advanced(laboratory(tes1ng(methods( · pdf fileadvanced(laboratory(tes1ng(methods ... outside...
TRANSCRIPT
NREL is a na*onal laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, operated by the Alliance for Sustainable Energy, LLC.
Advanced Laboratory Tes1ng Methods Use Case: PHIL An*-‐islanding Tes*ng
DERlab/SIRFN Workshop
19 March 2015
Blake Lundstrom, P.E. Research Electrical Engineer Power Systems Engineering Center Na*onal Renewable Energy Laboratory (NREL) Golden, CO, USA
2
Outline
• Introduc1on to PHIL-‐based Uninten1onal Islanding Tes1ng
• NREL Experimental Implementa1on and Capabili1es o AC/DC amplifiers (NREL and U.S.) o Lab power ra*ng / grid level o Real-‐*me systems available o Interoperability (technical/communica*on/interface)
• PHIL UI Test Results • PHIL co-‐simula1on
3
Introduc1on – IEEE 1547 and UI
��������������
� ��������������
�
Figure 2.4: Unintentional islanding test circuit (Simplified version of Figure 2 of IEEE Std1547.1 [39])
IEEE Std 1547.2-2008 [30] fills that gap by providing very detailed information as to the
interpretation, background, and impact of each requirement in IEEE Std 1547-2003 as well
as application guidance, tips, techniques, and rules of thumb to aide implementation of each
requirement. For example, IEEE Std 1547-2003 provides only a simple statement regarding
the requirement regarding voltage regulation: “The DR shall not actively regulate the voltage
at the PCC. The DR shall not cause the Area EPS service voltage at other Local EPSs to go
outside the requirements of ANSI C84.1-1995, Range A” [18]. However, IEEE Std 1547.2-
2008 provides much greater detail, such as that regarding interpretation: “there is a subtle
di↵erence between actively regulating and fulfilling an area EPS request to supply or absorb
reactive power” [30]; background on voltage regulation, typical utilization equipment, voltage
limits from ANSI C84.1 Range A [40], etc.; the potential impacts of DR on utility voltage
regulation schemes; and rules of thumb as to when to expect voltage regulation issues due
to DRs. Overall, IEEE Std 1547.2-2008 is an extremely valuable resource for understanding
IEEE Std 1547 and interconnection issues in general.
2.5 IEEE Std 1547.3
IEEE Std 1547 provides specific interconnection requirements that describe how a specific
DR or group of DRs must interact with the area EPS at a single PCC. However, the success-
24
Uninten1onal Islanding Requirement • For an uninten*onal island in which the DR energizes a
por*on of the Area EPS through the PCC, the DR interconnec*on system shall detect the island and cease to energize the Area EPS within two seconds of the forma*on of an island.
4
B usCirc uits
B us
Substat ion Feeds
Step-Dn Transfe rs
L
C irc uit Isla nd
N. C.
N.C.
N.C .
L L
Adja cent C ircuit
N .O. (c losed for adjacent
circuit island)
(open for circuit island)
Open for lateral island
CB2
© IEEE 1547.4-‐2011
Circuit Island
5
Introduc1on – Tradi1onal UI Test
5
Prac1cal Limita1ons: • RLC load bank overall (and step size) power level • Discrete elements in RLC load bank • Execu*on *me for large number of cases
6
Introduc1on – PHIL-‐based UI Test
6
Advantages: • Specialized RLC load bank no
longer needed (though power amplifier and RTS required)
• Tuning of RLC load bank much more precise with modeled elements instead of discrete elements
• Execu*on *me for a single test is much faster and tests can be automated
7
Introduc1on – Components Required for PHIL
• AC Power Amplifier (and possibly a dump load) of appropriate specifica1ons
• Real-‐1me Simulator (RTS) and RT model • AC Current Sensors • Stabiliza1on network (if applicable)
7
8
Outline
• Introduc1on to PHIL-‐based Uninten1onal Islanding Tes1ng
• NREL Experimental Implementa1on and Capabili1es o AC/DC amplifiers (NREL and U.S.) o Lab power ra*ng / grid level o Real-‐*me systems available o Interoperability (technical/communica*on/interface)
• PHIL UI Test Results • PHIL co-‐simula1on
9
PV
Energy Storage
Diesel / NG Generators
AC Loads
Aux / DC Loads
GS
Local Controller
Power Conditioningand Conversion
DC REDB AC REDB
Grid ModelDC Device Models
Bi-directionalProgrammable DC Supply
Bi-directionalGrid Simulator
M M
Local Hardwareat ESIF
