Airbus / Daher Readiness ReviewJuly 11-12, 2011
Day 1
Airbus / Daher Readiness Review Page 1
Presented by
Gilles CesconA350 XWB Chief Engineer Systems
DRAFT
Agenda
Monday, July 11, 201110:00 Airbus / Daher Program Updates Tracy DeCuir10:30 Program Production Schedule Tracy DeCuir11:00 Manufacturing Synchronization Patricia Ramirez11:30 Generic BOM Rick Molus12:00 Lunch 1:30 Level 2 Templates Plan Rick Molus2:00 Material Readiness Renato Torres
Templates / MSN 1~6China Import/Export
2:30 BaaN Readiness Jean WhiteSystem Modification Required
3:30 CM Database Readiness Luis ValenciaBaaN Download
4:00 Business Flow Jesus Castellanos 5:00 Closing Tracy DeCuir
Airbus / Daher Readiness Review Page 2
Agenda
Tuesday, July 12, 20119:00 Quality Updates Mariano Velarde
Daher Supplier QualificationLMS QualificationFAI – Factory/Installation
10:00 Master Schedule Jacobo Felix11:00 Engineering Readiness Rocio Godinez
Staffing & IT Data EntryADCN Plan Validation
11:30 Logistic Plan / Readiness Olga Reyes12:00 Lunch1:30 KaMEX Readiness Jose Burboa2:00 Project Timeline Jesus Castellanos 2:30 Actions Items Jesus Castellanos 3:00 Closing / Next Steps Tracy DeCuir
Airbus / Daher Readiness Review Page 3
Airbus Program Update
• Airbus
Airbus / Daher Readiness Review Page 4
Tracy DeCuir
Daher Program Schedule
• Airbus
Airbus / Daher Readiness Review Page 5
Tracy DeCuir
Airbus Program Update
• Engineering Readiness/Ramp-up is the number one concern Computers and software is received and operational Resources pending
(10) 2D Designers (7) 3D Designers (8) ME Designers
IP completion great challenge Budget Saving Opportunity needed
• Forward and Nose Section KODD are confirmed• Awaiting revised KODD for Center and AFT Section• Daher officially approved as TIS LMS sub contractor
Airbus / Daher Readiness Review Page 6
Tracy DeCuirTracy DeCuir
Section 13/14 - Forward
Airbus / Daher Readiness Review Page 7
Milestones Airbus requested date
TIS LtR planning iss25
Forward Section 13/14
Crown 56 P/N def2 P6-P6 Freeze IP 6/17/2011 3D design Mat C freeze 6/24/2011 Blanket presentation + red line drawing 7/25/2011 Freeze Def 4 definition + DMU cross check 7/28/2011 TIS Start of equiping 9/2/2011 8/19/2011
Upper side wall 112 P/N def2 P6-P18 LH+RH
Freeze IP 7/1/2011 3D design Mat C freeze 7/13/2011 Blanket presentation + red line drawing 8/16/2011 Freeze Def 4 definition + DMU cross check 8/19/2011 TIS Start of equiping 9/23/2011 9/12/2011
Side wall 98 P/N def2 P18-P27 LH+RH
Freeze IP 6/17/2011 3D design Mat C freeze 7/22/2011 Blanket presentation + red line drawing 8/24/2011 Freeze Def 4 definition + DMU cross check 8/29/2011 TIS Start of equiping 9/23/2011 9/20/2011 Cargo 69 P/N def2 P27-P38 LH+RH Freeze IP 6/17/2011 3D design Mat C freeze 7/29/2011 Blanket presentation + red line drawing 9/1/2011 Freeze Def 4 definition + DMU cross check 9/6/2011 TIS Start of equiping 9/23/2011 9/28/2011
Tracy DeCuirTracy DeCuir
Section 11/12 - Nose
Airbus / Daher Readiness Review Page 8
Milestones Airbus requested date
TIS LtR planning iss25
Nose Section 11/12
S11 - Cokpit - 111 P/Ns - def2 Freeze IP 7/1/2011 3D design Mat C freeze 8/9/2011 Blanket presentation + red line drawing 9/12/2011 Freeze Def 4 definition + DMU cross check 9/14/2011 TIS Start of equiping 10/24/2011 10/6/2011
S11 - Burn through - 76 P/Ns - DEF4
Freeze IP 7/8/2011 3D design Mat C freeze 8/22/2011 Blanket presentation + red line drawing 9/21/2011 Freeze Def 4 definition + DMU cross check 9/22/2011 TIS Start of equiping 10/24/2011 10/17/2011 S12 - Cargo - 40 P/Ns - def2 Freeze IP 7/22/2011 3D design Mat C freeze 8/25/2011 Blanket presentation + red line drawing 9/28/2011 Freeze Def 4 definition + DMU cross check 9/29/2011 TIS Start of equiping 10/24/2011 10/21/2011
S12 - F2F - 90 P/Ns - def2 Freeze IP 7/22/2011 3D design Mat C freeze 9/2/2011 Blanket presentation + red line drawing 10/6/2011 Freeze Def 4 definition + DMU cross check 10/10/2011 TIS Start of equiping 10/24/2011 11/1/2011
Tracy DeCuirTracy DeCuir
Section 15/21- Center
Airbus / Daher Readiness Review Page 9
Milestones Airbus requested date
TIS LtR planning iss25
Center Section 15/21
Crown Area - 58 P/Ns def2 Freeze IP 7/29/2011 Mat C freeze 11/25/2011 Blanket presentation + red line drawing 1/20/2012 Freeze Def 4 definition + DMU cross check 1/30/2012 TIS Start of equiping 12/5/2011 2/24/2012
Upper sidewall Area - 114 P/Ns def2
Freeze IP Mat C freeze Blanket presentation + red line drawing Freeze Def 4 definition + DMU cross check TIS Start of equiping 12/5/2011 Sidewall Area - 135 P/Ns def2 Freeze IP Mat C freeze Blanket presentation + red line drawing Freeze Def 4 definition + DMU cross check TIS Start of equiping 12/5/2011
Cargo Area - 61 P/Ns def2 Freeze IP Mat C freeze Blanket presentation + red line drawing Freeze Def 4 definition + DMU cross check TIS Start of equiping 12/5/2011
Tracy DeCuirTracy DeCuir
Section 16/18 - AFT
Airbus / Daher Readiness Review Page 10
Milestones Airbus requested date
TIS LtR planning iss25
Aft section 16/18
Cargo (including FTTB) - 97 P/Ns def 2
Freeze IP 7/22/2011 3D design Mat C freeze 9/15/2011 Blanket presentation + red line drawing 10/13/2011 Freeze Def 4 definition + DMU cross check 10/18/2011 TIS Start of equiping 11/15/2011 11/9/2011
Cabin + bulkhead - 286 P/Ns def 2
Freeze IP 7/22/2011 Mat C freeze 10/17/2011 Blanket presentation + red line drawing 12/2/2011 Freeze Def 4 definition + DMU cross check 12/7/2011 TIS Start of equiping 11/15/2011 1/2/2012
Tracy DeCuirTracy DeCuir
Junctions
Airbus / Daher Readiness Review Page 11
Milestones Airbus requested date
TIS LtR planning iss25
Junctions
S11-14 - junction - 30 P/Ns - def4 Freeze IP 7/22/2011 Mat C freeze 12/1/2011 Blanket presentation + red line drawing 2/3/2012 Freeze Def 4 definition + DMU cross check 2/8/2012 TIS Start of equiping 1/22/2012 2/29/2012
FAL junction - 70 P/Ns def 4
Freeze IP 7/29/2011 Mat C freeze 12/14/2011 Blanket presentation + red line drawing 2/16/2012 Freeze Def 4 definition + DMU cross check 2/21/2012 TIS Start of equiping TBC 3/15/2012
Tracy DeCuirTracy DeCuir
Daher Program Update
• Manufacturing Sync is the number one concern • Two Teams Established
A350XWB Support Team (LMS & Installation) Legacy Production Transfer Team (Long Range & A320 Family)
• Legacy Production Transfer Workshop Update• Manufacturing Sync is the number one concern
Airbus / Daher Readiness Review Page 12
Tracy DeCuirTracy DeCuir
A350XWB Support Team
Airbus / Daher Readiness Review Page 13
Tracy DeCuirTracy DeCuir
A350XWB Support Timeline
Airbus / Daher Readiness Review Page 14
• 90 day HAM Initial – Go Live Currently Do NOT support Requested FWD section KODD Currently Engineering & Production also Do NOT support Requested FWD
section KODD
Jun2011
Jul2011
Aug2011
Sep2011
Oct2011
Nov2011
Dec2011
Jan2012
