addendum #3 - hess · 2014-08-01 · section 00210 – bid form a. replace. ... column 3n west to...

90
Come discover with us. ADDENDUM #3 To: Plan Holders From: HESS Construction + Engineering Services Date: 7/26/2011 Re: Oxon Hill High School Replacement Project DATE: July 26, 2011 OWNER: Prince George’s County Public Schools 13300 Old Marlboro Pike Upper Marlboro, MD 20772 CONSTRUCTION MANAGER: HESS Construction + Engineering Services 804 W. Diamond Ave, Suite 300 Gaithersburg, MD 20878 ARCHITECT: WMCRP Architects 8100 Professional Place Landover, MD 20785 PROJECT: Oxon Hill High School Oxon Hill, Maryland PSC No. 16.082.10 LP IFB# 107-11 Commission Number 0600 TO: All Plan Holders The following changes are made a part of the Invitation for Bid #107-11 dated 6-28-11 (Revised per ADD#1 7-13-11), and Drawings and Specifications for the subject project dated June 15, 2011. Receipt of this Addendum in the space provided in the Bid Form is to be acknowledged. Failure to do so may subject the Bid to be considered as non- responsive. SPECIFICATIONS 1. Section 00210 – BID FORM a. Replace bid form (ADD#1) with the revised Bid Form (ADD#3) 2. Section 00800 – CONTRACT PACKAGES a. Replace b. the 02A Work Scope with the revised 02A work scope (ADD#3) Replace c. the 03A Work Scope with the revised 03A work scope (ADD#3) Replace d. the 04A Work Scope (ADD#1) with the revised 04A Work Scope (ADD#3) Replace e. the 09A Work Scope (ADD#1) with the revised 09A Work Scope (ADD#3) Replace f. the 09B Work Scope with the revised 09B Work Scope (ADD#3) Replace the 16A Work Scope with the revised 16A Work Scope (ADD#3)

Upload: dinhnhi

Post on 13-Jul-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Come discover with us.

ADDENDUM #3 To: P lan Holders

From: HESS Construct ion + Engineer ing Serv ices

Date: 7/26/2011

Re: Oxon Hi l l H igh School Replacement Project

DATE: July 26, 2011 OWNER: Prince George’s County Public Schools 13300 Old Marlboro Pike Upper Marlboro, MD 20772 CONSTRUCTION MANAGER: HESS Construction + Engineering Services 804 W. Diamond Ave, Suite 300 Gaithersburg, MD 20878 ARCHITECT: WMCRP Architects 8100 Professional Place

Landover, MD 20785 PROJECT: Oxon Hill High School Oxon Hill, Maryland PSC No. 16.082.10 LP IFB# 107-11 Commission Number 0600 TO: All Plan Holders The following changes are made a part of the Invitation for Bid #107-11 dated 6-28-11 (Revised per ADD#1 7-13-11), and Drawings and Specifications for the subject project dated June 15, 2011. Receipt of this Addendum in the space provided in the Bid Form is to be acknowledged. Failure to do so may subject the Bid to be considered as non-responsive. SPECIFICATIONS

1. Section 00210 – BID FORM a. Replace

bid form (ADD#1) with the revised Bid Form (ADD#3)

2. Section 00800 – CONTRACT PACKAGES a. Replace b.

the 02A Work Scope with the revised 02A work scope (ADD#3) Replace

c. the 03A Work Scope with the revised 03A work scope (ADD#3)

Replaced.

the 04A Work Scope (ADD#1) with the revised 04A Work Scope (ADD#3) Replace

e. the 09A Work Scope (ADD#1) with the revised 09A Work Scope (ADD#3)

Replacef.

the 09B Work Scope with the revised 09B Work Scope (ADD#3) Replace the 16A Work Scope with the revised 16A Work Scope (ADD#3)

Page 2: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

2

3. Section 05500 – METAL FABRICATIONS:

a. Add "2.8 STEEL LADDERS

paragraph to "Part 2 - Products" to read:

A. General: Fabricate ladders for the locations shown, with dimensions, spacings, details, and anchorages as indicated. Comply with requirements of ANSI A14.3.

B. Siderails: Continuous, steel, 1/2-by-2-1/2-inch (12-by-64-mm) flat bars, with eased edges, spaced 18 inches (460 mm) apart.

C. Bar Rungs: 3/4-inch- (19-mm-) diameter steel bars, spaced 12 inches (300 mm) o.c.

E. Fit rungs in centerline of side rails, plug weld and grind smooth on outer rail faces. F. Support each ladder at top and bottom and at intermediate points spaced not

more than 5 feet (1.5 m) o.c.

1. Size brackets to support design dead and live loads indicated and to hold centerline of ladder rungs clear of the wall surface by not less than 7 inches (180 mm).

2. Extend side rails 42 inches (1.1 m) above top rung, and return rails to wall or structure unless other secure handholds are provided. If the adjacent structure does not extend above the top rung, goose-neck the extended rails back to the structure to provide secure ladder access.

G. Provide nonslip surfaces on top of each rung, either by coating the rung with

aluminum-oxide granules set in epoxy-resin adhesive, or by using a type of manufactured rung that is filled with aluminum-oxide grout.."

b. Change

paragraph 2.11.A.1 to read: "1. Thickness: 14 gauge".

4. Section 07720 – ROOF ACCESSORIES: a. Add

subparagraph to paragraph 2.1.A to read: "d. Nystrom Building Products”.

5. Section 09310 – CERAMIC TILE: a. Add

"Ceramic Tile Type Schedule" (new page 12), attached.

5. Section 10416 – SCOREBOARDS: a. Add

subparagraph to paragraph 2.1.A to read: "3. Sportable Scoreboards”.

6. Section 11065 – STAGE LIGHTING EQUIPMENT: a. Changeb.

paragraph 1.3 to read "Add Alternate #9, Additional Lighting Instruments." Change

c.

paragraph 2.13.A to read " A. The Emergency Transfer Panel shall transfer a minimum of 12 circuits from the normal dimmer to emergency power. Each circuit...". Change

d. Change paragraph 2.15.B.5 to read " 5. Ellipsoidal Spotlight, 10 degree, 575W lamp. A total of 2 to be furnished. ETC Source Four #7060A1206, Strand/Phillips LekoLite #11510C, Altman Shakespeare #S6-10 ".

paragraph 2.15 to read "Stage Lighting Fixtures And Accessories, Add Alternate #9".

e. Change paragraph 2.15.B.6 to read " 6. Zoom Ellipsoidal Spotlight, 25-50 degree, 575W lamp. A total of 4 to be furnished. ETC Source Four #7060A1242-0X, Strand/Phillips LekoLite #11440C, Altman Shakespeare #S6-3055Z ".

Page 3: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

3

7. Section 11067 – STAGE PRODUCTION A/V EQUIPMENT:

a. Changeb.

paragraph 1.3 to read "Summary of Work: Add Alternate #10" Change

c.

paragraph 1.3.B to read " B. Portable equipment: Furnish and turn over to the owner the portable speakers, cables, intercom, and video equipment identified and detailed below as within the Alternate 10 scope." Change

d. paragraph 2.4.D to read "D. Equipment: Alternate 10."

Changee.

paragraph 2.5.C to read "C. Theater Equipment: Alternate 10." Change

f. paragraph 2.6.C.15 to read "15 Add alternate 10 wireless mic package".

Change

paragraph 2.8 to read "2.8 Portable Equipment: Alternate 11".

8. Section 12715 – LECTURE ROOM SEATING: a. Deleteb.

paragraph 1.2.A.3. Delete

c. paragraph 1.5.A.2.

Deleted.

paragraph 1.5.B.3. Delete

e. paragraph 1.5.D.6.

Deletef.

paragraph 1.7.A.1.c. Delete

g. paragraph 1.8.A.1.c.

Deleteh.

paragraph 2.1.B. Delete

i. paragraph 2.3.J.

Deletej.

paragraph 3.1.B. Delete

k. paragraph 3.2.C.

Deletel.

paragraph 3.3.A.3. Delete

paragraph 3.3.A.4.

m. Addn.

subparagraph to paragraph 2.3.A.1 to read: "c. Hussey Seating Company”. Change

paragraph 2.3.K to read "K. Tablet Arms: Manufacturer's standard, foldaway tablet arm with plastic-laminate writing surface over medium-density fiberboard or plywood core and with rounded, matching PVC edges."

9. Section 13125 – GRANDSTANDS AND BLEACHERS: a. Add "2.7 Covered Dugout

paragraph to "Part 2 - Products" to read:

A. Covered dugout by Gametime, a PlayCore, Inc. company, model 2398 or equal."

DRAWINGS Sheet C-15: Add

"General Notes: note:

1. Contractor to furnish and install one set of Kwik Goal Interscholastic Extended Fusion Football Gooseneck Goals, Kwik Goal Model #2D405.

2. Contractor to furnish and install two 5” thick concrete pads 10’ by 10’ for discus and shot put throwing pads.

3. Contractor to furnish and install Gill Aluminum Toe Boards or equal for each concrete pad."

Sheet G-002: Add

under "Notes" the following: "3. High-Impact Gypsum Board To Be Installed At All Exposed Gypsum Board Locations To A Height Of 8' Above Finish Floor.

Page 4: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

4

Sheet A-112: a. First Floor Area 1C, at Loading Dock: Revise

b. First Floor Area 1C, at Loading Dock:

"Conc. Stairs With Pipe Railing " to read "3'-0"H Handrail (2 Line Rail)".

Revise

c. First Floor Area 1C, at Can Wash Room, Room #C116:

"Pipe Railing" to read "3'-9"H Guardrail (2 Line Rail)".

Add

the following note to read: "4'-0" x 5'-10" Can Wash Area With Bottom Sloped To Drain. Provide 6" x 6" Concrete Curb on Non-Wall Sides. Relocate Plumbing As Required".

Sheet A-113: Add

note and arrow to columns K-11 and L-11 to read "16" Diameter Column Covers By Pittcon Industries, Series 200. Install In Accordance With Manufacturers Instructions".

Sheet A-171: a. Section 6/A-171: Reviseb. Section 6/A-171:

"3'-0"H Handrail" to read "3'-0"H Handrail (2 Line Rail)". Revise

"3'-9"H Guardrail" to read "3'-9"H Guardrail (2 Line Rail)".

Sheet A-503, Head Detail 20: Change

note "Perforated Stainless Steel Panel" to read "24" High Perforated Metal Panel (Return Air Grille) above doors C-105C, C-105D, C-105-E and C-105F. See 1/A-302".

Sheet A-950: a. Casework And Equipment Schedule: Add Mark: "PS-20" ; Width (W): "160""; Height (H): "120"".

the following in "Boards & Screens":

b. Casework And Equipment Schedule: Change Mark: "SE"; Product: "A/V Equipment Cabinet"; Manuf.: "TMI"; No.: "B9456"; Width (W):

"27""; Depth (D): "18""; Height (H): "34"".

the following in "Misc.":

c. Add

note "All Equipment Noted As "TS" or "Tackable Surface" To Be Natural Cork Tackboards With Trim In Accordance With Specification Section 10100".

Sheet A-958: Add

new drawing sheet Addendum Drawing AD3-01, attached.

Sheet A-971, Media Center Plan: Change

note "Display" between entry doors into Main Use Room to read:"Provide (3) Display Cases by Gaylord, Model W4024, Finish to be Selected, Exact Location To Be Determined" .

Sheet A-974, Section 1/A-974: Add

note "Provide Continuous Wall Mounted Rail At Both Outside Walls At Upper Seating Area Similar To Rail Shown On B/A-974".

Sheet A-976: Delete in its entirety and replace

with Addendum Drawing AD3-02, attached.

Sheet S-124,Second Floor And Low Roof Framing Plan Area 2F: Change

indication for beam spanning from column J-14 southeast to masonry wall from "W" to read "W12x14 (12)".

Sheet S-125, Second Floor And Low Roof Framing Plan Area 2G: Add

indication for beam spanning from column 3N west to W12x26 steel beam to read "W10x15".

Sheet S-143, High Roof Framing Plan At Higher Deck Area 4F: Add

indication for 6 beams spanning north-south for framing support of AHU-2 to read "W8x10".

Sheet S-502, Column Schedule (Area E), at Mark E.9-4.5: Delete

column indication from First Floor to Roof noted as "HSS8x8x1/4".

