TOM JOBIM INTERNATIONAL AIRPORT 01

NEW EXPERIENCETECHNOLOGY TO IMPROVE THE PASSENGER JOURNEY 02

RIO DE JANEIROFUTURE CHALLENGES 03

RIOGALEÃOTOM JOBIMINTERNATIONAL AIRPORT

ESTIMATED CAPEX:

US$1,5BI

CONTRACT LENGTH:

25 years

CONTRIBUTION:

+

5%OF GROSS REVENUE

US$5,2BI

OPERATION, MAINTENANCE, AND EXPANSION

OF TOM JOBIM INTERNATIONAL AIRPORT

51%49%

60%

40%

SHAREHOLDER STRUCTURE

Aircraft maintenance station for Code C, D, E & F

First airport in the country authorized to operate Code F aircraft flights

2 independent runways with the longest runway in Brazil (4000 m)

Terminal 1 and 2 area: 316.175m²

Airport area of 17 MM m²

PAX in 2014

17MM

Yearly average

passenger growth

14% in the last 10 years

Dist. from downtown

20km

Cities served

50in more than 20 countries

Busiest international

airport in Brazil

2nd

Busiest domestic

airport in Brazil

Busiest cargo

airport in Brazil

4th

4th

THE AIRPORT WITH THE MOST VISIBILITY

DURING THE WORLD CUP AND OLYMPICS

TWO LARGE SCALE EVENTS

IN 2016

AUG 5-21 SEPT 7-18

ATHLETES FROM 206 NATIONS11,000

VOLUNTEERS45,000

ACCREDITED MEDIA PROFESSIONALS 25,000

ATHLETES FROM 178 NATIONS 4,500

VOLUNTEERS 25,000

ACCREDITED MEDIA PROFESSIONALS 7,000

NEW EXPERIENCETECHNOLOGY TO IMPROVE THE PASSENGER’S JOURNEY

BCBP – BAR CODE BOARDING

PASS AND AUTOMATED PASSPORT CONTROL

TOTAL COMMON USE

CUTE AND CUSS

BEACONS MOBILE APP(WAYFINDING,

INFO, SURVEYS, OFFERS, INSTANT

FEEDBACK...)

MAIN TECHNOLOGY

BASED INVESTMENTS FOR

THE PASSENGER EXPERIENCE

AUTOMATED APRON

CONTROL

AIRPORT MANAGEMENT

SYSTEM

INTEGRATED SECURITY AND SITUATIONAL AWERENESS

MAIN TECHNOLOGY

BASED INVESTMENTS FOR

OPERATIONAL EFFICIENCY

QUEUE MANAGEMENT

RIO DE JANEIROFUTURE CHALLENGES

TRANSPORTATION

SYSTEM IN RIO

2009

7 YEARS LATER...

IN 2016

2017 to 2021

Construction of new independent

runway system expected

and beginning of Domestic East

Pier construction.

2022 to 2026

Expansion of east apron and

second phase of Domestic East

Pier construction.

2027 to 2031

Conclusion of east apron

expansion adding 20 new

apron stands

NEW CHALLENGES

PASSENGERS (2014)

17MM

EXPECTED PASSENGERS (2039)

+80MM