addendum no. 1 may 15, 2019 project: morton valley...

74
Page 1 of 2 ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY WSC PUMP STATION IMPROVEMENTS BID DATE: June 11, 2019 @ 10:00 AM The following changes and/or additions shall be made to the Plans, Specifications, and Contract documents for the above referenced project. Bidder shall acknowledge receipt of this Addendum by signing below and returning this Addendum with the Bid. Plans, Specifications, and Contract Documents: 1. CHANGE: The specification sections listed below shall be added or replace existing specifications and are attached to this addendum: a. Table of Contents b. 09-03-01 (Coating & Painting for Water Treatment Plants) c. 13-04-01 (Steel Doors & Frames) d. 11-02-01 (Chemical Feed Equipment) e. 25-02-01 (Instrumentation Equipment) f. 25-04-01 (Supervisory Control and Data Acquisition) g. 26-01-01 (General Electrical for Small Buildings and Facilities) 2. CHANGE: The bid schedule shall be replaced with the bid schedule attached to this addendum. 3. ADDITION: Plan sheets for the “Morton Valley Alternate SCADA Site” are attached to this addendum (two sheets total) which correspond to the bid item described in pump station contract alternate bid #2. 4. ADDITION: A plan sheet for the “100,000 gallon GST Aeration System” is attached to this addendum (one sheet total) which corresponds to the aeration system for base bid item #4 and alternate bid #1. 5. Specification 01-09-01 (Disinfection of Potable Water Piping and Tanks) a. CHANGE: Section 3.2, Item F. The first sentence shall be replaced with “The CONTRACTOR will take samples from the sterilized line through a suitable point in accordance with AWWA C651 (not a fire hydrant) and submit to the testing laboratory. b. CLARIFICATION: The CONTRACTOR shall be responsible for all costs related to disinfection of potable water piping and tanks (sampling, transportation to laboratory, lab fees, reporting, etc.). 6. Liquidated Damages a. CHANGE: Contract Documents, EJCDC C-520, Agreement Between Owner and Contractor for Construction Contract. i. Item 4.03 (A) (1) shall be replaced with the following: “Substantial Completion: Contractor shall pay Owner $1,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified in Paragraph 4.02.A above for Substantial Completion until the Work is substantially complete. ii. Item 4.03 (A) (2) shall be replaced with the following: “Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as

Upload: others

Post on 04-Apr-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Page 1 of 2

ADDENDUM NO. 1

May 15, 2019

PROJECT: MORTON VALLEY WSC PUMP STATION IMPROVEMENTS BID DATE: June 11, 2019 @ 10:00 AM The following changes and/or additions shall be made to the Plans, Specifications, and Contract documents for the above referenced project. Bidder shall acknowledge receipt of this Addendum by signing below and returning this Addendum with the Bid. Plans, Specifications, and Contract Documents:

1. CHANGE: The specification sections listed below shall be added or replace existing specifications and are attached to this addendum:

a. Table of Contents b. 09-03-01 (Coating & Painting for Water Treatment Plants) c. 13-04-01 (Steel Doors & Frames) d. 11-02-01 (Chemical Feed Equipment) e. 25-02-01 (Instrumentation Equipment) f. 25-04-01 (Supervisory Control and Data Acquisition) g. 26-01-01 (General Electrical for Small Buildings and Facilities)

2. CHANGE: The bid schedule shall be replaced with the bid schedule attached to this addendum. 3. ADDITION: Plan sheets for the “Morton Valley Alternate SCADA Site” are attached to this

addendum (two sheets total) which correspond to the bid item described in pump station contract alternate bid #2.

4. ADDITION: A plan sheet for the “100,000 gallon GST Aeration System” is attached to this addendum (one sheet total) which corresponds to the aeration system for base bid item #4 and alternate bid #1.

5. Specification 01-09-01 (Disinfection of Potable Water Piping and Tanks) a. CHANGE: Section 3.2, Item F. The first sentence shall be replaced with “The

CONTRACTOR will take samples from the sterilized line through a suitable point in accordance with AWWA C651 (not a fire hydrant) and submit to the testing laboratory.

b. CLARIFICATION: The CONTRACTOR shall be responsible for all costs related to disinfection of potable water piping and tanks (sampling, transportation to laboratory, lab fees, reporting, etc.).

6. Liquidated Damages a. CHANGE: Contract Documents, EJCDC C-520, Agreement Between Owner and

Contractor for Construction Contract. i. Item 4.03 (A) (1) shall be replaced with the following: “Substantial Completion:

Contractor shall pay Owner $1,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified in Paragraph 4.02.A above for Substantial Completion until the Work is substantially complete.

ii. Item 4.03 (A) (2) shall be replaced with the following: “Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as

Page 2: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Page 2 of 2

duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $1,000.00 for each day that expires after such time until the Work is completed and ready for final payment.

b. CHANGE: Specification 01-02-01, Item 1.39 (Liquidated Damages) i. The first sentence in this paragraph shall be replaced with the following: “It is

understood and agreed between the parties hereto that time is of the essence under this Contract, and that for each calendar day of delay beyond the stipulated number of calendar days awarded under this Contract, the CONTRACTOR shall pay the OWNER as liquidated damages the sum of $1,000.00 (one thousand dollars) per day.”

Prepared by: JACOB & MARTIN, LLC Firm # 2448 Consulting Engineers 3465 Curry Lane Abilene, TX 79606 _______________________________ Bidder’s Acknowledgement

Page 3: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 01 DEFINITIONS AND TERMINOLOGY

01 01 01 SUMMARY OF WORK

01 02 01 SPECIAL TECHNICAL SPECIFICATIONS AND CONDITIONS

01 03 01 MEASUREMENT AND PAYMENT

01 04 01 SUBMITTALS

01 07 01 PLANT TESTING AND STARTUP

01 09 01 DISINFECTION OF POTABLE WATER PIPING AND TANKS

DIVISION 02 - EXISTING CONDITIONS

02 01 01 SITE CLEARING

DIVISION 03 - CONCRETE

03 09 01 GENERAL CONCRETE

DIVISION 09 - FINISHES

09 01 01 COATING & PAINTING FOR NEW STEEL WATER STORAGE TANKS

09 03 01 COATING & PAINTING FOR WATER TREATMENT PLANTS

DIVISION 10 - SPECIALTIES

10 01 01 SIGNS

DIVISION 11 - EQUIPMENT

11 02 01 CHEMICAL FEED EQUIPMENT

11 02 02 CHEMICAL FEED SKID PACKAGE

11 05 01 CENTRIFUGAL PUMPS

11 11 03 TRIHALOMETHANE REMOVAL FLOATING SPRAY EQUIPMENT

DIVISION 13 - SPECIAL CONSTRUCTION

13 02 01 CHAIN LINK FENCE

13 03 01 HYDROPNEUMATIC SYSTEMS

13 04 01 STEEL DOORS AND FRAMES

PROJECT TABLE OF CONTENTS Page 1

Page 4: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

13 07 01 WELDED STEEL WATER STORAGE RESERVOIRS

13 10 01 CONCRETE BLOCK BUILDING

DIVISION 25 - INTEGRATED AUTOMATION

25 01 01 INSTRUMENTATION GENERAL PROVISIONS

25 02 01 INSTRUMENTATION EQUIPMENT

25 04 01 SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA)

DIVISION 26 - ELECTRICAL

26 00 00 BASIC ELECTRICAL REQUIREMENTS

26 01 01 GENERAL ELECTRICAL FOR SMALL BUILDINGS AND FACILITIES

DIVISION 31 - EARTHWORK

31 02 01 STRUCTURAL EXCAVATING, BACKFILLING AND COMPACTING

31 03 01 TRENCHING, BACKFILLING AND COMPACTING

31 04 01 TRENCH EXCAVATION SAFETY PROTECTION SYSTEM

31 06 01 SITE GRADING AND EARTHWORK

31 11 01 CRUSHED AGGREGATE BASE COURSE

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 02 01 SEEDING - HYDROMULCH

DIVISION 33 - UTILITIES

33 01 01 GENERAL REQUIREMENTS FOR PIPING SYSTEMS

33 01 02 FIELD TESTING OF PIPING SYSTEMS

33 01 03 DUCTILE IRON PIPE

33 01 06 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE

33 01 08 PIPE COUPLINGS AND EXPANSION JOINTS

33 01 11 HIGH-DENSITY POLYETHYLENE (HDPE) PIPE

33 02 01 MISCELLANEOUS VALVES

33 02 03 CHECK VALVES

33 02 04 GATE VALVES

PROJECT TABLE OF CONTENTS Page 2

Page 5: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

09 03 01

COATING & PAINTING FOR WATER TREATMENT PLANTS

PART 1 GENERAL

1.1 REFERENCES

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA D102 (2006) Coating Steel Water-Storage Tanks

ASTM INTERNATIONAL (ASTM)

ASTM D 2200 (2013) Standard Practice for Use of Pictorial Surface Preparation Standards and Guides for Painting Steel Surfaces

ASTM D 4417 (2003) Field Measurement of Surface Profile of Blast Cleaned Steel

ASTM D 520 (2000; R 2005) Zinc Dust Pigment

ASTM D 6386 (2010) Standard Practice for Preparation of Zinc (Hot-Dip Galvanized) Coated Iron and Steel Product and Hardware Surfaces for Painting

INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI)

ICRI 03732 (1997) Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays

NACE INTERNATIONAL (NACE)

NACE SP0178 (2007) Design, Fabrication, and Surface Finish Practices for Tanks and Vessels to be for Immersion Service

NSF INTERNATIONAL (NSF)

NSF/ANSI 61 (2010a) Drinking Water System Components - Health Effects

THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC PA 1 (2000; E 2004) Shop, Field, and Maintenance Painting of Steel

SSPC PA 2 (2004) Measurement of Dry Coating Thickness With Magnetic Gages

SSPC SP 1 (1982; E 2004) Solvent Cleaning

SSPC SP 10/NACE No. 2 (2007) Near-White Blast Cleaning

SECTION 09 03 01 Page 1

Page 6: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

SSPC SP 11 (1987; E 2004) Power Tool Cleaning to Bare Metal

SSPC SP 2 (1982; E 2004) Hand Tool Cleaning

SSPC SP 3 (1982; E 2004) Power Tool Cleaning

SSPC SP 5/NACE No. 1 (2007) White Metal Blast Cleaning

SSPC SP 6/NACE No.3 (2007) Commercial Blast Cleaning

SSPC SP 7/NACE No.4 (2007) Brush-Off Blast Cleaning

SSPC VIS 1 (2002; e 2004) Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning

1.2 WORK INCLUDED

A. The work of this section includes the coating of all interior surfaces, and the painting of all exterior surfaces.

1.3 RELATED WORK

N/A

1.4 CONTRACTOR QUALIFICATIONS

A. The CONTRACTOR shall have three years practical experience and successful history in the application of specified product to surfaces of steel water tanks. Upon request, he shall substantiate this requirement by furnishing a list of references and job completions.

B. The CONTRACTOR shall submit with his bid a written statement by the coatings manufacturer stating that the CONTRACTOR is familiar with the materials specified and has workers capable of performing the work specified herein.

C. The personnel performing the work shall be knowledgeable and have the required experience and skill to adequately perform the work for this project, in accordance with SSPC PA 1 .

1.5 QUALITY ASSURANCE

A. General: Quality assurance procedures and practices shall be utilized to monitor all phases of surface preparation, application and inspection throughout the duration of the project. Procedures or practices not specifically defined herein may be utilized provided they meet recognized and accepted professional standards and are approved by the ENGINEER.

B. Surface Preparation: Surface preparation will be based upon

comparison with: SSPC VIS 1 , ASTM D 2200 , "Pictorial Surface Preparation Standards for Painting Steel Surfaces", ASTM D 4417 or NACE Standard RP0287-87 "Field Measurement of Surface Profile of Abrasive Blast Cleaned Steel Surfaces Using a Replica Tape". In all cases the written standard shall take precedence over the visual standard. In addition, NACE SP0178, "Fabrication Details, Surface Finish Requirements, and Proper Design Considerations for Tanks and

SECTION 09 03 01 Page 2

Page 7: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

Vessels to be Lined for Immersion Service", along with the Visual Comparator, shall be used to verify the surface preparation of welds.

C. Application: No coating or paint shall be applied when: 1) the surrounding air temperature or the temperature of the surface to be coated or painted is below the minimum surface temperature for the products specified herein, 2) rain, snow, fog or mist is present, 3) the surface temperature is less than 5F above the dew point, 4) the air temperature is expected to drop below the minimum temperature for the products specified within six hours after application of coating. Dewpoint shall be measured by use of an instrument such as a Sling Psychrometer in conjunction with U.S. Department of Commerce Weather Bureau Psychometric Tables. If any of the above conditions are prevalent, coating or painting shall be delayed or postponed until conditions are favorable. The day's coating or painting shall be completed in time to permit the film sufficient drying time prior to damage by atmospheric conditions.

D. Coating Thickness: Thickness of coatings and paint shall be measured checked according to the procedures outlined in SSPC PA 2 with a non-destructive, magnetic-type thickness gauge that has been calibrated according to the procedures outlined in SSPC PA 2 . Pass/fail criteria shall require that ninety (90) percent of the spot measurements (average of 3 gauge readings within a 1.5 inch diameter area) be at or above the minimum specified dry film thickness. Of the remaining ten (10) percent of the spot measurements (average of 3 gauge readings within a 1.5 inch diameter area) that are below the minimum specified dry film thickness, they shall be no less than ninety (90) percent of the minimum specified dry film thickness. Areas that fail to meet these criteria shall be corrected at no expense to the OWNER. Use of an instrument such as a Tooke Gauge, precision groove grinder, etc. is permitted if a destructive test is deemed necessary by the ENGINEER and the total DFT is less than 50 mils.

E. Holiday (Pinhole) Testing: The integrity of interior coated surfaces shall be tested for holidays in accordance with NACE Standard SP0188. For dry films less than 20 mils, a non-destructive holiday detector shall not exceed 67.5 volts, nor shall destructive holiday detector exceed the voltage recommended by the manufacturer of the coating system. A solution of 1 ounce non-sudsing type wetting agent, such as Kodak Photo-Flo, and 1 gallon of tap water shall be used to perform the holiday testing. For coating thickness at 20 mils and greater, a high voltage Tinker & Rasor AP/W holiday tester shall be used. Contact coating manufacturer for voltage recommendations and curing parameters.

All pinholes and/or holidays shall be marked and repaired in accordance with the manufacturer's printed recommendations and retested. No pinholes or other irregularities will be permitted in the final coating.

F. Inspection Devices: The CONTRACTOR shall furnish, until final acceptance of coating and painting is accepted, inspection devices in good working condition for detection of holidays and measurement of dry film thickness of coating and paint. The CONTRACTOR shall also furnish U.S. Department of Commerce, National Bureau of Standards certified thickness calibration plates and/or plastic shims, depending upon the thickness gauge used, to test the accuracy of dry film

SECTION 09 03 01 Page 3

Page 8: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

thickness gauges and certified instrumentation to test the accuracy of holiday detectors. Dry film gauges and holiday detectors shall be made available for the ENGINEER's use at all times until final acceptance of application. Holiday detection devices shall be operated in the presence of the ENGINEER.

G. Inspection: Inspection for this project shall consist of 'hold point' inspections. The ENGINEER or his representative shall inspect the surface prior to abrasive blasting, after abrasive blasting but prior to application of coating materials, and between subsequent coats of material. Final inspection shall take place after all coatings are applied, but prior to placing the tank in service. CONTRACTOR will insure that sufficient rigging is in place so that the ENGINEER or his representative shall be able to conduct the required inspections.

H. Warranty Inspection: Warranty inspection shall be conducted during the eleventh month following acceptance of all coating and painting work. All defective work shall be repaired in accordance with this specification and to the satisfaction of the ENGINEER and/or OWNER.

Specifier Note: The warranty inspection must be scheduled and coordinated by the ENGINEER or the OWNER.

1.6 SAFETY AND HEALTH REQUIREMENTS

A. General: In accordance with requirements set forth by regulatory agencies applicable to the construction industry and manufacturer's printed instructions and appropriate technical bulletins and manuals, the CONTRACTOR shall provide and require use of personal protective lifesaving equipment for persons working on or about the project site.

B. Head and Face Protection and Respiratory Devices: Equipment shall include protective helmets which shall be worn by all persons while in the vicinity of the work. In addition, workers engaged in or near the work during sandblasting shall wear eye and face protection devices and air purifying halfmask or mouthpiece respirators with appropriate filters. Barrier creams shall be used on any exposed areas of skin.

C. Ventilation: Where ventilation is used to control hazardous exposure,

all equipment shall be explosion-proof. Ventilation shall reduce the concentration of air contaminants to a degree a hazard does not exist. Air circulation and exhausting of solvent vapors shall be continued until coatings have fully cured.

D. Sound Levels: Whenever the occupational noise exposure exceeds maximum allowable sound levels, the CONTRACTOR shall provide and require the use of approved ear protection devices.

E. Illumination: Adequate illumination shall be provided while work is in progress, including explosion-proof lights and electrical equipment. Whenever required by the ENGINEER, the CONTRACTOR shall provide additional illumination and necessary supports to cover all areas to be inspected. The level of illumination for inspection purposes shall be determined by the inspector.

F. Temporary Ladders and Scaffolding: All temporary ladders and scaffolding shall conform to applicable safety requirements. They shall be erected where requested by the ENGINEER to facilitate inspection and be moved by the CONTRACTOR to locations requested by

SECTION 09 03 01 Page 4

Page 9: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

the ENGINEER.

1.7 DELIVERY, STORAGE AND HANDLING

A. All materials shall be brought to the jobsite in original sealed containers. They shall not be used until the ENGINEER has inspected the contents and obtained data from information on containers or label. Materials exceeding storage life recommended by the manufacturer shall be rejected.

B. All coatings and paints shall be stored in enclosed structures to protect them from weather and excessive heat or cold. Flammable coatings and paints must be stored to conform with City, County, State and Federal safety codes for flammable coating or paint materials. At all times coatings and paints shall be protected from freezing.