Page 5: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

5

Sheet TE-3.8: a. Stage Lighting Distribution Equipment Schedule, ID #124: Add

b. Stage Lighting Distribution Equipment Schedule, ID #125:

length under column "Strip Length/Box Size" to read "48 Feet".

Add

c. Stage Lighting Distribution Equipment Schedule:

length under column "Strip Length/Box Size" to read "48 Feet".

Add

d. Stage Lighting Distribution Equipment Schedule:

under new equipment as follows: ID#: "201-207"; Location: "Black Box"; Strip Length/Box Size: to read "24 Feet".

Add

under new equipment as follows: ID#: "301-306"; Location: "TV Studio"; Strip Length/Box Size: to read "20 Feet".

Sheet TE-3.10: a. Drawing 7/TE3.10 Second Typical Dimmer Room Layout Suggestion: Change

b. Drawing 7/TE3.10 Second Typical Dimmer Room Layout Suggestion:

Stage LightingTransformer size from "500KVA" to read "300 KVA"".

Change

c. Drawing 7/TE3.10 Second Typical Dimmer Room Layout Suggestion:

Main Auditorium/Black Box Dimmer Racks circuit breaker from "800A" to read "700A"".

Change

TV Studio Rack circuit breaker from "300A" to read "200A"".

ADDITIONAL INFORMATION: 1. RFI Question and Answer Log END OF ADDENDUM

Page 6: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Oxon Hill High School Replacement Question and Answer Log Issued via ADD#3

NOTE: For RFI Responses #1-6 & 7-44 Please see ADD#1 & ADD#2 45) RFI from Pleasants Construction Question: You indicate the 2Acontractor is responsible to patch and repair all roads, surfaces, and curb. Does this include streets that are off site as well? If so, do you have a condition survey of these streets Answer: The 02A Contractor is not required to patch, repair, and/or replace off-site conditions beyond what is indicated on the drawings. Answered by: Todd Ward, HESS 46) RFI from Pleasants Construction Question: We are to include 5% of the quantity for repair. Whose quantities is the 5% based on? Is the 5% the proposed paving or all of the proposed and temporary paving? Does the 5% include any off site repair Answer: The repair quantity is based on 5% of permanent work indicated on the drawings, and should not include temporary work. Answered by: Todd Ward, HESS 47) RFI from Pleasants Construction Question: The asphalt cement index references January 2011 which was $477.00, but the asphalt cement index is currently $630.00 for July 2011 and the asphalt producers on will price current index. Can this be revised to the month the project will be bid as you are already 32% increase from the Jan. 2011 index Answer: Bid should be based on current price index for the month that the project was bid. Answered by: Todd Ward, HESS 48) RFI from Pleasants Construction Question: If we are unclassified to subgrade, but may be required to grade as much as 4' higher that subgrade and indicated in the documents, what is the deciding factor? Will we be required to cut to subgrade, then replace this material to insure no unsuitable material? Answer: All excavation for this project is unclassified to lowest design sub-grade, which is defined by item #1 of the special considerations section of the 02A scope. If unsuitable soils are encountered at lowest sub-grade elevation, then any additional excavation required to

Page 7: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

reach suitable conditions will be compensated through the unsuitable soils allowance, which is further defined by item #2 of the special conditions section of the 02A Scope. Answered by: Todd Ward, HESS 49) RFI from Pleasants Construction Question: Is the 40000 CY allowance paid by cross sectioning the area (in place)? Answer: Usage of the unsuitable soils allowance will be based on the quantity of CY of compacted replacement material. The manner in which the quantity is measured will be determined in the field by the CM and Geotechnical engineer, based on what is most practical for the specific condition. The 02A Contractor must receive written direction from the Construction Manager prior to proceeding with additional work. Answered by: Todd Ward, HESS 50) RFI from Pleasants Construction Question: Is there any contaminated dirt (from underground tanks or fuel spillage)? Answer: The conditions are unknown Answered by: Todd Ward, HESS 51) RFI from Pleasants Construction Question: If the earthwork does not balance between phases, will we be allow to stockpile excess as needed Answer: The 02A Contractor is responsible for surplus or shortage quantities of on-site materials in order to grade the site to designed grades per phase. On-site stockpiling is permissible, but the 02A Contractor must coordinate with the CM on the location and duration, as stockpiling may not impact the progression of new work, and/or impact areas of the site designated for school use. Answered by: Todd Ward, HESS 52) RFI from Pleasants Construction Question: Do to the limited space, will topsoil be allowed to be stockpiled and/or screened on site? Answer: Limitations described by Pre-Bid RFI #51 answer would apply for topsoil stockpiling and screening operation. Answered by: Todd Ward, HESS 53) RFI from Kinsley Manufacturing Question: Please clarify if our crane can get on the foot print of the building to set the steel Answer: It is not anticipated that crane staging would occur inside the building footprint for steel erection, as this would impact process of other trades’ work. However, in limited conditions and at the sole discretion of the CM, crane staging/crane paths within the building footprint may be permitted, if no other means/method of steel erection is feasible. Answered by: Todd Ward, HESS

Page 8: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

54) RFI from Pleasants Construction Question: I was informed this morning that the Phasing plan and Sequence of Construction do not match with the grading requirements. Additionally, they do not address at any point when the Traps and Basins are converted to Bio-retention Areas. We are making assumptions but the work requires going beyond the Phases Limit of Disturbance. We will keep you up to date items as we encounter them Answer: Regarding grading requirements, the contract documents do not indicate every grading condition that may exist as the phasing/schedule progresses. There will be some flexibility allowed to determine the grading limits of new work (per phase) to accommodate existing conditions to remain (per phase), provided critical aspects of new work can be performed within its intended phase, and final grades at project completion are in accordance with the contract documents. Regarding trap/basin conversion, The SEC Phasing plans do address the sequence of work. In general, the conversation of basins/traps will occur after the drainage area associated for each device is developed to final condition. Answered by: Todd Ward, HESS 55) RFI from Kinsley Manufacturing Question: Please clarify the sprayed on fireproofing requirements. Package 05A Spec Section 05120 Structural Steel Section 2.6 – A – 4 states that surfaces that are to receive sprayed-on fireproofing do not get prime painted. Please clarify the steel that will require sprayed-on fireproofing. I have not seen anything on the structural drawings denoting that the steel is to be fireproofed. Answer: There is no sprayed on fireproofing requirements for this project. Answered by: Jim Gladhill, Hess 56) RFI from Karon Masonry Question: EGF – A (exterior ground face unit color A) is listed in the specification as a 16” high unit. The coursing references on the elevations, and wall cuts, are drawn for a unit that is 8” high. Wanted to double check that the height of EGF-A is 16” high. Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP) 57) RFI from Kinsley Manufacturing Question: Please advise if there are site rails on this project. I find no site rails indicated or detailed on the contract drawings. Site rails are referenced in the following bid packages.Package 05A – Steel Specific Scope item 2 lists: Site railings, Site handrails, Site guard rails, Package 02A – Sitework under Site Amenities item 4 on page 14 of 18 lists: All exterior steel railings at exterior stairs, ramps, retaining, walls and all other areas throughout the site and building exterior. If site rails are required, please clarify which bid package is responsible for site rails Answer: No site railings exist on this project, other than what is associated with the grandstand work. Grandstands are provided by the 02A Contractor. Answered by: Marty Lubin (WMCRP)

Page 9: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

58) RFI from R.D. Bean Question: Paragraph 2.5.8.2 has a list of approved manufacture's for the metal panels, but paragraph 2.5.B.3.b calls for the color to be "Tundra" by MBCI. MBCJ is not listed as an approved standing seam panel manufacture, but they do have a standing seam panel that is similar to the approved manufacture's standing seam panels. I would like to confirm that either the MBCI standing seam panel will be accepted, or that the color will be selected from any of the approved manufacture's standard colors. If the approved manufacture's are required to match the MBCI color then this would be considered a custom color and there is a significant up charge to match this color. Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP) 59) RFI from R.D. Bean Question: The following question is regarding Section 07412 "Metal wall Panels" Paragraphs 2.4.B.2.b, 2.4.C.2.b, and, 2.4.D.2.b calls for the metal color to match the Architect's sample. I would like to confirm that the listed manufacture's standard colors will be accepted. I the metal wall panels are to match the Architect's sample and the selected color is not a manufacture's standard color then this would be considered a custom color and there is a significant up charge to match this color. Also, if the color is to match the Architect's sample then we would need to know what the color will be prior to bid date so that we can have the manufacture's provide a price for the custom color. Please advise. Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP) 60) RFI from R.D. Bean Question: The following question is regarding Sections 07540 "Thermoplastic Membrane Roofing", and Section 07552 "SBS Modified Bituminous Membrane Roofing" Paragraph 3.8.A in section 07540, and paragraph 3.11.A calls for the roofer to protect the roof from damage after the roof has been installed. We can advise on the roof protection, but will not have a worker stationed on the job to watch and insure that no one is damaging the roof, nor do we have the authority to insure that the other contractors adhere to those procedures. I would like to confirm that in the event that the roof has been damaged by other contractor's then resulting repairs to the roof will be at the expense of the contractors who caused said damage. Please advise. Answer: Confirmed, Protection of the roof will be the responsibility of the trades performing work on/above the roof. Answered by: Todd Ward/HESS 61) RFI from Kinsley Manufacturing Question: Exterior bollards are referenced in the following bid packages. Package 05A – Steel Specific Scope item 3 lists: bollards (interior and exterior) Package 02A – Sitework under Site Amenities item 3 on page 13 of 18 lists: Furnish and install all bollards throughout the site. Bollards are shown, but not noted on C-7 at the generator and fuel tank. These are shown and noted on L-101 so I know they are bollards. No reference to a detail is made, but a detail is

Page 10: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

provided on C-13. Please advise who furnishes these bollards and if the detail on C-13 is correct for them. There are dark dots indicated on L-101 along the curved sidewalk just north of the Generator and fuel tank. The marks are not shown on C-7. Are these indicating bollards? If they are, please advise who furnishes them and if the detail on C-13 is correct for them. Answer: See Addendum #2 for clarification of bollards. Package 02A is responsible for bollards Answered by: Marty Lubin (WMCRP) 62) RFI from Kinsley Manufacturing Question: Rails seem to be indicated at the steps to Projection Rm G-208 in Section 1/A-972 and Plan B/A-972. Can a detail be provided, or a note describing the type of rail and finish? I would guess something to the 2-line steel rails in front of Overlook G-209. Also, can you confirm that handrails are not needed at the outside walls of the upper seating areas similar to the center walls shown in section B/A-972? Answer: See Addendum #2 for clarification of railings at Projection Room Overlook. See Addendum #3 for clarification of railings at upper seating area of Auditorium. : See Addendum #3 for clarification of railings outside walls of upper seating area. Answered by: Marty Lubin (WMCRP) 63) RFI from Facchina Construction Question: On sheet C-8 I need to know the height & type of fence across from the Proposed Bus Parking Lot. On sheet C-9 can you let me know the height & type of fence both in & next to the retaining wall to the right of Elkins Ave. Please clarify? Answer: See Addendum #2 Answered by: Nick Barrick (KCI) 64) RFI from Facchina Construction Question: I have not been able to find a plan that shows the layout of the irrigation system for the fields or in the bid documents that references the areas that are being irrigated? Please clarify? Answer: Layout is in the specifications Answered by: Marty Lubin (WMCRP) 65) RFI from Facchina Construction Question: Where is the section for synthetic turf alternate specification? Please clarify? Answer: Synthetic turf is covered by an allowance in the alternate (see section 01030). The requirement or type will be determined if the alternate is selected. Answered by: Marty Lubin (WMCRP) 66) RFI from Ronco Mechanical Question: Specification 15150-10, 3.11 Piping Schedule, paragraph E states that either service class cast-iron piping, gaskets and gasketed joints OR solid wall PVC pipe, PVC socket fittings and solvent cemented joints can be used for Sanitary Underground 4” and smaller. Answer: See Addendum #2