Feb2012
Mar2012
Apr2012
May2012
Jun2012
Jul2012
LMS/Install Dossier FWD
Install Start
Go LiveHAM Initial (90 days) Go LiveHAM Final
Go LiveSNZ
Go LiveTLS
NOF
Install Start
Sect KODD /Installation Start
FWD 19/08/2011
NOF 15/09/2011
CEF 01/11/2011
AFT 09/11/2011CEF
Install Start
AFT
Install Start
HAM Initial (90 days)
IPCA
IPCA
IPCA
Install Team
Ready
Install Team
Ready
FAL Start
Tracy DeCuirTracy DeCuir
Legacy Production Transfer Team
Airbus / Daher Readiness Review Page 15
Airbus Industrial LeadStefan Reim
Daher / TIS Project ManagerTracy DeCuir
Daher / TIS Project ManagerTBD
Production LeadMartha Cruze (Acting)
Manufacturing EngineeringPatricia Ramirez
Production ControlJacobo Felix
Project CoordinatorJesus Castellanos
Quality LeadMariano Velarde (Acting)
Technical LeadRick Molus (Acting)
LogisticBjoern Schneider
ProcurementRenato Torres
Project CoordinatorProduction Lead,
Production ControlRonan Bellec (Acting)
Technical & Quality Lead,Manufacturing Engineering
Laurent Godard (Acting)Andy Hibschele
(Design Support)
Logistic / Supply Chain Sandrine Moyon (Acting)
KaMex Lead (China)Bernhard Schueler
Installation Audrey Amano (Acting)
Airbus Industrial LeadEric Guignard
Tracy DeCuirTracy DeCuir
Production Schedule
• Airbus/Daher
Airbus / Daher Readiness Review Page 16
Global Capacity Ramp-up Chart NOF = 296 FWD = 344 CEN = 514 AFT = 496 305 485 DAHER A320 = 486
FY 2012
Dates (Friday)
4/1/
11
4/8/
11
4/15
/11
4/22
/11
4/29
/11
5/6/
11
5/13
/11
5/20
/11
5/27
/11
6/3/
11
6/10
/11
6/17
/11
6/24
/11
7/1/
11
7/8/
11
7/15
/11
7/22
/11
7/29
/11
8/5/
11
8/12
/11
8/19
/11
8/26
/11
9/2/
11
9/9/
11
9/16
/11
9/23
/11
9/30
/11
10/7
/11
10/1
4/11
10/2
1/11
10/2
8/11
11/4
/11
11/1
1/11
11/1
8/11
11/2
5/11
12/2
/11
12/9
/11
12/1
6/11
12/2
3/11
12/3
0/11
1/6/
12
1/13
/12
1/20
/12
1/27
/12
2/3/
12
2/10
/12
2/17
/12
2/24
/12
3/2/
12
3/9/
12
3/16
/12
3/23
/12
3/30
/12
Tota
ls
Est. Shipset Demand CW13 CW14 CW15 CW16 CW17 CW18 CW19 CW20 CW21 CW22 CW23 CW24 CW25 CW26 CW27 CW28 CW29 CW30 CW31 CW32 CW33 CW34 CW35 CW36 CW37 CW38 CW39 CW40 CW41 CW42 CW43 CW44 CW45 CW46 CW47 CW48 CW49 CW50 CW51 CW52 CW1 CW2 CW3 CW4 CW5 CW6 CW7 CW8 CW9 CW10 CW11 CW12 CW13
A350-XWB NOF 1.0 1.0 1.0 1.0 1.0 1.0 1.0 7
A350-XWB FWD 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 8
A350-XWB CEN 1.0 1.0 1.0 1.0 1.0 5
A350-XWB AFT 1.0 1.0 1.0 1.0 1.0 1.0 6
DAHER A330/A340 NOF 1.0 1.0 1.0 1.0 1.2 1.2 1.6 1.6 1.6 1.6 1.6 1.6 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 48
DAHER A330/A340 CEN 1.0 1.0 1.0 1.0 1.0 1.2 1.2 1.6 1.6 1.6 1.6 1.6 1.6 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 49
Daher A320 Family 0.5 0.5 1.0 2.0 3.0 4.0 4.0 5.0 5.0 5.0 6.0 36
Est. Blanket DemandA350-XWB NOF 0 0 0 0 0 0 0 0 0 0 0 0 0 296 0 0 296 0 0 0 296 0 0 0 0 296 0 0 0 0 0 296 0 0 0 296 0 0 0 0 0 0 296 0 0 2072
A350-XWB FWD 0 0 0 0 0 0 0 0 0 0 0 344 0 0 344 0 0 344 0 0 0 0 0 0 344 0 0 0 344 0 0 344 0 0 344 0 0 0 0 0 0 344 0 0 0 2752
A350-XWB CEN 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 514 0 0 0 0 0 0 0 0 514 0 0 0 0 0 514 0 0 0 0 0 0 0 514 0 0 0 0 514 2570
A350-XWB AFT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 496 0 0 0 0 0 0 0 0 496 0 0 0 0 496 0 0 0 496 0 0 0 0 0 496 0 0 0 496 2976
A350-XWB Total 0 0 0 0 0 0 0 0 0 0 0 344 0 296 344 0 1306 344 0 0 296 0 0 0 344 1306 0 0 344 0 496 1154 0 0 840 296 0 0 0 514 496 344 296 0 1010 10370
DAHER A330/A340 NOF 0 0 0 0 0 0 0 0 0 0 0 0 0 0 305 0 305 305 305 366 366 488 488 488 488 488 488 549 549 549 549 549 549 549 549 549 549 549 549 549 549 549 549 549 549 14762
DAHER A330/A340 CEN 0 0 0 0 0 0 0 0 0 0 0 0 485 0 485 0 485 485 485 582 582 776 776 776 776 776 776 873 873 873 873 873 873 873 873 873 873 873 873 873 873 873 873 873 873 23959
Daher A320 Family 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 243 0 0 0 0 243 0 0 486 972 1458 1944 1944 2430 2430 2430 2916 17496
Daher Total 0 0 0 0 0 0 0 0 0 0 0 0 485 0 790 0 790 790 790 948 948 1264 1264 1264 1264 1264 1264 1422 1665 1422 1422 1422 1422 1665 1422 1422 1908 2394 2880 3366 3366 3852 3852 3852 4338 56217
Est. Total Blanket Demand 0 0 0 0 0 0 0 0 0 0 0 344 485 296 1134 0 2096 1134 790 948 1244 1264 1264 1264 1608 2570 1264 1422 2009 1422 1918 2576 1422 1665 2262 1718 1908 2394 2880 3880 3862 4196 4148 3852 5348 66587
Est. Total Blanket CUM 0 0 0 0 0 0 0 0 0 0 0 344 829 1125 2259 2259 4355 5489 6279 7227 8471 9735 10999 12263 13871 16441 17705 19127 21136 22558 24476 27052 28474 30139 32401 34119 36027 38421 41301 45181 49043 53239 57387 61239 66587
Production Location
Kamex 0 0 0 0 0 0 0 0 0 0 0 292 412 252 964 0 1782 964 672 806 1057 1074 1074 1074 1367 2185 1074 1209 1708 1209 1630 2190 1209 1415 1923 1460 1622 2035 2448 3298 3283 3567 3526 3274 4546 56599
LMS Hamburg 0 0 0 0 0 0 0 0 0 0 0 86 0 0 86 0 124 86 0 0 0 0 0 0 86 124 0 0 86 0 124 86 0 0 210 0 0 0 0 0 124 86 0 0 124 1432
LMS Saint Nazarie 0 0 0 0 0 0 0 0 0 0 0 0 0 74 0 0 203 0 0 0 74 0 0 0 0 203 0 0 0 0 0 203 0 0 0 74 0 0 0 129 0 0 74 0 129 1161
LMS Toulouse 0 0 0 0 0 0 0 0 0 0 0 34 0 30 34 0 131 34 0 0 30 0 0 0 34 131 0 0 34 0 50 115 0 0 84 30 0 0 0 51 50 34 30 0 101 1037
LMS Total 0 0 0 0 0 0 0 0 0 0 0 120 0 104 120 0 457 120 0 0 104 0 0 0 120 457 0 0 120 0 174 404 0 0 294 104 0 0 0 180 174 120 104 0 354 60228
Airbus Requested KODD
A350-XWB NOF
15-S
ep-1
1
3-N
ov-1
1
30-N
ov-1
1
5-Ja
n-12
28-F
eb-1
2
22-M
ar-1
2
6
A350-XWB FWD
5-A
ug
-11
14-O
ct-1
1
10-N
ov-1
1
29-D
ec-1
1
23-J
an-1
2
15-F
eb-1
2
9-M
ar-1
2
7
A350-XWB CEN
2-N
ov-1
1
26-J
an-1
2
23-F
eb-1
2
3
A350-XWB AFT
31-O
ct-1
1
10-J
an-1
2
2-F
eb-1
2
21-M
ar-1
2
4
A350-XWB Total 1 1 1 3 1 1 1 1 2 1 3 1 1 2 20
A350-XWBFAL
21-D
ec-1
1
April May June MarchFebuaryJanuaryDecemberNovember
DAHER A330/A340 NOF =
DAHER A330/A340 CEN =
OctoberSeptemberAugustJuly
Microsoft Excel 97-2003 Worksheet
Tracy DeCuirTracy DeCuir
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 17
Patricia Ramirez
2D Dwg
Cut File BOM
Routing ME1
Install DWG
CI / KITDEFINITION
Subject Expectations:• Plan Overview• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Training• Open Issues• Risk / Mitigations• Help Needed
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 18
Plan Overview
To Identify and obtain all the information necessary to achieve the Manufacturing Synchronization TIS-Daher
2D Dwg
Cut File BOM
Routing ME1
Install DWG
CI / KITDEFINITION
Patricia RamirezPatricia Ramirez
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 19
Identify Key Team Members
Placas Facility:• ME Leader Patricia Ramirez • ME Leader Daniel Jimenez
• ME Alfredo Torres
• Daher Counterpart (TBD)
Patricia RamirezPatricia Ramirez
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 20
• Layers convert program (IT)
• Automate Quotation Process (Outsourcing)
• Additional tools if needed, will be identified after Daher Visit.
