agile planning with rational team concert
TRANSCRIPT
Agile Planning with Rational Team Concert (RTC)
Reedy Feggins JrAgile Coach / CSM / WW Solution Architect
December 1, 2014
2
Rational Software
Overview
� Agile planning is one of the key strengths of RTC
� Supported Agile Practices
– Agile Planning (Product, Release and Sprint Planning)
– Whole Team (self-managed teams, sustainable pace, estimating)
– Shared Vision (Project Transparency)
� Demo
– In this webinar, see how to get started with RTC Agile Planning,as well as tailoring plans to suit your needs
3
Rational Software
QueryStorage
Collaboration
Discovery
Administration: Users, projects,
process
JAZZ SERVICES
Business Partner Extensions Your Extensions
Rational Developer for z
Rational Software Architect
Rational Systems Developer
Rational Business Developer
Rational Developer for i
Eclipse Clients Web Clients
Visual Studio
Microsoft .NET Clients Rational Desktop Clients
Rational Team Concert
Web 2.0Jazz Client Extensions
Eclipse Platform
IBM Rational Extensions
Best PracticesPresentation:
Mashups
Rational Team Concert: An open, extensible architectureSupporting a broad range of desktop clients, IDE’s and languages
4
Rational Software
Rational Team Concert User Interfaces
Feature RTC Eclipse Client
RTC Visual Studio Client
RTC Web Client
SCM Command Line
Source ControlYes Yes
View, Upload, Download
Yes
IDE Integration Yes Yes No No
Work Item Management
Yes Yes Yes No
Planning Yes Yes(Embedded Web UI)
Yes No
Build Yes Yes Yes No
Reports Yes(Embedded Web
UI)
Yes(Embedded Web UI)
Yes No
Dashboards Yes(Embedded Web
UI)
Yes(Embedded Web UI)
Yes No
5
Rational Software
Agile Teams
5
Open Lifecycle and Service Management Integration Platform
Continuously Integrate
Define Vision
Leverage Agile Practices
Rational Team Concert. Integrated by Design
Plan and Track Projects Manage Change
StakeholdersProduct Owners
The Rational solution for Agile ALMIntegrated capabilities to support your agile delivery needs
6
Rational Software
The Rational solution for Agile ALMIntegrated capabilities to support your agile delivery needs
6
Open Lifecycle and Service Management Integration Platform
Rational Team Concert. Integrated by Design
� Agile Templates � In-tool Process Guidance
� Epics & User Stories� Product Backlogs
� Collaborative Source Code Management � Multi-level Build Automation
� Collaboration & Team Awareness
Leverage Agile Practices
Define Vision
� Release & Sprint Plans� Sprint Reviews &
Demos� Retrospectives
Plan and Track Projects Manage Change
� Dashboards & Reports
� Issues & Tasks� Defects & Risks� Impediments
Continuously Integrate
7
Rational Software
The Rational solution for Agile ALMAdopt components as your practice matures
7
Rational Team Concert. Integrated by Design
� Agile Templates � In-tool Process Guidance
� Epics & User Stories� Product Backlogs
Leverage Agile Practices
Define Vision
� Release & Sprint Plans� Sprint Reviews &
Demos� Retrospectives
Plan and Track Projects
Open Lifecycle and Service Management Integration Platform
� Collaboration & Team Awareness� Dashboards & Reports
Manage Change
� Issues & Tasks� Defects & Risks� Impediments
� Collaborative Source Code Management � Multi-level Build Automation
Continuously Integrate
Equip your teams with Scrum practices and tools
Add comprehensive change management Complete the solution with collaborative code and build automationEach component comes with the capabilities of Jazz
8
Rational Software
� Team advisor for defining / refining “rules”and enabling continuous improvement
� Process enactment and enforcement� In-context collaboration shows team
members and status of their work
� Single structure for project related artifacts� World-class team on-boarding / off-boarding
including team membership, sub-teams and project inheritance
� Role-based operational control for flexible definition of process and capabilities
Jazz Team Server
� Integrated stream management with flow relationships
� Component level baselines� Server-based sandboxes� Identifies component in streams
and available baselines� ClearCase connector
SCM (Version Control) Work Items� Defects, enhancements
and conversations� Query results view and share
queries with team or member� Support for approvals and
discussions� ClearQuest connector� Query editor interface
� Work item and change set traceability
� Local or remote build servers� Supports ant and command
line tools� Integration with Build Forge� Build definitions for team
and private builds
Build
Agile Planning� Integrated iteration planning and execution
� Task estimation linked to key milestones
� Out of the box agile process templates
Project Transparency� Customizable web based dashboards
� Real time metrics and reports
� Project milestone tracking and status
Rational Team Concert – Overview
9
Rational Software
Planning
10
Rational Software
Agile Planning Onion*
• Strategy – defines the vision associated with a business need or direction.