ESIFEquipment
Distribution PMUWeather
Real-Time Data User Interface and Visualization
Real-TimeSimulator
LocalUser Interface
Ipv Id Rp
Rs
V
I
Market Pricing
Local UtilityConnection
GSAC Device Models
System Controller PCC
27
10
PV
Energy Storage
Diesel / NG Generators
AC Loads
Aux / DC Loads
GS
Local Controller
Power Conditioningand Conversion
DC REDB AC REDB
Grid ModelDC Device Models
Bi-directionalProgrammable DC Supply
Bi-directionalGrid Simulator
M M
Local Hardwareat ESIF
ESIFEquipment
Distribution PMUWeather
Real-Time Data User Interface and Visualization
Real-TimeSimulator
LocalUser Interface
Ipv Id Rp
Rs
V
I
Market Pricing
Local UtilityConnection
GSAC Device Models
System Controller PCC
Real-‐*me PMU Measurements
27
11
PV
Energy Storage
Diesel / NG Generators
AC Loads
Aux / DC Loads
GS
Local Controller
Power Conditioningand Conversion
DC REDB AC REDB
Grid ModelDC Device Models
Bi-directionalProgrammable DC Supply
Bi-directionalGrid Simulator
M M
Local Hardwareat ESIF
ESIFEquipment
Distribution PMUWeather
Real-Time Data User Interface and Visualization
Real-TimeSimulator
LocalUser Interface
Ipv Id Rp
Rs
V
I
Market Pricing
Local UtilityConnection
GSAC Device Models
System Controller PCC
Real-‐*me Solar Irradiance Measurements
27
12
PV
Energy Storage
Diesel / NG Generators
AC Loads
Aux / DC Loads
GS
Local Controller
Power Conditioningand Conversion
DC REDB AC REDB
Grid ModelDC Device Models
Bi-directionalProgrammable DC Supply
Bi-directionalGrid Simulator
M M
Local Hardwareat ESIF
ESIFEquipment
Distribution PMUWeather
Real-Time Data User Interface and Visualization
Real-TimeSimulator
LocalUser Interface
Ipv Id Rp
Rs
V
I
Market Pricing
Local UtilityConnection
GSAC Device Models
System Controller PCC
1.08 MVA Grid Simulator
27
13
1.08 MVA Grid Simulator Basic Specifica+ons (RS270) • Voltage: 0 – 400 Vl-‐n or 400 Vdc • Frequency:
o DC or 16 – 819 Hz (Sourcing) o DC or 16 – 500 Hz (Sinking)
• Current: 375 A (1500 A total) • Power Flow: Bi-‐direc*onal • Phase Control: Independent
phase control • PHIL Interface: Analog input
corresponding to instantaneous voltage waveform command
• Input Current THD: o Source Mode: ~ 3% o Sink Mode: ~ 5%
• Sobware Interface: o Transient List Editor o Arbitrary Waveform
Genera*on • Cooling: Air-‐cooled
Manufacturer and Base Model Ametek RS90 (90 kVA)
Modularity Four RS270 “Quads” capable of independent or parallel opera*on
14
1.0 MVA Grid Simulator – Addtl. Specs
Architecture • Topology: Three Single-‐Phase H-‐Bridges • Device Type: PFC = IGBT, Inverter = MOSFET • Inverter Switching Frequency: 60 kHz, interleaved to 240 kHz effec*ve Output Specifica+ons • Voltage Accuracy: ±0.3 V AC, ±1 V DC • Frequency Accuracy: ±0.01% • Phase Angle Accuracy: < 1.5° @ 16 – 100 Hz; < 2° @100 – 500 Hz • THD at full load
o Sourcing: < 0.5% @ 16 – 66 Hz; < 1% @ 66 – 500 Hz; < 1.25% up to 819 Hz o Sinking: < 1% @45 – 66 Hz; < 2% @ 66 – 500 Hz
• Load Regula1on: 0.25% FS @ DC – 100 Hz; 0.5% FS @ > 100 Hz • DC Offset Voltage: < 20 mV • Slew Rate: 200 µs for 20% -‐ 90% output change into resis*ve load, > 0.5 V/µs • Sedling Time: < 0.5 µs • -‐3dB Bandwidth: 4 kHz (but fundamental component limited to 1 kHz due to
output snubber power limita*ons)
15
Summary of MW-‐scale Power Amplifiers (U.S. Facili1es)
1.08 MVA (+1.08 MVA future) 480 V
6
� Installed at NWTC test site—November 2012 � Commissioning and characterization testing—end of 2013 � Row 4/turbine bus connection—FY14 � Energy storage site connection—end of 2014
NWTC’s 7-MVA CGI
Photo from Mark McDade, NREL
7 MVA (39 MVA short-‐circuit) 3.3 kV (13.2 kV)
NREL ESIF – Golden, CO NREL NWTC – Boulder, CO
• Su erconductivit and Cr o enics Labs
FSU-CAPS Lab Capabilities • Integrated 5 MW HIL Testbed
– 5 MW variable voltage/frequency converter
– 5 MW dynamometers – 5 MW MVDC converters (MMC)
• Real-time Digital Simulators RTDS & OPAL-RT using typical time step sizes from 2 µs to 50 µs Cyber-physical test bed
• Superconductivity and Cryogenics Labsy y gp – AC Loss and Quench Stability Lab – Cryo-dielectrics High Voltage Lab – Cryo-cooled Systems Lab
• Low Power and Smart Grid Labs • Extensive non-RT simulation tools and
expertise – PSCAD, PSS/E, Matlab, PLECS, OpenDSS, etc. – COMSOL, Magnet, etc.
