Advanced

Earned Value Management

Presented by

Dipo Tepede, PMP, SSBB, MBA

Page 2: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

This presentation is copyright © 2009 by POeT Solvers Limited. All rights reserved.

This presentation is protected by the Nigerian Copyright law and may not be reproduced,

distributed, transmitted, displayed, published or broadcast without the prior written permission

of POeT Solvers Limited. You may not alter or remove any trademark, copyright or other

notices. PMP®, CAPM®, PMI®, PMBOK® Guide are

registered marks of Project Management Institute, Inc.

Powered by POeT Solvers Limited

Page 3: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  Be able to know the formulas for:

– Cost and Schedule Performance Index

– Estimate at Completion – To complete Performance Index

•  Be able to explain Estimate to Complete

Powered by POeT Solvers Limited

At the end of this training, our goal is for you to:

Page 4: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  EVM – Earned Value Management

•  EVT – Earned Value Technique

•  AC – Actual Cost •  PV – Planned Value

•  EV – Earned Value

•  Cost Variance: CV = EV – AC

•  Schedule Variance: SV = EV – PV

•  Variance: Subtract/Index: Divide Powered by POeT Solvers Limited

Review

Page 5: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  Cost Performance Index

•  Measure of cost efficiency on a project

•  Ratio of earned value to actual costs •  CPI = EV/AC

– CPI: Cost Performance Index

– EV: Earned Value

– AC: Actual Cost

Powered by POeT Solvers Limited

CPI Overview and Formula

Page 6: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  Schedule Performance Index

•  Measure of schedule efficiency on a project

•  Ratio of earned value to planned value

•  SPI = EV/PV – SPI: Schedule Performance Index

– EV: Earned Value

– PV: Planned Value Powered by POeT Solvers Limited

SPI Overview and Formula

Page 7: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

Powered by POeT Solvers Limited

Things to Know

•  Positive is good • Negative is bad

•  < 1 is bad •  =1 is good •  > 1 is good

CV and SV

CPI and SPI

Page 8: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

Powered by POeT Solvers Limited

Earned Value Terms

Estimate to Complete

Estimate at Completion

• Estimate for the cost of all the remaining work in the project

• Forecasted estimate for the total cost of the project

Page 9: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

Powered by POeT Solvers Limited

Bottom-up ETC Estimate work left and multiply by the hourly

rate

Accurate estimate to complete

Re-estimating everything

EAC = AC + Bottom-Up ETC

Page 10: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  Takes time

•  Time spent in re-estimating is lost and cannot be regained

•  Re-estimation is costly

Powered by POeT Solvers Limited

Problems

Page 11: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

Powered by POeT Solvers Limited

EAC Questions to Ask

• Project Progress so far?

• Will progress rate be same in future?

Page 12: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

Powered by POeT Solvers Limited

Conclusions Drawn

Original estimate was right and the current project performance is wrong

Original estimate was wrong and the current project performance is correct

Might also have to consolidate both cost and schedule while calculating EAC

Page 13: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  EAC = AC + BAC – EV

•  Abbreviations:

– EAC = Estimate at Collection – AC = Actual Costs

– BAC = Budget at Completion

– EV = Earned Value

Powered by POeT Solvers Limited

EAC at Budgeted Rate

Page 14: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  EAC = BAC/CPI

•  Abbreviations:

– EAC = Estimate at Completion – BAC = Budget at Completion

– CPI = Cost Performance Indexe

Powered by POeT Solvers Limited

EAC at Present CPI Rate

Page 15: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

Powered by POeT Solvers Limited

EAC With CPI & SPI Factored in

EAC = AC + ((BAC - EV)/(CPI*SPI))

Page 16: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  EAC at budgeted rate

– EAC = AC + BAC – EV

•  EAC at present CPI rate – EAC = BAC/CPI

– EAC = AC + ((BAC - EV)/CPI)

•  EAC with CPI & SPI factored in

– EAC = AC + ((BAC - EV)/CPI*SPI)

Powered by POeT Solvers Limited

EAC Review

Page 17: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  Situational questions

•  Identity EVM situations

•  Decide which formula to use •  All formulas must be on your cheat sheet

•  There is only one way to learn them:

– Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice,

Powered by POeT Solvers Limited

Know the Reasoning

Page 18: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

560 km at 80km/h = 7hours

Leaving at 8am / Arrive at 3pm

At 1pm, you have driven 300km

Powered by POeT Solvers Limited

TCPI Example

Page 19: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  Using your original arrival time:

•  You have 2 hours left

•  There are 250 km to go •  That means that you must drive 250km/2h

= 125km/h to reach your target

•  So your TCPI based on your original arrival estimate = 125

Powered by POeT Solvers Limited

TCPI based on original BAC

Page 20: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  Using new arrival time:

•  4’o clock: you have 3 hours left

•  There are 250km to go •  You must drive 250km/3h = 83km/h to

reach the target

•  TCPI based on new arrival estimate = 83

Powered by POeT Solvers Limited

TCPI based on New EAC

Page 21: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  Your Target is BAC:

•  TCPI = (BAC - EV) / (BAC - AC)

•  Your Target is EAC: •  TCPI = (BAC - EV) / (EAC - AC)

Powered by POeT Solvers Limited

TCPI Formulas

Page 22: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

Powered by POeT Solvers Limited

Two More Formulas

Variance at Completion

Calculation of the Percent

Spent

• VAC = BAC - EAC

• % Spent = AC/BAC

Page 23: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  Earned Value Techniques concern with:

– Earned value Mgt.

– Forecasting – To-Complete Performance Index

•  Terms and abbreviations that you need to know are: – AC – Actual Cost

– PV – Planned Value

– EV – Earned Value Powered by POeT Solvers Limited

Review

Page 24: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

•  CV & CPI – Cost Variance and Cost Performance Index

•  SV & SPI – Schedule Variance and Schedule Performance Index

•  EAC – Estimate at Completion

•  ETC – Estimate to Complete

•  BAC – Budget at Completion •  TCPI – To Complete Performance Index

•  VAC – Variance at Completion Powered by POeT Solvers Limited

Review

Page 25: Advanced Earned Value Management Presented by · PDF fileAdvanced Earned Value Management Presented by Dipo Tepede, PMP, SSBB, ... • SPI = EV/PV ... Might also have to consolidate

Powered by POeT Solvers Limited

Review

Positive Variances Negative

Variances

Good

Index = 1

Index > 1

Bad

Index < 1