15 akleh p2 - monthly meeting no 15 presentation (03092015)

21
MONTHLY PROGRESS MEETING NO. 15 (ENDING AUGUST 2015) – 03 SEPTEMBER 2015 THE CONSTRUCTION AND COMPLETION OF PROPOSED AMPANG-KUALA LUMPUR ELEVATED HIGHWAY (AKLEH) PHASE 2 EAST BOUND FROM JALAN JELATEK INTERCHANGE (KM 4.6) TO ULU KELANG INTERCHANGE (KM 6.0) FOR PROJEK LINTASAN KOTA SDN BHD

Upload: ainulyaqhin

Post on 12-Jul-2016

10 views

Category:

Documents


4 download

DESCRIPTION

as

TRANSCRIPT

Page 1: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

MONTHLY PROGRESS MEETING NO. 15

(ENDING AUGUST 2015) – 03 SEPTEMBER 2015

THE CONSTRUCTION AND COMPLETION OF PROPOSED AMPANG-KUALALUMPUR ELEVATED HIGHWAY (AKLEH) PHASE 2 EAST BOUND FROM

JALAN JELATEK INTERCHANGE (KM 4.6) TO ULU KELANG INTERCHANGE (KM 6.0) FOR PROJEK LINTASAN KOTA SDN BHD

Page 2: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

CONTENTS

1. EXECUTIVE SUMMARY

2. PROJECT OVERALL LAYOUT

3. SUMMARY OF PHYSICAL PROGRESS FOR MONTH OF AUGUST 2015

4. WORK DONE IN MONTH OF AUGUST 2015

5. QA / QC SUBMISSIONS

PROJECT: AKLEH PHASE 2

6. WORKS PROGRESS PHOTOS

7. STATUS OF PROGRESS CLAIM

8. MONTHLY LOOKAHEAD (1 SEPT 2015 ~ 30 SEPT 2015)

9. MAIN CONTRACTOR’S CONCLUSION

2

Page 3: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

1. EXECUTIVE SUMMARY

Day Lapsed = 378 / 443 scheduled workdays

Weeks Lapsed = 67 / 79

Physical Progress (Planned) = 92.35 %

Physical Progress (Actual) = 92.74 %

Physical Variance = + 0.39 % (2.98 % in July 2015)

Financial Progress (Planned) = 90.67 %

3

Financial Progress (Planned) = 90.67 %

Financial Progress (Actual) = 89.05 %

Financial Variance = - 1.62 %

Average Manpower on Site = 106 nos.

Total Mandays Worked = 398 days

Total Manhours Worked = 398,360 manhoursCumulative

Page 4: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

1. EXECUTIVE SUMMARY

120

140

160

180

200

4

0

20

40

60

80

100

Planned

Actual

Page 5: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

2. PROJECT OVERALL LAYOUT

JELATEKINTERCHANGE

KM4.6

SECTION 1 (P1 ~ P19)

SECTION 2 (P20 ~ P31)

SECTION 3 (P32 ~ P44)

AMPANG INTERCHANGE

KM6.0

5

Page 6: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

3. SUMMARY OF PHYSICAL PROGRESS FOR AUGUST 2015

6

Page 7: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

3. WORK DONE IN MONTH OF AUGUST 2015

Component Activity / Description%

CompletionStatus

A. Design 1) Construction drawings currently issued up to designof Parapet.

Info

B. Physical Works

2) Bridge Structure Works

7

Worksa) Casting of Deck Slab – 45 spans out of 45 spans

completed.

b) Fabrication of Precast Parapet Panels in SPCIndustries – 1,822 nos. out of 1,857 nos.completed.

c) Installation of Precast Parapet Panels – 1,658nos. out of 1,857 nos. completed.

d) Casting of Road Kerbs – 39 nos. out of 45 spanscompleted.

100.00 %

98.1 %

89.3 %

86.7 %

2 nos. (July)4 nos. (August)

389 nos. (July)835 nos. (August)

11 nos. (July)22 nos. (August)

Page 8: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

3. WORK DONE IN MONTH OF AUGUST 2015

Component Activity / Description%

CompletionStatus

C. AuthoritiesRequirements

3) Tenaga Nasional Berhad (TNB)

a) Completed TNB Pylon Relocation Works whichincludes the following:-i. Erection of two (2) new towers;ii. Stringing Works (conductors, earthwire and

optical ground wire)

100.0 % Taking Over Certificate

(TOC) signed by TNB on 11

August.