4
15 MVA (20 MVA) 4.16 kV (23.9 kV)
5 MVA 4.16 kV
Clemson/DOE – N. Charleston, SC Florida State Univ. CAPS – Tallahassee, FL
See Proceedings of Second Interna*onal Workshop on Grid Simulator Tes*ng of Wind Turbine Drivetrains: htp://www.nrel.gov/electricity/transmission/grid-‐simulator-‐workshop-‐2.html
M. Steurer, FSU CAPS J.C. Fox, Clemson University
16
PV
Energy Storage
Diesel / NG Generators
AC Loads
Aux / DC Loads
GS
Local Controller
Power Conditioningand Conversion
DC REDB AC REDB
Grid ModelDC Device Models
Bi-directionalProgrammable DC Supply
Bi-directionalGrid Simulator
M M
Local Hardwareat ESIF
ESIFEquipment
Distribution PMUWeather
Real-Time Data User Interface and Visualization
Real-TimeSimulator
LocalUser Interface
Ipv Id Rp
Rs
V
I
Market Pricing
Local UtilityConnection
GSAC Device Models
System Controller PCC
1 MVA RLC Load
27
17
1 MVA Load Bank Manufacturer and Base Model LoadTec OSW4c 390 kW/kVARL/kVARC RLC Load Banks
Modularity Four modules can be operated independently or in parallel
Basic Specifica+ons • Voltage: 0 – 346 Vl-‐n / 600 Vl-‐l • Frequency:
o L and C: 45 – 65 Hz o R: DC – 400 Hz
• Power: o 390 kW/kVAR @ 346/600 V 3ɸ o 250 kW/kVAR @ 277/480 V 3ɸ o 47 kW/kVAR @ 120/208 V 3ɸ o 47 kW/kVAR @ 120 V 1ɸ
• Resolu1on o 234 W/VAR @ 346/600 V 3ɸ o 150 W/VAR @ 277/480 V 3ɸ o 28 W/VAR @ 120/208 V 3ɸ o 10 W/VAR @ 120 V 1ɸ
• Phase Configura1on: o Balanced or Unbalanced 3ɸ o Single Phase o Split-‐Phase
• PHIL Interface: Digital kW/kVAR commands
• Sobware Interface: o Load Profile Entry
• Cooling: Air-‐cooled
18
PV
Energy Storage
Diesel / NG Generators
AC Loads
Aux / DC Loads
GS
Local Controller
Power Conditioningand Conversion
DC REDB AC REDB
Grid ModelDC Device Models
Bi-directionalProgrammable DC Supply
Bi-directionalGrid Simulator
M M
Local Hardwareat ESIF
ESIFEquipment
Distribution PMUWeather
Real-Time Data User Interface and Visualization
Real-TimeSimulator
LocalUser Interface
Ipv Id Rp
Rs
V
I
Market Pricing
Local UtilityConnection
GSAC Device Models
System Controller PCC
1.5 MW PV Simulator
27
19
1.5 MW PV Simulator Basic Specifica+ons (MTD1000-‐250) • Voltage: 25 – 1000 V (up to 4000 V) • Current: 250 A (up to 1500 A) • Power Flow: Supply Only • PHIL Interface: Analog input corresponding
to instantaneous voltage / current waveform command
• Bandwidth: o Voltage: 60 Hz o Current: 45 Hz
• Slew Rate: o Voltage: 4 ms for 0 – 63% step o Current: 8 ms for 0 – 63% step
• Load Transient Response: 10 ms to recover to within ± 1% of regulated output with a 50 – 100% or 100 – 50% load step
• Load Regula1on: o Voltage: ±0.01% of full scale o Current: ±0.04% of full scale
• Sobware Interface: o PV IV Curve Emula*on o Profile Genera*on
• Cooling: Air-‐cooled
Manufacturer and Base Model Magna-‐Power MTD1000-‐250 (250 kW)
Modularity Six Modules capable of independent, parallel, or series opera*on (up to 4000 V)
20
PV
Energy Storage
Diesel / NG Generators
AC Loads
Aux / DC Loads
GS
Local Controller
Power Conditioningand Conversion
DC REDB AC REDB
Grid ModelDC Device Models
Bi-directionalProgrammable DC Supply
Bi-directionalGrid Simulator
M M
Local Hardwareat ESIF
ESIFEquipment
Distribution PMUWeather
Real-Time Data User Interface and Visualization
Real-TimeSimulator
LocalUser Interface
Ipv Id Rp
Rs
V
I
Market Pricing
Local UtilityConnection
GSAC Device Models
System Controller PCC
660 kW DC Supply 27
21
660 kW Badery/PV Simulator Basic Specifica+ons (AC2660P) • Voltage: 264 – 1000 V (up to 2000 V) • Current: 2500 A (up to 5000 A) • Power Flow: Bi-‐direc*onal • PHIL Interface: Digital voltage,
current, irradiance, and/or temperature commands
• Bandwidth: • Slew Rate: • Load Regula1on:
o Steady-‐state: ±0.5% o Transient: ±3%
• Load Transient Response: < 10 ms for 10 – 90% or 90 – 10% load step
• Bandwidth: o Voltage Control: 180 Hz (500 Hz) o Current Control: 2.0 kHz (2.5 kHz)