• Portfolio – defines the overall product offering that consists of applications and tools and how they integrate.
• Product – defines a product vision and outlines the road-map for the product.
Strategy
Portfolio
Product
Release
Iteration
Day
(*) Mike Cohn, Agile Estimating and Planning
11
Rational Software
Agile Planning Onion*
Product – defines a product vision and outlines the road-map for the product.
Release – represents a prioritized backlog of product features that are committed to be delivered inagiven time period.
Sprint / Iteration – defines short, fixed-length subsets of releases, typically 2-4 week time frame.
Day – represents the actions taken in a day to achieve the iteration goals.
Strategy
Portfolio
Product
Release
Iteration
Day
(*) Mike Cohn, Agile Estimating and Planning
Agile team plans at the innermost three levels. RTC offers support for all these levels
12
Rational Software
Rational Team Concert (RTC) Plan Definition
13
Rational Software
Rational Team Concert (RTC) Plan Definition
• Unified view of Information
– What - Work Items
– Who – Project Area / Team Area
– When – Iteration
• Plans are owned by a team or project and are associated with an iteration
• Plan content is derived fromAll work items which have a Filed Against value set to a category owned by the Plan’s team or project and are planned for plan’s iteration.
• Plans have a plan type, which define the layer in the planning “onion”.
14
Rational Software
TIP: Named Iterations vs Calendar-based Iterations
� Use calendar-based iterations when individual teams have their own sprint schedules that differ from other teams
� Lowest common denominator is the calendar
� All teams need to reach the same end point but get there at their own pace
� Use named iterations when all teams are sync’d to the same schedule
NOTE: •Iterations are displayed and sorted by name•Iterations with the same names will not be easily differentiated during selection•TRICK: Use a naming convention that makes selection easy!
15
Rational Software
Rational Team Concert (RTC) Planning Support
� Process neutral
– Out of box templates (works with Scrum, OpenUp, Formal Project Management)
– Customized templates
� No separation between planning/implementing of features and bug fixing
– Both planning and defect management share a common data model
– They are supported in the same tool and are highly integrated
– Plans are in fact a query for work items
� Supports:
– Top down planning (project manager, product owner, team leads, …) AND
– Bottom Up (team members) AND
– Plan consolidation (Sprint planning meetings, stand-ups, …)
16
Rational Software
What is a backlog?
� The product backlog is an ordered list of "requirements" that is maintained for a product.
� The release backlog is an ordered list of "requirements" that is planned for the next release.
� The sprint backlog is the list of work the Development Team must address during the next sprint.
– The stories/features are broken down into tasks by the Development Team
– Tasks on the sprint backlog are never assigned; rather, tasks are signed up for by the team members
Product ‘Backlog’ iteration(no dates)
Sprint ‘Backlog’ iteration
Release ‘Backlog’ iteration
TIP: Until a work item is actively being worked on it is really on ‘the backlog’ at some planning level
17
Rational Software
Planning Onion Layer: Product Backlog
• Prioritized feature list
• Plan Views• Ranked List• Work Breakdown
• Work Item Types• Plan items: Work items that are relevant forplanning. Ex: Epics, Stories, etc.
Product
Release
Iteration
Day
• Reports• How your product backlog is evolving?• How many items are there on the product backlog?• Can we find out how long it would take to complete the product backlog?
• Top down Planning
18
Rational Software
Managing a Product Backlog
• High-level plan that contains stories not planned for any release or iteration yet
• Targeted for the iteration marked as Backlog Iteration
• Prioritized feature list based on risk,business value, etc.
• Plan items – include only non executionitems such as Epics and Stories
• Customize with themes,business value, etc• Define the Done Criteria
19
Rational Software
Managing a Product Backlog
• Sizing in Story points - rough estimates based on complexity and development effort
• Ranking - ensure that the most valuable functionality is delivered first
TIP: Plans are an actionable interface. Drag and Drop, in-context editing and new work item creation are supported
20
Rational Software
Planning Onion Layer: Release Backlog
• Planned/Committed features for the release of the product
• Plan Views• Iterations• Ranked List• Roadmap• Teams• Traceability (optional)• Work Breakdown
• Work Item Types• Plan items: Work items that are relevant for theplanning. Ex: Themes, Epics and Stories
• Reports• Team Velocity
All the story points that were 'achieved' grouped by the iteration they were targeted for.• Release Burndown
Amount of outstanding work for the release, broken down by iteration.