Page 11: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Answered by: Dwayne Smith, ASE 67) RFI from Ronco Mechanical Question: Specification 15150-10, 3.11 Piping Schedule, paragraph F states that ONLY service class cast-iron piping, gaskets and gasketed joints is to be used for Sanitary Underground 5” and larger. Answer: See Addendum #2 Answered by: Dwayne Smith, ASE 68) RFI from Ronco Mencanical Question: Typically for underground systems the same class of materials is used for the entire system; i.e. All cast iron OR all PVC. Is all PVC acceptable OR please confirm that a combination of PVC and Cast Iron is required. Answer: See Addendum #2 Answered by: Dwayne Smith (ASE) 69) RFI from Kinsley Manufacturing Question: Drawing A-173 has details for Stair Railing and Railing at Floor Levels for this building. The rails have woven wire mesh infill panels. Details indicate a 1 x 1/2 inch bar size channel at the bottom and ends of the wire mesh panels. The details show a 1-1/2 x 1-1/2 x 1/8 steel channel closed with a 2 x 1/8 inch bar at the top of the panels. Mesh panel manufacturers typically frame their panels with 1 x ½ channels all four sides. Those I have talked with do not recommend using the design as shown on the drawings. Can we propose changing the 1-1/2 x 1-1/2 channel to a square tube and building the infill panels with 1 inch channels 4-sides? Answer: The detailing in the bid documents will be maintained. The contractor may recommend alternative detailing after the award with accompanying cost (credit) impact. Answered by: Marty Lubin (WMCRP) 70) RFI from Secoa Question: Section 110652.15 B 5 Calls out 10 degree ellipsoidal spotlight fixtures and then goes on to list model numbers of 36 degree ellipsoidal spotlight fixtures. What degree fixtures shall be bid? Answer: This fixture is to be 10 degree ERS. .See Addendum #3 Answered by: Duane Wilson (Consulting For Theater Systems) 71) RFI from Secoa Question: Section 11065 2.15 B 6 Calls out 25-50 degree ellipsoidal zoom fixtures and then goes on to list model numbers of 15-30 degree ellipsoidal zoom fixtures. What degree fixtures shall be bid? Answer: This fixture is to be a 25 to 50 degree zoom ERS. See Addendum #3 Answered by: Duane Wilson (Consulting For Theater Systems) 72) RFI from Secoa

Page 12: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Question: The Bid Form released with Addendum #1 lists Alternate #9 – Upgraded Stage Lighting. Specification section 11065 does not this alternate. If Alternate #9 is to be bid, what equipment is to be included? Answer: See Addendum #3 Answered by: Duane Wilson (Consulting For Theater Systems) 73) RFI from R.D. Bean Question: The roof area between column lines 16.5 and 20.3; and column lines D .3 and B.5 do not slope as indicated on the Architectural roof plan. The roof structurally slopes from column Iine C. 9 to D.3 and C.9 to B.5. If the roof is to slope as indicated on the structural drawings then roof drains and crickets will need to be added. Please advise. Answer: See Addendum #2 Answered by: Chenping Ku (ReStl) 74) RFI from R.D. Bean Question: The low roof area on the drawings S 121 below column line column line T has the roof sloping towards the gymnasium, but the Architectural roof plan shows the roof sloping the opposite way. Please advise. Answer: See Addendum #2 Answered by: Chenping Ku (ReStl) 75) RFI from R.D. Bean Question: There are no bottom of the deck indications at the roof area between column lines 12.7 and 14; and column lines E and F. Please advise. Answer: See Addendum #2 Answered by: Chenping Ku (ReStl) 76) RFI from Homewood General Contractors Question: Room B 143 appears to have some casework and shelving in it, but we can’t locate any details or elevations. Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 77) RFI from Homewood General Contractors Question: Room B 145 appears to have shelving in it, but we can’t locate any details or elevations. Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 78) RFI from Homewood General Contractors Question: Rooms F 170, F 171 appear to have casework in them, but we can’t locate any elevations or details. – Addendum 1 corrects some or all Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP)

Page 13: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

79) RFI from Homewood General Contractors Question: Room D 126 appears to have casework in it, but we can’t locate any details or elevations Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 80) RFI from Homewood General Contractors Question: Room D 112 appears to have casework in it, but we can’t locate any details or elevations Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 81) RFI from Homewood General Contractors Question: Room E 109 appears to have shelving in it, but we can’t locate any details or elevations Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 82) RFI from Homewood General Contractors Question: Are there lockers on the corridor wall of room W 111? There is no tag Answer: There is no room W111. Cannot find referenced room. Answered by: Marty Lubin (WMCRP) 83) RFI from Homewood General Contractors Question: Classroom D 114 appears to have casework in the recess on the East wall, but we can’t locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 84) RFI from Homewood General Contractors Question: Room D 112 appears to have casework in it, but we cannot locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 85) RFI from Homewood General Contractors Question: Room D 108 appears to have casework in it, but we cannot locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 86) RFI from Homewood General Contractors

Page 14: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Question: Rooms D 124, D 125, D121, D 129, D 110 all appear to have casework in an alcove, but we can’t locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 87) RFI from Homewood General Contractors Question: Rooms F 152, F 151B, F 151A, F 160, F 197 all appear to have casework in them, but we can’t locate any elevations or details. Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP) 88) RFI from Homewood General Contractors Question: Room G 121 appears to have shelving in it, but we can’t locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 89) RFI from Homewood General Contractors Question: Room G 115 appears to have a counter in it, but we can’t find any details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 90) RFI from Homewood General Contractors Question: Rooms G 140, G 145 and G 149 appear to have shelving, but we can’t locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 91) RFI from Homewood General Contractors Question: Rooms G 150, G 151, G 152 and G 153 all appear to have similar casework or something in them, but we can’t locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 92) RFI from Homewood General Contractors Question: Room D 209 appears to have casework in the alcove on the North wall, but we can’t locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 93) RFI from Homewood General Contractors Question: Room D 206 appears to have things on the West wall, but we can’t locate any elevations or details Answer: This equipment is N.I.C.

Page 15: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Answered by: Marty Lubin (WMCRP) 94) RFI from Homewood General Contractors Question: Rooms D 215, D 216 and D 218 appear to have shelving in them, but we can’t locate any elevations or details Answer: This equipment is N.I.C Answered by: Marty Lubin (WMCRP) 95) RFI from Homewood General Contractors Question: Room D 220 appears to have casework on the East wall, but we can’t locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 96) RFI from Homewood General Contractors Question: What are the objects on the North, South and West walls of room D 219 Answer: This equipment is N.I.C Answered by: Marty Lubin (WMCRP) 97) RFI from Homewood General Contractors Question: Rooms F 212 and F 213 appear to have casework on their West walls. But we can’t locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 98) RFI from Homewood General Contractors Question: Room F 229 appears to have casework on the North and South walls, but we can’t locate any elevations or details Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP) 99) RFI from Homewood General Contractors Question: Room F 235 appears to have a large, 3-sided desk, but we can’t find any elevations or details Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP) 100) RFI from Homewood General Contractors Question: There is an item labeled “display” in room F 235 at concourse F 201, But we can’t locate any information on it other than for the borrowed lites Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 101) RFI from Homewood General Contractors

Page 16: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Question: Rooms G 201, G 202, and G 208 appear to have counters in them, but we can’t locate any sections or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 102) RFI from Homewood General Contractors Question: Room F 312 appears to have casework on the West wall, but we can’t locate any elevations or details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 103) RFI from Homewood General Contractors Question: Most rooms have a “secure equipment cabinet”. Sheet A 950 says “see detail” We can’t locate any details Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 104) RFI from Homewood General Contractors Question: Item AW-1 “pencil sharpener block” also lacks a detail Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 105) RFI from Homewood General Contractors Question: Who furnishes and installs the Smart Boards Answer: Per Addendum #2, Smart Boards are N.I.C. Answered by: Marty Lubin (WMCRP) 106) RFI from Homewood General Contractors Question: Plan sheet A955 shows lots of items labeled “TS” which the legend shows to be tackable surface. Which package is to provide this? We need a specification or section details of it. What is it framed with Answer: 6A Package is responsible for this work. See Addendum #3 for clarification of "TS and "Tackable Surface". Answered by: Marty Lubin (WMCRP) 107) RFI from Facchina Construction Question: We cannot find the details or information for the Proposed segmental retaining wall, and the 4 other retaining walls? More information needed? Please provide manufacture of acoustic wall Answer: The segmental wall is a design/build item, and must meet the requirements of the specifications. See Addendum #2 for manufacturer information on the acoustic wall. Answered by: Marty Lubin (WMCRP)

Page 17: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

108) RFI from Facchina Construction Question: Please provide details and specifications for all the track and field equipment and what athletic standards these must adhere to Answer: Track Construction & Triple Jump/Long Jump runways - Shall be constructed following the light-duty paving detail with a 0.5” surface synthetic rubber. Triple Jump/Long Jump Pit - Shall be constructed using the SportsField Specialties SP6010 JumpForm Log/Triple Jump Sand Pit or approved equal. Pole Vault - Shall be constructed using the SportsField Specialties TFPV001CA – Cast Aluminum Vault Box and TFPV003ALTR – Aluminum Vault Box Plug. All work shall be in accordance with NFHS Standards and Manufacturer’s Instructions. Answered by: Nicholas Barrick 109) RFI from Secoa Question: please address the following questions regarding Section 11065 – Stage Lighting Equipment. There are some connector strips lengths missing from the drawings. Please provide the connector strip lengths for the following:

A. Length of Light Pipe #1 – ID #124 B. Length of Light Pipe #2 – ID #125 C. Length of Black Box Connector Strips – ID #201-#207

Length of TV Studio Connector Strips – ID #301-#306 Answer: See Addendum #3 Answered by: Duane Wilson (Consulting For Theater Systems) 110) RFI from Kinsley Manufacturing Question: Steel and Miscellaneous Metals Specific Scope: Item 2 on page 2 of 5 includes: column covers and decorative column covers I find no details for these on the contract drawings. Are they required? Can details be provided for bidding Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 111) RFI from Kinsley Manufacturing Question: Steel and Miscellaneous Metals Specific Scope: Item 4 on page 3 of 5 includes: miscellaneous metals for support of folding partitions, etc as indicated Item 12 on page 3 of 5 includes: tracks, bracing There are moving partitions and folding partitions indicated on the plans. I find no section details for any of these on the contract drawings. Bid package 06A appears to be responsible for the installation of the complete operable panel partition systems as noted on page 8 of 13 of their bid package including the track. Can section details be provided indicating any steel requirements at these in addition to holes in steel beams above? Answer: Coordination of any steel requirements necessary for installing a specific manufacturer's operable partition is the responsibility of the contractor. Answered by: Marty Lubin (WMCRP)

Page 18: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

112) RFI from Kinsley Manufacturing Question: Please clarify the sprayed on fireproofing requirements. Package 05A Spec Section 05120 Structural Steel Section 2.6 – A – 4 states that surfaces that are to receive sprayed-on fireproofing do not get prime painted. Please clarify the steel that will require sprayed-on fireproofing. I have not seen anything on the structural drawings denoting that the steel is to be fireproofed. Answer: No spray fireproofing is required, therefore all steel shall be primed. Answered by: Marty Lubin (WMCRP) 113) RFI from AGM Contracting Question: Hollow Metal Frame shown on A-503 has 16 gauge steel face composite panels, what specification do i need to look at for these steel panels Answer: See specifications 8114-2.4 Answered by: Marty Lubin (WMCRP) 114) RFI from JP Construction Question: Clarify location of high impact gypsum specifications 09255-6 2.4 D, however drawings . G 002 does not mention to used Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 115) RFI from JP Construction Question: RCP drawings A-713, A 721, @ long corridor E 101 and D 201 and similar drawings shows tectum panels in the middle, and gypsum soffit at the sides, however soffits is shown in lines every 2' a part, is that a miss print or different material clarify Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 116) RFI from Pleasants Construction Question: The demolition plans indicate water line remaining in place and also being removed, please clarify Answer: All work pertaining to water and sewer pipes/structures shall be per the WSSC utility plans. See sheets C-31 to C-39. Answered by: Nicholas Barrick (KCI) 117) RFI from Pleasants Construction Question: There is no fencing indicated at the traps/basins, please confirm they are not required Answer: Fencing is not required at the traps/basins. Answered by: Nicholas Barrick (KCI) 118) RFI from Pleasants Construction Question: There is not tree protection fence or root pruning indicated, please confirm it is not required