Tools
Patricia RamirezPatricia Ramirez
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 21
Time Line
Patricia RamirezPatricia Ramirez
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 22
Training
• Training on the Layers Convert Program
• Training on the Quotation Program
• If it is necessary to create all new Methods, Operations & Work Instructions, training will be necessary
Patricia RamirezPatricia Ramirez
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 23
Open Issues
DXF Files Layers Differences
Patricia RamirezPatricia Ramirez
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 24
Open Issues
Patricia RamirezPatricia Ramirez
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 25
Open Issues
Patricia RamirezPatricia Ramirez
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 26
Risk / Mitigations
• Risks: Find something different about the 50 DXF files already received from Daher or on the manufacture process that could produce delay on the time line already given.
• Mitigations: Prepare Files samples for a run test on Daher site if possible, to clarify all the doubts and get the correct information.
Patricia RamirezPatricia Ramirez
Manufacturing Synchronization
Airbus / Daher Readiness Review Page 27
Help Needed
• Strong Collaboration of IT Department on the programs development.
• Data Entry support for Operations creation or modification (If necessary).
Patricia RamirezPatricia Ramirez
Generic BOM
Airbus / Daher Readiness Review Page 28
Rick Molus
Subject Expectations:• Plan Overview• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Open Issues• Risk / Mitigations• Help Needed
Generic BOM
Timeline
• No foreseen impact to existing proposed schedule• Base Material definition and quantities calculations driven
from weight model will be performed prior to or concurrent with 2D Def. 2 drawing phase for each section sub-kit
• Other materials (i.e. Foam Rings, Tapes, Hook and Loops) not in existing weight model will be estimated and added to Base Material calculations by ME team for each part number using current ME WoW
• Routings will be created using current ME WoW• Baan entry will be concurrent with ME activities for each
section sub-kitAirbus / Daher Readiness Review Page 29
Rick MolusRick Molus
Generic BOM
Open Issues• Support materials (i.e. tapes, hook and loops) can only
be estimated on initial GBOM, recommended to create estimated additional support materials definition as a separate kit for each sub-section
Risks/Mitigations• Material quantities for templates (blanket type) will be
estimated therefore actual usage may need to be adjusted in MRP for inventory control purposes
• BOM’s and Routings will have to be redefined and entered into BaaN system for Def. 4 blankets
Airbus / Daher Readiness Review Page 30
Rick MolusRick Molus
Lunch
Airbus / Daher Readiness Review Page 31
Level 2 Templates Plan
Airbus / Daher Readiness Review Page 32
Rick Molus
Subject Expectations:• Plan Overview / Diagrams• Identify Key Team Members• Tools (Computer, Software…)• Training• Timeline• Open Issues• Risk / Mitigations• Help Needed
Level 2 Templates Plan
Airbus / Daher Readiness Review Page 33
Rick Molus
Template ADCN Process Produce blankets QTY
FactoryFAI
InstallationFAI CAIR
Warehouse
MSN 2
MSN 1Replacement
Level 2nd to 4th Level KODD
3 WEEKS
DEV 2 TAKING DELTA
10-30 Days
2 - 5 Days
Level 2 Templates Plan
Plan Overview• On MSN1 first delivery (FWD section Crown) template for
all parts will all be physical Def. 2 blankets made using low cost materials
• Paper templates will also be created for each field blanket to validate and optimize concept at first installation (fit-check)
• Validate feasibility for use of strip blanket materials at fit-check
• Generic BOM will be generated using existing weight model and entered in BaaN system
• Def 2. templates will have same part number as actual blanket with a T prefix of suffix added (TBD)
Airbus / Daher Readiness Review Page 34
Subject Expectations:
• Plan Overview / Diagrams
• Identify Key Team Members
• Tools (Computer, Software…)
• Training
• Timeline
• Open Issues
• Risk / Mitigations
• Help Needed
Rick MolusRick Molus
Level 2 Templates PlanKey Team Members• Rick Molus• Carlos Navarro• Victor Calderon• Section Leads• DAHER Counterparts (TBD)
Tools• Wide Format Plotter• Printer/Scanner, 2 Tray, 11” x 17” capable• Engineering Laptop Computer w/CATIA and AutoCAD (node locked licenses will
be required)• Steel measuring tape, fabric measuring tape, scissors, knife, markers, red pens
and pencils, paper, clip boards (1 set for each person)• Support materials including strip blanket material, 25, 50 and 75mm wide KB42
tape, hook/loops, 0.42 PCF fiberglass, Terul 18 cover-film, foam discs, pins and washers
Airbus / Daher Readiness Review Page 35
Rick MolusRick Molus
Level 2 Templates Plan
Training• Propose visit by key members to DAHER installation site at
Airbus SNZ to familiarize with current RE process used on Long Range
• Perform simulation Dry-run at Placas of complete process (including creation of 2D drawing, Redlining, ADCN)
Open Issues• Timeline to be synchronized with master schedule• Finalize part number scheme to be used for Def. 2 templates• Data Transfer process flow needs to be determined• Will we have access to required GSE equipment (i.e. ladders
and/or platforms, workbenches)• Use of paper templates not known to be viable solution
Airbus / Daher Readiness Review Page 36
Rick MolusRick Molus
Level 2 Templates Plan
Risks/Mitigations• Visit to DAHER installation will not be possible.
Current TIS key members have no experience using paper template concept for RE
Current TIS key members have limited experience using Def 2. blanket to create Def 4. drawing
• Paper template concept will not prove to be viable• Cut files, BOM’s and routings will have to be
regenerated for Def. 4
Airbus / Daher Readiness Review Page 37
Rick MolusRick Molus
Level 2 Templates Plan
Airbus / Daher Readiness Review Page 38
Rick MolusRick Molus
Level 2 Templates Plan
Airbus / Daher Readiness Review Page 39
Rick MolusRick Molus
Material Readiness
• Level 2 Templates • MSN 1~6
Airbus / Daher Readiness Review Page 40
Renato Torres
Subject Expectations:• Plan Overview• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Open Issues• Risk / Mitigations• Help Needed
Material Readiness
Plan Overview To have material and processes in place to cover the demand of material to build MSN
1 -6 in all manufacturing locations including LMS
Key MembersEmmanuel Hernandez Airbus Buyer for TIS Placas Sandrine Moyon Materials Mgr. for Daher-Socata
Olga Reyes Logistic Mgr. for TIS PlacasRico Wang Customs Spv. TIS Kamex
Tools All equipment software to perform the first 6 MSN’s are in place in all locations, TIS
will input all activities made at LMS locations in regards of the FG reporting and RM, all inventory activities will be coordinated by Placas by Emmanuel Hdz.
