MONITORING KONTRAK PROYEK MUSIM MAS - LUBUK GAUNGPERIODE s/d 28 FEBRUARI 2013
NILAI KONTRAK NILAI KONTRAK PERSENTASE
No. URAIAN AWAL ADDENDA KERJA TAMBAH KETERANGAN
(Include PPn 10%) (Include PPn 10%)
SUMMARY
A PROYEK MUSIM MAS XXXVIII 10.516.000.000,00 1.466.300.000,00 13,94%
B PROYEK MUSIM MAS XXXIX 103.398.900.000,00 10.039.030.250,00 9,71%
GRAND TOTAL 113.914.900.000,00 11.505.330.250,00 10,10%
Hal. 1/4 File: MM Lbkgaung Mntr Kontrak & SI/gs
MONITORING KONTRAK PROYEK MUSIM MAS XXXVIIIPERIODE s/d 28 FEBRUARI 2013
NILAI KONTRAK NILAI KONTRAK
No. URAIAN AWAL ADDENDA KETERANGAN
(Include PPn 10%) (Include PPn 10%)
A KONTRAK AWAL
1 Kontrak No. 002/IBPT-LG/PRJ/I/2012 10.516.000.000,00
Upah Pemancangan Tiang Pancang
SUB TOTAL 10.516.000.000,00 -
B KONTRAK ADDENDA
1 Kontrak No. 008/IBPT-LG/PRJ/IV/2012 1.466.300.000,00 Selesai dikerjakan
Pek. Timbunan Tanah Lahan Bangunan Main Office, PKE Godown, Chemical Warehouse dan
Tank Farm 1670m3 & Tank Farm 3500m3 (Pek. Timbunan Paket 1)
- Main Office (SI No. 03/SI/BP/DM/III/2012)
- PKE Godown (SI No. 04/SI/BP/DM/III/2012)
- Chemical Warehouse (65mx31m) (SI No. 05/SI/BP/DM/III/2012)
- Tank Farm 1670m3 / 3500m3 (93mx125m) (SI No. 06/SI/BP/DM/III/2012)
SUB TOTAL - 1.466.300.000,00
TOTAL MUSIM MAS XXXVIII 10.516.000.000,00Rp 1.466.300.000,00Rp 11.982.300.000,00Rp
1.466.300.000,00Rp
10.516.000.000,00Rp x 100% = 13,94%Persentase kerja tambah terhadap kontrak awal =
Hal. 2/4 File: MM Lbkgaung Mntr Kontrak & SI/mm38
MONITORING KONTRAK PROYEK MUSIM MAS XXXIXPERIODE s/d 28 FEBRUARI 2013
NILAI KONTRAK ADDENDDUM
No. URAIAN PEK. ± KETERANGAN
(Include PPn 10%) (Include PPn 10%)
A KONTRAK AWAL
1 Kontrak No. 003/IBPT-LG/PRJ/II/2012 103.398.900.000,00
Pek. Struktur, Finishing & MEP
SUB TOTAL 103.398.900.000,00 -
B KONTRAK ADDENDA
1 Kontrak No. 014/IBPT-LG/PRJ/VIII/2012 2.487.100.000,00
Pek. Urugan Tanah Timbun termasuk pemadatan untuk
peninggian lantai dibawah lantai bangunan dan lantai
selasar (Pek. Timbunan Paket 3)
- Bang. Main Office (SI NO : 11/SI/IBP/DM/VI/2012) Selesai dikerjakan
- Bang. Lab & Archive (SI NO : 12/SI/IBP/DM/VI/2012) Selesai dikerjakan
- Tank Farm 1670m3 / 3500m3 (SI NO : 13/SI/IBP/DM/VI/2012) Selesai dikerjakan
- Bang. Refinery (SI NO : 14/SI/IBP/DM/VI/2012) Selesai dikerjakan
- Cooling Tower (SI NO : 15/SI/IBP/DM/VI/2012) Selesai dikerjakan
- Weighing Hopper (SI NO : 17/SI/IBP/DM/VI/2012) Selesai dikerjakan
- PKE Godown Selesai dikerjakan
- Chemical Warehouse Selesai dikerjakan
- Workshop & Sparepart Workshop Selesai dikerjakan
- Kernel Crushing Plant Sedang dikerjakan
ADDENDUM : - SI no. 27 (Timbunan Public Toilet) 1.383.800,00 Selesai dikerjakan