Page 19: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Answer: All tree protection fencing shall be installed per the Sediment & Erosion Control Plan. Answered by: Nicholas Barrick (KCI) 119) RFI from Pleasants Construction Question: Is there any contaminated dirt (from underground tanks or fuel spillage)? Answer: Conditions are unknown. 02A Contractor will not be held responsible for contaminated soils. Answered by: Todd Ward/HESS 120) RFI from Pleasants Construction Question: The Heavy Duty paving has 2.5" 12.5mm paving. Please confirm as this is normally a binder & surface paving mix Answer: The detail calls for 1-1/2” of 9.5mm surface course with a 2-1/2” 12.5mm base course. Answered by: Nicholas Barrick (KCI) 121) RFI from Pleasants Construction Question: The sewer pipe is list as Schedule 40, but WSSC does allow SDR-35 up to certain depths. Please confirm Answer: The sewer pipe is to be installed per the WSSC Site Utility Plans. See sheets C-31 to C-39. Answered by: Nicholas Barrick (KCI) 122) RFI from Pleasants Construction Question: There are no details, either on the place or in the DPWT specifications, for the bedding or stone envelop for HDPE pipe? Please forward these requirements. Answer: Prince George’s County Standards and Specifications call out the type and depth of stone. Please see section 02200-4 of the county standards and specifications. “Bedding for elliptical pipe shall be aggregate meeting requirements of MSHA gradation No. 9 (AASHTO M43 size No. 8) to a depth of at least six inches below the pipe invert and 1/3 the diameter of the pipe in height. Bedding for all other pipes shall be granular bedding, ASTM C33 Course Aggregate, size number 67 except size number 57 or 4 may be used for reinforced concrete pipe larger than 15-inch diameter.” Copies of the county standards and specifications are available at the county building at 9400 Peppercorn Place. Answered by: Nicholas Barrick (KCI) 123) RFI from Pleasants Construction Question: There are two sets of specifications for the utility work, which apply? Answer: We cannot find 2 specifications for utility work. Answered by: Marty Lubin (WMCRP) 124) RFI from Pleasants Construction Question: Is there a layout for the field striping and logo Answer: Schematic Striping has been shown on the plans. The contractor is to submit submittals for all final striping/logos for review and approval by PG County Board of Education.

Page 20: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Answered by: Nicholas Barrick (KCI) 125) RFI from RFI from Pleasants Construction Question: In the specification for the Grandstand & Bleachers, the Snow Load is "by local jurisdiction", what are these loads? If this is unknown, who's design where these based on? Answer: It is the responsibility of the Grandstand contractor to provide a complete design/build installation in accordance with the specs that meets all applicable codes. Answered by: Marty Lubin (WMCRP) 126) RFI from RFI from Pleasants Construction Question: If the onsite material can be blended with onsite or offsite materials to become acceptable, will that be allowed Answer: All materials are to comply with the project specifications. Answered by: Nicholas Barrick (KCI) 127) RFI from Ridgeview Glass Question: normally on a project this size with various wall types there are architectural sheets that show enlarged elevations of the different systems. For instance, sheet A-503 has elevations of hollow metal frames. I need the same thing for windows, curtainwalls and translucent openings. If I have to size these openings off 1/16" scale, a lot of guessing will occur which will impact cost. Also some openings are hidden by building conditions which also means a lot of guessing of true opening sizes will occur. Enlarged building elevations would also help identify correct opening dimensions. Suppliers are not responsive to quoting material due to lack of information Answer: Refer to plan and section dimensions. Final dimensions will be reviewed in shop drawings. Answered by: Marty Lubin (WMCRP) 128) RFI from Douron Library & High Density Question: There is a reference desk mentioned in the specifications (12352-2.C) for which I cannot find a detailed drawing. We will be bidding the specified line (Worden) but the line comes in parts and pieces-- I need to know which pieces to price Answer: Referenced desk is N.I.C. Answered by: Marty Lubin (WMCRP) 129) RFI from Douron Library & High Density Question: The item tags on drawing A-922 do not appear to align with the schedule on drawing A-950. The double faced carrels, listed in the schedule as M-006, appear to be tagged as M-005, which is single faced magazine shelving in the schedule. Additionally, the end-of-range computer catalog stations are listed in the schedule as M-008, but on the drawing they are marked M-006 Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP)

Page 21: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

130) RFI from Douron Library & High Density Question: And while I assume it is a generic schedule, please confirm that the following items do not appear in the drawing at all: Single face magazine shelving (M-005) Dictionary Stand (M-007)* Atlas Stand (M-011)* Book Cart (M-012)* *Please note the last three items are mentioned in the specs but do not appear on the drawings. Answer: See Addendum 2 for magazine shelving. The Dictionary Stand, Atlas Stand and Book Cart are to be standard products from the list of acceptable manufacturers. Answered by: Marty Lubin (WMCRP) 131) RFI from FiberPlus Question: Drawing T-201 states all Active Electronics will be bid as a 17B package at a later date, does this include Wireless and UPS Power equipment also? When will this be bid? Answer: 17B shall include switches, routers, telephone electronics, wireless controllers, wireless access points, specifically related server equipment, televisions, projectors and DVD/VCR/Tuners. PGCPS shall provide a bid date for this equipment. Answered by: Bryan Jones, ESP 7-21-11 132) RFI from FiberPlus Question: What does Voice backbone cables terminate on, Voice grade patch panels or 110 punch blocks Answer: Per Sheet T-900, Detail 12, Note 7 all voice cables terminate on rack mounted patch panels. Answered by: Bryan Jones, ESP 7-21-11 133) RFI from FiberPlus Question: Drawing T-201 depicts a 10,000 KVA UPS in the Main Telecom Room F-225, is there a model or part # for this UPS Answer: 6 KVA ups is sufficient, see specification section 17100 for equipment information. Answered by: Bryan Jones, ESP 7-21-11 134) RFI from Building Specialties, Inc. Question: Tackable Surface in the Science rooms not specified in Section 10100 Answer: See item 77 above Answered by: Marty Lubin (WMCRP) 135) RFI from Building Specialties, Inc. Question: Display Cases in Rotunda on A975 are not in Section 10410 but must be custom built Answer: Yes Answered by: Marty Lubin (WMCRP) 136) RFI from Building Specialties, Inc.

Page 22: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Question: Display Cases (DC001 – DC004) on A950 are recessed and the display cases specified in Section 10410 are free standing style. I don’t see tags DC01 – DC04 used anywhere. Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP) 137) RFI from Building Specialties, Inc. Question: PS-20 in F118 on A915 is not listed on A950 Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 138) RFI from Building Specialties, Inc. Manual projection screens are not specified in Section 11132 Answer: See 11132-2.1.B Answered by: Marty Lubin (WMCRP) 139) RFI from Building Specialties, Inc. NUMEROUS discrepancies between the A900 Furniture series drawings between floor plans, enlarged Interior drawings and the elevations make it difficult to provide an accurate bid based on the deficiencies on bid document available on this project Answer: See Addenda #2 and #3 Answered by: Marty Lubin (WMCRP) 140) RFI from Building Specialties, Inc. Question: Sliding markerboards in the Science room are not specified in Section 10100 Also please confirm that they are sliding markerboards. The schedule on sheet A-950 shows sliding markerboards to be labeled MB-S. Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP) 141) RFI from Commercial Appliance Con tracts Question: 11400 – Food Service Equipment Questions: Item K-55 in the spec reads a quantity of 6, there is only 3 on the drawing, is the quantity 6 or 3? Item C-16 in the spec reads 8, the drawing reads 16, is the quantity 8 or 16? Item C-21 in the spec reads 4, the drawing reads 5, is the quantity 4 or 5? Answer: Quantities are as indicated on the Equipment Schedules, sheets K-1 and CA-1 Answered by: Marty Lubin (WMCRP) 142) RFI from Kinsley Manufacturing Question: Please clarify the size of the angles shown but not labeled in many of the sections on the structural drawings. Answer: See Addendum #2

Page 23: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Answered by: Chenping Ku (ReStl) 143) RFI from Kinsley Manufacturing Question: Reference drawing S-131Section B/S-301 is cut looking at line P and line S. Should this also be similar along line 10.1? I am asking because of the kickers shown going up to the columns along line10.1 and I am assuming that there is framing required on line 10.1 also. Please confirm Answer: Yes, along line 10.1 it shall have (4) tiers of horizontal HSS members with the same size as shown in section B/S-301 between col P-10.1, P.5-10.1, Q.1-10.1, R.1-10.1 & S-10.1. The (2) tiers HSS4x4x3/8 kicker as shown at col. 10.1 on section B/S-301 is typical at (7) locations as shown on plans S-122 & S-131. Answered by: Chenping Ku (ReStl) 144) RFI from Pleasants Construction Question: There are no elevations indicating the top or bottom of the retaining walls. This will at the very least increase the margin error of the takeoff and pricing. given we do not know the intent of the walls. Please clarify Answer: All walls shown on the plan are to be submitted by the contractor for review and approval. Answered by: Nicholas Barrick (KCI) 145) RFI from Pleasants Construction Question: Precast structures M22, M34, & M36 are too shallow to precast. This may require the structures to be cast in place, which is not per the specifications and may not be acceptable. Please clarify. Answer: Cast in place manholes are acceptable provided a submittal is submitted to the engineer for approval that shows compliance with PG county Standards and Specifications and is signed/sealed by a Registered Maryland Engineer. Answered by: Nicholas Barrick (KCI) 146) RFI from Systems Design & Sales Question: The specifications require bidders to confirm that the theatrical dimming equipment provided will fit into the dimmer room. We have been unable to locate a room on the plans labeled as the dimmer room. Could you please provide the room number & location in which the theatrical dimming equipment will be installed? Are both plan and elevation views of this room available? Answer: The dimmer room is G-206. This room is adjacent to the control booth of the main auditorium and is accessed from the Link room G-207 which connects the booth to the hallway leading to the TV studio and Library area of the school. A proposed equipment elevation is shown on TE-3.10. Answered by: Duane Wilson (Consulting For Theater Systems) 147) RFI from Atlascopco Construction Company, Inc Question: Where can we find toilets, restrooms, showers elevations for ceramic work for walls

Page 24: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 148) RFI from Atlascopco Construction Company, Inc Question: Are there any drawings with patterns for ceramic floors and walls, indicating where all specified ceramic tile are being used Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 149) RFI from Atlascopco Construction Company, Inc Question: A101 Gym Lobby , Gym Vest , Air locks and some other areas call for "Refinish Existing". Please advise what are the existing floors in these areas Answer: The original finishes were Fritz Tile and walkoff mats, but it is the responsibility of the contractor to visit the site and confirm existing conditions. Answered by: Marty Lubin (WMCRP) 150) RFI from Facchina Construction Question: The demolition plans call for the utilities water, sewer, and storm drain to be removed in there entirety. However the 02221 Specifications state to demolish existing utilities and below-grade utility structures that are within 5 feet (1.5 m) outside of footprint indicated for new construction. Abandon utilities outside this area? Which is correct? Answer: The utilities can be abandoned in place unless otherwise stated in the specifications or noted on the plans, provided they are not in conflict with new work. Abandoned pipes may have to be filled solid with flowable concrete fill, depending on location. Answered by: Nicholas Barrick (KCI) 151) RFI from Facchina Construciton Question: Ref C-16: The specified tennis posts are black iron and no manufacturer is referenced. After a web search, I found that these are vintage pieces and seem to only be available through the UK. Is this the correct spec Answer: We would offer that 3” OD 11 gauge steel posts with a powder coating finish of green or black. Winder shall be corrosion resistant aluminum, self-locking, internal mounted with a removable handle. Poles shall have welded lacing rods for mounting of the net. Poles shall be set on galvanized steel sleeves, install per the pole manufacturer. Answered by: Nicholas Barrick (KCI) 152) RFI from Facchina Construction Question: Ref Scope of Work, pg 23 or 88: There are no specs or details for the Soccer Goals or the Football Goals Ref Scope of Work, pg 22 or 88: No specs or details for litter receptacle. Ref Scope of Work, pg 22 or 88: Are there any other exterior benches besides the concrete seat Answer: Contractor to furnish and install one set of Kwik Goal Interscholastic Extended Fusion Football Gooseneck Goals, Kwik Goal Model #2D405. Contractor shall furnish and install two 5”