• Top down Planning
Product
Release
Iteration
Day
21
Rational Software
Managing a Release Backlog
• Connects the business value and the execution items.
• Iterations view: holistic view of which stories are planned for which iteration.
• Drag and drop : assign the stories to specific iterations.
• Progress/Load bars: avoid overloading an iteration considering the team's velocity and to track overall progress.
• Coarse grained: Estimation in size; estimated in relative values such as Story Points, lines of code, function points, etc.
22
Rational Software
Managing a Release Backlog …
• Single view for all sprints in the release
23
Rational Software
• Overview for multiple teams
Managing Release Backlog …
24
Rational Software
Track progress
• Team velocity: measures a team rate of progress.• Completing 2 Stories of 5 story points in one iteration gives a velocity of 10• Good guess is to assume the same velocity for the next iteration
25
Rational Software
Planning Onion Layer: Sprint Backlog
• Tasks planned for the iteration
• Plan Views• Planned Time• RankedList• Roadmap• Taskboard / Kanban• Workbreakdown
• Work Item Types• Execution items: Work items which have work assigned. Ex: Task and Defect.
• Reports• Sprint Burndown
Estimated hours required to complete remaining work items.
Product
Release
Iteration
Day
26
Rational Software
Planning a Sprint
• Focus on Execution : large stories broken down into smaller sub-stories and execution items
• Fine grained: Estimation of effort: typically estimated in Ideal Hours/Days
• Custom view: Does the execution task rank relate to the business value expressed on the product backlog?
27
Rational Software
Planning a Sprint …
• Roadmap view: illustrates the schedule of the execution items (e.g. defects and tasks) and the rolled-up schedule of the plan items (e.g. stories and epics).
28
Rational Software
Planning a Sprint …• Taskboard view:
• shows plan items in the left column and execution items in the state group columns. • visualize the progress of the stories and their children.• ability to adjust the state quickly with drag and drop from this view.• color tags can be used to show the state of the plan items.
29
Rational Software
Planning a Sprint …• Kanban
• Define limits (counts or complexity or estimates).• Deviations from the ideal are shown as a small box in the column header. The further you are from your
ideal, the more red the box gets.• Shows where capacity is available as well as when capacity limits might be exceeded
30
Rational Software
Planning a Sprint …
• Load Bars : capacity planning• Do I have enough time to finish all my work in this iteration?
• Progress Bars : track progress• Considering all my work for this iteration. Where am I now?
Aids in assessment of the health of the Plan
31
Rational Software
Planning a Sprint …Quality of Planning:• The more work items you estimate the more precise the work can be computed.
• The quality is excellent if all work items are estimated, it is good if the majority is estimated, ...
• Visually, the percentage of estimated work items is represented as a fill-level.
• The height of load and progress bars shows how many work items have an estimate.
• If no work item is estimated, the bar is not visible, if all work items are estimated, the bar is fully visible.
32
Rational Software
TIP: Plans Are Fancy Queries & Queries Answer Questions
� Primary query/filter parameters are:
– Owner (i.e. Team)
– Iteration
– Plan item types or all items (Plan & Execution)
� Additional parameters for filtering, grouping and display can be defined in a Plan View
– Setup views to help answer specific questions or to draw attention to anomolies
Example:Verification
View
33
Rational Software
TRICK: Work Item Exclusion vs Inclusion in Plan Views
� Plan default is to EXCLUDE work items based on selected parameters
� Behavior is to show only current and future work, which burns down over time
Show work itemsthat includethis string
Exclude workitems meeting
this criteria
How manywork items are
not shown
Expression Syntax:type:Defect [Excludes]
!type:Defect [Includes]
34
Rational Software
TIP: Performance recommendations
� Large plans unmanageable
� Build simpler view modes (outsource other plan view modes into separate plans and link them together so that navigation is easier)
35
Rational Software
Planning Onion Layer in Rational Team Concert: Day
• My Work View : Developers plan their assigned work and adjust estimates• Managing new work
• Managing current work
• Managing future work
• Work Load
• Find, filter, and colorize planned work items
• Daily Stand ups : Developer Taskboard view to see what people are working on.
• Planned Time : Developers sort the work items in the order in which they intends to work onthem
• Bottom Up Planning
Product
Release
Iteration
Day
36
Rational Software
How does an individual developer work during a sprint?
• My work view: in place estimation, feeds, …
• Planned time view: Developers sort the work items in the order in which they intend to work on them in my work view.