- SI no. 28 (Timbunan Ruang Trafo) 8.835.750,00 Selesai dikerjakan
- SI no. 29 (Timbunan Guard Pos & Custom Room) 5.161.200,00 Selesai dikerjakan
2 Kontrak No. 015/IBPT-LG/PRJ/VIII/2012 1.568.600.000,00
Pek. Timbunan Tanah Lahan Bangunan Unloading Station For Kernel, unloading
Station, Silo dia. 14,63m, Kernel Crushing Plant, Weighing Hoppper, SWRO Plant &
Power Plant (Pek. Timbunan Paket 2)
- Unloading For Kernel (SI NO : 07/SI/IBP/DM/IV/2012) Selesai dikerjakan
- UNLOADING 96m' (SI NO : 08/SI/IBP/DM/IV/2012) Selesai dikerjakan
- SILO 14,63 (SI NO : 09/SI/IBP/DM/IV/2012) Selesai dikerjakan
- Kernel Crushing Plant (SI NO : 10/SI/IBP/DM/IV/2012) Selesai dikerjakan
- Weighing Hopper Selesai dikerjakan
- SWRO Plant Selesai dikerjakan
- Power Plant, Boiler & Turbin Selesai dikerjakan
ADDENDUM : - SI no. 26 (Timbunan SEP) 513.383.000,00 Selesai dikerjakan
- SI no. 30 (Timbunan Waste Water Treatment Plant) 176.689.500,00 Selesai dikerjakan
3 Kontrak No. 021/IBPT-DUM/PRJ/XI/2012 357.500.000,00
Pek. Struktur Site - C, Dumai Pelabuhan
4 Kontrak No. 024/IBPT-LG/PRJ/XII/2012 272.800.000,00 Selesai dikerjakan
Pek. Penambahan Silo Semen kap. 60 ton
5 Kontrak No. 025/IBPT-LG/PRJ/XII/2012 1.331.000.000,00 Selesai dikerjakan
Pek. 1 unit Batching Plant
6 Kontrak No. 001/IBPT-LG/PRJ/I/2013 876.700.000,00 Selesai dikerjakan
Gantry & Pipe Rack (SI no. 24)
SUB TOTAL - 7.599.153.250,00
C PENGAJUAN ADDENDA (ADA SURAT PENAWARAN)
1 SI no. 25 (SWRO Plant 2) 968.000.000,00
SUB TOTAL - 968.000.000,00
Hal. 3/4 File: MM Lbkgaung Mntr Kontrak & SI/mm39
MONITORING KONTRAK PROYEK MUSIM MAS XXXIXPERIODE s/d 28 FEBRUARI 2013
NILAI KONTRAK ADDENDDUM
No. URAIAN PEK. ± KETERANGAN
(Include PPn 10%) (Include PPn 10%)
D PENGAJUAN ADDENDA (BELUMA ADA PENAWARAN / PREDIKSI)
1 SI no. 20 (Pagar temporary Zona 2 Non Berikat) 68.970.000,00 Selesai dikerjakan
2 SI no. 31 (Pagar temporary Zona 1 Non Berikat) 20.625.000,00 Selesai dikerjakan
3 SI no. 32 (Pondasi Navigator Lamp Tower) 9.900.000,00 Sedang dikerjakan
4 SI no. 30a (Bangunan MV Room & Gardu Induk) 276.100.000,00 Segera dikerjakan
5 SI no. 31a (Cor Lantai Suspended Refinery) 633.600.000,00 Segera dikerjakan
6 SI no. 32a (Keramik lantai Suspended Refinery) 456.192.000,00 Segera dikerjakan
7 SI no. 33 (Pondasi Cymney Refinery) 6.490.000,00 Segera dikerjakan
SUB TOTAL - 1.471.877.000,00
TOTAL MUSIM MAS XXXIX 103.398.900.000,00Rp 10.039.030.250,00Rp 113.437.930.250,00Rp
10.039.030.250,00Rp
103.398.900.000,00Rp Persentase kerja tambah terhadap kontrak awal = x 100% = 9,71%
Hal. 4/4 File: MM Lbkgaung Mntr Kontrak & SI/mm39