• Sobware Interface: o PV IV Curve Emula*on o Batery Emula*on o Profile Genera*on
• Cooling: Liquid-‐cooled
Manufacturer and Base Model Anderson Electric Controls AC2660P (660 kW)
Modularity Currently one module, future two modules capable of independent, parallel or series opera*on
22
Addi1onal Equipment • PV Simulators
– 100 kW Ametek TerraSAS • DC Supplies
– 250 kW AeroVironment AV-‐900 • Load Banks
– 100 kW R-‐L (portable) – 100 kW R (portable)
• Small grid simulators – (3) 45 kW Ametek MX45 – (4) 50 kW Pacific Power – 15 kW Elgar
• Diesel generators – 125kVA and 80 kVA Onan/Cummins – 300kVA Caterpillar
• Hydrogen Systems – Electrolyzers: 50kW, 10kW – Storage tanks – Fuel cells
• Real-‐Time Digital Simulators – Opal-‐RT (3 racks) – RTDS (1 rack)
23
ESIF Laboratories
High Performance Compu1ng, Data Analysis, and Visualiza1on
16. ESIF Control Room 17. Energy Integra*on Visualiza*on 18. Secure Data Center 19. High Performance Compu*ng
Data Center 20. Insight Center Visualiza*on 21. Insight Center Collabora*on
Fuel Systems Laboratories 9. Energy Systems Fabrica*on 10. Manufacturing 11. Materials Characteriza*on 12. Electrochemical
Characteriza*on 13. Energy Systems Sensor 14. Fuel Cell Development &
Test 15. Energy Systems High
Pressure Test
Thermal Systems Laboratories 6. Thermal Storage Process and
Components 7. Thermal Storage Materials 8. Op*cal Characteriza*on
Electrical Systems Laboratories 1. Power Systems Integra*on 2. Smart Power 3. Energy Storage 4. Electrical Characteriza*on 5. Energy Systems Integra*on
24
ESIF Research Infrastructure Research Electrical Distribu*on Bus – REDB (AC 3ph, 600V, 1600A and DC +/-‐500V, 1600A) Thermal Distribu*on Bus Fuel Distribu*on Bus Supervisory Control and Data Acquisi*on (SCADA)
25
Research Electrical Distribu1on Bus (REDB)
AC • 4-wire plus ground
• Floating or grounded neutral
• 600 Vac
• 16 Hz to 400 Hz
• 250A and 1600A installed
• 250A and 2500A planned (future)
• 4-pole switches
• Connects PSIL, SPL, ESL, GSE, LBE, LVOTA, MVOTA, ESIL
DC • 3-wire plus ground
• Any pole may be grounded
• ±500Vdc or 1000Vdc
• 250A and 1600A installed
• 250A and 2500A planned (future)
• Experiment connection via cart contactor/fuse or direct (main lug only)
• Connects PSIL, SPL, ESL, PVE, LVOTA, MVOTA, ESIL
26
Example Racetrack and Lab Sec1on
PSIL Lateral A PSIL Lateral B PSIL Ladder Tie Switch
PSIL Ladder B Switch PSIL Ring Bus Switch
PSIL Ring Bus Switch
PSIL Ladder A Switch
PSIL Ladder Rung
UC Ring Bus Switch
Neighboring Ring Bus Switch for the UC
UC Lateral
Ring-‐*e Ring-‐*e
27
REDB Switchgear Room (AC)
27
28
Busway Connec1ons in PSIL
29
Outline
• Introduc1on to PHIL-‐based Uninten1onal Islanding Tes1ng
• NREL Experimental Implementa1on and Capabili1es o AC/DC amplifiers (NREL and U.S.) o Lab power ra*ng / grid level o Real-‐*me systems available o Interoperability (technical/communica*on/interface)
• PHIL UI Test Results • PHIL co-‐simula1on
30
Discrete Hardware UI Test
30
Prac1cal Limita1ons: • RLC load bank overall (and step size) power level • Discrete elements in RLC load bank • Execu*on *me for large number of cases
31
PHIL-‐based UI Test
31
Advantages: • Specialized RLC load bank no
longer needed (though power amplifier and RTS required)
• Tuning of RLC load bank much more precise with modeled elements instead of discrete elements
• Execu*on *me for a single test is much faster and tests can be automated
32
Results (1-‐ph) – qf = 1
32
breaker in the hardware test does not always occur on a zero crossing, but always does
in the PHIL case (the reason for phase o↵set in the results of the first two cases),
variance of trip time within a cycle or two is to be expected. All three cases are very
closely matched time-wise between the hardware and PHIL tests; the first two are
within one cycle and the third is nearly matched.
