 2015
Component Activity / Description%
CompletionStatus
C. AuthoritiesRequirements
3) Tenaga Nasional Berhad (TNB)
a) Completed TNB Pylon Relocation Works whichincludes the following:-i. Erection of two (2) new towers;ii. Stringing Works (conductors, earthwire and
optical ground wire)
100.0 % Taking Over Certificate
(TOC) signed by TNB on 11
August.
8
ii. Stringing Works (conductors, earthwire andoptical ground wire)
iii. Sagging of Conductorsiv. Installation of Jumpers, Vibration Dampers
& Aircraft Warning Spherev. Final Inspection by TNB
4) JPS Selangor
a) Continued construction of Gabion Mattress inSection 1 (between piers P3 ~ P19).
b) Continued construction of GeoBags (SoftrockFormation) in Section 3 (between piers P33 ~WE91).
55.0 %
80.0 %
by TNB on 11 August.
PROJECT: AKLEH PHASE 2
5. STATUS OF QA / QC SUBMISSIONS
No Item SubmittedApproved (or Reviewed withComments)
Under Review
Comments
1 Method Statement 34 29 217 nos. approved;3 nos. (No. 1, 14 & 19) withdrawnfrom submission.
2 Material Submission 122 119 3 109 nos. approved
Concrete Tests for the following Structural Elements:-
3 Bored Pile 347 347 0
9
3 Bored Pile 347 347 0
100 % COMPLIANCE WITH SPECIFICATIONS UP-TO-DATE
4 Pile Cap 74 74 0
5 Column 71 71 0
6 Crossbeam 111 111 0
7 RC Plinths 63 63 0
8 TM Beams 310 310 0
9 T-Beam 14 14 0
10 Diaphragm Beams 135 119 16
11 Deck Slab 195 174 21
12 Parapet 1,656 1,656 0
13 Kerb 75 38 37
PROJECT: AKLEH PHASE 2
6. WORK PROGRESS PHOTOS
View of Increasing Chainage from pierP4 – Completed Parapet and KerbCasting from Span 5 ~ Span 7.
July 2015
August 2015
10
August 2015
PROJECT: AKLEH PHASE 2
6. WORK PROGRESS PHOTOS
View of Increasing Chainage from pierP11- Completed Parapet and Kerb Castingfrom Span 11 ~ 14.
July 2015
August 2015
11
August 2015
PROJECT: AKLEH PHASE 2
6. WORK PROGRESS PHOTOS
View of Increasing Chainage from pierP14- Completed Parapet and Kerb Castingfrom Span 14 ~ 18.
July 2015
August 2015
12
August 2015
PROJECT: AKLEH PHASE 2
6. WORK PROGRESS PHOTOS
Newly Erected TNB Tower No. 3(located off Jalan Enggang)
July 2015
July 2015
13
Newly Erected TNB Tower No. 4 (located inJPS SMART Kg. Berembang CatchmentArea)
PROJECT: AKLEH PHASE 2
6. WORK PROGRESS PHOTOS
View of Increasing Chainage from pierP25- Installation of formwork and rebar fordeck slab at Span 26 & 27 in progressby end of July 2015.
July 2015
August 2015
14
View of Increasing Chainage from existingpier P25- Casting of Span 27 on 11 August 2015.
August 2015
PROJECT: AKLEH PHASE 2
View of Span 31 towards IncreasingChainage (from existing AKLEH)- Completed Parapet and Kerb Castingfrom Span 31 ~ 34.
6. WORK PROGRESS PHOTOS August 2015
August 2015
15
August 2015
View of Span 38 towards IncreasingChainage (from existing AKLEH)- Completed Parapet and Kerb Casting fromSpan 38 ~ 42.
PROJECT: AKLEH PHASE 2
JPS Selangor Requirements- Installation of Geobags in Section 3.
6. WORK PROGRESS PHOTOS August 2015
August 2015
16
JPS Selangor Requirements- Construction of Gabion Mattress inSection 1.
