ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
INTRODUCTIONS
Todd McCabeProject Executive
John LaMarreSenior Project Manager
Consigli Team Leadership
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
AGENDA
• Owner’s Project Manager• Consigli Goals• Construction Mitigation• February – July Construction Activities
• Student Drop-Off & Pick-Up• Pedestrian Access• Construction Access
• Project Information• Questions
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
OWNER’S PROJECT MANAGER
Jim BurrowsProject Manager
Victoria CliffordProject Engineer
Hal RaymondSite Representative
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
CONSIGLI GOALS
• Safety for Students & Workers• Minimize Disruption to School & Community• Proactive Communication
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
CONSIGLI MITIGATION
Separation of Construction Activities• Establish perimeter fencing at construction areas
• Build protective barriers and covered walkways to/from existing school entrances/exits as necessary
• Perform noise and air quality monitoring
• Establish clear wayfinding signage inside & outside of school
• Management for pest control by 3rd party company
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
Communication• Participate in school safety drills
• Provide weekly construction updates
• Full-time Consigli mitigation manager; one point of contact with Skanska and AHS
CONSIGLI MITIGATION
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
Construction Worker Management• Perform background checks on workers (CORI)
• Utilize hard hat IDs/badging systems to clearly identify authorized workers
• Enact and enforce zero tolerance policy for safety and fraternization
• Coordinate all deliveries around school activities
CONSIGLI MITIGATION
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
• Basketball courts converted to parking
• Softball, Baseball, Peirce Practice are not available
• No impacts to Peirce Turf Field
• Mass. Ave. front green offline
• Drop-off and pick-up traffic patterns
• Pedestrian walking routes
SPRING 2020 CONSTRUCTION IMPACTS
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
STUDENT DROP-OFF & PICK-UP: MARCH 2020VEHICLES
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
PEDESTRIAN ACCESS: MARCH 2020PEDESTRIANCONSTRUCTION
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
STUDENT DROP-OFF & PICK-UP: APRIL 2020 VEHICLES
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
PEDESTRIAN ACCESS: APRIL 2020PEDESTRIANCONSTRUCTION
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
STUDENT DROP-OFF & PICK-UP: MAY–JUNE 2020VEHICLES
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
PEDESTRIAN ACCESS: MAY - JUNE 2020PEDESTRIANCONSTRUCTION
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
ACCESS: JULY 2020PEDESTRIANCONSTRUCTION
VEHICLES
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
ACCESS: SEPTEMBER 2020PEDESTRIANCONSTRUCTION
VEHICLES
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
SIGNAGE EXAMPLES
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
Wheel Wash Station On Site Dust Control Measures
DUST CONTROL
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
GEOTHERMAL WELL INSTALLATION
• Two test wells prepared in February
• March-April installation starts
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
COVERED WALKWAY
ARLINGTON HIGH SCHOOL BUILDING PROJECT 2/4/2020
PROJECT INFORMATION
Sign Up for Weekly Construction Updates:
www.ahsbuilding.org
Questions & Concerns:
For Immediate On-Site Assistance:
Hal Raymond, Site Representative, Skanska
(617) 352-8593