Page 25: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

thick concrete pads 10’ by 10’ for discus and shot put throwing pads. Contractor shall furnish and install Gill Aluminum Toe Boards or equal for each concrete pad. Answered by: Nicholas Barrick (KCI) 153) RFI from Facchina Construction Question: Ref L-101: Covered dugouts are referenced on L-101. No further detail or spec's are offered for this item Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 154) RFI from Facchina Construction Question: Ref C-15: Homeplate and Pitching Rubber for the softball field has been detailed (on C-15), but no bases or equipment for the baseball field were referenced. Please provide information for specified bases and baseball equipment. Answer: Home plate, pitching rubber and bases shall be suitable for high school or college level play with “Hollywood” setting posts and breakaways. Answered by: Nicholas Barrick (KCI) 155) RFI from S.A. Halac Question: Bar stock fence panels and gates are cited by specification section 05500-1 but they can’t be located on the plans or among the details. Where are these items located? Answer: The gate/fence is at the third floor of Stair F2. See Addendum #3. Answered by: Marty Lubin (WMCRP) 156) RFI from S.A. Halac Question: Corner guards are cited by specification section 05500-1 but they cannot be located among the plans. Where are these located Answer: Continuous edge angle noted at loading dock, see sheet A-912 Answered by: Marty Lubin (WMCRP) 157) RFI from S.A. Halac Question: There is supposed to be a can wash in room number C-116 but it’s not detailed among the drawings. Will a detail describing its construction Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 158) RFI from S.A. Halac Question: There is a roof access ladder indicated in room C-149 (refer to drawing A-912). Is there a specification or drawing describing it’s material and construction Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 159) RFI from S.A. Halac

Page 26: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Question: What is the finish/material for the interior railings? Details A-173/5, 6, 8, 11 and the specifications are ambiguous and do not clarify Answer: As noted on bid set and Addendum #2, all handrails are stainless steel except at Catwalk Stairs and Catwalk. Balance of handrail/guardrail system is painted steel unless specifically noted. Answered by: Marty Lubin (WMCRP) 160) RFI from S.A. Halac Question: Could an elevation be provided for the railing at the loading dock stair (refer to drawing A-112)? It’s profile/construction are unclear Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 161) RFI from S.A. Halac Question: The catwalk grating is specified as 11 gauge with the McNichols company specified as the manufacturer. The McNichols company has informed us that they do not manufacture the specified grating at 11 gauge but only to 14 gauge. Can the grating’s weight be changed to conform to what McNichols manufactures Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 162) RFI from S.A. Halac Question: The typical stair railing is designated as stainless steel. The east and west catwalk stairs are completely enclosed from view, and in such situations we normally see plain/carbon steel railings installed in such locations. Can we confirm that it is actually the intention to place ornamental/stainless steel railings in the enclosed catwalk stairs Answer: See Addendum #3 and item #164 above. Answered by: Marty Lubin (WMCRP) 163) RFI from S.A. Halac Question: On drawing S-124 there is a structural member running diagonally above the intersection of column lines 1R and J. If this is structural steel then what is the type/size of this member Answer: See Addendum #3 Answered by: Chenping Ku (ReStl) 164) RFI from S.A. Halac Question: On drawing S-125 there is a member running vertically near the intersection of column lines G and 1N. If this is structural steel then what is the type/size of this member Answer: It is a lintel for the 5'-0" opening. See Structural Note J. Lintel on sheet S-001 for type and size. Answered by: Chenping Ku (ReStl) 165) RFI from S.A. Halac

Page 27: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Question: On drawing S-125 there is a member running horizontally near column lines 3N and 20.1. If this is structural steel then what is the type/size of this member Answer: See Addendum #3 Answered by: Chenping Ku (ReStl) 166) RFI from S.A. Halac Question: On drawing S-125 there are members running vertically between 10K1 joists, one left of the intersection of column lines A and 19 and the other to the right of the intersection of column lines A and 17.4. If this is structural steel then what is the type/size of this member Answer: It is a lintel for the double door opening in CMU wall. See Structural Note J. Lintel on sheet S-001 for type and size. Answered by: Chenping Ku (ReStl) 167) RFI from S.A. Halac Question: On drawing S-131 there are members along column line 14 that are unidentified. Section S-201/A shows wide-flanged steel members at that location. What are the types/sizes of all of the members along column line 14 at that location Answer: See Addendum #2 Answered by: Chenping Ku (ReStl) 168) RFI from S.A. Halac Question: On drawing S-133 there is an unidentified member at the opening to Stair F1. If this is structural steel then what is the type/size of this member Answer: It is a lintel for the opening in CMU wall. See Structural Note J. Lintel on sheet S-001 for type and size. Answered by: Chenping Ku (ReStl) 169) RFI from S.A. Halac Question: Drawing S-143 there are unidentified members running vertically to the right of column line 1R. Details S-303/B, and C show wide-flanged beams near this location but refer back to the plans. If this is structural steel then what is the type/size of this member Answer: See Addendum #3 Answered by: Chenping Ku (ReStl) 170) RFI from S.A. Halac Question: Drawing S-502 lists 2 HSS tube sections of the same height that share the same location (E.9-4.5). Which of the two tubes should be used at this location? Answer: See Addendum #3 Answered by: Chenping Ku (ReStl) 171) RFI from S.A. Halac Question: Specifications section 05580-5/2.78/A/1 states there are return air grilles at room Dining C-102. The grilles for the other rooms mentioned in this section are shown in the drawings but we haven’t located the grilles for Dining C-102. Can these be located among the

Page 28: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

drawings or else can we be provided with a quantities and sizes of the grilles in Dining C-102 for pricing Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 172) RFI from DES Question: No student table knee spaces are of proper size to accept wheelchairs. Additionally spacing between tables is not sized for proper accessibility Answer: Adjustment of sink location to be addressed in shop drawings for better accessibility. Answered by: Marty Lubin (WMCRP) 173) RFI from DES Question: Based on present design, students in wheelchairs cannot access sinks from either front approach or side approach even if space permitted them to get to the sink. Answer: Adjustment of sink location to be addressed in shop drawings for better accessibility. Answered by: Marty Lubin (WMCRP) 174) RFI from DES Question: If ADA students could properly access wall units where sinks are located, water fixture locations as shown would not be ADA accessible since rear valve for water cannot be properly reached Answer: Adjustment of sink location to be addressed in shop drawings for better accessibility. Answered by: Marty Lubin (WMCRP) 175) RFI from DES Question: Rear gas cock on combination hot and cold water/gas fixtures at sinks point directly at back splash and space between tip of gas cock and face of curb is not sufficient thus causing any gas hoses connected to kink, thus interrupting flow of gas. Additionally, connecting and disconnecting hoses to rear gas cock would be a real challenge. Answer: Adjustment of sink location to be addressed in shop drawings for better accessibility. Answered by: Marty Lubin (WMCRP) 176) RFI from DES Question: In other areas such as elevation J2A-955 it is noted that sink is to be ADA accessible. It would be helpfully to indicate if side approach accessibility is acceptable. If front approach is required, sink cabinet needs to be eliminated Answer: Adjustment of sink location to be addressed in shop drawings for better accessibility. Answered by: Marty Lubin (WMCRP) 177) RFI from CT Electric

Page 29: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Question: Is this project to be bid with Category 6A Cable- Category 6A jacks and patch panels making this a10GbE System Answer: Yes, 6A components should be used and deliver 10 gb performance. Answered by: Bryan Jones (ESP) 178) RFI from Pleasants Construction Question: There is a sewer manhole referencing to be built over sewer existing line, commonly referred to has a "Doghouse Manhole". However WSSC do not allow these anymore. Answer: See WSSC standard detail S/2.0 for Precast Concrete Manhole Built over Existing Sewer. Answered by: Nicholas Barrick (KCI) 179) RFI from Pleasants Construction Question: In the Phase 2 sewer there is referenced a 8x10" reducer that is to be installed during Phase 1, however it is not listed on the Phase 1 plans. Answer: : Phase one water only calls for installation of a 4” water line and the 6” sewer connection for the field house. Refer to the plans. Answered by: Nicholas Barrick (KCI) 180) RFI from CT Electric Question: Could you clarify Detail 1 on sheet TE-4.1? Is item 933 supposed to be panel 1GP? Are these the same circuits shown on sheet E-123 (1GP-3,5,7 / 1GP-7,9,11 / 1GP-2,4,6 / 1GP-8,10,12)? The panel schedule calls for 1” conduit for these circuits but sheet TE-4.1 shows 1-1/4” conduits. Where is item 930, the Drive Enclosure, to be located? What size conduit is to be used between items 932, 931 and 930? What wiring if any is to be installed between these items? What wiring is needed between item 930 and the Low-Voltage Connector Strips? What changes need to be made if item 930 is not used? Answer: Yes, 933 is to be 1GP on sheet E123. This is to provide 4 ea 60 amp, 480VAC three phase power circuits, one to each strip. I sized the conduits at 1.25" to allow for #4 conductors in case the run distance is long. As long as the distance is short and you use #6, 1" conduit would appear to be the code size. The location of 930 is flexible, as not all winch manufacturers would use a control enclosure in their systems. Some build all the controls into the hoist itself and the operators station. Ideally it would be located at the catwalk level, down stage of the proscenium. If 930 is not used, control strip wiring goes directly to the operator’s station or to a junction box then to the station. Wiring between the control strips and the operator station is typically 10 to 12 conductors with maybe a network cable or Belden cable, this again depends on manufacturer. I am calling out 1.25" conduit, but smaller conduit may be acceptable once you have shop drawings from the manufacturer. Shop drawing requirements would over ride what is shown on TE-4.1 Answered by: Duane Wilson (Consulting For Theater Systems) 181) RFI from W.L. Gary Question: The lab sinks on plumbing schedule P-601 calls for either an acid neutralization tank or an acid trap. Riser diagram on P-703 show these completely piped out to an acid tank. Are

Page 30: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

acid traps acceptable with only a small piece of corrosion resistant piping between sink/cup sink drain and trap? There is a substantial cost difference between the 2 options of either piping these our completely in corrosion resistant piping versus cast iron. Please clarify. Answer: It should be corrosive resistance piping and fittings all the way to an acid neutralization tank underneath of the sink groups. Answered by: Tom Green (ASE) 182) RFI from Steel Products Question: The specifications for the markerboards and tackboardss reference the snap on trim method of installation but mention factory built. If factory built is acceptable then the architect should reference claridge series 1 units as the basis of design or state only snap on trim on continuous grounds as the method of installation will be acceptable. Answer: This equipment is not factory built Answered by: Marty Lubin (WMCRP) 183) RFI from Steel Products Question: There are sliding markerboards labeled on the drawings but are not specified. Unless spe’s are issued we will submit a bid using the most economical setup Answer: See Addendum #2 Answered by: Marty Lubin (WMCRP) 184) RFI from Steel Products Question: There are 3” deep display cases which should be bulletinboards; no spec. Also there are no other prefabricated display cases. Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 185) RFI from TJ Distributors, Inc. Question: Section 12710, paragraph 2.1.F.5.b (page 9), states a power / data raceway is needed for the orchestra seating areas to extend the power from the opposite side of the seating section. Would it be possible for the seating contractor to locate the floor boxes required and have the electrical contractor install these in lieu of providing a raceway? Answer: : I have no objection to this approach as long as the seating contractor takes full responsibility for locating the boxes and any subsequent rework to get them in the correct place. Experience has shown that the coordination to locate the boxes in practice is iffy at best. This is the reason for specifying the seating raceway, as it would allow more flexibility in allowing the electrical contractor locate boxes in the knee wall and require less critical planning in pouring the seating slab. Answered by: Duane Wilson (Consulting For Theater Systems) 186) RFI from TJ Distributors, Inc.