PART 2 PRODUCTS

2.1 GENERAL

A. All materials shall be lead-free as defined by the Consumer Product Safety Act, Part 1303.

B. All zinc dust pigment contained in any zinc-rich material shall meet the requirements of ASTM D 520 as regards zinc content and purity.

C. All materials for the interior wetted portion of the tank shall meet the requirements of NSF/ANSI 61 for potable water contact.

D. All catalyzed polyurethane products shall meet the minimum requirements of SSPC Paint Specification Number 36, Level 3 Performance Level.

E. No products containing MOCHA shall be allowed.

2.2 ACCEPTABLE MANUFACTURERS

A. Materials specified are those that have been evaluated for the specific service. Products of the Tnemec Company, Inc. are listed to establish a standard of quality. Equivalent materials of other manufacturer's may be submitted on written approval of the ENGINEER. As part of the proof of equality, the ENGINEER will require at the cost of the CONTRACTOR, certified test reports from a nationally known, reputable and independent testing laboratory conducting comparative tests as directed by the ENGINEER between the product specified and the requested substitution.

B. Requests for substitution shall include manufacturer's literature for each product giving name, product number, generic type, descriptive information, solids by volume, recommended dry film thickness and certified lab test reports showing results to equal the performance criteria of the products specified herein. In addition, a list of five projects shall be submitted in which each product has been used and rendered satisfactory service.

C. All requests for product substitution shall be made at least 10 days prior to the bid date.

D. Any material savings shall be passed to the OWNER in the form of a

SECTION 09 03 01 Page 5

Page 10: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

contract dollar reduction.

E. Manufacturer's color charts shall be submitted to the ENGINEER at least 30 days prior to coating and/or paint application. General CONTRACTOR and Painting CONTRACTOR shall coordinate work so as to allow sufficient time (normally seven to ten days) for paint to be delivered to the job site.

2.3 MATERIAL PREPARATION

A. Mix and thin materials according to manufacturer's latest printed instructions.

B. Do not use materials beyond manufacturer's recommended shelf life.

C. Do not use mixed materials beyond manufacturer's recommended pot life.

D. Do not split kits of multi-component products.

2.4 SUBMERGED & INTERMITTENTLY SUBMERGED COATING SCHEDULE

The number of coats called for in this schedule shall be considered minimum. If more coats are required for complete coverage and uniform appearance, they shall be applied. Colors will be selected by the OWNER from standard manufacturer's color samples

A. Ferrous Metal Tanks, Clarifiers And Clarifier Equipment, Filters, Aerators, Splitter And Junction Boxes:

1. Surface Preparation Prior to Abrasive Blast Cleaning: Weld flux and spatter shall be removed by power tool cleaning. Sharp projections shall be ground to a smooth contour. All welds shall be ground to a smooth contour as per NACE SP0178, Designation D.

2. Surface Preparation: SSPC SP 10/NACE No. 2 . Anchor profile shall be 1.5 to 2.5 mils as per ASTM D 4417, Method C or NACE Standard RP0287.

3. Coating System:

First Coat: Tnemec Series 91-H2O Hydro-Zinc applied at 2.5 to 3.5 dry mils. Thin only with approved thinner, Tnemec 41-2 or 41-3 Thinner.

Stripe Coat: Tnemec Series 20HS-15BL Pota-Pox applied by brush and scrubbed into all weld seams. In addition to weld seams, all edges, corners, bolts, rivets, pits, etc. shall receive a stripe coat.

Second Coat: Tnemec Series 141 Epoxoline applied at 10.0 to 12.0 dry mils. Thin only with approved thinner, Tnemec 41-4 Thinner.

Total dry film thickness shall be a minimum of 12.5 mils.

B. Concrete Clarifiers, Aerators, Splitter, Junction and Filter Boxes:

1. Surface Preparation: Allow concrete to cure 28 days. Level protrusions and mortar spatter. Abrasive blast as per SSPC-SP13/NACE 6 CSP 5 for "Severe Service". Fill voids and

SECTION 09 03 01 Page 6

Page 11: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

bugholes with Tnemec Series 218 MortarClad.

2. Coating System:

First Coat: Tnemec Series 20HS-1255 Beige Pota-Pox applied at 4.0 to 6.0 dry mils.

Second Coat: Tnemec Series 22-WH07 Off-White Pota-Pox 100 applied at 16.0 to 20.0 dry mils.

Total minimum dry film thickness shall be 20.0 mils.

C. Concrete Fluorosilicic Acid Injection Chambers:

1. Surface Preparation: Allow new mortar and masonry to cure 28 days. Level all protrusions and mortar spatter. Prepare as per SSPC-SP13/NACE 6 for "Severe Service", achieving a minimum surface profile equal to or greater than ICRI CSP 5. Fill voids and bugholes with Tnemec Series 215 Surfacing Epoxy or Series 218 MortarClad.

2. Painting System:

First Coat: Tnemec Series 120-5002 Beige Vinester Primer applied at 12.0-18.0 dry mils.

Second Coat: Tnemec Series 120-5001 Gray Vinester Finish applied at 12.0-18.0 dry mils.

Total dry film thickness shall be 30.0 mils minimum.

D. Galvanized Metal Surfaces:

1. Surface Preparation: Clean as per SSPC SP 1 . Abrasive blast as per SSPC-SP 16 uniformly and thoroughly to provide tooth and anchor.

2. Coating System:

First Coat: Tnemec Series 1 Omnithane applied at 2.5 to 3.5 dry mils.

Second Coat: Tnemec Series 20HS Pota-Pox applied at 4.0 to 6.0 dry mils.

Total minimum dry film thickness shall be 7.0 mils.

E. Wood Surfaces Of Baffles And Paddles:

1. Surface Preparation: All surfaces shall be dry, clean and free of all contaminants. Sand rough areas smooth. Seal knots and pitch pockets.

2. Coating System:

First Coat: Tnemec Series 20HS Pota-Pox applied at 4.0 to 6.0 dry mils.

Second Coat: Tnemec Series 141 Epoxoline applied at 8.0 to 10.0

SECTION 09 03 01 Page 7

Page 12: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

dry mils.

Total minimum dry film thickness shall be 12.0 mils.

F. Ductile Iron Piping & Valves:

1. Surface Preparation: No piping to be painted or coated shall be delivered with bitumastic coating. Clean all surfaces as per SSPC-SP1 Solvent Cleaning using stiff bristle brushes to remove all grease, oil, factory-applied tar or bitumastic coatings and any other contaminants. If surface profile is equal to or greater 1.5 mils, clean as per SSPC SP 3 taking care not to burnish the metal. If the surface profile is less than 1.5 mils, abrasive blast as per SSPC SP 7/NACE No.4 Brush-Off Blast Cleaning to achieve required profile.

2. Coating System:

First Coat: Tnemec Series 20HS Pota-Pox applied at 6.0 to 8.0 dry mils.

Second Coat: Tnemec Series 141 Epoxoline applied at 10.0 to 12.0 dry mils

Total minimum dry film thickness shall be 16.0 mils.

G. Below Grade Masonry & Concrete, Exterior (Ground) Side:

1. Surface Preparation: All surfaces shall be dry, clean and free of all contaminants. Allow new masonry to cure for 28 days. Abrasive blast as per SSPC-SP13/NACE 6 for "Severe Service", achieving a surface profile equal to ICRI CSP 3.

2. Coating System:

One Coat: Tnemec Series 46-465 H.B. Tnemecol at 8.0 to 12.0 dry mils.

For severe soil conditions: One coat of Tnemec Series 46H-413 Tneme-Tar applied at 16.0 dry mils minimum.

2.5 NON SUBMERGED PAINTING SCHEDULE

The number of coats called for in this schedule shall be considered minimum. If more coats are required for complete coverage and uniform appearance, they shall be applied. Colors will be selected by the OWNER from standard manufacturer's color samples.

A. Exterior Exposed Ferrous Metal.

1. Surface Preparation Prior to Abrasive Blast Cleaning: Weld flux and spatter shall be removed by power tool cleaning. Sharp projections shall be ground to a smooth contour. All welds shall be ground to a smooth contour as per NACE SP0178, Designation D.

2. Surface Preparation: SSPC-SP6 Commercial Blast Cleaning. Anchor profile shall be 1.5 to 2.0 mils as per ASTM D 4417, Method C or NACE Standard RP0287.

SECTION 09 03 01 Page 8

Page 13: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

3. Coating System:

First Coat: Tnemec Series 90-97 Tneme-Zinc applied at 2.5 to 3.5 dry mils.

Stripe Coat: Tnemec Series 66 HS H.B. Epoxoline applied by brush and scrubbed into all weld seams. In addition to weld seams, all edges, corners, bolts, rivets, pits, etc. shall receive a stripe coat.

Second Coat: Tnemec Series 66 HS H.B. Epoxoline applied at 4.0 to 6.0 dry mils. (Application by brush or roller may require two coats to achieve specified film thickness.)

Third Coat: Tnemec Series 700 Hydroflon applied at 2.0 to 3.0 dry mils. (Application by brush or roller may require two coats to achieve specified film thickness.)

Total minimum dry film thickness shall be 8.5 mils.

B. Interior Exposed Structural & Miscellaneous Steel, Piping, Valves, Etc.

1. Surface Preparation Prior to Abrasive Blast Cleaning: Weld flux and spatter shall be removed by power tool cleaning. Sharp projections shall be ground to a smooth contour. All welds shall be ground to a smooth contour as per NACE SP0178, Designation D for Lap, Butt & Fillet Welds.

2. Surface Preparation: SSPC SP 6/NACE No.3 . Anchor profile shall be 1.5 to 2.0 mils as per ASTM D 4417, Method C or NACE Standard RP0287.

3. Coating System:

First Coat: Tnemec Series 90-97 Tneme-Zinc applied at 2.5 to 3.5 dry mils.

Second Coat: Tnemec Series 66 HS H.B. Epoxoline applied at 4.0 to 6.0 dry mils.

Third Coat: Tnemec Series 66 HS H.B. Epoxoline applied at 4.0 to 6.0 dry mils.

Total minimum dry film thickness shall be 10.5 mils.

C. Exterior Exposed Ductile Piping.

1. Surface Preparation: Clean all surfaces as per SSPC-SP1 Solvent Cleaning using stiff bristle brushes to remove all grease, oil, factory-applied tar or bitumastic coatings and any other contaminants. If surface profile is equal to or greater 1.5 mils, clean as per SSPC SP 3 taking care not to burnish the metal. If the surface profile is less than 1.5 mils, abrasive blast as per SSPC SP 7/NACE No.4 Brush-Off Blast Cleaning to achieve required profile.

2. Coating System:

First Coat: Tnemec Series 66 HS Hi-Build Epoxoline applied at

SECTION 09 03 01 Page 9

Page 14: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

6.0 to 8.0 dry mils.

Second Coat: Tnemec Series 66 HS Hi-Build Epoxoline applied at 6.0 to 8.0 dry mils.

Third Coat: Tnemec Series 73 Endura-Shield applied at 2.0 to 3.0 dry mils.

Total minimum dry film thickness shall be 14.0 mils.

D. Interior Exposed Ductile Piping.

1. Surface Preparation: Clean all surfaces as per SSPC-SP1 Solvent Cleaning using stiff bristle brushes to remove all grease, oil, factory-applied tar or bitumastic coatings and any other contaminants. If surface profile is equal to or greater 1.5 mils, clean as per SSPC SP 3 taking care not to burnish the metal. If the surface profile is less than 1.5 mils, abrasive blast as per SSPC SP 7/NACE No.4 Brush-Off Blast Cleaning to achieve required profile.

2. Coating System:

First Coat: Tnemec Series 66 HS Hi-Build Epoxoline applied at 6.0 to 8.0 dry mils.

Second Coat: Tnemec Series 66 HS Hi-Build Epoxoline applied at 6.0 to 8.0 dry mils

Total minimum dry film thickness shall be 12.0 mils.

E. Exterior Exposed Galvanized Metal.

1. Surface Preparation: Clean as per SSPC SP 16 . Sweep-blast or mechanically abrade as per SSPC SP 16 uniformly and thoroughly to provide tooth and anchor.

2. Coating System:

First Coat: Tnemec Series 66 HS Hi-Build Epoxoline applied at 3.0 to 5.0 dry mils.

Second Coat: Tnemec Series 700 Hydroflon applied at 2.0 to 3.0 dry mils. (Application by brush or roller may require two coats to achieve specified film thickness.)

Total minimum dry film thickness shall be 5.0 mils.

F. Interior Exposed Galvanized Metal.

1. Surface Preparation: Clean as per SSPC SP 1 . Sweep-blast or mechanically abrade as per ASTM D 6386 uniformly and thoroughly to provide tooth and anchor.

2. Coating System:

First Coat: Tnemec Series 66 HS Hi-Build Epoxoline at 3.0 to 5.0 dry mils.

SECTION 09 03 01 Page 10

Page 15: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

Second Coat: Tnemec Series 66 HS Hi-Build Epoxoline at 3.0 to 5.0 dry mils.

Total minimum dry film thickness shall be 6.0 mils.

G. Exterior Exposed Plastic (PVC & CPVC) Pipe.

1. Surface Preparation: Hand sand to roughen pipe surface. Clean as per SSPC SP 1 with a suitable solvent to remove all inked numbers and provide a surface profile.

2. Coating System:

First Coat: Tnemec Series 66 HS Epoxoline applied at 2.0 to 4.0 dry mils.

Second Coat: Tnemec Series 73 Endura-Shield applied at 2.0 to 4.0 dry mils.

Total minimum dry film thickness shall be 4.0 mils.

H. Exterior Exposed Factory Primed Metal.

1. Surface Preparation: All surfaces shall be dry, clean and free of all contaminants. Clean all surfaces as per SSPC SP 2 or SSPC SP 3 . Prepare damaged areas as per SSPC SP 11 . Apply a test patch to ensure compatibility.

2. Coating System:

First Coat: Tnemec Series 1 Omnithane applied at 2.5 to 3.5 dry mils.

Second Coat: Tnemec Series 700 Hydroflon applied at 3.0 to 5.0 dry mils.

Total minimum dry film thickness shall be 5.5 mils.

I. Interior Exposed Factory Primed Metal.

1. Surface Preparation: All surfaces shall be dry, clean and free of all contaminants. Clean all surfaces as per SSPC SP 2 or SSPC SP 3 . Prepare damaged surfaces as per SSPC SP 11 . Apply a test patch to ensure compatibility.

2. Coating System:

First Coat: Tnemec Series 1 Omnithane applied at 2.5 to 3.5 dry mils.

Second Coat: Tnemec Series 66 HS Hi-Build Epoxoline applied at 4.0 to 6.0 dry mils.

Total minimum dry film thickness shall be 6.0 mils.

J. Exterior CMU Walls.

1. Surface Preparation: Allow new mortar and masonry to cure 14 days. Level all protrusions and mortar spatter. Prepare as per

SECTION 09 03 01 Page 11

Page 16: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

SSPC-SP13/NACE 6 for "Light Service". Fill voids and bugholes with Tnemec Series 218 MortarClad.

2. Coating System:

First Coat: Tnemec Series 130-6602 Envirofill applied at the rate of 60 to 80 square feet per gallon over light-weight block to provide a pinhole-free surface.

Second Coat: Tnemec Series 156 Enviro-Crete applied at 6.0 to 8.0 dry mils.

Third Coat: Tnemec Series 157 Enviro-Crete applied at 7.0 to 9.0 dry mils.

Note: Substitute Series 156 for the third coat of Series 157 for a smooth finish.

Total minimum dry film thickness shall be 14.0 mils.

K. Exterior Cast-In-Place Walls.

1. Surface Preparation: Allow new mortar and masonry to cure 14 days. Level all protrusions and mortar spatter. Prepare as per SSPC-SP13/NACE 6 for "Light Service". Fill voids and bugholes with Tnemec Series 218 MortarClad.

2. Coating System:

First Coat: Tnemec Series 180 W.B. Tneme-Crete applied at 6.0 to 8.0 dry mils. (Application by brush or roller may require two coats to achieve specified film thickness.)

Second Coat: Tnemec Series 180 W.B. Tneme-Crete applied at 6.0 to 8.0 dry mils. (Application by brush or roller may require two coats to achieve specified film thickness.)

Note: Substitute Series 181 for a sand-texture finish.

Total minimum dry film thickness shall be 12.0 mils.

L. Interior CMU Walls.

1. Surface Preparation: Allow new mortar and masonry to cure 14 days. Level all protrusions and mortar spatter. Prepare as per SSPC-SP13/NACE 6 for "Light Service". Fill voids and bugholes with Tnemec Series 218 MortarClad.

2. Coating System:

First Coat: Tnemec Series 130-6602 Envirofill applied at the rate of 60 to 80 square feet per gallon over light-weight block to provide a pinhole-free surface.

Second Coat: Tnemec Series 287 Enviro-Pox applied at 2.0 to 3.0 dry mils.

Third Coat: Tnemec Series 287 Enviro-Pox applied at 2.0 to 3.0 dry mils.

SECTION 09 03 01 Page 12

Page 17: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

Total minimum dry film thickness shall be 4.0 mils.

M. Interior Cast-In-Place Walls.

1. Surface Preparation: Allow new mortar and masonry to cure 14 days. Level all protrusions and mortar spatter. Prepare as per SSPC-SP13/NACE 6 for "Light Service". Fill voids and bugholes with Tnemec Series 218 MortarClad.

2. Coating System:

First Coat: Tnemec Series 287 Enviro-Pox applied at 2.0 to 3.0 dry mils.

Second Coat: Tnemec Series 287 Enviro-Pox applied at 2.0 to 3.0 dry mils.

Total minimum dry film thickness shall be 4.0 mils.

N. Interior Lab Floors, Locker Room Floors, Hallways.

1. Surface Preparation: Allow new mortar and masonry to cure 14 days. Level all protrusions and mortar spatter. Prepare and mechanically abrade by shot blasting as per SSPC-SP13/NACE 6 for "Severe Service", providing a surface profile equal to ICRI CSP 5. Fill voids and bugholes with Tnemec Series 218 MortarClad.

2. Coating System:

First Coat: Tnemec Series 201 Epoxoprime applied at 6.0 to 8.0 dry mils.