• Warnings/errors are shown if the work is lagging behind the schedule
• My work view approximation in the web: Customized Planned Time View show a specific owner.
37
Rational Software
How does an individual developer work during a sprint? …
• One place to view queries that impact my work
38
Rational Software
Additional Information
� Effective Planning with Rational Team Concert 5.x
–https://jazz.net/library/article/594
� Cross-Project Tracking with Rational Team Concert, Version 5.x
–https://jazz.net/library/article/1152
39
Rational Software
Tips & Tricks: Summary
� A plan is an actionable interface
� Iterations
– Names vs Calendar
� Cross project planning
� Work Item Exclusion vs Inclusion
� Performance recommendations
– Large plans unmanageable
– Build simpler view modes (outsource other plan view modes into separate plans and link them together so that navigation is easier)
� Dashboards
– Dashboard in a plan
– Plan in a dashboard
� Additional information:
– Effective Planning with Rational Team Concert 5.x: https://jazz.net/library/article/594
40
Rational Software
CollaborationScaling Agile
© 2013 IBM Corporation
41
Rational Software
ScrumGet the team off to a fast start with pre-defined project artifacts
Roles, Dashboards, Plans and Work Items
created
Dashboard populated with widgets including burndown, velocity and
plan status
Commonly used Scrum and development work
items created
42
Rational Software
42
In-Tool Process GuidancePractice and tool guidance available at your fingertips
Links to process guidance are provided from within the RTC
work item
Comprehensive Scrum practice guidance supports the organization to deliver
consistent results
43
Rational Software
Agile planning linked to executionSpend your time deciding where to go, instead of determining where you are…
Project Estimating &
Tracking
Project Planning
EvolutionaryPlans
Tasks linked to execution
Real-time Status
StatusReporting
Business As Usual
Real-time Agile Planning
Ad-hoc estimating and manually intensive tracking
efforts
Self directed teams continuously plan their releases and sprints
Lengthy status meetings and reliance on email
All team members understand project status at any given time.
Estimates are integrated into the planning and tracking
process allowing for continuous improvement
43
Static plans in spreadsheets or disconnected tools
SpreadsheetsEmail
44
Rational Software
Multiple planning and tracking viewsMaximize team productivity with multiple planning views
44
Task Board
Kanban
Backlog Mgmt
45
Rational Software
45
Find all discussions and decisions
within the related task, including
instant messages.
Agile team collaboration and team awarenessCollaborate in real-time and in context of project work to maximize progress
Subscribe to work items that are impact your work
46
Rational Software
Collaborative source code managementCan your tool do this?
Easily suspend and resume work
Reproduce the exact workspace of any build
Work in parallel without making branch copies
Maintain copy of workspace on Jazz
server to assure changes are protected
Personal builds allow developers to test their code against the latest
baseline
47
Rational Software
47
Continuous build integrationKeep your builds healthy with Personal, Team and Integration builds
Stream based SCM allows multi-level
build that scales to Scrum of Scrums
Teams can see what builds there are,
inspect build results, monitor builds in
progress, and request builds at any time
Developers can compare builds to quickly
troubleshoot issues
48
Rational Software
48
Full Transparency for Project StakeholdersWeb interfaces allow the team to proactively manage risks
Open Lifecycle Integration Platform
Mini-Dashboard allows Managers to quickly see and act on issues or defects that could jeopardize the release
Track the throughput or “velocity” of
project teams
Visibility to which sprints and
releases are behind schedule
Track the throughput or “velocity” of project teams over time and remaining effort with “burndown” of projects in flight
49
Rational Software
© Copyright IBM Corporation 2012. All rights reserv ed. The information contained in these materials is provided for informational purposes only, and is provided AS IS without warranty of any kind, express or implied. IBM shall not be responsible for any damages arising out of the use of, or otherwise related to, these materials. Nothing contained in these materials is intended to, nor shall have the effect of, creating any warranties or representations from IBM or its suppliers or licensors, or altering the terms and conditions of the applicable license agreement governing the use of IBM software. References in these materials to IBM products, programs, or services do not imply that they will be available in all countries in which IBM operates. Product release dates and/or capabilities referenced in these materials may change at any time at IBM’s sole discretion based on market opportunities or other factors, and are not intended to be a commitment to future product or feature availability in any way. IBM, the IBM logo, Rational, the Rational logo, Telelogic, the Telelogic logo, and other IBM products and services are trademarks of the International Business Machines Corporation, in the United States, other countries or both. Other company, product, or service names may be trademarks or service marks of others.