Airbus / Daher Readiness Review Page 41
Renato TorresRenato Torres
Airbus / Daher Readiness Review Page 42
Material Readiness
Open Issues• P-BOM defined for MSN no. 5-6 at this point only 1 – 4 are defined to use legacy raw
material.• Heavy layer, Peek material and felt qualification pending.• Determine Mock up quantity and the material content.
Risks• Material availability at Kamex/LMS and or Placas• Material content for MSN’s (Paper or raw material)
Mitigation• Material available for 4 MSN (legacy products) at Placas• Material available and open orders with supplier to fulfill up to 9 MSN.
Help Needed• Firm visibility of build sites, dates , mock ups qty and material content (Paper or RM)
Renato TorresRenato Torres
China Import/Export Material
• Import/Export Plan
Airbus / Daher Readiness Review Page 43
Renato Torres
Subject Expectations:• Plan Overview• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Training• Open Issues• Risk / Mitigations• Help Needed
International Import/Export Material
Plan Overview TIS must have for the upcoming events a very solid Logistic process in place to succeed. As part of the Logistic process there is a process that needs to be address to avoid
problems in customs such as China, US, France and Germany. It is also important to have all compulsory activities in place to avoid future fines and to
be able to be in compliance. At the same time to reduce the duties and taxes that can cause an extreme burden to
our profit resulting in a major compromise to the P&L.
Team MembersRico Want TIS Kamex Customs Specialist
Olga Reyes Logistic Mgr TIS PlacasSalvador Ocampo Customs Spv. TIS Placas
Tools Log Book in China is manually update however there are systems in place that can
control de in and out of raw material thus log book is updated. Daher-Socata customs control will be defined, all other tools are available.
Airbus / Daher Readiness Review Page 44
Renato TorresRenato Torres
International Import/Export Material
Open Issues• P-BOM defined to be able to apply accordingly to Chinese customs log book• LTA with WW logistics company, ALCL , DHL, Expeditors and Kuhne and Nagel are in the quoting process.• Returnable packaging in quoting process.• Pay Duties and taxes to Chinese customs in advance for upcoming import activities
Risks• Delays at customs in China• Miscalculation of raw material in P-BOM that will cause fines in China.• Delays at EU customs due to documentation and incorrect declaration of information (i.e. material
content, quantities, tariff codes etc.
Mitigations• Log Book requested to Chinese customs with increased assumptions• Use actual import power force from Daher-Socata
Help Needed• Define P-BOM to be able to apply correctly the log book
Airbus / Daher Readiness Review Page 45
Renato TorresRenato Torres
BaaN Readiness
• System Modification Required Placas KaMex Airbus Interfaces CM Database Interface Daher Interfaces???
Airbus / Daher Readiness Review Page 46
Jean White
Subject Expectations:• Plan Overview / Diagrams• Identify Key Team Members• Tools (Computer, Software…)• Training• Timeline• Open Issues• Risk / Mitigations• Help Needed
BaaN Readiness
• Plan Overview: Diagram, Highlights Highlights:
New: Supplier/customer relationship with Daher New: Engineering configuration coming from
Configuration Management Database New: Purchase Orders from Airbus will be for Kits (CI). New: Kits are likely to be ‘partially’ shipped. New: Kamex to be primary production location New: Logistics partner to transport product to Airbus New: Invoice to customer after blanket installation to
aircraft
Airbus / Daher Readiness Review Page 47
Jean WhiteJean White
Baan process overview
AIRBUSA350
Purchase Order for KIT (CI)
Sales OrderFor Kit (CI)
(SO initially to TIS)
EBOM copy Kit (CI) to Project
Sales Forecast MRP-DRP
Travelers Released for Kit Kamex or Placas
Mat. Purchase Orders
Mat. Replenishment
Orders
Raw Material Main Whse
Raw Material WIP Whse
MaterialsBackflush
Purchase Order to Daher for Kit or
Blankets
QA Plant Clearance
Check customer PO Kits
QA Production Order Final Inspection
Manufacture
Report to TIS Kit transactions
7/10/2011
ERP Business Flow per Kit
Kamex Mat Warehouse
TIS CM database
CI pn and blankets
download from CM DB
Upload Kit to Baan Engineering item
and Eng BOM
Kit to Buid at Daher?
Print documents Ship Kit to Daher
PO Receipts in Baan
Purchase Order to Daher for Kitting and Installation
Kamed Wip Warehouse
DAHER St Nazaire:Kitting and
Manufacturing
Install blankets at Hamburg, St Nazaire and
Toulouse
Kit “Maintain Delivery” at
Installation sign off
Invoice to AirbusPayment to Daher
Jean WhiteJean White
Plan Overview, cont’d
Planning Description/StatusReceive from customer airplane delivery and installation schedule
Push- Airbus Purchasing Department -Power Point available on internet - Long horizon and Yearly -Herve Doan, international supply chain Airbus supply portal. Sample needed.
Receive blanket load schedules Airbus to supply data. Sample needed.
Determine material requirement per kit and load to Baan "sales forecast" by item and warehouse for material planning purposes
TIS engineering to supply material BOM per kit
Determine production location and capacity plan Production control to determine capacity plan
Material PlanningVerify MRP Same as current process
Set up and run DRP Distribution requirements Planning Data entry by RM item and warehouse
Check MRP Planned Purchase Orders Same as current process
Check and confirm DRP Planned orders DRP requirements in Baan are included in Planned MRP Purchase Orders
Baan Purchase order data entry Material receipt warehouse at Mexico
Baan Print Purchase order Same as current process
Baan Purchase order receipts Receipt completed at delivery warehouse if drop shipped
Nonconformance report Same as current process
Receiving Inspection Log Same as current process
RMA process RMA process training at remote locations - coordinate with AP Santa Ana
Transfer to BOND room and obsolete warehouse Same as current process
Material Transfer to WIP warehouse Same as current process
Inventory adjustments Same as current process
Cycle counts Not defined for remote locations
Physical inventories Not defined for remote locations
PROPOSED A350
Jean WhiteJean White
Plan Overview, cont’dCustomer service
Receive project and CI from Engineering to load to 'internal' Sales Order
New communication from engineering department
Receive PO from customer from Esupply Chain Airbus Web based application
Training and end user access needed for Esupply chain Airbus application
When PO is received, copy existing internal Sales Order to "Airbus" customer
New process, testing needed
Customer service to create purchase order to Daher for services of Kitting and Installation
Proposed new task for customer service
Engineering
First Article Part number quotation processReceive blanket engineering-drawing, part list and copy data to network location
Same as current process, Mexico only
Master Tracking data entry Same as current process, Mexico only
Quotation system used to determine blanket bom and routing Same as current process, Mexico only
Calculate Time Standard Operations Same as current process, Mexico only
Blanket item and bom data entry to Baan Same as current process, Mexico only
Blanket routing uploaded to Baan Same as current process, Mexico only
Track first articles built in multiple production locations Modification needed of First Article tracking in BaanKit Blanket configuration
Determine "stop date" for each CI per MSN, the date that the CI blanket configuration is frozen
TIS engineering to supply data for 'manufacture' ready kit
Upload to Baan engineering module from CM database the final kit configuration
Airbus to supply daily set of XML files to reflect data in PDM Link relating to AC insulation.File output for Baan upload
Perform EBOM copy process from Engineering Baan module to Project module (Customized Items and boms)
Same as current process
Verify CI Blanket configuration Need algorithm to verify blankets.
Engineering change process
Track IP changes from IRMAT Proprietary database application definition and application developmentReceive engineering change notification ADCN Process definition neededTrack ADCNs per kit Documents neededDaher Build, Kit and Installation Procedure needed for ADCN change at LSM
Jean WhiteJean White
Plan Overview, cont’dProduction Control
Decide production Location Same as current process Mexico only
Run Baan PRP (project requirements planning) Same as current process Mexico only
Check warehouses for in stock finished goods Warehouse transfer process
Confirm and transfer Baan PRP production orders Mexico only
Baan Print travelers Kamex to print own travelers
Baan Release travelers to productionTraveler release process changes backflush warehouse to WIP warehouse of production
location
Release Nesting To CM Production location to download files
Release Nesting Cover to CM Production location to download files
Nesting Release FBG and Foam Production location to download files
Production
Manufacture blankets Same as current
Scan production orders complete Scanning complete program in remote locations
Material Requirement Administrator Control material issues
QA inspection
Inspection pass or rejectionQA process. Rejected blankets entered to QA application and disposition and reason for
rejection recorded.