−0.2 −0.15 −0.1 −0.05 0 0.05 0.1 0.15 0.2−20
−15
−10
−5
0
5
10
15
20
Time (s)
Cur
rent
(A
)
Inverter Current versus Grid Current
hw−iinv
phil−iinv
hw−igrid
phil−igrid
−0.2 −0.15 −0.1 −0.05 0 0.05 0.1 0.15 0.2−400
−300
−200
−100
0
100
200
300
400
Time (s)
Vol
tage
(V
)
Vpcc Voltage
hw−v
phil−v
Figure 5.9: Results from the task 1 unintentional islanding test for qf = 1.04
One will notice that the grid current (igrid) for the discrete hardware and PHIL tests
does not match perfectly. This is because the EPS model used in the two cases was not the
same; in the discrete hardware case, the EPS was the hardware power amplifier, while, in the
PHIL case, the EPS model was just an ideal voltage source. In any case, what really matters
108
1. B. Lundstrom, B. Mather, M. Shirazi, and M. Coddington, “Methods and Implementa*on of Advanced Uninten*onal Islanding Tes*ng using Power Hardware-‐in-‐the-‐Loop (PHIL),” in IEEE PVSC, 2013. 2. B. Lundstrom, M. Shirazi, M. Coddington, and B. Kroposki, “An Advanced Plazorm for Development and Evalua*on of Grid Interconnec*on Systems using Hardware-‐in-‐the-‐Loop: Part III–Grid Interconnec*on System Evaluator,” in IEEE Green Technologies Conference, Denver, CO, April 2013.
33
Results (1-‐ph) – qf = 2.84
33
−0.2 −0.15 −0.1 −0.05 0 0.05 0.1 0.15 0.2−20
−15
−10
−5
0
5
10
15
20
Time (s)
Cur
rent
(A
)
Inverter Current versus Grid Current
hw−iinv
phil−iinv
hw−igrid
phil−igrid
−0.2 −0.15 −0.1 −0.05 0 0.05 0.1 0.15 0.2−400
−300
−200
−100
0
100
200
300
400
Time (s)
Vol
tage
(V
)
Vpcc Voltage
hw−v
phil−v
Figure 5.10: Results from the task 1 unintentional islanding test for qf = 2.84
109
1. B. Lundstrom, B. Mather, M. Shirazi, and M. Coddington, “Methods and Implementa*on of Advanced Uninten*onal Islanding Tes*ng using Power Hardware-‐in-‐the-‐Loop (PHIL),” in IEEE PVSC, 2013. 2. B. Lundstrom, M. Shirazi, M. Coddington, and B. Kroposki, “An Advanced Plazorm for Development and Evalua*on of Grid Interconnec*on Systems using Hardware-‐in-‐the-‐Loop: Part III–Grid Interconnec*on System Evaluator,” in IEEE Green Technologies Conference, Denver, CO, April 2013.
34
Results (1-‐ph) – qf = 4.35
34
−0.2 −0.15 −0.1 −0.05 0 0.05 0.1 0.15 0.2−20
−15
−10
−5
0
5
10
15
20
Time (s)
Cur
rent
(A
)
Inverter Current versus Grid Current
hw−iinv
phil−iinv
hw−igrid
phil−igrid
−0.2 −0.15 −0.1 −0.05 0 0.05 0.1 0.15 0.2−400
−300
−200
−100
0
100
200
300
400
Time (s)
Vol
tage
(V
)
Vpcc Voltage
hw−vphil−v
Figure 5.11: Results from the task 1 unintentional islanding test for qf = 4.35
110
1. B. Lundstrom, B. Mather, M. Shirazi, and M. Coddington, “Methods and Implementa*on of Advanced Uninten*onal Islanding Tes*ng using Power Hardware-‐in-‐the-‐Loop (PHIL),” in IEEE PVSC, 2013. 2. B. Lundstrom, M. Shirazi, M. Coddington, and B. Kroposki, “An Advanced Plazorm for Development and Evalua*on of Grid Interconnec*on Systems using Hardware-‐in-‐the-‐Loop: Part III–Grid Interconnec*on System Evaluator,” in IEEE Green Technologies Conference, Denver, CO, April 2013.
