aerogeradores gigantes e queda de custos da energia ... · •50% menos parafusos três fundações...
TRANSCRIPT
Nordex N131/3300 Hub height 168m
GE 3.6/137 Hub height 178m
Enercon E141 4.2MW – Hub height 159m
Vestas V126-3.3 / 3.45 MW – Hub height 166m
Ricardo SavioAeronautical Engineer ITA
PhD Massachussets Institute of Technology20 Years in Aircraft Industry (EMBRAER, AIRBUS)
21 Years in Wind Industry6 Wind Technology Patents
Odilon CamargoAeronautical Engineer ITA
40 Years in Wind EngineeringFounder of Camargo Schubert, leading wind
consultancy in Brazil
Iñaki AltiAeronautical Engineer – UPM Madrid22 years in Intelectual Property Protection4 years in Aircraft Industry10 years in Wind Industry
Eneko SanzIndustrial Engineer13 Years in Wind Industry Innoblade Development18 Wind Technology Patents
> 15 years experience wind industry
> 35 patents
BACKGROUND
GENERALMANAGEREneko Sanz
MBJ PROGRAMMANAGER
Javier Callén
GENERAL SERVICESJose MaríaApesteguía
SENIORENGINEER
Cristina García
TECHNOLOGYHely
Ricardo Savio
BUSINESSDEVELOPMENT
Iñaki Alti
SENIORENGINEER
Javier Monreal
SENIORDESIGNER
Julián Vicente
SET PROGRAMMANAGER
Ion Arocena
SENIORDESIGNER
David Aranaz
ENGINEERING TEAM
STRESSMANAGERAndré Noel
DESIGNMANAGER
José Alberto Rojo
MATERIALSMANAGER
Emilio Rodríguez
SENIORENGINEER
Luis A. Mayor
SENIORDESIGNER
Oihan Elorriaga
SENIORENGINEER
Arantxa Esparza
SENIORENGINEER
Ana Fernández
SENIORENGINEER
Javier Iriarte
58
Good Poor
Modular Blade Joints Alternatives
Bonded T-BoltDouble
FittingBath Fitting
Strength
Mass & Cost
Assembly on
Site
Maintenance
Reliability
Source: MAKE
NABRAJOINT®
Competitors Analysis2
59
Good Poor
XXL Tower Alternatives
NABRALIFT®
Competitors Analysis3
Source: MAKE
Tubular
Steel
Segmented
Steel
Precast
Concrete or
Hybrid
Lattice
Tower Cost
Logistics
Assembly &
Erection
Modal
Coupling
Specialized
large crane
61
Soluções NABRAWIND x estado da arte 2018
REDUÇÃO FINAL NO LCOE – LEVELIZED COST OF ENERGY:
6%
nas condições européias de custo de aço, concreto, fabricação e logística