Finished goods and Shipping
Print shipping documents (also blanket boxing) Need definition for shipping documents
Print customs documents Need definition for customs documents
Baan WO transfer Std-Prj Same as current process
Baan Project excess transfer Prj-Std Same as current process
Ship blankets Change warehouse assignment in project to 'transit' warehouse
QA Plant Clearance
Verify all Same as current processJean WhiteJean White
Plan Overview, cont’d
Daher ProcessReceive product from Placas, Kamex Transfer from in transit to local warehouse
Verify kit and send to install location Handled by Daher
Red line drawings, build new or repair blankets ADCN review
Create work orders for blanket installation in Aircraft Daher system
Sign off on kit installation Communication of installation complete per kit
Provide weekly detailed reports to TIS Need account of blankets produced, installations complete, with details
FinanceBaan project costing Same as current process
Baan cost accounting Need process and procedure to determine kit cost
Baan Post transactions to finance Same as current process
Baan Print invoices Same as current process
Baan Accounts receivable Same as current process
Baan Accounts Payable Same as current process
Baan General Ledger Same as current process
Baan project close Same as current process
Finance requirement Daher buisness Need requirements for purchases and sales to/from Daher
Jean WhiteJean White
Strategy- Key Team Members,Tools, and Training
• IT team to create end to end ‘Simulation’ of Baan transactions in test company
• ‘Key users’ from each department to participate in simulation.
• ‘Key users’ to train team members• Suggestions for process improvement collected and
reviewed• Review and determination of how data will be received
and given to Daher• Review Airbus software tools
Jean WhiteJean White
Timeline (Project Planner to Insert)
Jean WhiteJean White
Open Issues: Need information
Receive information from Materials departmentDefine Intranet applications that will be need it at TIS-Beijing Any new reports for Kamex-online not currently availableDefine Windows desktop applications (in-house applications) Any new reports for Kamex-online not currently availableDefinition & Requirements for traveler sorting Document listing IT requirements for organizing sorting, and baggingDefinition & Requirements for Shipping documents Document with layout and requirement of what data elements are neededDefinition & Requirements for Customs documents Document with layout and requirement of what data elements are neededDefinition of documents required to provide Airbus Logistics Document with layout and requirement of what data elements are needed
Definition & Requirements for cycle counts and physical inventoryDocument containing process and procedure for KAMEX and LMS physical inventory and cycle counts
Define equipment that will be required (computers,printers,etc) Any new IT equipment and requirements for A350Define network folder access required for all TIS users (TIS-Beijing,TIS-Mexico, etc)
Any new access for A350 folders
Receive information from EngineeringDefine Intranet applications that will be need it at TIS-Beijing Any new reports for Kamex-online not currently availableDefine Windows desktop applications (in-house applications) Any new reports for Kamex-online not currently availableProcess definition for change management after design freeze Flowcharts illustrating details of process to be used to track changes List of blanket pns per CI for each MSN CSV or Excel files of part numbers and revision informationList of blankets per design solutions for each MSN CSV or Excel files of part numbers and revision informationDefinition of process to track first articles at two production locations (Placas-Kamex)
Flowchart of proposal
Definition of any IT requirement for blanket installation to aircraft Document for IT listing data requirement for installationDefine equipment that will be required (computers,printers,etc) New equipment requirements, A350Define network folder access required for all TIS users (TIS-Beijing,TIS-Mexico, etc)
Any new access for A350 folders, files
Jean WhiteJean White
Open Issues: Need information
Receive information from Manufacturing & Production Control
Define Intranet applications that will be need it at TIS-Beijing Any new reports for Kamex-online not currently availableDefine Windows desktop applications (in-house applications) Any new reports for Kamex-online not currently availableDefinition & Requirements for labels for blankets Printers and software neededValidation of existent Production Travelers and request changes Document listing traveler requirements A350Define equipment that will be required (computers,printers,etc) New equipment requirements, A350Define network folder access required for all TIS users (TIS-Beijing,TIS-Mexico, etc)
Any new access for A350 folders, files
Baan access requirements Any new requirements A350Receive information from QualityDefine Intranet applications that will be need it at TIS-Beijing Any new reports for Kamex-online not currently availableDefine Windows desktop applications (in-house applications) Any new reports for Kamex-online not currently availableDefine equipment that will be required (computers,printers,etc) New equipment requirements, A350Define network folder access required for all TIS users (TIS-Beijing,TIS-Mexico, etc)
Any new access for A350 folders, files
Baan access requirements Any new requirements A350Receive information from HRDefine Intranet applications that will be need it at TIS-Beijing Any new reports for Kamex-online not currently availableDefine Windows desktop applications (in-house applications) Any new reports for Kamex-online not currently availableDefine equipment that will be required (computers,printers,etc) New equipment requirements, A350Define network folder access required for all TIS users (TIS-Beijing,TIS-Mexico, etc)
Define network folder access required for all TIS users (TIS-Beijing,TIS-Mexico, etc)
Receive information from FinanceDefine Intranet applications that will be need it at TIS-Beijing Any new reports for Kamex-online not currently availableDefine Windows desktop applications (in-house applications) Any new reports for Kamex-online not currently availableDefine equipment that will be required (computers,printers,etc) New equipment requirements, A350Cost accounting requirements Document identifying any Baan configuration needed for accounting purposeCrystal report modifications Document identifying any Crystal report changes for A350
Jean WhiteJean White
Help Needed
Daher reporting to TIS needs to be definedCommunication among all entities needs definition
Risk/Mitigations
Key users to understand all aspectsKey users to test simulationKey users to train personnel
Jean WhiteJean White
CM Database Readiness
• BaaN Download
Airbus / Daher Readiness Review Page 58
Luis Valencia
Subject Expectations:• Plan Overview / Diagrams• Identify Key Team Members• Tools (Computer, Software…)• Training• Timeline• Open Issues• Risk / Mitigations• Help Needed
CM Database Readiness• General view of the Configuration Management Activities
Airbus / Daher Readiness Review Page 59
IRMAT ICC
TIS Configuration Database
BaaN
MOD/MP stacking
Supply Chain
Manufacturing
Red line activityDQN/ADCN
Sales order
Purchase order
New DS required ?
PDM link
MSNCILODSPNs
Create new LO-DS-PNs from DMU and
update LOs effectivity
Update LOs effectivity
No Yes
Update Part Number definition
IPM report.csv
MSNIPs
Link between P/N and IP
PNsIPs
AIR
BUS
TRIU
MPH IN
SULA
TIO
N SYSTEMS PN status :
Existing 2D Y/NADCN implemented Y/N
IP change implemented Y/N ...
Internal ?1
A
New part Numbers
A
MOD/MP impacted CIsMOD
CIs
Cabin Definition Freeze
CI/LO/DS MSN effectivity
MSNCILODS
MSNCILODSPNs
Customization process
Effectivity of IPs
BaaN
Stop order
Luis ValenciaLuis ValenciaLuis Valencia
CM Database Readiness
• Identify each MSN by a list of applicable changes (CINs).• Identify when a DS is needed for creation based on MOD stacking.• Tracking of IRs configuration changes.• ADCNs by part number follow up.• Output to Baan:
Comma delimited file containing 1)CI Kit part number with MSN number appended and 2) Blanket part numbers with quantities
Kits/blankets with engineering changes pending. (signal codes) Details to be determined.
• Provide PN status {Existing 2D; ADCN implemented; IP change implemented…}.
• Manually input of part number and IPs relationship.• Calculation and management of Engineering outstanding work (Delta 1
report).
Airbus / Daher Readiness Review Page 60
CM db expectations:
Status :
Ready to develop Process TBD Data is not enoughLuis ValenciaLuis Valencia
CM Database Readiness
TIS:Requirements and validation:• Martin Deschilder.• Michael Locht.• MEs/2D & 3D designers.• Jean White (Baan).
IT Support:• Oscar M.
Airbus / Daher Readiness Review Page 61
Key members:
Altran:CM Team:
• Gregory Hodoli.• Michael Constantine.
Airbus:PDM Link IT support:
• Diem Lam.
Luis ValenciaLuis Valencia
CM Database Readiness
Airbus / Daher Readiness Review Page 62
Task name Duration Start End Resources
CM db - Baan 15 days 6/7/2011 26/07/11 Luis Valencia Define the process flow and requirements between CM database and Baan.