First Lift: Tnemec Series 222 Deco-Tread applied at a nominal thickness of 1/16" inch when broadcast to rejection.

Second Lift: Tnemec Series 222 Deco-Tread applied at a nominal thickness of 1/16" inch when broadcast to rejection.

Finish Coat: Tnemec Series 222 Deco-Tread or 284 Deco-Clear applied at 10.0 to 12.0 dry mils.

Total nominal coating thickness shall be 1/8".

O. Interior Gypsum Drywall.

1. Surface Preparation: All surfaces shall be dry, clean and free of all contaminants. Sand joint compound smooth and feather edges.

2. Coating System:

First Coat: Tnemec Series 151-1051 Elasto-Grip FC applied at 1.0 to 1.5 dry mils.

Second Coat: Tnemec Series 1029 Enduratone applied at 2.0 to 3.0 dry mils.Third Coat: Tnemec Series 1029 Enduratone applied at 2.0 to 3.0 dry mils.

SECTION 09 03 01 Page 13

Page 18: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

Total minimum dry film thickness shall be 4.0 mils.

P. Interior Concrete - Damp Areas, Locker Rooms, Chlorine Storage Areas.

1. Surface Preparation: Allow concrete to cure 28 days. Level protrusions and mortar spatter. Abrasive blast as per SSPC-SP13/NACE 6 for "Severe Service". Fill voids and bug holes with Tnemec Series 63-1500 Filler and Surfacer or Series 218 MortarClad.

2. Coating System:

First Coat: Tnemec Series 287 Enviro-Pox applied at 2.0 to 3.0 dry mils.

Second Coat: Tnemec Series 297 Enviro-Glaze applied at 2.0 to 3.0 dry mils.

Total minimum dry film thickness shall be 5.0 mils.

Q. Interior Wood Doors, Framing, Window Sash And Woodwork.

1. Surface Preparation: Sand rough areas smooth. Seal knots and pitch pockets. Fill cracks and nail holes after primer is dry. All surfaces must be dry clean and free of all oil, grease, dust, dirt and other contaminants.

2. Coating System:

First Coat: Tnemec Series 10 Tnemec Primers or Kilz Original applied at 2.0 to 3.5 dry mils.

Second Coat: Tnemec Series 1029 Enduratone applied at 2.0 to 3.0 dry mils.

Third Coat: Tnemec Series 1029 Enduratone applied at 2.0 to 3.0 dry mils. Total minimum dry film thickness shall be 6.5 mils.

R. Exterior Wood Walls, Trim And Wood Siding.

1. Surface Preparation: Sand rough areas smooth. Seal knots and pitch pockets. Fill cracks and nail holes after primer is dry. All surfaces must be dry clean and free of all oil, grease, dust, dirt and other contaminants.

2. Coating System:

First Coat: Tnemec Series 151-1051 Elasto-Grip applied at 1.0 to 1.5 dry mils.

Second Coat: Tnemec Series 1028/1029-Color Enduratone applied at 2.5 to 3.0 dry mils.

Third Coat: Tnemec Series 1028/1029-Color Enduratone applied at 2.5 to 3.0 dry mils.

Total minimum dry film thickness shall be 7.0 mils.

SECTION 09 03 01 Page 14

Page 19: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

PART 3 EXECUTION

3.1 GENERAL

A. All surface preparation, coating and painting shall conform to applicable standards of the Society for Protective Coatings, NACE International and the manufacturer's printed instructions. Materials applied to the surface prior to the approval of the ENGINEER shall be removed and re-applied to the satisfaction of the ENGINEER at the expense of the CONTRACTOR.

B. All work shall be performed by skilled craftsmen qualified to perform the required work in a manner comparable with the best standards of practice. Continuity of personnel shall be coordinated with the ENGINEER.

C. The CONTRACTOR shall provide a supervisor at the work site during cleaning and application operations. The supervisor shall have the authority to sign and change orders, coordinate work and make decisions pertaining to the fulfillment of the contract.

D. Dust, dirt, oil, grease or any foreign matter that will affect the adhesion or durability of the coating or paint must be removed by washing with clean rags dipped in an approved cleaning solvent and wiped dry with clean rags.

E. Coating and painting systems include surface preparation, prime coating and finish coatings. Unless otherwise approved in writing by the ENGINEER, prime coating shall be field applied. Where prime coatings are shop applied, the CONTRACTOR shall instruct suppliers to provide the prime coat compatible with the specified finish coat. Any off-site work which does not conform to this specification, is subjected to damage during transportation, construction or installation shall be thoroughly cleaned and touched-up in the field as directed by the ENGINEER. The CONTRACTOR shall use repair procedures which insure the complete protection of all adjacent primer. The specified repair method and equipment may include wirebrushing, hand or power tool cleaning, or dry air blast cleaning. In order to prevent injury to surrounding painted surfaces, blast cleaning may require use of lower air pressure, smaller nozzle and/or abrasive blast particles, or shorter blast nozzle distances from surface shielding and masking. If damage is too extensive or uneconomical to touch-up, the entire item shall be blasted and then coated or painted as directed by the ENGINEER.

F. The CONTRACTOR's coating and painting equipment shall be designed for application of materials specified and shall be maintained in first class working condition. Compressors shall have suitable traps and filters to remove water and oils from the air. CONTRACTOR's equipment shall be subject to approval of the ENGINEER.

G. Application of the first coat shall follow immediately after surface preparation and cleaning and stripe coat, if applicable, before rust bloom occurs or the same day, whichever is less. Any cleaned areas not receiving first coat within this period shall be recleaned prior to application of first coat. Use of dehumidification equipment shall be first reviewed by the ENGINEER and coatings manufacturer prior to deviating from this provision.

SECTION 09 03 01 Page 15

Page 20: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

H. Prior to assembly, all surfaces made inaccessible after assembly shall be prepared as specified herein and shall receive the coating or paint system specified.

3.2 SURFACE PREPARATION

A. The latest revision of the following surface preparation specifications of the Society for Protective Coatings (SSPC) shall form a part of this specification. The summaries listed below are for informational purposes; consult the actual SSPC specification for full detail.

1. Solvent Cleaning ( SSPC SP 1 ): Removal of oil, grease, soil and other contaminants by use of solvents, emulsions, cleaning compounds, steam cleaning or similar materials and methods which involve a solvent or cleaning action.

2. Hand Tool Cleaning ( SSPC SP 2 ): Removal of loose rust, loose mil scale and other detrimental foreign matter to a degree specified by hand chipping, scraping, sanding and wire brushing.

3. Power Tool Cleaning ( SSPC SP 3 ): Removal of loose rust, loose mil scale and other detrimental foreign matter by power wire brushing, power impact tools or power sanders.

4. White Metal Blast Cleaning ( SSPC SP 5/NACE No. 1 ): Air blast cleaning to a gray-white uniform metallic color until each element of surface area is free of all visible residues.

5. Commercial Blast Cleaning ( SSPC SP 6/NACE No.3 ): The removal of all visible oil, grease, dirt, dust, mil scale, rust, paint, oxides, corrosion products and foreign matter by compressed air nozzle blasting, centrifugal wheels or other specified method. Discoloration caused by certain stains shall be limited to no more than 5% of each square inch of surface area.

6. Brush-Off Blast Cleaning ( SSPC SP 7/NACE No.4 ): Air blast cleaning to remove loose rust, loose mil scale and other detrimental foreign matter to a degree specified.

7. Near-White Metal Blast Cleaning ( SSPC SP 10/NACE No. 2 ): The removal of all visible oil, grease, dirt, dust, mil scale, rust, paint, oxides, corrosion products and foreign matter by compressed air nozzle blasting, centrifugal wheels or other specified method. Discoloration caused by certain stains shall be limited to no more than 5% of each square inch of surface area.

8. Power Tool Cleaning to Bare Metal ( SSPC SP 11 ): Power tool cleaning to produce a bare metal surface and to retain or produce a minimum of 1.0 mil surface profile. This standard is suitable where a roughened, clean, bare metal surface is required, but where abrasive blasting is not feasible or permissible.

9. Surface Preparation of Concrete (SSPC-SP13/NACE 6): Surface preparation of concrete by mechanical, chemical, or thermal methods prior to the application of bonded protective coating or lining systems.

SECTION 09 03 01 Page 16

Page 21: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

B. Slag, weld metal accumulation and spatters not removed by the Fabricator, Erector or Installer shall be removed by chipping and/or grinding. All sharp edges shall be peened, ground or otherwise blunted as required by the ENGINEER. All grinding and finishing of welds, edges, etc. shall be performed prior to solvent cleaning and abrasive blasting. Welds shall be prepared as per NACE SP0178 for all interior and exterior surfaces:

C. Concrete surfaces shall be abrasive blasted to produce a minimum surface profile of equal to 40 grit sandpaper with no loose concrete remaining. This preparation will be followed by vacuum cleaning to remove all dust, dirt or friable substances leaving clean, dust free surfaces for resurfacing. Concrete surfaces rubbed smooth shall not be considered an acceptably prepared surface.

1. Prepare concrete surfaces in accordance with manufacturer's instructions, SSPC-SP 13/NACE 6 and ICRI 03732 .

2. Allow concrete to cure for a minimum of 28 days.

3. Test concrete for moisture in accordance with ASTM D 4263 and F 1869.

4. Abrasive blast surface to remove laitance and solid contaminants and to provide clean, sound substrate with uniform anchor profile.

5. Fill holes, pits, voids, and cracks with Tnemec Series 218 MortarClad.

6. Ensure surfaces are clean, dry, and free of oil, grease, chalk, form release agents, and other contaminants.

D. Field blast cleaning for all surfaces shall be by dry method unless otherwise directed. Blast nozzles shall be venturi-type nozzles with a minimum pressure at the nozzle of 90 psi.

E. Particle size of abrasives used in blast cleaning shall be that which will produce a 1.5 - 2.5 mil (37.5 microns - 65.0 microns) surface profile or in accordance with recommendations of the manufacturer of the specified coating or paint system to be applied.

If the profile of the blasted steel exceeds the profile specified above, the CONTRACTOR shall be required to do one or both of the following:

1. Reblast the surface using a finer aggregate in order to produce the required profile.

2. Apply a thicker prime coat, if possible given the limitations of the products being applied, in order to adequately cover the blast profile.

F. Abrasive used in blast cleaning operations shall be new, washed, graded and free of contaminants that would interfere with adhesion of coating or paint and shall not be reused unless specifically approved in writing by the ENGINEER.

G. During blast cleaning operations, caution shall be exercised to insure that existing coatings or paint are not exposed to abrasion from blast

SECTION 09 03 01 Page 17

Page 22: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

cleaning.

H. The CONTRACTOR shall keep the area of his work and the surrounding environment in a clean condition. He shall not permit blasting materials to accumulate as to constitute a nuisance or hazard to the accomplishment of the work, the operation of the existing facilities or to the surrounding environment.

I. Blast cleaned surfaces shall be cleaned prior to application of specified coatings or paint. All surfaces shall be free of dust, dirt, and other residue resulting from the abrasive blasting operation. No coatings or paint shall be applied over damp or moist surfaces.

J. All welds shall be neutralized with a suitable chemical compatible with the specified coating or paint.

K. Pitted areas on ferrous metal scheduled for immersion shall be repaired by either filling with Tnemec Series 63-1500 Epoxy Filler and Surfacer or by welding. Epoxy filler shall be feathered smooth. No protrusions or spatter will be allowed. Pits deeper than 1/8" shall be filled by welding.

L. Specific Surface Preparation: Surface preparation for the specific system shall be as noted in Sections 2.4, 2.5.

3.3 APPLICATION - GENERAL

A. Coating and paint application shall conform to the requirements of SSPC PA 1 , latest revision, for "Shop, Field and Maintenance Painting".

B. Thinning shall be permitted only as recommended by the manufacturer and approved by the ENGINEER, and utilizing the thinners stated in Sections 2.4, 2.5.

C. Each application of coating or paint shall be applied evenly, free of brush marks, sags, runs, with no evidence of poor workmanship. Care shall be exercised to avoid lapping on glass or hardware. Coatings and paints shall be sharply cut to lines. Finished surfaces shall be free from defects or blemishes.

D. Protective coverings or drop cloths shall be used to protect floors, fixtures and equipment. Care shall be exercised to prevent coatings or paints from being spattered onto surfaces which are not to be coated or painted. Report to the ENGINEER surfaces from which materials cannot be satisfactorily removed.

E. When two coats of coating or paint are specified, where possible, the first coat shall contain sufficient approved color additive to act as an indicator of coverage or the two coats must be of contrasting color.

F. Film thickness per coat as specified in Sections 2.4, 2.5 are the minimum required. If roller application is deemed necessary, the CONTRACTOR shall apply additional coats as to achieve the specified thickness.

G. All material shall be as specified.

SECTION 09 03 01 Page 18

Page 23: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

3.4 COATING SYSTEMS APPLICATION

A. After completion of surface preparation as specified for the specific system, materials shall be applied as noted in Sections 2.4, 2.5.

B. Care shall be taken so as to eliminate overspray and dry spray on the tank interior. Where such conditions are encountered, the surface shall be cleaned of all over spray and dry spray prior to the application of the succeeding coat.

C. Areas rendered inaccessible after tank erection such as the spaces between roof plates and rafters shall receive the full coating system prior to erection and/or assembly.

3.5 COLOR SCHEME

A. The ENGINEER shall select colors for the project. The CONTRACTOR shall submit current charts of the manufacturer's available colors to the ENGINEER thirty (30) days prior to the start of coating and painting.

3.6 DISINFECTION

A. Disinfection of interior surfaces shall be performed in the presence of the ENGINEER in accordance with all the requirements of applicable AWWA Standards and regulatory agencies.

B. Disinfection shall be performed after protective coatings have been applied to the interior surfaces and allowed to thoroughly cure.

C. Prior to disinfecting, the complete interior shall be washed down with clean water and thoroughly flushed out.

D. All interior surfaces shall be thoroughly washed with a solution having a minimum chlorine content of 50 PPM. Chlorine solution accumulated on the bottom shall be drained to waste. Rinsing with clean water is not required.

3.7 SOLVENT VAPOR REMOVAL

A. All solvent vapors shall be completely removed by suction-type exhaust fans and blowers before placing tank in operating service.

B. All solvent vapors will be exhausted both during and after coating application as per AWWA D102 to allow the proper curing of the coating material.

C. Ventilation shall be continued until such time as the coating has reached "full cure" as specified by the coating manufacturer.

3.8 CLEAN UP

A. Upon completion of the work, all staging, scaffolding and containers shall be removed from the site or destroyed in a manner approved by the ENGINEER. Coating or paint spots or oil stains upon adjacent surfaces shall be removed and the jobsite cleaned. All damage to surfaces resulting from the work of this section shall be cleaned, repaired or refinished to the satisfaction of the ENGINEER at no cost to the OWNER.

SECTION 09 03 01 Page 19

Page 24: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

-- End of Section --

SECTION 09 03 01 Page 20

Page 25: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

13 04 01

STEEL DOORS AND FRAMES

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Steel doors.

B. Steel frames.

C. Steel sidelights and borrowed lights.

1.2 REFERENCES

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI/SDI A250.10 (R2004)Test Procedure and Acceptance Criteria for — Prime Painted Steel Surfaces for Steel Doors and Frames

ASTM INTERNATIONAL (ASTM)

ASTM A1008/A1008M (2010) Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy and High-Strength Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardened

ASTM A1011/A1011M (2010) Standard Specification for Steel, Sheet, and Strip, Hot-Rolled, Carbon, Structural, High-Strength Low-Alloy and High-Strength Low-Alloy with Improved Formability and Ultra-High Strength

ASTM A568/A568M (2009a) Standard Specifications for Steel, Sheet, Carbon, Structural, and High-Strength, Low-Alloy, Hot-Rolled and Cold-Rolled, General Requirements for

ASTM A653/A653M (2010) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process

ASTM A879/A879M (2006) Standard Specification for Steel Sheet, zinc Coated by the Electrolytic Process for Applications Requiring Designation of the Coating Mass on Each Surface

ASTM A924/A924M (2010a) Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process

SECTION 13 04 01 Page 1

Page 26: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 80 (2010; TIA 10-2) Standard for Fire Doors and Other Opening Protectives

STEEL DOOR INSTITUTE (SDI/DOOR)

SDI/DOOR 111 (2009) Recommended Selection and Usage Guide for Standard Steel Doors, Frames and Accessories

SDI/DOOR A250.11 (2001) Recommended Erection Instructions for Steel Frames

SDI/DOOR A250.4 (2001) Test Procedure and Acceptance Criteria for Physical Endurance for Steel Doors and Hardware Reinforcing

SDI/DOOR A250.6 (2003; R2009) Recommended Practice for Hardware Reinforcing on Standard Steel Doors and Frames

SDI/DOOR A250.8 (2003; R2008) Recommended Specifications for Standard Steel Doors and Frames

1.3 SUBMITTALS

A. Submit under provisions of Section 01 04 01.

B. Product Data: Submit manufacturer's data sheets on each product to be used, including:

1. Preparation instructions and recommendations.

2. Storage and handling requirements and recommendations.

3. Installation methods.

C. Certificates:

1. Provide manufacturer's certification that products comply with referenced standards as applicable.

2. Provide evidence of manufacturer's membership in the Steel Door Institute.

D. Shop Drawings:

1. Show all openings in the door schedule and/or the Drawings.

2. Provide details of door design, door construction details and methods of assembling sections, hardware locations, anchorage and fastening methods, door frame types and details, anchor types and spacing, and finish requirements.

3. Provide door, frame, and hardware schedule in accordance with SDI/DOOR 111 .

SECTION 13 04 01 Page 2

Page 27: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

1.4 QUALITY ASSURANCE

A. Manufacturer Qualifications: Provide all products from a single manufacturer who is a member of the Steel Door Institute.