8

ii. Stringing Works (conductors, earthwire andoptical ground wire)

iii. Sagging of Conductorsiv. Installation of Jumpers, Vibration Dampers

& Aircraft Warning Spherev. Final Inspection by TNB

4) JPS Selangor

a) Continued construction of Gabion Mattress inSection 1 (between piers P3 ~ P19).

b) Continued construction of GeoBags (SoftrockFormation) in Section 3 (between piers P33 ~WE91).

55.0 %

80.0 %

by TNB on 11 August.

Page 9: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

5. STATUS OF QA / QC SUBMISSIONS

No Item SubmittedApproved (or Reviewed withComments)

Under Review

Comments

1 Method Statement 34 29 217 nos. approved;3 nos. (No. 1, 14 & 19) withdrawnfrom submission.

2 Material Submission 122 119 3 109 nos. approved

Concrete Tests for the following Structural Elements:-

3 Bored Pile 347 347 0

9

3 Bored Pile 347 347 0

100 % COMPLIANCE WITH SPECIFICATIONS UP-TO-DATE

4 Pile Cap 74 74 0

5 Column 71 71 0

6 Crossbeam 111 111 0

7 RC Plinths 63 63 0

8 TM Beams 310 310 0

9 T-Beam 14 14 0

10 Diaphragm Beams 135 119 16

11 Deck Slab 195 174 21

12 Parapet 1,656 1,656 0

13 Kerb 75 38 37

Page 10: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

6. WORK PROGRESS PHOTOS

View of Increasing Chainage from pierP4 – Completed Parapet and KerbCasting from Span 5 ~ Span 7.

July 2015

August 2015

10

August 2015

Page 11: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

6. WORK PROGRESS PHOTOS

View of Increasing Chainage from pierP11- Completed Parapet and Kerb Castingfrom Span 11 ~ 14.

July 2015

August 2015

11

August 2015

Page 12: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

6. WORK PROGRESS PHOTOS

View of Increasing Chainage from pierP14- Completed Parapet and Kerb Castingfrom Span 14 ~ 18.

July 2015

August 2015

12

August 2015

Page 13: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

6. WORK PROGRESS PHOTOS

Newly Erected TNB Tower No. 3(located off Jalan Enggang)

July 2015

July 2015

13

Newly Erected TNB Tower No. 4 (located inJPS SMART Kg. Berembang CatchmentArea)

Page 14: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

6. WORK PROGRESS PHOTOS

View of Increasing Chainage from pierP25- Installation of formwork and rebar fordeck slab at Span 26 & 27 in progressby end of July 2015.

July 2015

August 2015

14

View of Increasing Chainage from existingpier P25- Casting of Span 27 on 11 August 2015.

August 2015

Page 15: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

View of Span 31 towards IncreasingChainage (from existing AKLEH)- Completed Parapet and Kerb Castingfrom Span 31 ~ 34.

6. WORK PROGRESS PHOTOS August 2015

August 2015

15

August 2015

View of Span 38 towards IncreasingChainage (from existing AKLEH)- Completed Parapet and Kerb Casting fromSpan 38 ~ 42.

Page 16: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

JPS Selangor Requirements- Installation of Geobags in Section 3.

6. WORK PROGRESS PHOTOS August 2015

August 2015

16

JPS Selangor Requirements- Construction of Gabion Mattress inSection 1.