4 days 7/7/2011 12/7/2011 Jean White, Jing, Luis Valencia
Work on CM database requirements raised from step 1. 5 days 13/07/11 19/07/11 Luis Valencia Work on Baan requirements raised from step 1. 5 days 13/07/11 19/07/11 Jean White Testing the final process. 3 days 20/07/11 22/07/11 Jean White, Luis Valencia Implementation/Release phase. 2 days 25/07/11 26/07/11 Jean White, Luis Valencia
Nombre de tarea
CM db - BaanDefine the process flow and requirements between CM database and Baan.Work on CM database requirements raised from step 1.Work on Baan requirements raised from step 1.Testing the final process.Implementation/Release phase.
Jean White,Jing,Luis Valencia
Luis Valencia
Jean White
Jean White,Luis Valencia
Jean White,Luis Valencia
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12mar 05 jul vie 08 jul lun 11 jul jue 14 jul dom 17 jul mié 20 jul sáb 23 jul mar 26 jul
Time line:
Notes:• This timeline is considering the basic needs from CM db and Baan interaction.• While the CM db is being completed, the output needed from it will be
maintained manually.Luis ValenciaLuis Valencia
• Delphi Embarcadero is needed to develop the user interface.• We are waiting for ICC access from Airbus (not files but user e-site).• Pending PDM data from Diem Lam at Airbus.• CIN (MOD/MP) data are deprecated from the *.xml files from PDM.• Optional: Access to Airbus Allocation Table (AAT) data.
Airbus / Daher Readiness Review Page 63
CM Database Readiness
Open issues
CM dbInput Output
IPM:• *.csv files from Airbus Brackets place.
PDM Link:• *.xml files from Airbus fts site.
ICC:• MOD-CI relationship.
• Tracking of all MOD/MP per MSN.• Define impacted CI and DS per MSN by CIN.
• Configuration per MSN detailed per CI, DS, PNR, IP.
• Planning of CR (Change Request) impacts in accordance to TRS.
• Tracking of all change impacts due to DQN, NC, ADCN.
• Part number effectivity control/traceability (backwards).
Status :
Ready to develop Process TBD Data is not enoughLuis ValenciaLuis Valencia
• The starting data will be manually updated while the CM db is being performed.
Airbus / Daher Readiness Review Page 64
CM Database ReadinessRisk and mitigations:
Luis ValenciaLuis Valencia
Business Flow
Airbus / Daher Readiness Review Page 65
Jesus Castellanos
Front End Production DeliveryInstall
Forecast ME FAI
Invoice
Subject Expectations:• Diagrams• Identify Key Team Members• Tools (Computer, Software…)• Training• Open Issues• Risk / Mitigations• Help Needed
Business Flow
Airbus / Daher Readiness Review Page 66
Jesus Castellanos
Forecast
Material Order
Production Order
Sales OrderK/N and KOD
Production Order Internal
Work order / Daher
Material OrderingResource
ToolLogistic
Engineer
Defi
nitio
n
GBO
M
Supp
ly C
hain
Proj
ecte
d KO
D
Eng.
Fre
eze
Location Define
Material
Nesting
Define Blankets brackets Assy
Jesus Castellanos
Jesus Castellanos
Business Flow
Airbus / Daher Readiness Review Page 67
IRMAT ICC
TIS Configuration Database
BaaN
MOD/MP stacking
Supply Chain
Manufacturing
Red line activityDQN/ADCN
Sales order
Purchase order
New DS required ?
PDM link
MSNCILODSPNs
Create new LO-DS-PNs from DMU and
update LOs effectivity
Update LOs effectivity
No Yes
Update Part Number definition
IPM report.csv
MSNIPs
Link between P/N and IP
PNsIPs
AIR
BUS
TRIU
MPH IN
SULA
TIO
N SYSTEMS PN status :
Existing 2D Y/NADCN implemented Y/N
IP change implemented Y/N ...
Internal ?1
A
New part Numbers
A
MOD/MP impacted CIsMOD
CIs
Cabin Definition Freeze
CI/LO/DS MSN effectivity
MSNCILODS
MSNCILODSPNs
Customization process
Effectivity of IPs
BaaN
Stop order
Jesus Castellanos
Jesus Castellanos
CM Database diagram
Airbus / Daher Readiness Review Page 68
STARTInfo on shipping structure
Info on materials per section
Determine contract structure
Submit for approval
Establish window frame for
approval
Contract
Approved?
Yes No
Ship
under contract
Determine $ to be
Paid tax/duties
ENDJesus
CastellanosJesus
Castellanos
Log – Mat Processing Contract Diagram
Business Flow
Airbus / Daher Readiness Review Page 69
Start
Identify CSR’s
Communicate CSRs
To potential
Logistics partner
L.P. meets
Requirements?
Yes No
R.F.Q.
ProcessOther options
Evaluation process
1Jesus Castellanos
Jesus Castellanos
Logistic Partner Definition Process Diagram
Business Flow
Airbus / Daher Readiness Review Page 70
Evaluation
Formal agreement
(Contract)
Development of
Working plans
Assure compliance
With Airbus requirements
As per logistics reqs
V258ORQ900688_V2
Establishment of
KPIs
Process
Evaluation
END
1
Jesus Castellanos
Jesus Castellanos
Logistic Evaluation Process Diagram
Business Flow
Airbus / Daher Readiness Review Page 71
Start Parts Installed
Fill the CI format testifying
that went well
Left? Document “Gaps”/rejections
ADCN Process
End
Yes
No
Jesus Castellanos
Jesus Castellanos
First Article Inspection Diagram
Business Flow
Airbus / Daher Readiness Review Page 72
Jesus Castellanos
Jesus Castellanos
ADCN Process
Business Flow
Airbus / Daher Readiness Review Page 73
AIRBUSA350
Purchase Order for KIT (CI)
Sales OrderFor Kit (CI)
(SO initially to TIS)
EBOM copy Kit (CI) to Project
Sales Forecast MRP-DRP
Travelers Released for Kit Kamex or Placas
Mat. Purchase Orders
Mat. Replenishment
Orders
Raw Material Main Whse
Raw Material WIP Whse
MaterialsBackflush
Purchase Order to Daher for Kit or
Blankets
QA Plant Clearance
Check customer PO Kits
QA Production Order Final Inspection
Manufacture
Report to TIS Kit transactions
7/10/2011
ERP Business Flow per Kit
Kamex Mat Warehouse
TIS CM database
CI pn and blankets
download from CM DB
Upload Kit to Baan Engineering item
and Eng BOM
Kit to Buid at Daher?