PART 2 PRODUCTS

2.1 MANUFACTURERS

A. Acceptable Manufacturers: Products shall be manufactured by a member of the Steel Door Institute, as follows:

1. Amweld Building Products, LLC.

2. Ceco Door Products.

3. Curries Company.

4. Deansteel Manufacturing Co.

5. Mesker Door, Inc.

6. Pioneer Industries, Inc.

7. Republic.

8. Security Metal Products Corp.

9. Steelcraft.

B. Substitutions: Not permitted.

2.2 MATERIALS

A. Doors, frames, frame anchors, and hardware reinforcing's for each of the levels and models specified shall be provided to meet the requirements of the performance levels specified. The material used in manufacturing these products and components shall comply with SDI/DOOR A250.8 . Hardware reinforcing on doors and frames shall comply with SDI/DOOR A250.6 . The physical performance levels shall be in accordance with SDI/DOOR A250.4 .

B. All steels used to manufacture doors, frames, anchors, and accessories shall meet at least one or more of the following requirements:

1. Cold rolled steel shall conform to ASTM A1008/A1008M and ASTM A568/A568M .

2. Hot rolled, pickled and oiled steel shall comply with ASTM A1011/A1011M and ASTM A568/A568M .

3. Hot dipped zinc coated steel shall be of the alloyed type and comply with ASTM A924/A924M and ASTM A653/A653M .

4. Steel Sheet, Electrolytic Zinc-Coated shall conform to ASTM A879/A879M.

SECTION 13 04 01 Page 3

Page 28: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

2.3 FRAMES

A. Provide Levels and Models in accordance with SDI/DOOR A250.8 as indicated in the door schedule.

B. Provide face welded type frames unless otherwise indicated.

C. Provide frames, with a minimum of three anchors per jamb suitable for the adjoining wall construction. Provide anchors of not less than 0.042 inch (1.0 mm) in thickness or 0.167 inch (4.2 mm) diameter wire. Frames over 7 feet 6 inches (2286 mm) shall be provided with an additional anchor per jamb.

J. Base anchors shall be provided, with minimum thickness of 0.042 inch (1.0mm).

K. Prepare all frames for all mortise template hardware and reinforced only for surface mounted hardware. Drilling and/or tapping shall be completed by others.

L. Minimum hardware reinforcing gages shall comply with Table 4 of SDI/DOOR A250.8 .

M. Provide glazing stops and beads where glazed lights are indicated.

2.4 DOORS

A. Doors: Provide doors in accordance with ANSI/SDI A250.8 and in the configuration and sizes as indicated on the door schedule.

B. End closure: The top and bottom of the doors shall be closed with channels or closures. The channels or closures shall have a minimum material thickness of 0.042 inch (1.0 mm).

C. Core: Provide in accordance with SDI/DOOR A250.8 .

D. Door edge design: Provide in accordance with SDI/DOOR A250.8 .

E. Minimum hardware reinforcing gages shall comply with Table 4 of SDI/DOOR A250.8 .

F. Provide louvers and vision lites where indicated on the Drawings in

accordance with SDI/DOOR A250.8 .

G. Provide steel astragals where indicated on the Drawings or where required by the manufacturer or NFPA 80 .

2.5 FABRICATION

A. Fabricate doors and frames in accordance with SDI/DOOR A250.8 .

B. Prime finish: Doors and frames shall be thoroughly cleaned, and chemically treated to insure maximum paint adhesion. All surfaces of the door and frame exposed to view shall receive a factory applied coat of rust inhibiting primer, either air-dried or baked-on. The finish shall meet the requirements for acceptance stated in ANSI/SDI A250.10 . All exterior door frames to be galvanized prior to applying the primer finish.

SECTION 13 04 01 Page 4

Page 29: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

C. Design clearances: Fabricate doors and frames to maintain the following clearances:

1. The clearance between the door and frame shall be 1/8 inch (3.2 mm) in the case of both single swing and pairs of doors.

2. The clearance between the meeting edges of pairs of doors shall be 3/16 inch (4.8 mm) plus or minus 1/16 inch (1.6 mm). For fire rated applications, the clearances between the meeting edges of pairs of doors shall be 1/8 inch (3.2 mm) plus or minus 1/16 inch (1.6 mm).

3. The clearance measured from the bottom of the door to the bottom of the frame (undercut) shall be a maximum of 3/4 inch (19.1 mm) unless otherwise specified. Fire door undercuts shall comply with NFPA 80 .

4. The clearance between the face of the door and the stop shall be 1/16 inch (1.6 mm) to 3/32 inch (2.4 mm).

5. All clearances shall be, unless otherwise specified in this document, subject to a tolerance of plus or minus 1/32 inch (0.8 mm).

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify that project conditions are suitable before beginning installation of frames. Do not begin installation until conditions have been properly prepared.

1. Verify that drywall construction walls are the correct thickness.

3.2 INSTALLATION

A. Install frames plumb, level, rigid, and in true alignment in accordance with SDI/DOOR A250.11 .

B. Doors shall be installed and fastened to maintain alignment with frames to achieve maximum operational effectiveness and appearance. Doors shall be adjusted to maintain perimeter clearances specified. Shimming shall be performed by the installer as needed to assure the proper clearances are achieved.

3.3 ADJUST AND CLEAN

A. Adjust doors for proper operation, free from binding or other defects.

B. Clean and restore soiled surfaces. Remove scraps and debris and leave site in a clean condition.

3.4 PROTECTION

A. Protect installed products until completion of project.

B. Touch-up, repair or replace damaged products before Substantial Completion.

SECTION 13 04 01 Page 5

Page 30: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

3.5 SCHEDULE

A. Refer to Door and Frame Schedule appended to this section.

-- End of Section --

SECTION 13 04 01 Page 6

Page 31: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

11 02 01

CHEMICAL FEED EQUIPMENT

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

HYDRAULIC INSTITUTE (HI)

HI 7.1-7.5 (2006) Controlled Volume Metering Pumps

NSF INTERNATIONAL (NSF)

NSF/ANSI 61 (2010a) Drinking Water System Components - Health Effects

UNDERWRITERS LABORATORIES (UL)

UL 778 (2010; Reprint Jan 2011) Standard for Motor-Operated Water Pumps

1.2 WORK INCLUDED

Furnishing, installing (by General CONTRACTOR), and testing (by General CONTRACTOR) of all chemical feed equipment including gas chlorination equipment and liquid chemical feed systems.

1.3 QUALITY ASSURANCE

A. Chemical feed equipment may be rejected for failure to meet any of the requirements of this specification.

B. Inspection: The quality of all chemical feed equipment, materials, and process or manufacture shall be subject to the inspection and approval of the ENGINEER.

C. All surfaces and materials in contact with water, or in contact with a chemical being added to water that is being treated for potable use, shall conform to NSF/ANSI 61 and be certified by an organization accredited by ANSI, or shall meet the TCEQ requirements for contact with potable water.

1.4 SUBMITTALS

A. The manufacturer shall submit complete shop drawings and engineering data to the OWNER or ENGINEER, upon request. These submittals shall include, at a minimum:

1. Drawings showing plan and elevation views of each chemical feed system.

SECTION 11 02 01 Page 1

Page 32: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

2. Control system layout drawing.

3. Control systems electrical diagram.

4. Manufacturer’s catalogue information on major system components.

5. Statement of design conditions and performance guarantee.

6. Statement of warranty.

B. The manufacturer shall submit complete Operation and Maintenance manuals to the OWNER. These manuals shall include at a minimum:

1. Information in hazards associated with the system and the appropriate safety precautions.

2. Material Safety Data Sheets.

3. Equipment installation instructions.

4. Equipment startup instructions.

5. Equipment maintenance procedures.

6. Troubleshooting guide.

7. Individual operation and maintenance information on major systemcomponents.

C. Submit affidavits of compliance with the referenced standards. Chemical feed equipment submitted upon without the affidavits of compliance shall be returned without review.

1.5 SUBSTITUTIONS

Any substitutions or deviations in equipment or arrangement from that shown on the drawings specified herein shall be the responsibility of the Manufacturer or CONTRACTOR. Any deviations must be accompanied by detailed structural, mechanical, electrical drawings and data for review by the ENGINEER. All costs associated with review of the substitutions ordeviations and costs associated with project drawing changes as a result of approval shall be borne by the Manufacturer or CONTRACTOR. There shall be no additional costs to the OWNER due to substitutions or deviations.

1.6 DELIVERY, STORAGE AND HANDLING

A. Materials are to be marked or tagged with part number and order number for field assembly requirements.

B. Touch-up paint with instructions for applications is to be supplied by the Manufacturer for application by the CONTRACTOR.

C. All supports, members, and miscellaneous parts shall be packaged forshipment in such manner to prevent abrasion or scratching.

SECTION 11 02 01 Page 2

Page 33: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

PART 2 PRODUCTS

2.1 CHLORINE (GAS) FEED EQUIPMENT

A. Direct Cylinder Mounted Gas Chlorination System: The chlorinator shall have a maximum capacity of 25 pounds per day (ppd) of chlorine feed and shall be equipped with a chlorine flow meter of 25 pounds per day (ppd).

The chlorinator shall be of modular design consisting of a vacuum regulator, flow meter/rate valve panel, and ejector/check valve. Each of these assemblies shall be capable of being individually located wherever safety and/or operator convenience dictates.

B. Direct Cylinder Mounted Automatic Switchover Gas Chlorination System: The chlorinator shall have a maximum capacity of 25 pounds per day (ppd) of chlorine feed and shall be equipped with a chlorine flow meter of 25 pounds per day (ppd).

The chlorinator shall be of modular design consisting of two (2) automatic switchover vacuum regulators, one (1) pressure relief/vent valve, one (1) flow meter/rate valve panel, and one (1) ejector/check valve. Each of these assemblies shall be capable of being individually located wherever safety and/or operator convenience dictates.

C. Universal Chlorine Ton Container Adaptor: The ton container adaptor shall be designed to mount directly onto the gas outlet valve of the ton container by means of a positive yoke type clamp. The yoke clamp shall have an integral tightening screw with a slide bar handle. The adaptor shall contain an auxiliary chlorine valve which shall permit the mounting of a standard direct cylinder mounted chlorinator vacuum regulator.

D. Automatic Flow Proportioning: The automatic flow proportioning device shall be designed to control the feed rate of chlorine gas when treating varying water flow rates. Devise shall be Superior Series 2000 Autovalve, or approved equal.

E. Acceptable Manufacturers:

1. Chemical Injection Technologies, Inc.

2. Or approved equivalent.

2.2 CYLINDER SCALES

A. Chlorine or SO2 Cylinder scale shall be of the hydraulic cell type. Scale platform shall be constructed of non-corrosive 1" (25mm) PVC plastic and sized to accept one (1) 150 lb/68kg. cylinder each. A total of 2 CL2/SO2 cylinders shall be weighed. Platform height shall be no more than 1-5/8" (38mm) to allow easy handling and unloading of cylinders. Platform scale coating system shall be a minimum dry thickness of 80 mils and be resistant to moisture, chemicals, abrasion, impact and UV light.

B. Load cell shall be of the temperature-stable, rolling diaphragm type. Flexible PVC coated copper tubing shall lead from the load cell to allow easy wall mounting of the dial and shall be 6 ft. in

SECTION 11 02 01 Page 3

Page 34: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

length (6 ft./2M standard length). Load cell system shall require no electric power and shall be immune to all RFI/EFI, power failures and lightening strikes. Cylinder chaining bracket shall be wall mounted and use a double coil chain and a spring loaded snap hook to secure cylinder. Chaining Bracket shall have an integral tool rack for storing cylinder change-out tools.

C. Dial diameter shall be at least 4-1/2"/114mm and read zero to 200 lbs. (100kg) net with provision for tare adjustment. Dial shall be temperature stable with damper installed to prevent shock damage.

D. Scale shall carry Full Five (5) Year Factory Warranty. "Limited" Warranties shall be considered unacceptable.

E. Full scale accuracy shall be better than 1%. Scale shall be CHLOR-SCALE® 150 with TUF-COAT TM coating and CENTURY® dial indicator, Model 4D150-2 as manufactured by FORCE FLOW, 2430 Stanwell Drive., Concord, CA 94520 USA (www.forceflow.com) or approved equal.

2.3 CHEMICAL METERING PUMPS

A. Pumps shall comply with the latest editions of the following codes and standards:

1. UL 778

2. NEMA 4X (IP65)

3. Hydraulic Institute Standards HI 7.1-7.5

4. National Electric Code

B. The pump mechanism shall be totally enclosed with no exposed moving parts. Metering pump shall be capable of pumping a maximum of 2.3 GPH against a maximum pressure of 50 PSI. Stroke length shall be adjustable from 20% to 100% by means of a readily accessible knob.

C. Acceptable Manufacturers:

1. Walchem Corporation.

2. LMI Milton Roy.

3. Or approved equivalent.

D. Two pumps shall be provided at each pump station - one pump in service and one shelf spare.

2.4 CHEMICAL METERING PUMP SKID

A. General. The operation of the Chemical Feed System shall be controlledat the Ranger Pump Station to turn ON and OFF based on the fill valve status.

B. The Chemical Metering Pump Skid shall contain the following:

1- Control Enclosure

2- Chemical Dosing Pumps

SECTION 11 02 01 Page 4

Page 35: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

1- Pressure relief valve

1- Back Pressure Valve

1- Calibration Cylinder

2.5 DAY TANK SPILL CONTAINMENT

CONTRACTOR shall provide a polyethylene spill containment pallet. The spill containment pallet shall provide spill containment for each chemical day tank as described in these Specifications. The spill containment pallet shall meet or exceed EPA requirements for secondary spill containment of hazardous materials (40 CFR 264.175). The spill containment pallet shall provide a spill capacity of 55 gallons (110% of tank capacity).

2.6 SOLENOID CONTROL

A ¾" solenoid valve with connections for installation in the water supply line for the start-stop operation of the chlorinator shall be installed in the chlorine room and attached to the wall with brackets. Solenoid valve shall be operated with an HOA switch mounted in the controller panel. Switch shall be NEMA 4, G.E. Push Button Station No. CR 2943HJ202H, or approved equal. At the Ranger Pump Station, the solenoid valve shall also be interconnected to the fill valve control circuitry so that it will operate when the fill valve opens. At the Morton Valley Pump Station, the solenoid valve shall be interconnected to operate when the Ranger Pump Station activates to pump water to the Morton Valley elevated storage tank. A ¾" pressure regulator, ¾" union and chlorine ejector are also required as shown on the Plans.

2.7 BOOSTER PUMP

If shown on the plans, the booster pump shall be a multi-stage centrifugal pump (1-2 HP) which is capable of producing the gpm and pressure required by the ejector, rotameter, and point of application pressure. The pump submittal data shall include the required pressure and flow rate for each site as required.

2.8 POWER VENTILATOR

A. The CONTRACTOR shall furnish and install one power ventilator and one gravity ventilator in each chlorination room as shown on the Plans. The 190 CFM power ventilator shall be as manufactured by ACME Engineering & Mfg., or equal with totally enclosed motor, square damper with insect screen, and fan guard. Power ventilator shall be installed in the top of the wall with exterior air supply to vent out the lower ventilator.

B. A gravity shutter shall be furnished and installed in the concrete opening for each ventilator on the interior. Gravity shutter shall be attached to the concrete block with 1" thick wood furring strips in a neat manner. Power shutter shall be operated by a wall switch located on the exterior of the building as noted on the Plans.

2.9 TESTING AND OPTIMIZATION EQUIPMENT

The CONTRACTOR shall provide the following testing and optimization

SECTION 11 02 01 Page 5

Page 36: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

equipment:

A. Free and Total Chlorine Field Test Kit:

1. The field test kit shall be capable of measuring the following parameters:a) Free Chlorine DPD Method 8021 0.02 to 2.00 mg/L Cl2 b) Total Chlorine DPD Method 8167 0.10 to 8.00 mg/L Cl2

2. The field test kit shall include the following equipment:a) Free and Total Chlorine Pocket Colorimeter II- (1) b) Reagents included: (100 tests, LR; or 50 tests, HR) c) Sample cells - (2) d) Scissors - (1) e) Beaker, 50 ml - (1)

B. Free Ammonia and Monochloramine Field Test Kit:

1. The field test kit shall be capable of measuring the following parameters:a) Ammonia 0.02 - 0.50 mg/L NH3 -Nb) Monochloramine 0.04 - 4.50 mg/L Cl2

2. The field test kit shall include the following equipment:a) Monochloramine and Free Ammonia Pocket Colorimeter II- (1) b) Reagents for 50 monochloramine and free ammonia tests c) Sample cells - (2) d) Scissors - (1) e) Beaker, 50 ml - (1)

C. Acceptable Manufacturers:

1. Hach Company

2. Or approved equivalent.

2.10 CORPORATION STOP WITH CHEMICAL INJECTION QUILL

A. Corporation Stops with a chemical injection quill shall be provided for each chlorine and LAS feed point.

B. Acceptable Manufacturers:

1. Primary Flow Systems, Inc.

2. Or approved equivalent.

2.11 PIPING AND APPURTENANCES

A. All suction and discharge piping shall be standard 1/2", Schedule 80 PVC. All valves, fittings, and connectors shall be Schedule 80 PVC.

B. All fill line piping shall be 2" Schedule 80 PVC. All fill line valves, fittings, and connectors shall be Schedule 80 PVC.

C. Fill line shall have a 2" stainless steel male camlock with a 2" plastic female camlock cap.

D. All chemical feed seals shall be compatible with the chemicals to be

SECTION 11 02 01 Page 6

Page 37: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

used in the regular operation, maintenance, and cleaning of the feed system.

E. All fittings shall be solvent-welded or threaded.

F. CONTRACTOR must install chemical feed discharge lines so that the product is injecting directly into the target streams and not onto structures or equipment. CONTRACTOR shall install a shut-off valve on discharge lines prior to entering the designated injection point.

2.12 MISCELLANEOUS EQUIPMENT

A. Calibration Cylinder. Each chemical metering pump shall be equipped with a calibration cylinder and the valves and fittings required to isolate the day tank from the calibration cylinder in order to perform a pump calibration test. The calibration cylinder shall have a maximum volume of 100 mL.

B. Pressure Relief Valve. Each chemical metering pump shall be equipped with a pressure relief valve. The pressure relief valve shall be preset for 20 p.s.i. The pressure relief valve shall be field adjustable from 0 – 150 p.s.i. via the adjustment screw with a special tool.