Page 31: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Question: Section 12715, paragraph 2.3.j (page 4), states a power/data is to be supplied with the lecture hall seating. I have reviewed the drawings and do not see the necessary stub ups that are required for these to be incorporated into the seating. Are power/data service packages required with all the seating the lecture room? Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 187) RFI from TJ Distributors, Inc Question: Section 12715, paragraph 2.3.k (page 4), states oversized tablet arem to be supplied. The current row spacing is only 36” which will only allow for standard size tablet arms. Oversized tablet arms requires 42: row spacing which would reduce the number os seats able to fit in the space. Which style tablet arms are to be supplied? Answer: See Addendum #3 Answered by: Marty Lubin (WMCRP) 188) RFI from Pleasants Construction Question: There is an additional Sewer Manhole not listed that requires installation. The plan view (sheet WS01) C-33 indicates a new sewer line to the building from the South from Elkines Ave. We tie in to the existing structure, but there is a new structure required as well. This is structure shown on the profile but it has a duplicate structure as another on the other run from the North. Answer: There is a new manhole, number 9, installed within the parking lot. Answered by: Nicholas Barrick (KCI) 189) RFI from Pleasants Construction Question: Profile Plan C-53 says the cistern is "by others". Who is responsible for the cistern? Also there is no profile of the system to get a clear understanding of what is required (Depth of system, stone bedding depth, is filter fabric required, etc.) Also, Plan C-61 shows a Vault near the system but there is no details showing what kind - precast? What size or what depth this vault is? More information is needed in order to price this aquabloz cistern system. Answer: The cistern is provided by the 02A Contractor. The drawings indicate the “basis of design” manufacturer, the installed system volume, and proposed elevations (NOTE: Replace Bottom of Stone elevation to read 172.33 on C-61 Cistern Plan) Final design of the cistern is to be provided by the manufacturer for approval. The pump design and installation is specified under 02811 – IRRIGATION SYSTEMS, also under the 02A Scope of work Answered by: Nicholas Barrick (KCI) / Todd Ward (HESS) 190) RFI from JP Construction Question: gypsum board assemblies specification 09255-15 mention drywall finish is level 4, scope of work 09A item 21 refers that drywall needs to be level 5 finish. Should we use specification or scope of work? Answer: Gypsum board assemblies shall be a level 4 drywall finish. Scope 9A has been revised and included with this addendum.

Page 32: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Answered by: Jim Gladhill, Hess 191) RFI from Pleasants Construction Question: Can Recycled stone be used for construction roads? Can the existing site concrete/asphalt if crushed or milled be used on site Answer: Yes, recycled stone can be used for construction roads. Yes, the existing site concrete/ asphalt can be used on site if crushed or milled. Answered by: Jim Gladhill, Hess 192) RFI from JP Construction Question: Typical roof top unit AHU Mechanical drawings M-901 is shown assembly of 4 layer of 1/2" cement board and 4 layer of 1" density fiber glass, confirm is this work is being picked up by the mechanical contractor or is the 09A package responsibility. Answer: This work is the responsibility of the 9A Contractor. Answered by: Jim Gladhill, Hess 193) RFI from Facchina Question: Were the amount of asbestos is quantified, It says what may be asbestos but nothing specific has it been quantified, Answer: Asbestos Abatement has been removed from the 02A Scope of Work. The 02A Contractor shall be responsible to coordinate the sequence of demolition work with the Abatement Contractor. Answered by: Todd Ward/HESS 194) RFI from Homewood General Contractors Question: Which package furnishes and installs the hardwood stringer and treads per detail J / A973 Answer: The wood stringer, riser and tread shall be provided by the 06A contractor. Answered by: Jim Gladhill, Hess 195) RFI from Hercules Fence Question: – The written spec’s 02831 item # 2.2 – C 1 & 3 call out for 6 gauge 2 o.z. wire and on drawings C-14 they show a 9 gauge black vinyl wire 1” mesh on all the fences, Which one do we use. Answer: See Addendum #3 Answered by: Marty Lubin, WMCRP 196) RFI from JP Construction Question: Rough carpentry specifications 2.9 section A calls for CD plywood for mounting electrical and telephone equipment, architectural drawings does not call for anything, on drawings E 154 electrical is equipment does not call for it, do we need or we don’t need to figure surface blocking for hanging electrical equipment please advice if this is 09A responsibility

Page 33: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Answer: : See Addendum #3 Answered by: Marty Lubin, WMCRP 197) RFI from JP Construction Question: specifications 05400 Cold formed metal framing under sheathing 2.7 item A calls for 1/2" exterior cement board details on architectural drawings A-406 A407 typical details for exterior walls call for 1/2" sheathing, please notify which of these products for exterior wall is the correct one. Answer: "Sheathing" is a generic term. Refer to G-002, Exterior Wall Finishes" for sheathing type. Answered by: Marty Lubin, WMCRP 199) RFI from Halac Iron Question: S-210 shows sections indicating what appears to be 1.5” B deck or similar profile at walls G-002 seems to be referring to the same material which is called out as : 1.5 “ metal siding. (EWP-C ) and 3” metal siding ( EWP-R) please confirm whether or not steel deck is required in these locations and if so: what is EWP-C referring to: 1.5” B, A, or F? and gage and finish requirements, same thing for EWP-R. On a similar but slightly different note, section 4 on A 413 has “metal wall panels on screen wall framing RE: structural” which structural section does this refer to? None seemed to match it. Is this metal wall panel a steel deck? If this is a steel deck, please specify the depth, type, gage and finish Answer: Metal wall panel types are clearly noted elevation sheets A-201 & A-202 and further clarified on "Exterior Wall Finishes" per sheet G-002. The wall panel types are also in the spec using the same wall type indicators. On their "slightly different note", I can track the section down on the bid set to detail B/S-301. Answered by: Marty Lubin, WMCRP 200) RFI from Halac Iron Question: General Structural Notes S-001 indicates that there is 6 inch 16 & 18 gage and 7 ½ inch 16 gage “WPA”(EPIC nomenclature) Cellular acoustic roof deck in the Auditorium and Gymnasium. S-001 also indicates that there is an Alternate roof deck for the Gymnasium, 7 ½ inch 16 gage Type “HA”(not EPIC nomenclature). There are no areas on the drawings that depict any of these profiles nor are there structural members that would be consistent with the spans where these roof deck profiles would be required. Further, it appears that the Gymnasium is existing so there is no building/space that would require these profiles or any other. Answer: See Addendum #3 Answered by: Chenping Ku, ReStl 201) RFI from Halac Iron Question: Drawing S-121 has a note that indicates that the roof deck in the Wrestling Room, Dance Studio, and Fitness Room are to be “3 ½ inch 20 gage EPICORE ER3.5A Roof deck.

Page 34: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Architectural Drawings indicate that the ceilings in these areas are to be a hung acoustical ceiling. What material is intended for these areas and what are the boundaries where the respective material is required Answer: See Addendum #3 Answered by: Chenping Ku, ReStl 202) RFI from Halac Iron Question: Specification section 05310 calls for “ER3.5A acoustical roof deck as manufactured by Epic Metals Corporation” but 6 or 7 ½ inch WPA cellular acoustic roof deck is not shown in the Specification. Please clarify whether WPA is required in any location as an alternate. And whether there is a new gymnasium in addition to the existing gymnasium Answer: ER3.5A Acousticl Deck Will Only Be Used In The Library Roof And High Roof Of Dining Area Answered by: Chenping Ku, ReStl 203) RFI from Atlascopco Construction Company, Inc. Question: The specifications call for self supporting stair treads/riser units. Detail 1/A-173 shows the length of these units as 9'8". Understand from Precast treads manufacturers , It is not recommended this type of tread at any length greater than 8' 0 " Solution could be to have self supporting treads/ risers 14-18" x 4" x 58 " ( requires additional stringer ) & self supporting landing panels 4" x 58 " OR For non self supporting treads / risers 14-18" x 2" x 58" ( requiring stair pan structure ) and standard 2" thick landing panels. Answer: The steel stair manufacturer is responsible for engineering, detailing and certifying the stair design based on the intent shown on the drawings and specs. If a manufacturer determines it needs a middle stringer for support, they should include it in their design The 9B flooring contractor must coordinate with the 5A steel contractor. Answered by: Marty Lubin, WMCRP / Jim Gladhill, Hess 204) RFI from Pleasants Construction Question: Is there a construction road required around the building? If so, do we maintain? Answer: See 02A Work Scope, page 7, item #12. Answered by: Todd Ward, HESS 205) RFI from Pleasants Construction Question: What bonds are you referring to that the 2A contractor will have to obtain and what are those cost? We are not the developer and have not been informed to these expect cost. Answer: In addition to 100% performance and payment bonds, 02A Contractor is responsible for providing the performance bond associated with the Right-of-Way permit as required by PGC DPW&T. Answered by: Todd Ward, HESS

Page 35: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Page 1 of 7 00210 BID FORM Revised Per ADD#1 7-13-11

Revised Per ADD#3 7-26-11

OXON HILL HIGH SCHOOL REPLACEMENT PROJECT BID FORM - Submit one (1) executed original and three (3) two (2)1 Duplicates of this form and required attachments (only one (1) original required for attachments)1

DATE:

in sealed envelope bid submission

OWNER:

CONST. MGR.

BOARD OF EDUCATION OF PRINCE GEORGE’S COUNTY

PROJECT TITLE:

HESS CONSTRUCTION + ENGINEERING SERVICES

PSC NO.

OXON HILL SCHOOL REPLACEMENT PROJECT

16.082.10 LP 1 IFB# 107-11

1

BID PACKAGE#:

BID PACKAGE TITLE:

BID SUBMITTED BY:

CONTRACTOR’S MAILING ADDRESS: CONTRACTOR’S STREET ADDRESS

(IF DIFFERENT):

CONTACT PERSON’S NAME: CONTACT PERSON’S TITLE:

TELEPHONE: STATE OF MD CONTRACTOR’S LICENSE:

FAX: LICENSE #:

EMAIL: EXP. DATE:

FED ID #:

Page 36: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Page 2 of 7 00210 BID FORM Revised Per ADD#1 7-13-11

Revised Per ADD#3 7-26-11

If the bidder is submitting bids for more than one (1) contract package, each bid must be made in separate sealed envelopes, using separate bid forms, bid bonds, and MBE forms. Bidder may not combine pricing for multiple bid packages, or submit separate bids within the same sealed envelope.

NOTICE TO ALL BIDDERS:

1.1 The undersigned BIDDER proposes and agrees, if this Bid is accepted, to enter into an Agreement with HESS CONSTRUCTION + ENGINEERING SERVICES in the form included in the Contract Documents to complete all Work as specified or indicated by the Contract Documents for the Contract Price and within the Contract Time indicated in this Bid and in accordance with the Contract Documents.

PART 1 - BASE BID

1.2 BIDDER has examined the site and locality where the Work is to be performed, the legal requirements (federal, state and local laws, ordinances, rules and regulations) and the conditions affecting cost, progress or performance of the Work and has made such independent investigations as BIDDER deems necessary.

1.3 BIDDER must submit bids including the State of Maryland Prevailing Wage Rates for each bid lump sum total amount.

1.4 BIDDER hereby agrees to furnish all labor, materials, equipment, services, applicable taxes, insurance premiums, 100% performance and payment bonds, and all other items required to complete the scope of work in strict accordance with the Contract Documents for the following price:

1.5

BASE BID

Dollars ($ )

2.1 BIDDER shall carefully review each alternate listed below, and determine if the bidder’s scope of work is impacted by the acceptance of the alternate. An alternate price shall include all costs associated with the described alternate per Section 01030 of the project manual, or reasonably inferable there-from. Claims for increases to the contract sum resulting from changes caused by the acceptance or rejection of an alternate will not be allowed. Alternates, the Drawings, Specifications, and other Contract Documents shall be considered appropriately modified by either the acceptance or rejection of the various alternates. The OWNER expressly reserves the right to accept or reject any, or all alternates and in any sequence. Acceptance or rejection of any alternate does not relieve the bidder of timely completion of the work within the time periods indicated.

PART 2 – ALTERNATES

2.2 BIDDER must submit bids for ALL alternates. BIDDER is to submit $0.00 for Alternates which do not affect the bidder’s scope. If a bidder submits a bid and writes “N/A”, “None” or leaves the alternate blank, the bidder assumes the risk of this work and it will be deemed the same as a $0.00 bid submission.

Page 37: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Page 3 of 7 00210 BID FORM Revised Per ADD#1 7-13-11

Revised Per ADD#3 7-26-11

2.3 Alternate bids must be include Prevailing Wage Requirements.

2.4 BIDDER hereby agrees to furnish all labor, materials, equipment, services, applicable taxes, insurance premiums, 100% performance and payment bonds, and all other items required to complete the scope of the alternate work in strict accordance with the Contract Documents for the following price:

A.