Print documents Ship Kit to Daher
PO Receipts in Baan
Purchase Order to Daher for Kitting and Installation
Kamed Wip Warehouse
DAHER St Nazaire:Kitting and
Manufacturing
Install blankets at Hamburg, St Nazaire and
Toulouse
Kit “Maintain Delivery” at
Installation sign off
Invoice to AirbusPayment to Daher
Business Flow
Airbus / Daher Readiness Review Page 74
Business Flow
Jesus Castellanos
Jesus Castellanos
LMS qualification and Site Qualification Diagram
Airbus / Daher Readiness Review Page 75
Business Flow
Jesus Castellanos
Jesus Castellanos
Master Schedule
Airbus / Daher Readiness Review Page 76
Business Flow
Jesus Castellanos
Jesus Castellanos
Reverse Engineering Diagram
Airbus / Daher Readiness Review Page 77
Business Flow
Jesus Castellanos
Jesus Castellanos
Data Entry Diagram
Airbus / Daher Readiness Review Page 78
Business Flow
Jesus Castellanos
Jesus Castellanos
Customer Service Diagram
Business Flow
Airbus / Daher Readiness Review Page 79
Area Leader Key Team MembersWolf Ebel
Stefan ReimMartin Deschilder
Jean WhiteJing Ping
Alejandro DelgadilloRenato Torres
Bjorn SchneiderBernhard Schueler
Miguel UribeHarold Alvarez
Jing PingAlejandro Delgadillo
Luis ValenciaCarlos NavarroDaniel JimenezAlfredo TorresMicheal LocthRocio Godinez
Martin DeschilderBernhard Schueler
Jose Luis CruzMiguel Uribe
Harold AlvarezLuis Valencia
Carlos NavarroMartin Deschilder
Jing PingMauricio Camacho
BIZ Jesus CastellanosLuis ValenciaMicheal Locth
Martin DeschilderJacobo Felix
Jesus MorenoMicheal Locth
Martin DeschilderHarold AlvarezCarlos NavarroMartha CastroJesus SolteroRocio Godinez
Project Timeline Jesus Castellanos Team
Validate Complete ADCN Rocio Godinez
Master Schedule Jacobo Felix
IT Engineering Oscar Magana
Re Engineering Rocio Godinez
Data Entry Carlos Garcia
KAMEX Readiness Jesus Castellanos
FAI Mariano Velarde
GBOM Rocio Godinez
BaaN Jean White
ME Sync Patricia Ramirez
Template Rick Molus
Master Schedule Tracy DeCuir
CMDB - BaaN Luis Valencia
Olga Reyes
Mariano VelardeDAHER LMS qualification
Logistic
Jesus Castellanos
Jesus Castellanos
Identify Key Members
Business Flow
Airbus / Daher Readiness Review Page 80
Jesus Castellanos
Jesus Castellanos
Tools
1. All team members must have access to common folder of timeline
2. Microsoft project license must be available for all team members managing a
portion of the timeline
3. Catia V5 for all new hired designers and drafters
Business Flow
Airbus / Daher Readiness Review Page 81
Jesus Castellanos
Jesus Castellanos
Training
1. Training in the way of working 2D 2 definition
2. Training in the way of working 2D 4 definition
3. Microsoft Project - Timeline managing training must be completed
Business Flow
Airbus / Daher Readiness Review Page 82
Jesus Castellanos
Jesus Castellanos
Open Issues
1. Way of working 2 D 2 definition not completed
2. Way of working 2 D 4 definition not completed
3. Integrate customer service team member and define tasks
4. Logistic partner flow must be approved as defined
5. Data entry flow chart must be modified accordingly needs of this project
Business Flow
Airbus / Daher Readiness Review Page 83
Risk Department ResponsibleEngineering designers head count will be required Engineering TBDOvertime will be required to approve ECO-ADCN's Engineering TBDLong time learning curve for kamex in regular production KAMEX TBDQA for FAI needs to happen along the manufacture to dismiss gaps for deliveries Quality TBDWe have not defined if all templates will be blankets or paper Engineering TBDWay of working for 2D 2 Def has a long time to be shared Engineering TBDWay of working for 2D 4 Def needs to be defined before releasing info to develop this 4 def of designEngineering TBDAll IT issues, connectivity, softwares, accesses must work at 100 % all the time IT TBDFinancial terms are not defined for samples and 4 def blankets Financial TBD
Production and engineering Support must be have presence in KAMEXProduction Engineering
TBD
Personnel qualified must attend the templates installation Engineering TBDME SYNC must be define to start up the 4 def design and ME Engineering TBD
Jesus Castellanos
Jesus Castellanos
Risk and Mitigations of Project
Business Flow
Airbus / Daher Readiness Review Page 84
1. Business flow sessions must take place to set ERP system IT
2. All team work sessions must take place to completely understand business flow
3. Team needs to have live presence with KAMEX to define challenges
Jesus Castellanos
Jesus Castellanos
Help Needed
Closing
• Airbus
Airbus / Daher Readiness Review Page 85
Tracy DeCuir
Airbus / Daher Readiness ReviewJuly 11-12, 2011
Day 1
Airbus / Daher Readiness Review Page 86
Presented by
Gilles CesconA350 XWB Chief Engineer Systems
Agenda
Tuesday, July 12, 20119:00 Quality Updates Mariano Velarde
Daher Supplier QualificationLMS QualificationFAI – Factory/Installation
10:00 Master Schedule Jacobo Felix11:00 Engineering Readiness Rocio Godinez
Staffing & IT Data EntryADCN Plan Validation
11:30 Logistic Plan / Readiness Olga Reyes12:00 Lunch1:30 KaMEX Readiness Jose Burboa2:00 Project Timeline Jesus Castellanos 2:30 Actions Items Jesus Castellanos 3:00 Closing / Next Steps Tracy DeCuir
Airbus / Daher Readiness Review Page 87
Quality Updates
• Daher Supplier Qualification• LMS Qualification• FAI – Factory/Installation
Airbus / Daher Readiness Review Page 88
Mariano Velarde
Subject Expectations:• Plan Overview• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Training• Open Issues• Risk / Mitigations• Help Needed
Master Schedule
Airbus / Daher Readiness Review Page 89
Jacobo Felix
CI / KIT
Build Blanket
Buy blanket Daher
Pull from stock (5)
Kit Assy
Install Daher Kit
Production Order
Purchase Order
Warehouse Order
Project Order
Service Order (KODD)
Logistic Order
Subject Expectations:• Plan Overview / Diagrams• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Training• Open Issues• Risk / Mitigations• Help Needed
Engineering Readiness
• Staffing & IT• Data Entry
Airbus / Daher Readiness Review Page 90
Rocio Godinez
Subject Expectations:• Plan Overview / Diagrams• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Training• Open Issues• Risk / Mitigations• Help Needed
ADCN Plan Validation
Airbus / Daher Readiness Review Page 91
Rocio Godinez
Subject Expectations:• Plan Overview / Diagrams• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Training• Open Issues• Risk / Mitigations• Help Needed
Logistic Plan / Readiness
Airbus / Daher Readiness Review Page 92
Olga Reyes
Subject Expectations:• Plan Overview / Diagrams• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Training• Contracts?• Open Issues• Risk / Mitigations• Help Needed
Plan Overview/Diagrams
Airbus / Daher Readiness Review Page 93
General aspects:
• MPC status for import and export activities China
• Raw Material/Finished Goods flows
established in coordination with Procurement
• Logistics Partner Definition• TIS / Daher Interaction
• Associated Transactions• Customer Requirements Compliance
based on Logistics Requirements as per Airbus’
V258ORQ900688_V2 A350 XWB Applicability
Olga ReyesOlga Reyes
Diagrams:
Material Processing Contract
START
Info on shipping structure
Info on materials per section
Determine contract structure
Submit for approval
(Chinese authorities)
Establish windowframe for
approval
Contract
Approved?
No
Determine $ to be
Paid tax/duties
END
Yes
Ship R.M.
Under contract
Olga ReyesOlga Reyes
Flow charts
• Raw material flow
Kamex Beijing:
Raw material
consignment stock
EU Suppliers-France
-Germany
USA suppliers
45 days
7 days
TIS Procurement Planning
Distribution center/LMS
SNZ
LMS TLS
LMS HAM
Drop Ships
HOV RM
45 days
Drop Ships
HOV RM
45 days
1 day
1 day
45 days45 days
Olga ReyesOlga Reyes
Flow charts
• Raw Material in LMS
LMS
Saint Nazaire
Forward stocking location
Blankets
Raw Mat
Blankets
Raw Mat
HAM
TLS
A350 Assembl
y
Install Sites
Olga ReyesOlga Reyes
Flow Charts
• Finished Goods flow
Airbus HAM
Airbus TLS
Airbus SNZ
Kamex Beijing
Truck to port
1 day
45 days
Manufacturing lead time
D.C./LMS SNZ
LMS TLS
LMS HAM
Install site
Install site
Install site
5 days
Olga ReyesOlga Reyes
Diagrams:
Logistics Partner Definition
Start
Identify CSR’s
Communicate CSRs
To potencial
Logistics partner
L.P. meets
Requirements?
Yes No
R.F.Q.