C. Back Pressure Valve. Each chemical metering pump shall be equipped with a back pressure valve. The back pressure valve shall be preset for 20 p.s.i. The back pressure valve shall be field adjustable from 0 – 150 p.s.i. via the adjustment screw.

D. Pulsation Dampener.

Each chemical metering pump shall be equipped with a pulsation dampner. Each pulsation dampener shall be rated to 150 p.s.i.

E. Anti-Siphon Valve. Each chemical metering pump shall be equipped with an anti-siphon valve. The relief setting shall be adjustable from 5 psi to 120 psi. Maximum inlet pressure is 150 psi.

F. In-Line Check Valve. Each chemical metering pump shall be equipped with an in-line check valve. Maximum working pressure shall be 150 psi inlet, 100 psi backpressure at 77° F.

2.13 SELF - CONTAINED BREATHING APPARATUS

A. When chlorine gas is used, a full-face self-contained breathing apparatus or supplied air respirator that meets Occupational Safety and Health Administration (OSHA) standards for construction and operation, and a small bottle of fresh ammonia solution (or approved equal) for testing for chlorine leakage shall be readily accessible outside the chlorinator room and immediately available to the operator in the event of an emergency.

PART 3 EXECUTION

3.1 INSTALLATION

The system shall be installed in accordance with the manufacturer’s instructions. All installation personnel shall be trained and qualified in the areas of plumbing, electrical work, and instrumentation as required

SECTION 11 02 01 Page 7

Page 38: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

to complete the installation.

3.2 FIELD TESTING

A. The performance of the system shall be demonstrated to feed the subject chemical at the rates set forth in these Specifications per manufacturer’s standard practice.

B. If required, Manufacturer shall make any changes to the system, at CONTRACTOR's expense, that may be necessary to assure satisfactory and efficient operation of this system.

-- End of Section --

SECTION 11 02 01 Page 8

Page 39: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

SECTION 25 04 01

SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA)

PART 1 GENERAL

1.1 WORK INCLUDED

Supervisory Control And Data Acquisition (SCADA) is a type of industrial control that is used in process applications. In a typical SCADA system, independent programmable logic controllers (PLCs) perform Input/Output (IO) control functions on field devices while being supervised by a Human Machine Interface (HMI) software package, typically running on a personal computer (PC). Process control technicians monitor PLC operations on the PC and send control commands to the PLCs as required. The HMI SCADA software may also trend and archive process data on the PC for later inspection.

The work to be performed under this Contract consists of the furnishing of all materials, tools, equipment, transportation, services, labor and superintendence necessary for the installation and completion of a SCADA system.

1.2 QUALITY ASSURANCE

All work shall be performed in a first class manner by mechanics skilled in their respective trades. The standards of work required throughout shall be such grade as will bring results of the first class only.

1.3 SPARE PARTS

A. PLC: SCADA Pack 334, Qty: 1

B. Radio: Freewave FGR-2-CE with Mfg. Hardware, Qty: 1

C. Polyphaser: 1

D. Power Supply: 1

E. Pressure Transducer: 0-40 FT, Qty: 1

F. SIU: SCADA Pack Vision 60, Qty: 1

1.4 OPERATION AND CONTRACTOR RESPONSIBILITIES

The OWNER currently has no SCADA System in place; therefore, CONTRACTOR shall be responsible for installing and integrating an entirely new system. The propsed SCADA system will include the following locations:

1. Ranger Pump Station

A fill valve will be located at this site to control flow into the proposed ground storage tank from the City of Ranger supply line. The tank will fill based on adjustable set-points visible on the SCADA System HMI of the current Morton Valley ground storage tank level. Low level lockout protection for the two pumps at this pump station will be based on an adjustable set point visible on the SCADA System HMI.

SECTION 25 04 01 Page 1

Page 40: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

A pressure gage / pressure transducer placed on the upstream side of the fill valve to monitor the pressure in the supply line from the City of Ranger. An alarm will notify personnel if this pressure falls below a level of 20 feet, with this set point adjustable by the operator. The alarm shall signal only if the fill valve is closed to prevent a false pressure reading.

Chemical feed operations at this pump station will be controlled by an Auto/Off switch at the SCADA HMI. Two separate chemical feed points are planned. The operation of the influent chemical feed points shall be controlled and operated based on the status of the tank fill valve at this location.

2. Morton Valley Pump Station

Data will be sent and received from this location back to the Ranger Pump Station via radio communication. The elevated storage tank may be utilized at this site as a means to relay signals to and from the Ranger Pump Station site and Morton Valley WSC office site.

Low level lockout protection for the two pumps at this pump station will be based on an adjustable set point visible on the SCADA System HMI.

Chemical feed operations at this pump station will be controlled by an Auto/Off switch at the SCADA HMI. Two separate chemical feed points are planned. The operation of the influent chemical feed points shall be controlled and operated based on the status of the Ranger Pump Station pumps operation at this location. Chemical feed points shall activate when the Ranger Pump Station pumps are in operation.

3. Morton Valley WSC Office - Eastland

A new desktop computer will service as the primary HMI platform at this location. Information from this HMI shall also be securely accessible remotely via a new laptop computer furnished by the CONTRACTOR as well as remotely via smartphone application or website via the OWNER's existing mobile phones (Android and iOS).

PART 2 PRODUCTS

2.1 DETAILED MATERIALS DESCRIPTION

2.1.1 PROGRAMMABLE LOGIC CONTROLLER (PLC)

A PLC is a special-purpose computer used in industrial monitoring and control applications. The PLC shall be as follows, or an approved equal:

SCADA Pack 334 (P334)Analog Inputs, On-board: 8 User SelectableAnalog Outputs, On-board: None StandardDigital Inputs, On-board: 16Digital Outputs, On-board: 10 dry contact relays or 10 solid state relays.Communication Ports: 2 RS232/RS485, 1 RS 232Integrated Ethernet Ports: 1 10/100 Base TSerial Protocols: Modbus TCP, Modbus ASCII, DNP3, and DF1.Ethernet Protocols: Modbus TCP, Modbus RTU in UDP, Modbus ASCII in UDP, DNP in TCP, DNP in UDP.

SECTION 25 04 01 Page 2

Page 41: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

2.1.2 RADIO

A radio transceiver sends commands and monitoring information between the SCADA sites via radio frequency waves. The radio waves are transmitted and received through a radio antenna mounted at each site.

Freewave:Model FGR-2-CE

Frequency Range: 902-928 MHz (FHSS)Output Power: 5 mW to 1 WattRange, Line of site: 60 MilesLink Throughput: 115.2 Kbps standard speed, 80 Kbps std. speedData Interface: SerialProtocol: RS232 / 485 / 422 or TTL, 1200 Baud to 115.2 KBaud, DCEOperating Voltage: 6 - 30 VDCOperating Temperature Range: -40 Degrees C to +75 degrees C

2.1.3 ANTENNA

Antenna shall be as follows, or an approved equal:

YAGI:New-Tronics YU10-89060

MHz: 902-928Gain Connector: 10 dBd TNC, UHF, N, SMADescription: U-Channel Construction

2.1.4 COAXIAL CABLE

Coaxial cable for each site from Polyphaser to antenna shall be as follows or an approved equal:

Times Microwave SystemsTimes Mic LMR-400 Description: 50 Ohm Coaxial Cable - Low Loss RG8/U cable Type: 3/8" Braided Shield %: 100% foil, 85% braided Center Conductor: 0.108" Solid

2.1.5 Polyphaser

Polyphaser shall be as follows, or an approved equal:

Polyphaser Corporation:IS-B50LN-C2, Broadband dc Blocked Protector Frequency: 125 - 1000 MHz RF Power: VHF 375, UHF 125 Watts Application: Single Transmitter Only Weatherized: No

2.1.6 ENCLOSURE

Hammond Manufacturing1418 N4 Series Single Door Enclosure - NEMA 4Size: 24"W x 24"H x 8"DHinge Type: Continuous

SECTION 25 04 01 Page 3

Page 42: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

Cover Type: ClampedStandards: UL 508 Type 3R, 12, 4 CSA Type 3R, 12, 4

2.1.7 24V POWER SUPPLY

IDEC: PS5R-C24Status: ActiveInput Voltage: 240VAC; 110-340VDCOutput Voltage: 24V DCOutput Power: 30WOutput Current: 1.3ASpecial Certification: UL 508Degree of Protection: IP20 (fingersafe)

2.1.8 UNINTERRUPTABLE POWER SUPPLY (UPS)

A UPS will ensure continued operation and flow of information from theradio and PLC at SCADA sites during short term power outages. UPS shall beas follows, or an approved equal:

APCAPC Back-Ups 650, for site useOutput Connection: 4 NEMA 5-15R battery backup, 4 NEMA 5-15R surgeprotection)

2.1.9 SOFTWARE

Integration software allows for the monitoring and control information from the PLC's at SCADA sites to be shown graphically on a PC computer with peripherals.

InvensysWonderware In-Touch Version 2017500 I/OWindows 8.1 / Windows 10

2.1.10 DESKTOP COMPUTER

Desktop computer shall be manufactured by Dell Corp. or an approved equal. Minimum requirements are as follows:

Precision Tower 3420Intel Core i3 (Dual-Core 3.9 GHz, 3MB, w/ HD Graphics 630Windows Professional Operating System Operating SystemMicrosoft Office 2016 Basic and Adobe Acrobat Standard DC24" monitor, flat panel w/adjustable stand, VGA/DVI4.0 GB RAM500 GB Hard Drive2-button external mouse with mouse padpcAnywhere or Laplink

2.1.11 LAPTOP COMPUTER

Laptop computer shall be manufactured by Dell Corp. or an approved equal. Minimum requirements are as follows:

Intel Core i3 (2.3 GHz, 3M CacheWindows Professional Operating SystemMicrosoft Office 2016 basic and Adobe Acrobat Standard DC

SECTION 25 04 01 Page 4

Page 43: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

15.4" Ultrasharp Wide WXG+ (1440 x 900) LED4GB RAM500 GB hard drive, 7200 RPMpcAnywhere or Laplink

2.1.12 PRINTERS

Printer shall meet the following or an approved equal:

Brother HL-3170CDW Laser Color PrinterBlack print speed: 23 pages per minuteColor print speed: 23 pages per minuteDuplex CapableRendered dotes per inch (dpi): 600 x 2400 dpi

2.1.13 AUTODIALER

An autodialer will automatically notify the OWNER if any preset alarm condition is triggered by calling up to 3 different telephone, mobile phone or pager numbers from an OWNER-furnished identified list. autodialer shall be as follows, or an approved equal:

Sensaphone Express IIMonitoring Capacity: 8 universal channels standard configurationOutput type: 1 built in relay, SPST latching 2A 250 VACExpansion: up to 32 channels available for input/output expansionMessage types: 1 recordable ID message, 1 recordable alarm message for each input channelPower Requirements: 120 VAC, 60 Watts maxInternal Battery back-up: 12 hour gel cell with built-in charger

2.1.14 SITE INTERFACE UNIT (SIU)

The SIU will allow the OWNER to access information about all SCADA sitesfrom a digital menu provided on each SU.

Control MicroSystems:

SCADAPack Vision60

Memory: EEPROM 120k Application MemoryPower: Powered from SCADAPack Serial Port, 185 mA max. @ 5VData Format: HEX, BCD, FLOAT, BIN, ASCII, Signed INT, UnsignedINT

PART 3 SCADA SITES

3.1 SITE # 1 - Ranger Pump Station

Site details, Longitude -98.692973, Latitude 32.471287, Elev 1561.5

3.1.1 FUNCTIONALITY

Monitor, record and trend Morton Valley WSC GST tank level

Monitor, record, and trend City of Ranger GST tank level via pressure gage

SECTION 25 04 01 Page 5

Page 44: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

/ transducer on upstream side of Morton Valley GST fill valve

Monitor, record and trend system pressure

Monitor, record and trend pump discharge pressure

Monitor and record flow

Monitor, record and trend CL2 Residual

Pump Status will be displayed for 2 pumps

Pump "Run Hours" and "Maintenance Hours" will be recorded for all pumps

Site power and communications status will be monitored and displayed

"Hand/Off/On (HOA)" Pump controls for 2 pumps based on user-defined setpoints and tank level of Morton Valley Elevated Storage Tank

Provide "Low Level Lockout" protection for pumps based on user-defined setpoints and tank level of Ranger Pump Station Ground Storage Tank

"Hand/Off/On (HOA)" Control of Tank Fill Valve based on user-defined setpoints and tank level of Ranger Pump Station Ground Storage Tank

"Auto/Off" Control of Chemcial Feed System (CL2 & LAS) based on status of Ranger Pump Station Tank Fill Valve

CONTRACTOR shall perform path study to determine required antennae height

3.1.2 SITE MATERIALS SUMMARY

PLC, SCADA Pack 334

SIU, SCADA Pack Vision 60

Radio

Antenna

YAGI

Coax

Polyphaser

Tower

Flowmeter(s)

Quantity: 1Application: Flow measurement from City of Ranger SupplyPipe Size and Type: 4" Ductile IronPipe Access: Exposed, inside buildingLocation of Electronics: Inside pump station building

Tank Level Transmitter

Quantity: 1

SECTION 25 04 01 Page 6

Page 45: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

Application: Morton Valley Ground Storage Tank LevelRange: 0-20 feet

Tank Level Transmitter

Quantity: 1Application: Tank Level in City of Ranger GSTRange: 0-70 Feet

Pressure Transmitter

Quantity: 1Application: Pump Discharge PressureRange: 0-200 psi

Chlorine Analyzer

Quantity: 1Application: FreeLocation: Inside Ranger Pump Station Building

Enclosure

24V Power Supply

Uninterruptible Power Supply

3.2 SITE # 2

Pump station under existing Morton Valley WSC elevated storage tank, Longitude -98.814014, Latitude 32.472984, Elev 1610

3.2.1 FUNCTIONALITY

Monitor, record and trend tank level

Monitor, record and trend system pressure

Monitor, record and trend pump discharge pressure

Monitor and record flow

Monitor, record and trend CL2 Residual

Pump Status will be displayed for 2 pumps

Pump "Run Hours" and "Maintenance Hours" will be recorded for all pumps

Site power and communications status will be monitored and displayed

"Hand/Off/On (HOA)" Pump controls for 2 pumps based on user-defined setpoints and tank level of pressure tank on site

Provide "Low Level Lockout" protection for pumps based on user-defined setpoints and tank level of Morton Valley WSC elevated storage tank

"Hand/Off/On (HOA)" Control of Pressure Tank Air Compressor based on user-defined setpoints and air pressure.

SECTION 25 04 01 Page 7

Page 46: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

"Auto/Off" Control of Chemcial Feed System (CL2 & LAS) based on status of Ranger Pump Station pumps

Antenna height shall be determined by path study performed by CONTRACTOR. Antennae may be placed on elevated storage tank if necessary.

3.2.2 SITE MATERIALS SUMMARY

PLC, SCADA Pack 334

SIU, SCADA Pack Vision 60

Radio

Antenna

OMNI

YAGI

Coax

Polyphaser

Tower

Flowmeter(s)

Quantity: 2Application: Pump Discharge FlowPipe Size and Type: 4"Pipe Access: 4" Pump Discharge LinesLocation of Electronics: Inside Pump Station building

Tank Level Transmitter

Quantity: 1Application: Elevated Storage Tank LevelRange: 0 - 150 Feet

Pressure Transmitter

Quantity: 1Application: Pump Discharge PressureRange: 0-150 psi

Chlorine Analyzer

Quantity: 1Application: FreeLocation: Inside Pump Station Building

24V Power Supply

Uninterruptible Power Supply

3.3 SITE # 3

Morton Valley WSC Office, 1704 West Commerce Street, Eastland, TX,

SECTION 25 04 01 Page 8

Page 47: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

Longitude -98.837658, Latitude 32.400887, Elev 1503 (approx.)

3.3.1 FUNCTIONALITY

Central location for receiving, recording, storing data from pump station sites. Site for main HMI functionality, autodialer for notification of alarms.

CONTRACTOR shall perform path study to determine necessary height for antennae

Existing phone service shall be used for auto-dialer functionality

3.3.2 SITE MATERIALS SUMMARY

PLC, SCADA Pack 334

Radio

Antenna

YAGI

Coax

Polyphaser

Tower

Software

Lookout

Wonderware

pcAnywhere

Desktop Computer

Laptop Computer

Printer

Uninterruptible Power Supply

Autodialer

3.4 REPORT SUMMARY

Daily Reports shall include the following at a minimum:

RANGER PUMP STATIONDaily Influent FlowPump #1 Daily Pump HoursPump #2 Daily Pump HoursInfluent Average Chlorine ResidualMorton Valley WSC Distribution Average Chlorine Residual

MORTON VALLEY PUMP STATION

SECTION 25 04 01 Page 9

Page 48: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

Pump #1 Discharge Daily FlowPump #2 Discharge Daily FlowPump #1 Daily Pump HoursPump #2 Daily Pump Hours

Alarm Report

3.5 DATA TREND SUMMARY

RANGER PUMP STATIONMorton Valley Ground Storage Tank LevelCity of Ranger Ground Storage Tank LevelInfluent Daily FlowInfluent CL2 ResidualEffluent CL2 ResidualPump Discharge Pressure

MORTON VALLEY PUMP STATIONElevated Tank LevelInfluent Daily FlowPressure Tank LevelInfluent CL2 ResidualEffluent CL2 ResidualSystem Pressure

-- End of Section --

SECTION 25 04 01 Page 10

Page 49: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

SECTION 25 02 01

INSTRUMENTATION EQUIPMENT

PART 1 GENERAL

1.1 WORK INCLUDED

The CONTRACTOR shall furnish and install instrumentation equipment as shown on the Plans and specified herein.

1.2 SUBMITTALS

Submit the following in accordance with Section 01 04 01.

PART 2 PRODUCTS

2.1 FLOWMETER

Meter for flow into Ranger Pump Station / Meters for Morton Valley Pump Station Discharge Flows

1). Krohne - Model Waterflux 3000 (4" Diameter)

2). Approved equal.