ALTERNATE #1: ELEVATOR #2

ADD:

Dollars ($ )

B.

ALTERNATE #2: ARTIFICIAL TURF

ADD:

Dollars ($ )

C.

ALTERNATE #3: FRONT ENTRANCE CANOPY

ADD:

Dollars ($ )

D.

ALTERNATE #4: STADIUM SPORTS LIGHTING

ADD:

Dollars ($ )

E.

ALTERNATE #5: INCREASED BLEACHER SEATING CAPACITY

ADD:

Dollars ($ )

F.

ALTERNATE #6: PHENOLIC WALL PANELS (EWP-Q)

ADD:

Dollars ($ )

G.

ALTERNATE #7: POLISHED CONCRETE

ADD:

Dollars ($ )

H.

ALTERNATE #8: ADDITIONAL STAGE RIGGING EQUIPMENT

ADD:

Dollars ($ )

I.

ALTERNATE #9: UPGRADED STAGE LIGHTING

ADD:

Dollars ($ )

Page 38: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Page 4 of 7 00210 BID FORM Revised Per ADD#1 7-13-11

Revised Per ADD#3 7-26-11

J. ALTERNATE #10: ADDITIONAL STAGE LIGHTING A/V 3

SYSTEM EQUIPMENT

ADD:

Dollars ($ )

K. ALTERNATE #11: ADDITIONAL STAGE AUDIO/VISUAL EQUIPMENT

3

K. ALTERNATE #11: FSC CERTIFIED WOOD

3

ADD:

Dollars ($ )

L. ALTERNATE #12: FSC CERTIFIED WOOD

3

L. ALTERNATE #12: TRANSLUCENT GLAZING, TYPE 1

3

ADD:

Dollars ($ )

M.

ALTERNATE #13: TRANSLUCENT GLASS WALL PANEL SYSTEM, TYPE 2

ADD:

Dollars ($ )

3.1 UNIT PRICE FOR REPLACEMENT OF UNSUITABLE SOILS BELOW LOWEST DESIGNED SUBGRADE ELEVATION (02A CONTRACTOR ONLY):

PART 3 - UNIT PRICES

The 02A Contractor shall carry an allowance of 40,000 cubic yards within the base bid amount to address unclassified, unsuitable soils below lowest designed sub-grade elevation

. The allowance represents the quantity of material anticipated to be excavated, removed, and replaced with imported structural fill suitable for the building pad, including placement and compaction in accordance with specification requirements. Contractor shall provide a cubic yard unit price with the bid (02A Contractor to fill in space provide below). Actual compensation for replacement of unsuitable soils (below lowest designed sub-grade elevations) through use of the allowance will be based on actual quantities verified in the field by the Construction Manager. If the actual work performed is less than 40,000 cubic yards, the unused allowance quantity multiplied by the unit price will determine the credit amount due by the Contractor. If the actual work performed is more than 40,000 cubic yards, the additional compensation due (via change order) to the Contractor will be determined by the additional quantity of cubic yards multiplied by the unit price, with no additional mark-ups allowed. Unit price includes all overhead, profit, applicable taxes, bonds, labor, fringes, materials, labor, equipment, and any other incidentals related to the completion of the work. Prices as stated shall remain in effect through the end of the Contract period.

Page 39: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Page 5 of 7 00210 BID FORM Revised Per ADD#1 7-13-11

Revised Per ADD#3 7-26-11

A.

UNIT PRICE FOR REPLACEMENT OF UNSUITABLE SOILS BELOW LOWEST DESIGNED SUBGRADE ELEVATION:

COST PER CUBIC YARD:

Dollars ($ )

3.2 FIXED UNIT PRICES APPLICABLE TO THE CONTRACT: This unit prices provided by paragraph 3.2 A. will be submitted with the Bid and shall

become a part of the Contract upon its award. Unit prices listed are applicable to all Work in this project involving extra materials/services performed by the Contractor or its Subcontractors and/or credits to the Owner/CM for materials/services deleted from the project. Unit price includes all overhead, profit, applicable taxes, bonds, labor, fringes, materials, labor, equipment, and any other incidentals related to the completion of the work. Prices as stated shall remain in effect through the end of the Contract period. The undersigned acknowledges the unit price values as part of this bid and agrees to add or delete items for the unit prices identified when directed to do so by the Owner/CM. The Owner reserves the right to negotiate until prices, depending on the quantities to which the unit prices become applicable.

A.

ITEM #

SCHEDULE OF FIXED UNIT PRICES:

DESCRIPTION OF ITEM UNIT PRICE ($) 8 Site Concrete – Combination Curb & Gutter LF 8.50 12.00 3

9 Site Concrete – 4’ wide sidewalk (4” stone, 4” conc) w/#10 WWF SY 30.00 36.00 3

10 Asphalt Paving, including stone subgrade - Standard Duty Paving Section - Heavy Duty Paving Section

SY SY

20.00 23.00 3

22.00 25.00 3

11 Landscaping – Sod - Yardage under 5,000 - Yardage over 5,000

SY SY

3.25 3.00

12 Landscaping – Hydroseeding SY 0.85 13 Concrete – Under-slab Gravel CY 30.00 14 Concrete – Reinforced Concrete Footings CY 225.00 260.00 3

15 Masonry - Non-load Bearing CMU - 4” CMU Wall - 6” CMU Wall - 8” CMU Wall - 12” CMU Wall

SF SF SF SF

6.00 6.60 8.10 9.00

16 Masonry – 4” Face brick SF 14.40 16.00 3

17 Painting – includes drywall point-up for minor repairs. Unit Price is for work below 12’ in height. - Two (2) coats drywall primer + Two (2) finish coats - One (1) additional finish coat

SF SF

0.90 0.20

18 Electrical – Exit Light (include with 50’ of conduit, hardware, and wiring) EA 500.00

19 Electrical – Light Switch (include with 100’ of conduit, hardware, and wiring) - Single pole - 3-way

EA EA

425.00 475.00

20 Electrical – Outlets 400.00

Page 40: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Page 6 of 7 00210 BID FORM Revised Per ADD#1 7-13-11

Revised Per ADD#3 7-26-11

(include 100’ of conduit, hardware, and wiring) - Duplex outlet - Double Duplex (Quad) outlets

EA EA

475.00

21 Electrical – Tech Wiring (include 200’ of wiring, hardware, sleeves) - Single Data outlet - Single Call Back outlet - PA Ceiling Speaker - Analog Telephone Outlet - Clerical data outlet - Student data outlet - Video outlet

EA EA EA EA EA EA EA

250.00 320.00 400.00 250.00 250.00 250.00 200.00

22 Electrical – Fire Alarm Devices (include 100’ of conduit, hardware, wiring, and programming) - Fire Alarm Pull Station - Fire Alarm Strobe (Floor or Ceiling) - Fire Alarm Addressable Module - Fire Alarm Duct Smoke Detector

EA EA EA EA

500.00 500.00 525.00 550.00

PART 5 – REQUIRED ACKNOWLEDGEMENTS AND ATTACHMENTS

5.1 ADDENDA: BIDDER acknowledges receipt of the following Addenda to the Drawings and Specifications:

A. Addendum No. ____ Dated ______________ B. Addendum No. ____ Dated ______________ C. Addendum No. ____ Dated ______________ D. Addendum No. ____ Dated ______________ E. Addendum No. ____ Dated ______________

5.2 BIDDERS AFFIDAVIT: BIDDER includes one (1) original and three (3) two (2)1

duplicates of an executed Bidder’s Affidavit in the form set forth by Section 00250 the project manual.

A. Bidder’s Affidavit included: ________ (due with bid submission) 5.3 BID BOND: BIDDER includes one (1) original and three (3) duplicates 1

of a Bid Bond in an amount not less than five percent (5%) of the bid amount, and in the form set forth by Section 00300 of the project manual.

A. Bid Bond included: ________ (due with bid submission)

Page 41: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

Page 7 of 7 00210 BID FORM Revised Per ADD#1 7-13-11

Revised Per ADD#3 7-26-11

5.4 MBE FORMS: BIDDER includes one (1) original and three (3) duplicates 1

the following Minority Business Enterprise Forms with the Bid Proposal, in accordance with Section 00350 of the project manual.

A. Attachment 1 included: ________ (due with bid submission)

B. Attachment 2 included: ________ (due with bid submission)

PART 6 – CONTRACT, PROJECT SCHEDULE, AND LIQUIDATED DAMAGES

6.1 If the undersigned receives written notice of the acceptance, at his designated address, within ninety (90) calendar days after bid opening (or later if bid has not been withdrawn), the undersigned agrees to execute and deliver a Contract and Bonds in accordance with the bid as accepted, within ten (10) calendar days after receiving notice, or forfeit the amount of the Bid Bond.

6.2 The undersigned agrees to complete the Work in strict accordance with the Contract Documents and be substantially complete by not later than the date(s) set forth in the Construction Schedule prepared and amended by the Construction Manager. The Owner may retain up to the sum of One Thousand, Five Hundred Dollars ($1,500.00)

for each calendar day of delay beyond the Substantial Completion date of each phase of the project as stipulated in the Contract, without limitation.

BIDDER:

PART 7 – SIGNATURE AND SEAL

SIGNATURE:

PRINTED NAME:

PRINTED TITLE:

Signed and Sealed this day of , 2011.

NOTARY PUBLIC: SEAL:

My commission expires the day of , 2011.

END OF SECTION 000210

Page 42: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 1 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

WORK SCOPE CATEGORY 02A SITEWORK The work of this bid category includes but is not limited to providing all labor, equipment, materials, scaffolding, hoisting and incidentals to complete all SITEWORK work in accordance with the specifications, drawings and applicable codes. All work is to be performed as shown on the plans and / or specified under the following technical sections: SECTION Division 0

NAME

Division 1 02220 Selective Demolition 02221 Building Demolition and Rodent Extermination 02230 Site Clearing

02260 Excavation Support and Protection 02300 Earthwork 02370 Soil Erosion & Sediment Control 02510 Water Systems 02530 Sanitary Sewer Systems 02620 Subdrainage 02630 Storm Drainage System 02741 Hot Mix Asphalt Paving 02751 Portland Cement Concrete Paving 02790 Exterior Athletic Surfacing 02810 Irrigation Systems 02831 Chain Link Fences and Gates 02832 Segmental Concrete Retaining Wall 02835 Outdoor Sound-Barrier Walls 02900 Landscape Work 02937 Seeding and Sodding 03300 Cast-In-Place Concrete (as it relates to this scope) 05500 Metal Fabrications (as it relates to this scope)

07135 Self-Adhering Sheet Waterproofing (as it relates to this scope) 07901 Joint Sealants (as it relates to this scope) 10350 Flagpoles 13125 Grandstands and Bleachers 15901 Geothermal System Division 15 Mechanical (as it relates to this scope) Division 16 Electrical (as it relates to this scope) ALL OTHER SPECIFICATION SECTIONS – FOR COORDINATION PURPOSES Geotechnical Report issued by GEOTECH Engineers, Inc In addition to the above, trade contractors are to include, but are not limited to, AIA Documents and various other Technical Specifications interfacing with this work. The Contractors are required to review the work descriptions of the other categories so as to not misunderstand the scope responsibilities. The Contractors are also bound to the HESS Safety Manual and the HESS Trade Contractors Procedures Manual for Oxon Hill High School Replacement for the administration of the contract.

Page 43: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 2 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

Contractor is responsible for General Scope of Work listed elsewhere in this specification section General Scope:

THE SPECIFIC SCOPE OF WORK IS TO INCLUDE

, but is not limited to, the following items:

Abatement Specific Scope:

1. Contractor to remove all Asbestos Containing Materials (ACM), Asbestos Containing Building Materials (ACBM) in compliance with the National Emission Standard for Hazardous Air Pollutants (NESHAP), Occupational Safety and Health Administration (OSHA), Asbestos Hazards Emergency Response Act (AHERA), Asbestos Maryland Occupational Safety and Health Administration (MOSHA) guidlines . Unless specified elsewhere, all material removed shall be removed and disposed of as contaminated waste.

2. Contractor acknowledges in addition to the school building, all ACBM’s found in or on any other structures or equipment shall be considered within the scope of work in this contract and therefore shall be removed according to all requirements set forth in these documents. Any demolition necessary to access ACM or ACBM in suspect locations shall be considered within the scope of this contract, ie, behind fixtures in walls, pipe chases, or above plaster ceilings.