ProcessOther options
Evaluation process
1Olga ReyesOlga Reyes
Diagrams:
Evaluation Process
1
Evaluation
Formal agreement
(Contract)
Development of
Working plans
Assure compliance
With Airbus requirements
As per logistics reqs
V258ORQ900688_V2
Establishment of
KPIs
Process
Evaluation
END
Olga ReyesOlga Reyes
Key Team Members
Airbus / Daher Readiness Review Page 100
• RENATO TORRES – TIS Supply Chain Director• BJORN SHNEIDER – TIS Logistics Europe
• MANUEL STRATTA –TIS Mexico Materials Manager• BERNHARD SHUELER - Kamex General Manager• OLGA REYES L. – TIS Logistics Coordinator
Olga ReyesOlga Reyes
• Customs software for ChinaCurrently in review by Rico Wang, Kamex
Airbus / Daher Readiness Review Page 101
Tools
• Hardware/software definition for LMSs Currently in review by IT
• Airbus supply chain Hub Set up of compatible links and interfaces
Currently in review by IT GTC’s to access and use Airbus’ Supplier Portal,
separate agreement to be signed by both parties
• RFID Use to be defined by AirbusOlga ReyesOlga Reyes
Timeline
-
Olga ReyesOlga Reyes
Training
Olga ReyesOlga Reyes
Contracts
Logistics conditions between Airbus and Triumph Contract Ref: MSA X2580CT0900784 WPA V2580CT0900832
- Reviewed by TIS Logistics - Compliance matrix generated - Signature by TIS management pending
Olga ReyesOlga Reyes
Open issues
• Logistics Conditions contract approval • Logistics partner definition based on quotes and evaluation• Packaging units acquisition• KPIs establishment in conjunction with Quality• Secondary and return flow review
Olga ReyesOlga Reyes
Help needed
• Material per section (barrel) definition Being worked by Engineering
• Review of data transmission requirements Being worked by IT
Olga ReyesOlga Reyes
Airbus / Daher Readiness Review Page 107
Lunch
KaMEX Readiness
Airbus / Daher Readiness Review Page 108
Jose Burboa
Subject Expectations:• Plan Overview / Diagrams• Identify Key Team Members• Tools (Computer, Software…)• Timeline• Training• Open Issues• Risk / Mitigations• Help Needed
Project Timeline
Airbus / Daher Readiness Review Page 109
Jesus Castellanos
Subject Expectations:• Plan• Open Issues• Risk / Mitigations• Help Needed
Project Timeline
Airbus / Daher Readiness Review Page 110
ID WBS Task Name Duration Start Finish PredecessorsResource Names
285 7 A350 / Daher Schedule 201 d? Mon 7/4/11 Mon 4/9/12 Tracy DeCuir
286 7.1 CMDB - BAAN 15 d Wed 7/6/11 Tue 7/26/11 Luis Valencia
296 7.2 Logistics 62 d Mon 7/4/11 Tue 9/27/11 Olga Reyes
336 7.3 Daher Qualification LMS qualification 20 d Tue 7/5/11 Mon 8/1/11 Mariano Velarde
337 7.3.1 Daher Qualification 20 d Tue 7/5/11 Mon 8/1/11 M. Uribe
357 7.4 BAAN 36 d Wed 7/6/11 Wed 8/24/11 Jean White
393 7.5 ME SYNC 24 d Tue 7/26/11 Fri 8/26/11 Patricia Ramirez
412 7.6 Templates 2nd phase 85 d Wed 7/6/11 Tue 11/1/11 Rick Molus
450 7.7 Material Template MSN 1 - 6 1 d? Tue 7/5/11 Tue 7/5/11 Renato Torres
460 7.8 KAMEX Readiness 43 d? Thu 7/7/11 Mon 9/5/11 Jose Burboa
482 7.9 First Article Inspection Quality 164 d Wed 7/27/11 Tue 3/13/12 Mariano Velarde
517 7.10 G BOM 1.2 d Wed 7/6/11 Thu 7/7/11 Rocio Godinez
522 7.11 Engineering IT Fix 1 d? Mon 7/4/11 Mon 7/4/11 Oscar Magana
523 7.12 Biz Flow 13 d Thu 7/7/11 Mon 7/25/11 Jesus Castellanos
527 7.13 Reengineering 143 d Fri 8/26/11 Tue 3/13/12 Rocio Godinez
544 7.14 Data Entry 163 d Mon 8/1/11 Wed 3/14/12 Jesus Moreno
579 7.15 Validate Complete ADCN 149 d Thu 8/11/11 Tue 3/6/12 Rocio Godinez
649 7.16 Master Schedule 201 d Mon 7/4/11 Mon 4/9/12 Jacobo Felix
763 7.17 Project Timeline 5 d Mon 7/4/11 Fri 7/8/11 Jesus Castellanos
Oscar Magana
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayQtr 3, 2011 Qtr 4, 2011 Qtr 1, 2012 Qtr 2, 2012
Jesus Castellanos
Jesus Castellanos
Plan
Project Timeline
Airbus / Daher Readiness Review Page 111
Jesus Castellanos
Jesus Castellanos
Open Issues
1. Definition of blankets or templates needs to be clarified
2. Overtime will be required to comply with the approval and design after ADCN
process
3. Timeline needs to be discussed with our team in Europe
4. Logistic partner must be defined ASAP, and include European participants
5. Way of working of 2d 2def must be immediately defined
6. The timeline is in compliance with Martin Deschilder timeline – Needs review
7. Head for engineering must increase from 10 to 18 resources
8. There are deliveries out of the targeted date
Project Timeline
Airbus / Daher Readiness Review Page 112
Jesus Castellanos
Jesus Castellanos
Risk and Mitigations
1. Airbus latest ramp up file is not available
2. Accordingly airbus ramp up we are out of schedule
3. Europe activities must be clearly defined for the reengineering process
4. MSN 1 templates of FWD crown and upper side wall deliveries are out of
targeted date
5. Cross training must take place for Daher and TIS for the ME SYNC
6. Workshop with Daher must take ASAP
7. Direct communication within eng. responsible is not possible at this time
8. ADCN approval process must be automated
Project Timeline
Airbus / Daher Readiness Review Page 113
Jesus Castellanos
Jesus Castellanos
Help Needed
1. Support will be required to chase information within all entities
Actions Items
Airbus / Daher Readiness Review Page 114
Item12
3
45
6
7
89
10
11
12
13141516
17
181920212223242526
27
28
29
30
31
323334
Increase Internet used at TIS-Germany to connect VPN to Mexico from 2MB to 6MB. ECD end of July
Replace legacy switches and configuration of VLAN for Airbus computers. ECD July the 24thInstallation of Airbus computers & printers (CATIA, AutoCad & Airbus suite). ECD July the 4th
Validation of Airbus Cache proposal for VPM starts July the 4th to July the 15th ;following Airbus recommendations (feedback from Engineering is required)
Quotation project proposal from Aster (external company). Waiting for sample file from Engineering.
Define if templates will be blankets or paper
Solve label printing problems KAMEX
Implement Power Emergency Plant
Solve performance problems of Warehouse with Controlled Humidity and Temperature.
Solve IT room problems. KAMEX
Increase 2 to 6 megs speed in Network
TasksInstallation of Fiber optic at TIS-Mexico. TIS-Mexico VPN connection to Germany from 2MB to 6MB.
ResponsibleOscar MaganaOscar Magana
Computers, access and e mail accounts for personnel needed to define location and namesImprove the program Cover fiber (have correction)Catia Licences for Victorreset VPN accountsSoftware delphi required for CM database (follow up)
Harold movement to design areaUpdate for software download for A350 - Suite 5.3 RU1Solicite Baan password for Patricia Ramirez and define access
Review additional tools or equipment at Kamex based on Daher ME definition. Acquire Aline Thermal Impulse Machine. Define if we need tape cutters. Call to a meeting for label printing
Solve general air conditioning issues. KAMEX
Engineering desginers hiring processGet and obtain way of working 2D 2nd phase Close cage of MRB area for traveler storage (quality reads)
We need to define the quantity of material for the Forward Section 13/14, Crown 56 blankets // and Upper side wall 112 P/N def2 P6-P18 LH+RHevaluate with Emmanuel Hernandez3 SS will pax taxes to get to KAMEX (impo/expo) Total taxes for approval $ 40,000 USDCreate nesting for FWD section 13/14 crown to know the needs of material to provide feedback to EmmanuelADCN ECO approval process lead time needs to be improved to at least 5 daysWhat do we need to keep in track for the templates manufacture in the ERP system (Ask Tracy)what financial trasactions will be covered for this templates, PO from customer, and details.
Oscar MaganaOscar Magana
Rick Molus JL. Cruz /
Castellanos
B. ShcuelerCastellanos
Oscar Magana
Oscar MaganaOscar Magana
Oscar Magana
Oscar Magana
Oscar MaganaOscar MaganaOscar MaganaRocio GodinezOscar Magana
Paty RamirezAlfredo TorresDaniel Jimenez
Jacobo Felix
B. ShcuelerCastellanos
Renato Torres
Luis Valencia
Rocio Godinez
Castellanos
Suzana Rivas
A. DelgadilloOscar MaganaOscar MaganaOscar Magana
Luis Valencia
8-Jul-118-Jul-118-Jul-11
11-Jul-11
COMPLETED
ECD18-Jul-1122-Jul-11
22-Jul-11
24-Jul-11COMPLETED
COMPLETED
COMPLETED
TBDTBD
11-Jul-11
11-Jul-11
8-Jul-11
Michael locthB. Schueler
COMPLETED18-Jul-11
COMPLETED
8-Jul-11
COMPLETED8-Jul-11
COMPLETED11-Jul-1118-Jul-11
8-Jul-11
COMPLETED
11-Jul-11
8-Jul-11
In process18-Jul-11Jesus
CastellanosJesus
Castellanos
Closing / Next Steps
Airbus / Daher Readiness Review Page 115
Tracy DeCuir