2.2 PRESSURE TRANSDUCERS

Endress+HauserCerabar T PMC131Measuring Principle: Absolute and gauge pressureSupply / Communication: 11...30V DVAccuracy: 0, 55Measuring Range:0-15 psiMax. overpressure limit: 150 psiOutput:4...20mA analogue

Endress+HauserCerabar T PMC131Measuring Principle: Absolute and gauge pressureSupply / Communication: 11...30V DVAccuracy: 0, 55Measuring Range:0-30 psiMax. overpressure limit: 270 psiOutput:4...20mA analogue

Endress+HauserCerabar T PMC131Measuring Principle: Absolute and gauge pressureSupply / Communication: 11...30V DVAccuracy: 0, 55Measuring Range:0-50 psiMax. overpressure limit: 375 psiOutput:4...20mA analogue

Endress+HauserCerabar T PMC131

SECTION 25 02 01 Page 1

Page 50: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

Measuring Principle: Absolute and gauge pressureSupply / Communication: 11...30V DVAccuracy: 0, 55Measuring Range:0-150 psiMax. overpressure limit: 600 psiOutput:4...20mA analogue

Endress+HauserCerabar T PMC131Measuring Principle: Absolute and gauge pressureSupply / Communication: 11...30V DVAccuracy: 0, 55Measuring Range:0-300 psiMax. overpressure limit: 600 psiOutput:4...20mA analogue

2.3 CHLORINE VACUUM ALARM SWITCHChemical Injection Technologies

Model: VAS-3, Digital Chlorine Vacuum Alarm SwitchHigh Vacuum AlarmLow Vacuum AlarmEnclosure: Fiberglass NEMA 4XPower: 115V AC @ 5amps general useDry Contact Relays

2.4 CAPACITIVE LEVEL MEASUREMENTEndress+Hauser

Model: Liquicap M FMI514-20mA Output with HART protocol

2.5 LOOP POWERED FIELD INDICATOREndress+Hauser

Model: RIA16Measuring Range: 4-20 mAInput: Line Voltage Drop < 4V at 3-22 mATransmission Behavior: The indicator allows the HART transmissionprotocol to pass unimpeded

PART 3 NOT USED

-- End of Section --

SECTION 25 02 01 Page 2

Page 51: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

SECTION 26 01 01

GENERAL ELECTRICAL FOR SMALL BUILDINGS AND FACILITIES

PART 1 GENERAL

This item of the Specifications covers the furnishing of all labor, materials, tools, equipment, and incidentals necessary for the installation of a complete electrical wiring and control system as shown on the Plans, specified under other items of the Specifications, and required for a finished project.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI C62.2-1987 IEEE Guide for the Application of Gapped Silicon-Carbide Surge Arresters for Alternating Current Systems

ASTM INTERNATIONAL (ASTM)

ASTM A307 (2010) Standard Specification for Carbon Steel Bolts and Studs, 60 000 PSI Tensile Strength

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA 250 (2008) Enclosures for Electrical Equipment (1000 Volts Maximum)

ANSI C80.1 (2005) American National Standard for Electrical Rigid Steel Conduit (ERSC)

ANSI C80.3 (2005) American National Standard for Electrical Metallic Tubing (EMT)

ANSI/NEMA FB 1 (2007; AMD 2010) Standard for Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit, Electrical Metallic Tubing, and Cable

ANSI/NEMA OS 1 (2008; Amd 2010) Sheet-Steel Outlet Boxes, Device Boxes, Covers, and Box Supports

ANSI/NEMA OS 2 (2008; AMD 2010) Nonmetallic Outlet Boxes, Device Boxes, Covers, and Box Supports

NEMA PB 1 (2006; Errata 2008) Panelboards

NEMA TC 2 (2003) Standard for Electrical Polyvinyl Chloride (PVC) Conduit

SECTION 26 01 01 Page 1

Page 52: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

NEMA TC 3 (2004) Standard for Polyvinyl Chloride (PVC) Fittings for Use With Rigid PVC Conduit and Tubing

NEMA WD 1 (1999; R 2005; R 2010) Standard for General Color Requirements for Wiring Devices

NEMA WD 6 (2002; R 2008) Wiring Devices Dimensions Specifications

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2011) National Electrical Code

UNDERWRITERS LABORATORIES (UL)

UL 67 (2009; Reprint Sep 2010) Standard for Panelboards

1.2 CODES AND STANDARDS

The performance of all work, testing, and completed installations covered by this contract shall conform to current standards, rules, regulations, and specifications of the following authorities:

A. National Board of fire Underwriters (National Electric Code)

B. Bureau of Standards (National electrical Safety Code)

C. National Electrical Manufacturer's Association (NEMA)

D. National electrical Contractors Association (NECA)

E. City Codes

1.3 WORKMANSHIP

All work shall be performed in a first class manner by mechanics skilled in their respective trades. The standards of work required throughout shall be such grade as will bring results of the first class only.

1.4 SUBMITTALS

The CONTRACTOR shall furnish to the ENGINEER for approval detailed electrical shop drawings cross-referenced with a schedule of materials listing all equipment the CONTRACTOR contemplates incorporating in the work. The CONTRACTOR shall also furnish to the ENGINEER four (4) sets of final electrical drawings showing all new and existing controls, equipment, and fixtures.

1.5 FIELD QUALITY CONTROL

1.5.1 WIRE AND CABLE

A. Perform field inspection and testing.

B. Inspect wire and cable for physical damage and proper connections.

SECTION 26 01 01 Page 2

Page 53: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

C. Measure tightness of bolted connections and compare torque measurements with manufacturer's recommended values.

D. Verify continuity of each branch circuit conductor.

1.5.2 WIRING DEVICES

A. Inspect each wiring device for defects.

B. Operate each wall switch with circuit energized and verify proper operation.

C. Verify that each receptacle device is energized.

D. Test each receptacle device for proper polarity.

E. Adjust devices and wall plates to be flush and level.

1.5.3 SECONDARY GROUNDING

A. Inspect all grounding an bonding system conductors and connections for tightness and proper installation.

B. Measure ground resistance from system ground connections at service entrance to convenient ground reference point using suitable ground testing equipment. Resistance shall not exceed 10 ohms.

PART 2 MATERIALS

All proposed materials shall be new unless otherwise specified, of the latest manufacture, and first class in every respect. All materials of a type for which the Underwriters Laboratories have established a standard shall be listed by the Underwriters Laboratories, Inc.,and shall have their label. Samples of materials shall be submitted for approval when so directed. Equipment, materials, and articles installed or used without such approval shall be at the risk of subsequent rejection. The schedule of materials shall include catalog numbers and specifications shall not relieve the CONTRACTOR of the responsibility for the satisfactory performance of the equipment as furnished and installed.

2.1 CONDUIT

A. DELIVERY, STORAGE, AND HANDLING

1. Deliver, store, protect, and handle products on site.

2. Accept conduit on site. Inspect for damage, remove any damaged conduit from site.

3. Protect conduit from corrosion and entrance of debris by storing above grade. Provide appropriate covering.

4. Protect PVC from sunlight.

B. PROJECT CONDITIONS

1. Verify that field measurements are as shown on the Drawings.

2. Verify routing and termination locations of conduit prior to

SECTION 26 01 01 Page 3

Page 54: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

rough-in.

3. Conduit routing is shown on Drawings in approximate locations unless dimensioned. Route as required to complete wiring system.

C. CONDUIT REQUIREMENTS

1. Minimum size: 3/4 inch unless otherwise specified.

2. Underground Installation:a. In or Under Slab on Grade: Use rigid steel conduit or thick walled PVC nonmetallic-conduit as shown on drawings.b. Minimum Size: 3/4 inch.

3. Outdoor Locations, Above grade: Use rigid steel conduit.

4. In slab Above Grade:a. Use rigid steel conduit.b. Minimum size conduit in slab: 3/4 inch to include for conduits crossing each other.

5. Wet and damp locations: Use rigid steel or schedule 40 or 80.

D. METAL CONDUIT

1. Rigid steel conduit conforming to ANSI C80.1 .

2. Intermediate Metal Conduit (IMC): Rigid Steel.

3. Fittings and conduit bodies: ANSI/NEMA FB 1 ; material to match conduit, except aluminum fittings may be used with steel conduit.

E. LIQUID-TIGHT FLEXIBLE METAL CONDUIT

1. Description: Interlocked steel construction with VC jacket.

2. Fittings: ANSI/NEMA FB 1 .

F. ELECTRICAL METALLIC TUBING (EMT)

1. Description: Galvanized tubing conforming to ANSI C80.3 .

2. Fittings and conduit bodies: Steel compression type meeting ANSI/NEMA FB 1 .

G. NONMETALLIC CONDUIT

1. Description: Schedule 80 PVC meeting NEMA TC 2.

2. Fittings and conduit bodies: shall meet NEMA TC 3.

2.2 METER LOOP

The CONTRACTOR shall furnish and install the meter loop, including Weatherhead or underground conduit and conductors, 60-cycle service with voltage(s) and location(s) as shown on the plans.

SECTION 26 01 01 Page 4

Page 55: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

2.3 PANELBOARDS

Panelboards shall conform with NEMA PB 1 and UL 67 . CONTRACTOR shall provide dead front, safety-type panel boards with voltage ratings as scheduled. Panelboards shall be circuit breaker type and suitable for the short circuit ratings specified. Panel boards shall be UL listed and manufactured by General Electric, Cutler-Hammer, Square D, Westinghouse, or equal.

Enclose panelboards located indoors in a single sheet metal cabinet with hinged front doors, catches, and locks. Provide holder for the directory on the inside of the door. Panelboard locks shall be keyed alike. Enclose panelboards located outdoors in a sheet metal cabinet without front door. Mount panel within a NEMA 4X fiberglass enclosure. Provide metal trim on panelboard to cover wire terminations. Provide space for controls, such as timeclocks and contactors, in a separate compartment with hinged doors within respective panel boards. Where limited by the height of the panels, locate controls in a separate cabinet adjacent to the respective panel board.

Molded-case breakers shall be provided with quick-male and quick-break toggle mechanism, inverse-time trip characteristics, and trip free operation on overload or short circuit. Automatic tripping shall be indicated by a handle position between the manual OFF and ON position. Provide trip ratings as indicated in the panelboard schedules. Provide lock-on or lock-off devices where indicated in the drawings. Single-pole breakers shall be full module size; two poles shall not be installed in a single module. Multiple circuit breakers shall be of the common-trip type having a single operating handle. The CONTRACTOR shall furnish ground fault interrupter (GFI), 5-ma trip, 10,000-ampere interrupting capacity circuit breakers where indicated.

A. The CONTRACTOR shall provide 3O-ampere mechanically held contactors, 100% rated for ballast and tungsten lighting loads, with coil-clearing contacts. Provide quantity of poles as indicated in the drawings.

B. The CONTRACTOR shall provide timeclocks with astro-dial, manual on/off lever, skip-a-day feature, spring-wound carryover, and NEMA 1 surface-mounted enclosure. Timing motor shall be 120 volts, 60 hertz, and switch rating shall be 40 amperes, DPST. Provide equipment to meet the following criteria: NEMA ICS 2, Class A300 Clock Timer 24 Hour Timer Astronomical Dial NEMA ICS 2 Class A150 Contacts

C. Circuit breaker current-carrying connections to the bus shall be plug-in type.

D. Bus bars shall be copper. Provide a copper ground bus bar installed on the panel board frame, bonded to the box, and containing at least 10 terminal screws.

E. Where "space only" is noted in the drawings, provide connectors and mounting brackets for the future insertion of an overcurrent device of the size indicated.

F. The CONTRACTOR shall provide typed circuit directories on the inside face of the door of each panel. Do not provide handwritten

SECTION 26 01 01 Page 5

Page 56: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

directories.

G. Panel boards shall be suitable as service entrance equipment where noted in the drawings. A factory-installed service-entrance type UL label shall be provided.

H. The CONTRACTOR shall provide nameplates as specified in 2.6 and designate the identifying nomenclature, voltage, and phase of the panel as shown in the drawings; for example, "PANEL LA, 277/480-volt, 3-phase, 4-wire, 225-ampere bus."

I. The CONTRACTOR shall stub up from the top of flush-mounted panels four 1-inch conduits to the nearest ceiling space or other accessible location and cap for future use.

J. Panelboards shall be installed so that the top of the highest circuit breaker is not more than 6 feet 6 inches above the floor or working platform.

K. Each circuit breaker shall be operated and it shall be verified that all phases of each load are disconnected.

L. CONTRACTOR shall verify that loads turn on and off at the selected times.

2.4 SWITCHBOARDS

A. Switchboards shall be manufactured by General Electric, Square D, Westinghouse, or equal.

B. Main service and distribution switchboards shall be NEMA Class 1 metal clad floor standing, dead front and rear enclosure, requiring front access only. Switchboards installed outdoors shall be provided with a NEMA 3R nonwalk-in type enclosure. A 10-inch-minimum front access space between the exterior door and the front of the interior switchboard door shall be provided. Construct sections with a minimum thickness of 12-USSG formed sheet steel and of overall dimensions that will fit within the space limitation indicated in the drawings. Service switchboards shall be provided with metering and current transformer space, pull sections, and fully removable front covers of the widths, depths, and heights required by the service utility and as necessitated by the physical requirements of the conduits and cables entering the sections. Distribution switchboards shall be provided with circuit breakers, fusible switches, space for controls behind hinged lockable doors (common keyed with panelboards), motor starters, transformers, and other equipment as indicated. Circuit breakers and fusible switches shall be provided with fault current ratings equal to or larger than the switchboard rating shown in the drawings. Switchboards shall comply with NEMA, UL, and ANSI standards for industrial control. Provide UL label on each switchboard section.

C. Switchboards shall be provided with rectangular copper bussing. Cross bussing shall be full capacity. Vertical bussing shall be full height and rated for the load to be carried, but in no case less than one-third the capacity of the main bus. Horizontal and vertical bussing shall be braced to withstand 50,000 amperes symmetrical fault current. Ground bus with a cross section meeting code requirement shall extend the entire length of the distribution sections of the switchboards. Connections shall be tin plated. Belleville dished

SECTION 26 01 01 Page 6

Page 57: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

spring washers shall be provided at each bolted joint. Heavy-duty pressure-type terminal lugs for connections of incoming and outgoing cables shall be provided. Support cables and internal wiring with bolted cleats.

D. The main disconnect device shall be as located in the drawings. The device shall be capable of being padlocked in the off position. Phase monitoring relay shall be provided to protect against undervoltage, single-phase voltage, and incorrect phase rotation. The disconnectshall be permanently marked to identify it as a service disconnecting means, in accordance with NEC Article 230,part VI(B).

E. Fusible switches shall be of the quick-make, quick-break, visible-blade type and shall be UL listed and horsepower rated. Provisions for padlocking external disconnect handles in the OFF position shall be provided. Switches shall have rejection-type fuse clips. Provide time delay, current limiting, NEMA Class RK5 fuses.

F. Circuit breakers shall be molded-case type. Quick-make and quick-break toggle mechanism, inverse time trip characteristics, and trip-free operation on overload or short circuit.

G. Automatic tripping shall be indicated by a handle position between the manual OFF and ON position. Trip ratings and number of poles shall be provided. Provide provisions for padlocking external disconnect handles in the OFF position.

H. Power circuit breakers shall be provided with the frame size and trip rating shown, fixed mounting, manually operated, with a solid-state trip device having an adjustable long time delay, adjustable instantaneous trip, and a stored-energy close and trip mechanism.

I. Power circuit breakers of the molded or insulated case type shall be provided with the frame size and trip rating shown, fixed mounting, manually or electrically operated, with a solid-state trip device having an adjustable long time delay, adjustable instantaneous trip, and a stored-energy close and trip mechanism.

J. A nameplate shall be provided for each circuit breaker or fusible switch to indicate load served. The main nameplate shall give the switchboard designation in 1/2-inch-high letters. A second line in 1/4-inch-high letters shall indicate the voltage and phases.

K. Voltmeters and ammeters shall be switchboard class with 25O-degree scale and scale range indicated in drawings. Selector switches shall be 3 phase, four position.

L. Surge arrester shall be 650-volt rated, secondary arrester complying with ANSI C62.2-1987 . Arrester shall be three-pole version suitable for indoor and outdoor use, sealed in LEXAN housing. Include mounting bracket for switchboard mounting. Arrester shall be UL listed. General Electric Model 9L 15ECCOO 1 or equal.

M. The CONTRACTOR may, in lieu of individual phase monitor relay, ammeter, voltmeter, and selector switches, provide a microprocessor-based monitoring and protective device providing electrical metering and system voltage protection. Device shall be Westinghouse IQ Data Plus, Multilin MTM Plus, or equal.

SECTION 26 01 01 Page 7

Page 58: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

N. The CONTRACTOR shall secure switchboards rigidly to walls and floors or mounting pads with anchor bolts or Phillips Drill Company concrete anchors. Anchor bolts or concrete anchors shall be carbon steel per ASTM A307, Grade B.

O. When the installation is essentially complete and the plant is in operation, check the voltage at the point of termination of the power company supply system to the project. Check voltage amplitude and balance between phases for loaded and unloaded conditions.

P. If the unbalance (as defined by NEMA) exceeds 1%, or if the voltage varies throughout the day and from loaded to unloaded conditions more than .5% of nominal, make a written request to the power company that the condition be corrected. If corrections are not made, request from a responsible power company official a written statement that the voltage variations and/or unbalance are within their normal standards.

Q. Operate each switch and circuit breaker at least three times, demonstrating satisfactory operation each time.

R. Provide six spare fuses of each type and ampere rating installed.

2.5 BUILDING LOAD CENTER AND ELECTRICAL

A. The CONTRACTOR shall furnish and install a building load center at the location shown on the Plans. The load center shall have adequate 120 vol, 230 volt, or 480 volt breakers for control of the circuit runs required. Individual breakers for outside circuits shall be ground fault type andall multiple breakers shall have an internal common trip. Load center panel shall be NEMA 3R constructed with door, and breaker ratings and circuit numbers shall be readily visible when viewing the panel directly from the front. The load center shall have a complete, detailed directory.

B. The CONTRACTOR shall furnish and install receptacles, switches and fixtures as shown on the Plans. Interior 115 volt receptacles shall be straight blade, 3-wire grounding duplex outlets, General Electric, Bryant, or equal, with decorative wall plates. Exterior 115-V receptacles shall be straight blade, 3-wire grounding duplex outlets General Electric, Bryant or equal, with weatherproof cover. Where 220-V receptacles are called for, they shall be flush type range and dryer outlets, 2 pole, 3-wire, 30 amps, General Electric, Bryant or equal.