35
Results (1-‐ph) – repe11on of qf = 2.84 case
35
is that the inverter’s response matches in both hardware and PHIL tests. This was the case,
so no emphasis was placed on trying to use the same EPS model in both cases to get better
matching between the grid currents of the two tests. In terms of repeatability, the results of
five runs of the same test case (qf = 2.84) using the PHIL method are shown in Figure 5.12.
It can be seen that the PHIL is very repeatable. Again, a small variance (1-2 cycles) in trip
times is expected due to the variance in the inverter’s anti-islanding algorithms. In all, these
results show very clearly that the PHIL and discrete hardware methods match very closely
and that the PHIL technique is repeatable, validating the PHIL approach.
−0.1 −0.05 0 0.05 0.1 0.15 0.2−20
−15
−10
−5
0
5
10
15
20Currents
1
2
3
4
5
−0.1 −0.05 0 0.05 0.1 0.15 0.2−400
−300
−200
−100
0
100
200
300
400Voltages
1
2
3
4
5
Figure 5.12: Inverter current and voltage from repeated tests of the task 1 unintentionalislanding test for qf = 2.84
111
Consistency of Results
36
Results (1-‐ph) – repe11on of qf = 2.84 case
36
Precision of Circuit Model (Tuning) in PHIL
%%)%&* %%)%&*' %%)%&+ %%)%&+' %%)%&, %%)%&,' %%)"
-%$
$
%$
������� ��(�
���������-��� ����
������ �
Figure 5.13: Results from the task 2 unintentional islanding test for qf ⇠= 1 with a poorly-tuned RLC load (igrid1 ⇠= 0.02 · iinv,FL)
113
qf = 1 (discrete HW tuning) Trip in 0.156s
����� ����� ����� ����� ��� ����� �����
���
�
��
(������
Figure 5.14: Results from the task 2 unintentional islanding test for qf ⇠= 1 with a well-tunedRLC load (igrid1 ⇠= 0.002 · iinv,FL)
114
qf = 1 (well tuned in SW) Trip in 1.08s
limit of IEEE Std 1547-2003 [18]. When repeating the same test, but for a quality factor
of 5, the inverter never detected the island condition and continued to operate indefinitely.
These results confirm that the variable RLC load PHIL approach is e↵ective for achieving
conditions di�cult to replicate with discrete hardware and that the technique is applicable
over a wide range of quality factors.
�� !" �� !# ��$ ��$!% ��$! ��$!" ��$!# ��" ��"!% ��"! ��"!"
&�'
'
�'
������ �
Figure 5.15: Results from the task 2 unintentional islanding test for qf ⇠= 3 with a well-tunedRLC load (igrid1 ⇠= 0.002 · iinv,FL)
115
qf = 3 (well tuned in SW) Trip in 1.8s
qf = 5 (well tuned in SW) Ran indefinitely
37
Hardware: • (EUT) Advanced Energy 500TX 500 kW PV Inverter
• 810 kVA Grid Simulator with analog control
• 1.5 MW PV Simulator • 1 MVA (150 VA) RLC Load Bank
• LEM current and voltage transducers
Real-‐1me Modeling: • Opal-‐RT eMegaSim RTS • Real-‐*me model developed in SimPowerSystems (no co-‐simula*on)
• ITM interface • Phase compensa*on • HW feedback filtering • 33 μs < Ts < 66 μs
PV Simulator
AC RLC Load BankInverterLocal PCC Model
Grid Simulator
M
Local Controller
Grid Model
DC R
EDB
M
AC REDB
VpccIinv
Vpcc
Vpcc
Iinv
StaticPV Array
Uninten1onal Islanding PHIL: Test Setup
38
Uninten1onal Islanding PHIL: Test Setup
39
Results (3-‐ph) – Best Comparison Example
40
Preliminary Results (3-‐ph) – Spread
0 100 200 300 400 500 600 700
PHIL-‐UF
PHIL-‐OF
HW-‐UF
HW-‐OF
Trip Time (ms) for same RLC Load Condi*on
Also see: M. Steurer et. al., “Progress on PHIL based An*-‐Islanding Tes*ng of PV Converters”. Proceedings of Second Interna8onal Workshop on Grid Simulator Tes8ng of Wind Turbine Drivetrains. Available: htp://www.nrel.gov/electricity/transmission/grid-‐simulator-‐workshop-‐2.html for similar results on smaller converter
41
Outline
• Introduc1on to PHIL-‐based Uninten1onal Islanding Tes1ng
• NREL Experimental Implementa1on and Capabili1es o AC/DC amplifiers (NREL and U.S.) o Lab power ra*ng / grid level o Real-‐*me systems available o Interoperability (technical/communica*on/interface)
• PHIL UI Test Results • PHIL co-‐simula1on
42
PHIL Co-‐simula1on: Mo1va1on