August 2015
PROJECT: AKLEH PHASE 2
7. STATUS OF PROGRESS CLAIM
NoDate Claim
Submitted
Amount Claimed (RM)
Cumulative Amount(RM)
Certified Amount(RM)
Cumulative Certified (RM)
Amount Received (RM)
Date Payment Received
9 29/01/2015 6,166,849.93 49,646,249.93 6,166,000.00 49,645,400.00 6,166,000.00 13/02/2015
10 25/02/2015 7,565,766.29 57,211,166.29 7,565,000.00 57,210,400.00 7,565,000.00 18/03/2015
11 27/03/2015 8,894,880.84 66,105,280.84 8,894,000.00 66,104,400.00 8,894,000.00 16/04/2015
12 27/04/2015 3,184,099.14 69,288,499.14 3,184,000.00 69,228,400.00 3,184,000.00 20/05/2015
17
12 27/04/2015 3,184,099.14 69,288,499.14 3,184,000.00 69,228,400.00 3,184,000.00 20/05/2015
13 28/05/2015 4,924,954.88 74,213,354.88 4,924,000.00 74,212,400.00 4,294,000.00 25/06/2015
14 24/06/2015 6,661,898.05 80,874,298.05 6,661,000.00 80,873,400.00 6,661,000.00 09/07/2015
15 29/07/2015 3,857,505.93 84,731,803.98 3,850,000.00 84,723,400.00 3,850,000.00 21/08/2015
16 01/09/2015 2,422,060.80 87,153,864.78 2,422,000.00 87,145,400.00
PROJECT: AKLEH PHASE 2
8. MONTHLY LOOKAHEAD (1 SEPT 2015 ~ 30 SEPT 2015)
Component Activity / Description
A. Physical Works 1. Bridge Structure Works
a) To complete installation of Precast Parapet Panels and Kerb Casting forthe following spans:-
i. P21 ~ P22 – 02 September 2015 – Span 22
18
i. P21 ~ P22 – 02 September 2015 – Span 22ii. P22 ~ P23 – 04 September 2015 – Span 23iii. P26 ~ P27 – 05 September 2015 – Span 27iv. P25 ~ P26 – 07 September 2015 – Span 26v. P24 ~ P25 – 09 September 2015 – Span 25vi. P23 ~ P24 – 11 September 2015 – Span 24
Cumulative total of 45 / 45 spans to be completed by 11-Sept 2015.
2. Pavement Works
a) To commence premix works by 10 Sept 2015.b) To commence installation of traffic signs on 21 Sept 2015.c) To commence installation of directional signages and gantry works by
25 Sept 2015.
PROJECT: AKLEH PHASE 2
8. MONTHLY LOOKAHEAD (1 SEPT 2015 ~ 30 SEPT 2015)
Component Activity / Description
B. Authorities Requirements
3. JPS Selangor
a) To complete installation of gabion mattress in Section 1 by 30 Sept2015.
b) To complete installation of GeoBags in Section 3 by 21 Sept 2015.
19
C. Other Works 4. Drainage Works
a) To complete reconstruction of drainage services by 30 Sept 2015.
5. Defects Listing (as part of Handover Process)
a) To commence listing of Defects on completed structural elements ateach pier and span by 07 Sept 2015.
PROJECT: AKLEH PHASE 2
9. MAIN CONTRACTOR’S CONCLUSION
� Overall progress achieved in Month of August 2015 has been satisfactory dueto the following reasons:-
1) Regression on Overall Physical Progress compared to previous month (+0.39 % compared to+2.98 % in July 2015 and +6.00 % in June 2015) – ahead by 2 days in overall activities and nolonger recording delays on critical path.
2) Regression in % ahead is due to the reduced manpower over Hari Raya Aidilfitri period (whichaffected the parapet installation works and kerb casting) and the requirement to completecurrent ongoing activities prior to commencement of the next milestone works i.e. Pavementworks on new bridge deck.
20
current ongoing activities prior to commencement of the next milestone works i.e. Pavementworks on new bridge deck.
3) We positively note that TNB Pylon Relocation Works were completed as scheduled, with zero (0)HSE related incidents and within approx. one (1) year from official communication with TNB on22 July 2015.
� Areas of Improvement as commented by Consultants:-
1) Contractor advised to pay special attention to concrete finishes especially now that the worksare limited to parapet and kerb.
2) Defects Listing as part of Handover and LLM requirement for SKPL should be commenced assoon as practical and rectification works should be targeted to complete prior to completion ofnew bridge deck.
THANK YOU FOR YOUR TIME