C. Switches shall be 15, 20 or 30 amp as required, toggle type, General Electric, Bryant or equal, with decorative wall plates.

D. Lighting fixtures shall be in accordance with the fixture schedule shown on the Plans. The CONTRACTOR shall also furnish and install telephone jacks, complete with decorative wall plate, 2 in the office and 2 in the laboratory at locations designated by the OWNER if shown on the Plans. Telephone wiring shall terminate in the junction box, furnished and installed by the CONTRACTOR, located adjacent to the electrical control center.

E. The CONTRACTOR may use enclosed breakers in lieu of safety switches for the building load.

SECTION 26 01 01 Page 8

Page 59: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

2.6 WIRE AND CABLE

A. PROJECT CONDITIONS

1. Verify that field measurements are as shown on Drawings.

2. Conductor sizes are based on copper unless indicated as aluminum or "AL".

3. Wire and cable routing shown on Drawings is approximate unless dimensioned. Route wire and cable as required to meet Project Conditions. Include wire and cable lengths within 10 feet of length as shown.

4. Where wire and cable routing is not shown, and destination only is indicated, determine exact routing and lengths required.

B. WIRE AND CABLE

1. Description: Single conductor insulated wire.

2. Conductor: Copper.

3. Insulation Voltage Rating: 600 volts.

4. Insulation: NFPA 70 , type THHN, THW, or THWN.

C. SERVICE ENTRANCE CABLE

1. Description: NFPA 70 , TYPE se.

2. Conductor: Copper.

3. Insulation voltage rating: 600 volts.

4. Insulation: Type THHN, THW, or THWN.

2.7 BOXES

A. PROJECT CONDITIONS

1. Verify field measurements are as shown on Drawings.

2. Electrical boxes are as shown on Drawings in approximate locations unless dimensioned. Install at location required for box to serve intended purpose. Include installation within 10 feet of location shown.

B. OUTLET BOXES

1. Sheet metal outlet boxes: shall be galvanized steel meeting ANSI/NEMA OS 1.

2. Luminair and Equipment Supporting Boxes: Rated for weight of equipment supported, include 1/2 inch male fixture studs where required.

3. Nonmetallic Outlet Boxes: Shall meet ANSI/NEMA OS 2 .

SECTION 26 01 01 Page 9

Page 60: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

4. Cast Boxes: Shall meet ANSI/NEMA FB 1 , Type FD, cast feralloy. Provide gasketed cover by box manufacturer. Provide threaded bolts.

C. PULL AND JUNCTION BOXES

1. Sheet Metal Boxes: Shall be galvanized steel meeting ANSI/NEMA OS 1 .

2. Surface-Mounted Cast Metal Box: NEMA 250, type 4, flat-flanged, surface-mounted junction box, cast aluminum.

3. In-Ground Cast Metal Box: NEMA 250, Type 6, outside flanged, recessed cover box for flush mounting. Cast aluminum nonskid cover with neoprene gasket and stainless steel cover screws and the word "Electric" on front.

2.8 WIRING DEVICES

A. WALL SWITCHES

1. Description: NEMA WD 1, heavy duty, AC only general use snap switch.

2. Device body: Ivory plastic with toggle handle.

3. Voltage rating: 120 volts AC.

4. Current rating: 20 amperes.

5. Ratings: Match branch circuit and load characteristics.

B. RECEPTACLES

1. Description: NEMA WD 1, heavy duty general use receptacle.

2. Device body: White Plastic.

3. Configuration: NEMA WD 6, Type as specified and indicated.

4. Convenience Receptacle: Type 5-20.

C. WALL PLATES

1. Cover Plate: Galvanized Steel.

2.9 SUPPORTING DEVICES

A. MATERIAL

1. Support Channel: Galvanized or painted steel.

2. Hardware: Corrosion Resistant.

2.10 ELECTRICAL IDENTIFICATION

A. MATERIAL

1. Nameplates: Engraved three layer laminated plastic, black letters on white background.

SECTION 26 01 01 Page 10

Page 61: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

2. Tape Labels: Not allowed.

3. Wire and Cable Markers: Split sleeve or tubing type, tape acceptable provided abrasion, Heat/Cold, UV, waterproof, and spill proof resistant.

2.11 SECONDARY GROUNDING

A. SYSTEM DESCRIPTION

1. Ground electrical service system at service entrance equipment to metallic water service and to supplementary grounding electrodes as shown on Drawings.

2. Ground each separately derived system neutral to nearest effectively grounded building structural steel member or separate grounding electrode.

3. Bond together system neutrals, service equipment enclosures exposed non-current carry metal parts of electrical equipment, metal raceway systems, grounding conductor in raceways and cables, receptacle ground connectors, and piping systems.

B. MATERIALS

1. Ground rods: Copper encased steel, 5/8 inch diameter, minimum length 8 feet.

PART 3 EXECUTION

3.1 CONDUIT

1. Install conduit in accordance with NECA "Standard of Installation".

2. Install nonmetallic conduit in accordance with manufacturer's instructions.

3. Arrange supports to prevent misalignment during wiring installation.

4. Support conduit using coated steel or malleable iron straps, lay-in adjustable hangers, clevis hangers, and split hangers.

5. Group related conduit, support using conduit rack. Construct rack using steel channel, provide space on each for 25 percent additional conduits.

6. Fasten conduit supports to building structure and surfaces.

7. Do not support conduit with wire or perforated pipe straps. Remove wire used for temporary supports.

8. Do not attach conduit to ceiling support wires.

9. Arrange conduit to maintain head room and present neat appearance.

10. Route exposed conduit parallel and perpendicular to walls.

SECTION 26 01 01 Page 11

Page 62: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

11. Route conduit in and under slab from point-to-point.

12. Maintain adequate clearance between conduit and piping.

13. Maintain 12 inch clearance between conduit and surfaces with temperatures exceeding 104 degrees F (40 degrees C).

14. Cut conduit square using saw or pie cutter, de-bur cut ends.

15. Bring conduit to shoulder of fittings, fasten securely.

16. Join nonmetallic conduit using cement as recommended by manufacturer. Wipe nonmetallic conduit dry and clean before joining. Apply full even coat of cement to entire area inserted in fitting. Allow joint to cure for 20 minutes, minimum or per manufacturer recommendations.

17. Use conduit hubs or sealing locknuts to fasten conduit to sheet metal boxes in damp and wet locations and to cast boxes.

18. Install no more than equivalent of three 90 degree bends between boxes. Use conduit bodies to make sharp changes in direction, as around beams. Use factory elbows for bends in metal conduit larger than 2 inch size.

19. Avoid moisture traps, provide junction box with drain fitting at low points in conduit system.

20. Provide suitable fittings to accommodate expansion and deflection where conduit crosses control and expansion joins.

21. Provide suitable pull string in each empty conduit except sleeves and nipples.

22. Use suitable caps to protect installed conduit against entrance of dirt and moisture.

23. Ground and bond conduit.

3.2 WIRE AND CABLE

1. Verify that mechanical work likely to damage wire and cable has been completed.

2. Completely and thoroughly swab raceway before installing wire.

3. Concealed and Dry locations: Use only building wire, Type THHN/THWN insulation in raceway.

4. Exposed Dry interior location: Use only building wire, Type THHN/THWN insulation in raceway.

5. Wet or Damp interior locations: Use only building wire, Type THW/THWN insulation in raceway or underground feeder and branch-circuit cable.

6. Exterior locations: Use only building wire, Type THW/THWN insulation in raceway, underground feeder, and branch-circuit cable or service-entrance cable.

SECTION 26 01 01 Page 12

Page 63: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

7. Underground installations: Use only Type THW/THWN insulation in raceway, underground feeder, and branch-circuit cable.

8. Use wiring methods indicated on Drawings.

9. Install products in accordance with manufacturer's instructions.

10. Use solid conductor for feeders and branch circuits 10 AWG and smaller.

11. Use stranded conductors for control circuits.

12. Use conductor not smaller than 12 AWG for power and lighting circuits.

13. Use conductor not smaller than 16 AWG for control circuits.

14. Use 10 AWG conductors for 20 ampere, 120 volt branch circuits longer than 75 feet.

15. Pull all conductors into raceway at same time.

16. Use suitable wire pulling lubricant for building wire 4 AWG and larger.

17. Protect exposed cable from damage.

18. Use suitable cable fittings and connectors.

19. Neatly train and lace wiring inside boxes, equipment and panelboards.

20. Clean conductor surfaces before installing lugs and connectors.

21. Make splices, taps and terminations to carry full ampacity of conductors with no perceptible temperature rise.

22. Terminate aluminum conductors with tin-plated aluminum-bodied compression connectors only. Fill with anti-oxidant compound before installing conductor.

23. Use suitable reducing connectors or mechanical connector adapters for connecting aluminum conductors to copper conductors.

24. Use split bolt connectors for copper conductor splices and taps 6 AWG or larger. Tape uninsulated conductors and connectors with electrical tape to 150 percent of insulation rating of conductor.

25. Use solderless pressure connectors with insulating covers of copper conductor splices and taps 8 AWG and smaller.

26. Use insulated spring wire connectors with plastic caps or copper inductor splices on taps 10 AWG and smaller.

3.3 BOXES

1. Install electrical boxes as shown on Drawings, and as required for splices, taps, wire pulling, equipment connections and compliance

SECTION 26 01 01 Page 13

Page 64: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

with regulatory requirements.

2. Install electrical boxes to maintain headroom and to present a neat mechanical appearance.

3. Align adjacent wall-mounted outlet boxes for switches, thermostats, and similar devices with each other.

4. Secure flush mounting box to interior wall and partition studs. Accurately position to allow for surface finish thickness.

5. Use adjustable steel channel fasteners for hung ceiling outlet box.

6. Support boxes independently of conduit except cast box that is connected to two rigid metal conduits both supported within 12 inches of box.

7. Use gang box where more than one device is mounted together. Do not use sectional box.

8. Use cast outlet box in exterior locations exposed to weather and inside pump houses.

9. Large Pull boxes: Boxes larger than 100 cubic inches in volume or 12 inches in any dimension.a. Interior Dry Locations: Use screw cover enclosure.b. Other Locations: Use surface-mounted cast metal box.

3.4 WIRING DEVICES

1. Verify conditions.

2. Verify outlet boxes are installed at proper height.

3. Verify wall openings are neatly cut and will be completely covered by wall plates.

4. Verify branch circuit wiring installation is completed, tested, and ready for connection to wiring devices.

5. Clean debris from outlet boxes.

6. Install products in accordance with manufacturer's instructions.

7. Install devices plumb and level.

8. Install switches with OFF position down.

9. Install receptacles with grounding pole on bottom.

10. Connect wiring device grounding terminal to branch circuit equipment grounding conductor.

11. Install decorative plates on switch, receptacle, and blank outlets in finished areas.

12. Install galvanized steel plates on outlet boxes and junction boxes in unfinished areas, above accessible ceilings, and on surface mounted outlets.

SECTION 26 01 01 Page 14

Page 65: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

3.5 SUPPORTING DEVICES

1. Fasten hanger rods, conduit clamps, and outlet junction boxes to building structure using expansion anchors or beam clamps. Do not use spring steel clips and clamps.

2. Use toggle bolts or hollow wall fasteners in hollow masonry, or gypsum board partitions and walls, expansion anchors or preset inserts in solid masonry walls, self-drilling anchors or expansion anchor on concrete surfaces, sheet metal screws in sheet metal studs, and wood screws in wood construction.

3. Do not fasten supports to piping, ductwork, mechanical equipment,or conduit.

4. Do not use powder-actuated anchors.

5. Do not drill structural steel members.

6. Fabricate supports from structural steel or steel channel, rigidly welded or bolted to present a neat appearance. use hexagon head bolts with spring lock washers under all nuts.

7. In wet locations install free-standing electrical equipment on concrete pads.

8. Install surface-mounted cabinets and panelboard with minimum of four anchors. Provide steel channel supports to stand cabinet one inch off wall.

3.6 ELECTRICAL IDENTIFICATION

1. Degrease and clean surfaces to receive nameplates.

2. Install nameplates parallel to equipment lines.

3. Secure nameplates to equipment fronts using screws. Secure nameplate to inside face of recessed panelboard doors in finished locations.

4. Embossed tape will not be permitted for any application.

5. Provide wire markers on each conductor in panelboard gutters, pull boxes, motor control centers, and at load connections. Identify with branch circuit or feeder number for power and lighting circuits, and with control wire number as indicated on schematic and interconnection diagrams for control wiring.

6. Provide nameplates to identify all electrical distribution and control equipment, and loads served. Letter height: 1/8 inch for individual switches and loads served, 1/4 inch for distribution and control equipment identification.

7. Provide nameplates of minimum letter height as scheduled below:a. Panelboards, Switchboards, Motor Control Centers, Identify equipment designation, 1/4 inch.b. Identify voltage rating and source, 1/8 inch.c. Individual circuit breakers, switches, motor starters in

SECTION 26 01 01 Page 15

Page 66: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Morton Valley WSC - Water System Improvements Pump Stations 15048PS

panelboards, switchboards, and motor control centers, identify circuit and load served, include location, 1/8 inch.d. Individual circuit breakers, enclosed switches and motor starters, identify load, 1/8 inch.e. Transformers, identify equipment designation, identify primary and secondary voltages, primary source, and secondary load and location, 1/8 inch.

3.7 SECONDARY GROUNDING

1. Provide a separate , insulated equipment grounding conductor in feeder and branch circuits. Terminate each end on a grounding lug, bus, or bushing.

2. Connect grounding electrode conductors to metal water pipe using a suitable ground clamp.

3. Supplementary Grounding Electrode: Use driven ground rod on exterior of building. Install ground rod in suitable recessed well, fill with gravel after connection is made use effectively grounded metal from building.

4. Provide grounding and bonding at the first service disconnect.

-- End of Section --

SECTION 26 01 01 Page 16

Page 67: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Show prices in numerals. Round off unit prices to two decimal places only.

These Bid Prices must include all labor, materials, equipment, insurance, overhead, superintendence,

transportation, profits & incidentals to cover the finished Work called for in the Contract Documents.

For all Labor, Materials, Equipment and Incidentals to Furnish and Install the Following:

Bid Est. Unit Extended

Item Description Qty. Unit Price Amount

1 MOBILIZATION, BONDS, & INSURANCE 1 LS

2100,000 GALLON GROUND STORAGE TANK

(32 FT. DIAMETER, 18 FOOT HEIGHT)1 LS

3 3,000 GALLON PRESSURE TANK 1 LS

NOTES

1).

2).

3).

I). BBII). BB - AB#1

BASE AND ALTERNATE BIDS SHALL BE APPLIED IN THE FOLLOWING ORDER TO BRING PROJECT WITHIN BUDGET

MORTON VALLEY WATER SUPPLY CORPORATION

BASE BID SCHEDULE - STORAGE TANKS (CONTRACT #1)

WATER SYSTEM IMPROVEMENTS

TOTAL BASE BID (Items 1 - 3)

BID ITEM 3 WILL INCLUDE TANK AND FEATURES AS SHOWN ON PLAN SHEET 8, AND PIPING FROM PRESSURE

TANK UP TO BUT NOT INCLUDING 8" GATE VALVE SHOWN ON SHEET 6

(ADDENDUM #1 MODIFIED)

BID ITEM 2 (GROUND STORAGE TANK) WILL INCLUDE TANK AND FEATURES AS SHOWN ON PLAN SHEET 4

Page 68: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Show prices in numerals. Round off unit prices to two decimal places only.

These Bid Prices must include all labor, materials, equipment, insurance, overhead, superintendence,

transportation, profits & incidentals to cover the finished Work called for in the Contract Documents.

For all Labor, Materials, Equipment and Incidentals to Furnish and Install the Following:

Bid Est. Unit Extended

Item Description Qty. Unit Price Amount

AB1-1 3000 GALLON PRESSURE TANK 1 LS

MORTON VALLEY WATER SUPPLY CORPORATION

ALTERNATE BID #1 - STORAGE TANKS (CONTRACT #1)

WATER SYSTEM IMPROVEMENTS

(ADDENDUM #1 MODIFIED)

ALTERNATE BID #1 TOTAL (AB#1)

ALTERNATE BID #1 SCHEDULE

Page 69: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Show prices in numerals. Round off unit prices to two decimal places only.

These Bid Prices must include all labor, materials, equipment, insurance, overhead, superintendence,

transportation, profits & incidentals to cover the finished Work called for in the Contract Documents.

For all Labor, Materials, Equipment and Incidentals to Furnish and Install the Following:

Bid Est. Unit Extended

Item Description Qty. Unit Price Amount

1 MOBILIZATION, BONDS, & INSURANCE 1 LS

2 RANGER PUMP STATION 1 LS

3 MORTON VALLEY PUMP STATION 1 LS

4AERATION SYSTEM FOR GROUND STORAGE

TANK1 LS

NOTE

I). BB

II). BB - AB#1III). BB - AB#1 - AB#2

1). BASE AND ALTERNATE BIDS SHALL BE APPLIED IN THE FOLLOWING ORDER TO BRING PROJECT WITHIN BUDGET

MORTON VALLEY WATER SUPPLY CORPORATION

BASE BID SCHEDULE - PUMP STATIONS (CONTRACT #2)

WATER SYSTEM IMPROVEMENTS

TOTAL BASE BID (BB) (Items 1 - 4)

(ADDENDUM #1 MODIFIED)

Page 70: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Show prices in numerals. Round off unit prices to two decimal places only.

These Bid Prices must include all labor, materials, equipment, insurance, overhead, superintendence,

transportation, profits & incidentals to cover the finished Work called for in the Contract Documents.