• Leverage benefits of PHIL: o Examine system-‐level and mul*-‐device impacts o Repeatability of complex scenarios o Flexible, modular
• But add: o Simplify model conversion o Allow use of more complex, mul*-‐discipline system models without simplifica*on or abstrac*on
o Connec*on/link of mul*ple sites into a single PHIL simula*on
• Within limita1ons
43
A Testbed for Distributed Integra1on
• Arbitrary Grid o Loca*on o Topology & Equipment
• Any scenario o Rou*ne o Con*ngency
• Actual Hardware o No (proprietary) model required
• Co-‐simula1on o U*lize exis*ng off-‐the-‐shelf so|ware with no model conversion required
25
Grid Interconnec*on Hardware Simula8on
Power System Simula*on
Computer Model
Device(s) Under Test
Device Under Test Device(s) Under Test
Co-‐Simula*on
PHIL Simula*on
44
GridLAB-D Electric Distribution System ModelRunning in Real-Time Mode
PV Inverter 1
PV Simulator 1
Phase A
Phase C
Phase BN
Load Bank 1
Grid Simulator
ControlSet points
Measurements
NREL
PNNL
Weather Data
InverterCurrents
PCC Voltages
PV Inverter 2
PV Simulator 2
Load Bank 2
InverterCurrent
7200V Primary 3-phase
75 kVASplit-phase
Center-tappedTransformers
Triplex Nodes
HomesInverter 2Inverter 1 Homes
VPCC1 VPCC2
IEEE 8500 Node Feeder with Building Loads Phase A Phase C
Triplex Line
Hardware under Test (HUT)
FPGA-based I/O
JSON-Link UDP/IP Communication over Ethernet
Grid PCC Model Weather Model
Real-Time Simulator
VPN Tunnel
PV Model
200
400
600
800
1000
1200IEEE8500 Inverter 2 Time Series
PO
A Ir
radi
ance
(W/m
2 )
20
30
40
50
60
70
80
Rea
l Pow
er(k
W)
−50
−40
−30
−20
−10
0
10
Rea
ctiv
e P
ower
(kV
Ar)
12:47 12:48 12:49 12:50 12:51 12:52240
245
250
255
260
265
270P
CC
Vol
tage
(V
)
Time (MDT)
No Solar PF=1 PF=0.81 absorbing Volt/VAR Control
28
45
27
Test Case # 3: Three-phase Inverter • IEEE 8500-node test feeder
- One 7 kVA real-inverter output scaled up to 140 kVA in GridLAB-D simulation
- This hardware inverter was operating in VVC
- Added a large number small UPF inverters; combined output of 800 kW
• Cloud transient was implemented based on historical weather data
• The hardware inverter with VVC was capable of maintaining constant voltage on the secondary
12:35 12:40 12:45122
123
124
125
126
127
128
|V| m
ax
Maximum voltage magnitude on secondary system
no solar base case
distributed PF=1.0 solar
distributed PF=1.0 solar and VVC solar
0
500
1000
1500
Irra
dia
nce
(W/m
2)
10
20
30
40
50
Ph
ase
A R
eal
Po
wer
(kW
)
-40
-20
0
20
Ph
ase
A R
eact
ive
Po
wer
(kV
Ar)
12:35 12:40 12:45275
280
285
290
Ph
ase
A |V
| at
PC
C(V
)
base PF=1.0 PF=0.81
Figure 4 shows power generation and |V| at the inverter PCC over a 10-minute period with a cloud transient. As in the case of the single-phase inverters, voltage increases as compared to the no-solar base case when the inverter is operated with PF = 1.0. Unlike in the single-phase inverter case described above, the PF = 0.81 case is not well-tuned to control voltage with this combination of inverter output and PCC location. This demonstrates how operating in a fixed-PF mode, while it has the benefits of simplicity, will not result in optimal behavior. The impact to the distribution feeder’s voltage profile will differ depending on the interaction of the PV output under changing irradiance conditions, the inverter size, and the characteristics of the feeder at the PCC. B.2 Hardware inverter with additional modeled solar
The voltage on the secondary system can be studied under different PV penetration scenarios. In systems without distributed generation (DG), power flow is unidirectional, and voltage may drop up to 3V from the transformer to the meter due to the impedance of the triplex cable [12]. In systems with DG, there may be local reverse power flow in the triplex line, potentially leading to over-voltage problems. ANSI C84.1 defines acceptable operating envelope for steady-state voltage levels as 95-105% of nominal voltage [19], which may be violated when there is reverse power flow [20].