August 2015

Page 17: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

7. STATUS OF PROGRESS CLAIM

NoDate Claim

Submitted

Amount Claimed (RM)

Cumulative Amount(RM)

Certified Amount(RM)

Cumulative Certified (RM)

Amount Received (RM)

Date Payment Received

9 29/01/2015 6,166,849.93 49,646,249.93 6,166,000.00 49,645,400.00 6,166,000.00 13/02/2015

10 25/02/2015 7,565,766.29 57,211,166.29 7,565,000.00 57,210,400.00 7,565,000.00 18/03/2015

11 27/03/2015 8,894,880.84 66,105,280.84 8,894,000.00 66,104,400.00 8,894,000.00 16/04/2015

12 27/04/2015 3,184,099.14 69,288,499.14 3,184,000.00 69,228,400.00 3,184,000.00 20/05/2015

17

12 27/04/2015 3,184,099.14 69,288,499.14 3,184,000.00 69,228,400.00 3,184,000.00 20/05/2015

13 28/05/2015 4,924,954.88 74,213,354.88 4,924,000.00 74,212,400.00 4,294,000.00 25/06/2015

14 24/06/2015 6,661,898.05 80,874,298.05 6,661,000.00 80,873,400.00 6,661,000.00 09/07/2015

15 29/07/2015 3,857,505.93 84,731,803.98 3,850,000.00 84,723,400.00 3,850,000.00 21/08/2015

16 01/09/2015 2,422,060.80 87,153,864.78 2,422,000.00 87,145,400.00

Page 18: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

8. MONTHLY LOOKAHEAD (1 SEPT 2015 ~ 30 SEPT 2015)

Component Activity / Description

A. Physical Works 1. Bridge Structure Works

a) To complete installation of Precast Parapet Panels and Kerb Casting forthe following spans:-

i. P21 ~ P22 – 02 September 2015 – Span 22

18

i. P21 ~ P22 – 02 September 2015 – Span 22ii. P22 ~ P23 – 04 September 2015 – Span 23iii. P26 ~ P27 – 05 September 2015 – Span 27iv. P25 ~ P26 – 07 September 2015 – Span 26v. P24 ~ P25 – 09 September 2015 – Span 25vi. P23 ~ P24 – 11 September 2015 – Span 24

Cumulative total of 45 / 45 spans to be completed by 11-Sept 2015.

2. Pavement Works

a) To commence premix works by 10 Sept 2015.b) To commence installation of traffic signs on 21 Sept 2015.c) To commence installation of directional signages and gantry works by

25 Sept 2015.

Page 19: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

8. MONTHLY LOOKAHEAD (1 SEPT 2015 ~ 30 SEPT 2015)

Component Activity / Description

B. Authorities Requirements

3. JPS Selangor

a) To complete installation of gabion mattress in Section 1 by 30 Sept2015.

b) To complete installation of GeoBags in Section 3 by 21 Sept 2015.

19

C. Other Works 4. Drainage Works

a) To complete reconstruction of drainage services by 30 Sept 2015.

5. Defects Listing (as part of Handover Process)

a) To commence listing of Defects on completed structural elements ateach pier and span by 07 Sept 2015.

Page 20: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

PROJECT: AKLEH PHASE 2

9. MAIN CONTRACTOR’S CONCLUSION

� Overall progress achieved in Month of August 2015 has been satisfactory dueto the following reasons:-

1) Regression on Overall Physical Progress compared to previous month (+0.39 % compared to+2.98 % in July 2015 and +6.00 % in June 2015) – ahead by 2 days in overall activities and nolonger recording delays on critical path.

2) Regression in % ahead is due to the reduced manpower over Hari Raya Aidilfitri period (whichaffected the parapet installation works and kerb casting) and the requirement to completecurrent ongoing activities prior to commencement of the next milestone works i.e. Pavementworks on new bridge deck.

20

current ongoing activities prior to commencement of the next milestone works i.e. Pavementworks on new bridge deck.

3) We positively note that TNB Pylon Relocation Works were completed as scheduled, with zero (0)HSE related incidents and within approx. one (1) year from official communication with TNB on22 July 2015.

� Areas of Improvement as commented by Consultants:-

1) Contractor advised to pay special attention to concrete finishes especially now that the worksare limited to parapet and kerb.

2) Defects Listing as part of Handover and LLM requirement for SKPL should be commenced assoon as practical and rectification works should be targeted to complete prior to completion ofnew bridge deck.

Page 21: 15 AKLEH P2 - Monthly Meeting No 15 Presentation (03092015)

THANK YOU FOR YOUR TIME

21