For all Labor, Materials, Equipment and Incidentals to Furnish and Install the Following:

Bid Est. Unit Extended

Item Description Qty. Unit Price Amount

AB1-1AERATION SYSTEM FOR GROUND

STORAGE TANK1 LS

MORTON VALLEY WATER SUPPLY CORPORATION

WATER SYSTEM IMPROVEMENTS

ALTERNATE BID SCHEDULE #1 - PUMP STATIONS (CONTRACT #2)

NOTE: ALTERNATE BID #1 SHALL DEDUCT THE GROUND STORAGE TANK AERATION SYSTEM FROM THE CONTRACT. TANK

AERATION SYSTEM SHALL INCLUDE AERATION EQUIPMENT (MIXER, BLOWER, SPRAY UNIT), REQUIRED STORAGE TANK

MODIFICATIONS, ELECTRICAL AND CONTROLS FOR AERATION SYSTEM, AND ELECTRICAL PANEL UPGRADE. SEE PLAN SHEET 23,

(100,000 GALLON GST AERATION SYSTEM).

(ADDENDUM #1 MODIFIED)

ALTERNATE BID #1 SCHEDULE

TOTAL AB1 (AB#1)

Page 71: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

Show prices in numerals. Round off unit prices to two decimal places only.

These Bid Prices must include all labor, materials, equipment, insurance, overhead, superintendence,

transportation, profits & incidentals to cover the finished Work called for in the Contract Documents.

For all Labor, Materials, Equipment and Incidentals to Furnish and Install the Following:

Bid Est. Unit Extended

Item Description Qty. Unit Price Amount

AB2-1

SUBSTITUTE ALTERNATE SCADA SITE AT

MORTON VALLEY ELEVATED STORAGE TANK

IN LIEU OF MORTON VALLEY PUMP STATION

1 LS

NOTE: ALTERNATE BID #2 PRICE SHALL BE FOR THE COST DIFFERENCE BETWEEN THE MORTON VALLEY PUMP STATION (BASE BID ITEM

#3) AND THE MORTON VALLEY ALTERNATE SCADA SITE FOR MONITORING TANK LEVEL. FOR EXAMPLE, IF THE MORTON VALLEY PUMP

STATION COST = $150,000 AND ALTERNATE SCADA SITE COST = $25,000, AB#2 COST = $125,000 ($150,000 - $25,000)

MORTON VALLEY WATER SUPPLY CORPORATION

ALTERNATE BID SCHEDULE #2 - PUMP STATIONS (CONTRACT #2)

WATER SYSTEM IMPROVEMENTS

(ADDENDUM #1 MODIFIED)

ALTERNATE BID #2 SCHEDULE

TOTAL AB2 (AB#2)

Page 72: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

S

S

A

X

E

F

T

O

T

E

A

T

P

R

E

EE

N

I

G

N

E

L

N

O

I

S

S

E

F

O

R

A

R

D

E

R

ET

S

I

G

E

44

02

5

KE

N M

AR

TIN

3465

CUR

RY L

ANE

ABIL

ENE,

TX

7960

632

5-69

5-10

70

1508

SAN

TA F

E DR

, STE

204

WEA

THER

FORD

, TX

7608

681

7-59

4-98

80

FIRM

# F

-244

8

BAR

IS O

NE

INCH

IN L

ENGT

H O

N O

RIGI

NAL

DRA

WIN

G.CH

ECK

SCAL

E &

ADJ

UST

ACC

ORD

INGL

Y.

05

/13

/19

AutoCAD SHX Text
1"=20'
AutoCAD SHX Text
1
AutoCAD SHX Text
NORTH
AutoCAD SHX Text
CONNECT TO WATER LINE CONTRACTORS 8" WATER LINE.
AutoCAD SHX Text
1
AutoCAD SHX Text
KM
AutoCAD SHX Text
KM
AutoCAD SHX Text
RM
AutoCAD SHX Text
DRAWN
AutoCAD SHX Text
DESIGNED
AutoCAD SHX Text
CHECKED
AutoCAD SHX Text
PROJECT #
AutoCAD SHX Text
DATE
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
SEQ.
AutoCAD SHX Text
NO.
AutoCAD SHX Text
WATER SYSTEM IMPROVEMENTS
AutoCAD SHX Text
MORTON VALLEY WSC
AutoCAD SHX Text
15048
AutoCAD SHX Text
X:\WS_Morton_Valley_WSC\15048-Morton Valley WSC Water System Improvement\Drafting\_Plans\PUMP STATION\ADDENDUM #1\SHEET 01.dwg
AutoCAD SHX Text
OF 2
AutoCAD SHX Text
MORTON VALLEY ALTERNATE SCADA SITE
AutoCAD SHX Text
ADDENDUM #1
AutoCAD SHX Text
EXISTING ELEVATED TANK
AutoCAD SHX Text
ELEVATED TANK SITE BOUNDARY
AutoCAD SHX Text
NOTES: 1. THIS ALTERNATIVE SCADA SITE SHALL CORRESPOND TO A DEDUCTION OF THE MORTON VALLEY PUMP STATION FROM THE CONTRACT. 2. IN LIEU OF 240/120/3 PHASE ELECTRIC SERVICE AT THE SITE, 120V SINGLE PHASE SERVICE SHALL BE BROUGHT TO SITE (PAID FOR BY OWNER). 3. ALL ELECTRIC & SCADA EQUIPMENT SHALL BE RATED NEMA 3R FOR OUTDOOR USE. 4. SCADA FUNCTIONALITY WITH THE ALTERNATE SCADA SITE SHALL BE LIMITED TO MONITORING, RECORDING, & TRENDING ELEVATED STORAGE TANK LEVEL AND CALLING RANGER PUMP STATION TO START/STOP AS TANK LEVEL REACHES LOW LEVEL AND HIGH LEVEL SET POINTS (ADJUSTABLE BY OPERATOR).
AutoCAD SHX Text
PROPOSED 8" ELEVATED TANK FILL LINE/DRAIN LINE (8" DR 25 PVC WL).
AutoCAD SHX Text
34" DR9 TANK LEVEL LINE TO PRESSURE TRANSMITTER (TIED TO SCADA)
AutoCAD SHX Text
48" DIAMETER x 6' DEEP CGM VAULT FOR TANK LEVEL TAP 8"x " TAPPING 34" TAPPING SLEEVE AND VALVE FOR TANK LEVEL LINE
AutoCAD SHX Text
EXISTING EASEMENT
AutoCAD SHX Text
EXISTING TANK FILL LINE TO BE ABANDONED
AutoCAD SHX Text
CUT AND PLUG WHEN COMPLETE
AutoCAD SHX Text
SCADA CONTROL RACK (SEE DETAIL ADDENDUM #1, SHEET 2)
AutoCAD SHX Text
8" TEE 8x6 REDUCER 6" GV 6" GALVANIZED I.P. RISER W/CAP
AutoCAD SHX Text
TIE TO EXISTING 6" TANK LINE W/ 6" TEE 8x6 REDUCER 6" GV (2) 8" GV 6" COUPLING (2)
Page 73: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

TYPICAL PANEL & DISCONNECT STAND GROUNDING PLAN

TO

PANEL

A

NTS

FRONT VIEW

SIDE VIEW

ELECTRIC PANEL AWNING DETAIL

NTS

3465

CUR

RY L

ANE

ABIL

ENE,

TX

7960

632

5-69

5-10

70

1508

SAN

TA F

E DR

, STE

204

WEA

THER

FORD

, TX

7608

681

7-59

4-98

80

FIRM

# F

-244

8

BAR

IS O

NE

INCH

IN L

ENGT

H O

N O

RIGI

NAL

DRA

WIN

G.CH

ECK

SCAL

E &

ADJ

UST

ACC

ORD

INGL

Y.

S

S

A

X

E

F

T

O

T

E

A

T

P

R

E

EE

N

I

G

N

E

L

N

O

I

S

S

E

F

O

R

A

R

D

E

R

ET

S

I

G

E

44

02

5

KE

N M

AR

TIN

05

/13

/19

AutoCAD SHX Text
PANEL A 60A 120/240V 1
AutoCAD SHX Text
BOND NEUTRAL AND GROUND AT PANEL
AutoCAD SHX Text
GROUNDING ROD AS PER NEC. BONDED TO GROUNDING LOOP
AutoCAD SHX Text
2EA. #6 AWG PHASE CONDUCTORS 1EA. #6 AWG NEUTRAL CONDUCTOR.
AutoCAD SHX Text
SCADA CONTROL PANEL
AutoCAD SHX Text
METER BY ONCOR AND METER CAN BY CONTRACTOR AS PER ONCOR'S REQUIREMENTS.
AutoCAD SHX Text
CONDUIT BY ELECTRICAL CONTRACTOR AS PER ONCOR'S REQUIREMENTS AND CABLE BY ONCOR.
AutoCAD SHX Text
12
AutoCAD SHX Text
1
AutoCAD SHX Text
NOTE: 1. ALL STEEL TO BE EPOXY COATED PER THE SPECS.
AutoCAD SHX Text
(4) #3 VERTICAL BARS #3 VERTICAL BARS WITH #3 TIES @ 12" OC PROVIDE DOUBLE TIES AT TOP
AutoCAD SHX Text
#3 BARS @ 18" CENTERS BOTH WAYS @ MID-DEPTH OF SLAB
AutoCAD SHX Text
(2) #3 HORIZONTAL BARS CONTINUOUS AROUND SLAB PERIMETER
AutoCAD SHX Text
CONTRACTOR SHALL LEAVE A 2/0 MCM BARE CONDUCTOR 6' PIG TAIL FOR FUTURE CONNECTIONS (TYPICAL TWO PLACES)
AutoCAD SHX Text
CONTRACTOR TO ADJUST STRUCTURE WIDTH TO PROVIDE ADEQUATE MOUNTING ROOM FOR REQUIRED PANELS AND DISCONNECTS AS NEEDED.
AutoCAD SHX Text
X
AutoCAD SHX Text
X
AutoCAD SHX Text
X
AutoCAD SHX Text
GROUND LOOP TO BE 30" DEEP AND 30" FROM STRUCTURE
AutoCAD SHX Text
LEGEND
AutoCAD SHX Text
GROUND CONNECTION
AutoCAD SHX Text
4/0 MCM BARE COPPER GROUNDING CONDUCTOR
AutoCAD SHX Text
2/0 MCM BARE COPPER GROUNDING CONDUCTOR
AutoCAD SHX Text
#2 THHN GREEN COVERED CABLE
AutoCAD SHX Text
X
AutoCAD SHX Text
4" C PURLIN
AutoCAD SHX Text
R-PANEL
AutoCAD SHX Text
4" C PURLIN
AutoCAD SHX Text
5 SACK CONCRETE
AutoCAD SHX Text
2-3/8"x1/4" STEEL PIPE
AutoCAD SHX Text
R-PANEL
AutoCAD SHX Text
1-1/2" SQUARE TUBING @ EACH END OF AWNING
AutoCAD SHX Text
ELECTRIC PANEL
AutoCAD SHX Text
CONCRETE SLAB
AutoCAD SHX Text
CONCRETE SLAB
AutoCAD SHX Text
DUPLEX OUTLET W/ WATERTIGHT WHILE IN USE BOX & COVER
AutoCAD SHX Text
2-3/8"x1/4" STEEL PIPE
AutoCAD SHX Text
2-3/8"x1/4" STEEL PIPE
AutoCAD SHX Text
R-PANEL
AutoCAD SHX Text
R-PANEL
AutoCAD SHX Text
4" C PURLIN
AutoCAD SHX Text
EATON CLOSED-40-SM-UNV (OR APPROVED EQUIVALENT) CLCSLED = PRODUCTIVE FAMILY 40 = 36W UNV = 120-277 V QUANTITY = 2 REQ'D MOUNT CENTERED HORIZONTALLY ON ADDITIONAL 4" C PURLIN CENTERED ON 4' SPAN
AutoCAD SHX Text
1"=200'
AutoCAD SHX Text
2
AutoCAD SHX Text
2
AutoCAD SHX Text
KM
AutoCAD SHX Text
KM
AutoCAD SHX Text
RM
AutoCAD SHX Text
DRAWN
AutoCAD SHX Text
DESIGNED
AutoCAD SHX Text
CHECKED
AutoCAD SHX Text
PROJECT #
AutoCAD SHX Text
DATE
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
SEQ.
AutoCAD SHX Text
NO.
AutoCAD SHX Text
WATER SYSTEM IMPROVEMENTS
AutoCAD SHX Text
MORTON VALLEY WSC
AutoCAD SHX Text
15048
AutoCAD SHX Text
X:\WS_Morton_Valley_WSC\15048-Morton Valley WSC Water System Improvement\Drafting\_Plans\PUMP STATION\ADDENDUM #1\SHEET 02.dwg
AutoCAD SHX Text
OF 2
AutoCAD SHX Text
MORTON VALLEY ALTERNATE SCADA SITE
AutoCAD SHX Text
ADDENDUM #1
Page 74: ADDENDUM NO. 1 May 15, 2019 PROJECT: MORTON VALLEY …jacobmartin.com/wp-content/uploads/2019/05/Addendum-1-PS... · 2019-05-14 · THE SOCIETY FOR PROTECTIVE COATINGS (SSPC) SSPC

3465

CUR

RY L

ANE

ABIL

ENE,

TX

7960

632

5-69

5-10

70

1508

SAN

TA F

E DR

, STE

204

WEA

THER

FORD

, TX

7608

681

7-59

4-98

80

FIRM

# F

-244

8

BAR

IS O

NE

INCH

IN L

ENGT

H O

N O

RIGI

NAL

DRA

WIN

G.CH

ECK

SCAL

E &

ADJ

UST

ACC

ORD

INGL

Y.

S

S

A

X

E

F

T

O

T

E

A

T

P

R

E

EE

N

I

G

N

E

L

N

O

I

S

S

E

F

O

R

A

R

D

E

R

ET

S

I

G

E

44

02

5

KE

N M

AR

TIN

05

/13

/19

AutoCAD SHX Text
INLET
AutoCAD SHX Text
NOTES: 1) EQUIPMENT SHOWN IS BY MEDORA CO. ALTERNATE EQUIPMENT MAY BE EVALUATED AS AN APPROVED EQUIVALENT PER THE SPECIFICATIONS. 2) IF AN ALTERNATIVE EQUIPMENT IS APPROVED AND USED, CONTRACTOR SHALL MAKE ANY AND ALL ADJUSTMENTS TO THE TANK MODIFICATIONS NECESSARY TO ACCOMMODATE OTHER EQUIPMENT (NO SEPARATE OR ADDITIONAL PAY). 3) MODIFICATIONS SHOWN SHALL BE COORDINATED WITH TANK MANUFACTURER AND MADE PRIOR TO APPLICATION OF TANK COATINGS. 4) ELECTRICAL MOTOR STARTERS AND CONTROL PANELS FOR AERATION EQUIPMENT SHALL BE LOCATED INSIDE OF PUMP STATION BUILDING. 5) CONTRACTOR SHALL ANCHOR RIGID METAL CONDUIT TO TANK. CONDUIT SHALL BE ANCHORED VIA CLIPS WELDED ONTO TANK BY TANK MANUFACTURER PRIOR TO COATING OR BY ATTACHING TO LADDER STANDOFFS. ATTACHMENT TO LADDER STANDOFFS SHALL NOT INTERFERE WITH SAFETY EQUIPMENT OR CLIMBING LADDER. 6) BID PRICE FOR TANK AERATION SYSTEM SHALL ALSO INCLUDE AN BID PRICE FOR TANK AERATION SYSTEM SHALL ALSO INCLUDE AN UPGRADE OF THE MAIN ELECTRICAL PANEL "A" LOCATED IN THE PROPOSED RANGER PUMP STATION BUILDING TO A 300 AMP, 240/120V, 3 PHASE PANEL.
AutoCAD SHX Text
18" VENT
AutoCAD SHX Text
100,000 GST AERATION SYSTEM
AutoCAD SHX Text
NTS
AutoCAD SHX Text
270°
AutoCAD SHX Text
AutoCAD SHX Text
90°
AutoCAD SHX Text
180°
AutoCAD SHX Text
NORTH
AutoCAD SHX Text
OUTLET
AutoCAD SHX Text
PROVIDE 1 x " 38" OR M8 EYELET ON TANK VENT PIPE INTERIOR
AutoCAD SHX Text
PROVIDE 1 x 4" PIPE SLEEVE ON ROOF. APPROXIMATELY 6 FT FROM TANK CENTER. SLEEVE SHALL EXTEND 4-6" ABOVE TANK ROOF. FINISH TOP WITH STANDARD 4" FLANGE FOR CONNECTION TO BLOWER DISCHARGE PIPING. PROVIDE " CONDUIT KNOCKOUT ON TEFC 12" CONDUIT KNOCKOUT ON TEFC MOTOR WIRING BOX.
AutoCAD SHX Text
2 x 3" PIPE SLEEVES FINISHED TOP WITH STANDARD FLANGE AND BOLTED BLIND FLANGE HAVING A 1-5/16" BORE THROUGH CENTER TO ACCEPT SEALED UNIVERSAL FIXTURE. POSITION NOT TO IMPEDE HATCH ACCESS.
AutoCAD SHX Text
GS-9 TANK MIXER (TANK INTERIOR)
AutoCAD SHX Text
BLOWER MOUNTED ON TANK ROOF
AutoCAD SHX Text
SN10 SPRAY UNIT (TANK INTERIOR)
AutoCAD SHX Text
KM
AutoCAD SHX Text
KM
AutoCAD SHX Text
RM
AutoCAD SHX Text
DRAWN
AutoCAD SHX Text
DESIGNED
AutoCAD SHX Text
CHECKED
AutoCAD SHX Text
PROJECT #
AutoCAD SHX Text
DATE
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
SEQ.
AutoCAD SHX Text
NO.
AutoCAD SHX Text
PUMP STATIONS & TANKS
AutoCAD SHX Text
MORTON VALLEY WSC
AutoCAD SHX Text
15048
AutoCAD SHX Text
X:\WS_Morton_Valley_WSC\15048-Morton Valley WSC Water System Improvement\Drafting\_Plans\PUMP STATION\SHEET 23-100K GAL GST AERATION SYSTEM.dwg
AutoCAD SHX Text
OF 23
AutoCAD SHX Text
N.T.S.
AutoCAD SHX Text
23
AutoCAD SHX Text
100,000 GALLON GST AERATION SYSTEM
AutoCAD SHX Text
23