Because the simulated electrical distribution systems modeled in GridLAB-D include detailed models of secondary service transformers and triplex cables, the PHIL test platform described here is well-suited to study how new modes of inverter control affect voltages on the secondary system.
Figure 5 shows the maximum voltage at any point in the secondary system. The modeled system is the IEEE 8500-node test feeder. Three cases are considered. 1. Base case. In the base case (black trace), no solar PV is added to the system, and the voltage is well within acceptable limits and almost constant over a 10-minute period. 2. Modeled distributed solar PV. High levels of modeled distributed solar PV generation are added to the base case (blue trace), with inverters operating at PF = 1.0. Each residential load is given a solar PV array of 15-30% of its total square footage, leading to a net feeder real power demand of near 0W during the 10-minute time period shown. The voltage on the backbone is held to normal levels by the action of the voltage regulators. The maximum voltage on the secondary system rises to over 125.2V and at the cloud transient shortly after 12:40, the maximum voltage tracks the irradiance levels. 3. Modeled distributed solar PV and hardware inverter. Case 2 is used as the model distribution system for a PHIL test case (red trace), where the three-phase hardware inverter is operated in VVC mode, modifying Q in response to |V| at the PCC. The distributed PV at unity PF have a combined power output of 800kVA; the hardware PV contribution is scaled up in software to a maximum power of 140kVA. The action of the hardware inverter in VVC mode has the effect of maintaining the maximum voltage on the secondary system at
a constant level through the cloud transient, mitigating some of the effects of the unity power factor solar PV.
IV. ADDITIONAL APPLICATIONS OF PHIL PLATFORM
In addition to the examples discussed above, there are many system-level quantities and phenomena that may be studied with this type of PHIL test platform. Two additional examples are briefly described in this section: the effect of an inverter’s control mode on actions of other voltage control devices throughout the feeder and the feeder-wide voltage profile.
A. Effect of Solar PV on Voltage Control Devices
The impact of high-penetration levels of solar PV on the actions of voltage control devices is of concern to utilities. High-penetration levels of solar PV may cause increased tap changes or switching operations, resulting in higher maintenance costs and decreased equipment lifetimes. Quasi-static time-series simulations have been used to study this effect [21], and show a range of impacts depending on feeder characteristics, solar PV size and placement, and inverter control mode. Changes in tap counts are highly sensitive to these parameters, making it important to use accurate representation of advanced inverter control modes in conjunction with detailed voltage control device and feeder power flow models. In situations where adequate models may not exist, as in the case of newly developed control modes, a PHIL test platform can provide the necessary accuracy, and has the additional advantage of being able to test a wide array of electric distribution system configurations.
In the test cases described in Section III, the output of the hardware inverters does not change in response to a cloud transient sufficiently to cause additional tap changes.
12:35 12:40 12:45122
123
124
125
126
127
128
|V| m
ax
Maximum voltage magnitude on secondary system
no solar base case
distributed PF=1.0 solar
distributed PF=1.0 solar and VVC solar
Figure 5: Maximum voltage magnitude at any point in the secondary system, for three different solar PV penetration scenarios.
29
46
Distributed Control of Energy Storage • NREL integrated Power Hardware in the Loop (PHIL)
simula1on of energy storage + PV with residen1al inverter • ±10kW badery + 10kW PV • 123 node grid simula1on
© CYME International, June 2011
CYME QA Validation Tests CasesLoad Flow -Unbalanced - IEEE 123 Node Test Feeder
CYME Power Engineering Software
A self-contained study file (.sxst) to use with this document is provided. The explanations below are based on the use of that file.
n Highlights
x Comparison between CYME Load flow analysis voltage drop unbalanced method results against those published in the document “IEEE 123 node test feeder” by IEEE Distribution system analysis subcommittee.
x Simulation includes comparison of results obtained with the method of voltage drop unbalanced: line currents and bus voltages.
x 123 bus system with overhead and underground line segments with various phasing , unbalanced loading with all combinations of load types (PQ, constant I, constant Z), four step-type voltage regulators, shunt capacitor banks and switching to provide alternate paths of power-flow.
o Load Flow Analysis
1. Open the IEEE_123_node_test_feeder.sxst self-contained study file. To do so, go to the the dialog box displayed using the Help > Validation Cases menu option. Select the “Load Flow - Unbalanced” option in the List of test cases and enable the check box next to the file name. Click on the Start Case button.
2. Select the Analysis > Load Flow menu option. Ensure that the Calculation Method is Voltage Drop – Unbalanced. Leave all the other parameters intact.
3. Click on to Run the analysis.
IEEE 123 Node Feeder Model
47
28
Panorama of Complete Hardware Setup
Three-phase Setup
Real-time System (Opal-RT)
Grid Simulator
Single-phase Setup
30