3. Contractor acknowledges the information concerning the type of ACM known by PGCPS to be located

at Oxon Hill High School is included in the contract documents for informational purposes, and PGCPS or the Construction Manager does not warrant it accuracy, contractor is advised to conduct a thorough review of the existing building, contract documents, and any other available record to determine the exact amount of work required to perform a complete abatement of HAZMAT at this facility.

4. Contractor acknowledges all areas will be tested for final clearance by Transmission Electron

Microscopy (TEM), as per AHERA protocol. TEM clearance analysis will take up to three business days. Contractor is responsible for costs of hiring a third party independent laboratory for all air samplings required until project abatement completion.

5. Contractor to remove all ACM and ACBM prior to building razing per the submitted Asbestos

Abatement Plan approved by the Asbestos Coordinator.

6. It is the responsibility of this contractor to remove any building materials which prohibit access to the ACM or ACBM.

7. Contractor is responsible for the erection of all barriers, both primary and secondary, protective plastic

sheeting, false ceilings and decontamination chambers, initial and final cleaning/decontamination; waste collection and disposal; and all other associated tasks standard to asbestos abatement industry and which are necessary to successfully abate the ACM or ACBM.

8. Prior to removal of floor tile and mastic, contractor to remove and dispose of all floor cabinetry, built –

ins, etc as it is expected floor tile and mastic are under these items.

9. Contractor to remove all interior doors, chalkboards, bulletin (tack) boards, white boards, display cases, and other items glued to the wall and the glue spots behind each of these items throughout the building as ACM. Other items of concern which may be ACM / ACMB are ceiling tiles, floor tiles, spray applied insulation, fire board (transite type), mastics, roofing materials and tar, pipe insulation, pipe fitting insulation, folding doors, caulking, duct insulation, boiler insulation, drywall, spackle, plaster, adhesives, glazing, toilet partitions, fire doors, etc.

10. Removal and disposal of all transite panels at the exterior of the building is considered ACM.

Page 44: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 3 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

11. It is assumed that any areas of the existing building which have carpet or 12 x12 floor tiles, are over ACBM and must be removed, unless noted elsewhere otherwise.

12. It is expected asbestos removal includes all roof flashing and fire doors.

13. Contractor to include removal of all insulation, inclusive of fiberglass, duct insulation, pipe insulation,

associated fittings, elbows, tees, hangers, hanger blocks, debris, bowls and fittings, and AC fire proofing.

14. Contractor to include prior to asbestos abatement, removal of all existing lighting fixtures. Contractor

must provide an AHERA certified licensed electrician to disconnect light fixtures. Prior to asbestos abatement the light fixtures are to be disconnected at the junction boxes and wire ends covered with wire nuts for safety. After removal of fixtures, ballasts are to be inspected for PCB names. Contractor includes removal of all PCB light fixtures per standards and regulations. No ACM or ACBM work can commence until after completion of PCB work. Contractor to include disposal of all fluorescent light tubes in accordance with standards and regulations.

15. Contractor includes removal and disposal of all HVAC refrigerant.

16. Contractor includes removal and disposal of all storage tanks, above and below grade, within the

building footprint. Contractor includes removal and disposal of all fluids from said tanks at no additional cost to the owner

17. Any suspect material encountered during abatement, Contractor is to immediately notify the

Construction Manager in writing prior to removal of said material.

18. Contractor to provide to Construction Manager all Waste Manifests, and or Bill of Lading as part of substantial completion. All material removed from this project must be tracked from cradle to grave with Certificates of disposal provided prior to retainage reduction or final payment.

19. Contractor to provide or has provided training as follows for all personnel involved on this project:

• 40 Hours OSHA Training • 24 Hours RCRA Training • AHERA Certified “Asbestos Abatement Workers”

o Physical characteristics of asbestos health hazards associated with asbestos o Respiratory protection o Use of protective equipment o Negative air systems o Work practices including hands on or job training o Personal decontamination procedures o Air monitoring personal and area

• All valid/required Federal, State and Local Training and Certifications 20. Contractor is responsible for all utility disconnects.

21. The limited use of Glove Bag Removal

will be allowed with prior written approval from the State of Maryland Department of the Environment and final approval of the Owner (PGCPS).

22. Contractor to submit a detailed plan of procedures for use in complying with the requirements of the specification. Contractor to include location of the decontamination areas, sequencing of the asbestos work, list of possible interface of other trades involved with the work, disposal plan inclusive of the disposal sites, and a detailed description of the methods to be employed to control pollution.

Page 45: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 4 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

23. Contractor to coordinate with Construction Manager for placement of all equipment, storage containers, disposal containers etc. If additional storage is required, Contractor has included such storage offsite.

24. No equipment and or materials may be left out unprotected after the scheduled work shift is complete.

The Contractor will not store any materials onsite outside of the work area.

25. Asbestos removal work shall not be performed without the industrial hygienist onsite. Contractor has included all required third party testing and inspections to be performed.

26. Failure to comply with Federal, State and Local regulations will force the issuance of a stop work order

by the Construction Manager or Owner Asbestos Coordinator. Contractor cannot commence work until authorized in writing by Construction Manager or Owner Construction Coordinator.

Abatement scope has been removed from the 02A scope of work per ADD#3 3

Demolition Specific Scope:

1. This contractor is responsible to review existing conditions before his work commences for both onsite and offsite activities to ensure all utilities have been properly disconnected.

2. This contractor is responsible for its own vertical access and transportation of men, materials, and

equipment into and out of the building. 3. This Contractor shall provide for all building demolition shown or implied on the drawings, or directly

related to the existing building which includes, but is not limited to, the complete demolition, removal, and disposal of all drywall, concrete, masonry, plaster, walls and attached items, ceilings, partitions, soffits, windows, storefronts, frames, sills, cabinets, shelving, flooring, chimneys, foundations walls, foundations, lockers, markerboards, tackboards etc, steel, mechanical, electrical, plumbing, low voltage, roofing, equipment, roof top equipment, chillers, boilers etc, a complete demolition and removal of the existing facility as indicated on the contract documents.

4. This contractor is responsible for all site demolition shown or implied on the drawings, or directly

related to the existing conditions of the site which must be removed to perform new work which includes, but is not limited to parking lots, drives, tracks, running lanes, and other asphalt pavement, walkways, curbs, gutters, paving, steps, ramps, and other site concrete, pavers, retaining walls, areaways, outbuildings, sheds, bleachers, exterior athletic equipment, scoreboards, bollards, railings, flagpoles, storm drain and structures, SWM facilities, sanitary sewer system(s), domestic water service(s), fire service(s), site electrical systems, light poles and bases, and all other items indicated on the drawings unless specifically identified to remain.

5. This contractor is responsible for safely cutting and separating the existing main gymnasium to remain

from other work to be demolished. Contractor is responsible to provide temporary shoring/protection plan to the Construction Manager prior to the start of work. Engineering requirements for temporary shoring is this Contractor’s responsibility.

6. Contractor to review site conditions prior to start of work, inclusive of inspections of any underground

storage tanks. Contractor to include hazmat and non hazmat liquid(s) removal as part of work. 7. Contractor to review existing conditions prior to start of work, inclusive of inspecting mechanical

equipment, capturing existing coolants and removal prior to the start of demolition is the responsibility of this contractor.

8. All salvageable material listed shall remain the property of Owner. Owner material will be removed

prior to start of Demolition. All remaining items will be the responsibility of the Contractor.

Page 46: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 5 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

9. Contractor shall provide daily clean-up and disposal of all trash, debris, and excess material generated

by this work to own dumpsters in compliance with submitted and approved waste management plan. Should the contractor’s clean up be unsatisfactory, the Construction Manager shall perform the work at the contractor’s expense. Construction Manager will issue one “Notice to Cure”. Subsequent “Notice to Cure’s” will not be required prior to performance of work at contractor’s expense.

10. Contractor is responsible for restoration of sidewalks or other improvements not scheduled for

demolition damaged by this contractor. 11. This contractor is responsible to coordinate with all Trade Contractors before and during demolition

activities. 12. This contractor is responsible for all shoring and engineering associated with the demolition.

13. Contractor This contractor shall haul all debris off site and recycle at least 75% of the debris in

compliance with the specification and LEED Green Building requirements. Onsite separating operations will not be allowed.

14. As a requirement of reaching substantial completion of this contractors work he shall provide all

relevant documentation for the disposal of the debris in accordance with the LEED Green Building requirements.

15. This contractor responsible to keep all streets free of mud and debris generated by own work.

16. Contractor includes demolition and removal of masonry mockup panel(s) and foundation as directed

by Construction Manager.

17. Contractor includes demolition of foundations, steps, and ramps for the Construction Manager’s trailer at the completion of the project.

18. Contractor is responsible to contract with 3rd party rodent removal company and provide certification

letter to county stating work has been performed, prior to demolition permit release.

Earthwork and Utilities Specific Scope:

1. Remove trees, shrubs, grass, and other vegetation, improvements, or obstructions, as required, to permit installation of new construction. Site clearing and grubbing, including removal and disposal, shall be as indicated on the plans. The contractor will acknowledge locations of all protected foliage per the plans and specifications prior to the start of any work, and will be responsible for installation, root pruning, signage, etc and maintenance of this protection while contractor is on the project. This Contractor includes dressing up and stabilization around Construction Manager Trailer and removal and restoration of area at project completion.

2. Contractor shall furnish, install, maintain and remove at the direction of the Construction Manager

and/or any governing agency all sediment and erosion control measures and devices, stabilized construction entrances, storm water management facilities and all sediment traps/basins required by the Contract Documents. This Contractor is responsible for keeping streets clean of debris as a result of their work throughout duration of project, and/or as a result of unsatisfactory stabilization of site conditions. This Contractor is responsible for all temporary seed required for the site stabilization including maintenance and watering as required per the specifications. Contractor shall furnish, install, and maintain all structures, manholes, clean outs, and the like associated with its work as required by the Contract Documents for the entire duration of the project. Contractor shall furnish, install, and maintain all concrete, reinforcing, rip-rap, stone and filter cloth related to this work for the entire

Page 47: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 6 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

duration of the project. Contractor shall furnish, install, and maintain all required protection of inlets, structures, and any other erosion and sediment control device that is shown, implied, or required for the entire duration of the project at the Construction Manager’s and/or governing agency’s direction. Contractor shall remove and properly dispose of all protection after site is stabilized with approvals of Local Authorities, Owner and Construction Manager. Contractor is to provide temporary signs as required by SEC Drawings.

3. This Contractor is responsible for dust control on-site until project completion. This is limited to dust control created by the 02A package and all site related activities (all vehicles and equipment maneuvering throughout the construction area). The 02A package is not responsible for controlling dust generated from within the building or building pad, or from cutting/mixing operations unless dust is created from a direct operation of the 02A contractor.

4. Contractor is responsible for all sheeting and shoring requirements to perform this scope of work. Contractor to coordinate final location with Construction Manager, 03A, 04A, and 05A contractors. Contractor is responsible to coordinate design loading of sheeting and shoring with live load operations adjacent to sheeting and shoring to allow all contractors to perform their work. Contractor to include temporary wire rope railings and angles at all locations for safety reasons. Contractor to include jersey barriers at areas of construction traffic roadways.

5. It is this contractor’s responsibility to provide, install and maintain driven six foot perimeter of the site

security fencing with flagging as well as fencing required throughout the site to separate the construction activities from the existing facility operations dictated by project phasing. Contractor shall provide and maintain wind/privacy screening mechanically fastened to all construction fence. Contractor to assume four (4) twenty foot (20’-0”) rolling gates at various entrance locations. Contractor shall add/remove/relocate fencing as required to maintain construction separation from occupied school areas. At completion of project, this contractor to remove from site all security fencing and gates and make repairs as necessary to restore to existing conditions.

6. Contractor understands that S&EC Measures, including ponds, traps, diversion dikes, swales, inlet

protection, silt fence, super silt fence, construction entrances, and the like may have to be removed, altered, repaired, and / or replaced in order for the permanent storm system, sewer system, water system, electrical system, and other work elements to be installed. It shall be this Contractor’s responsibility to remove, alter, repair and / or replace and consistently maintain any and all aspects of the S&EC measures for work to be installed. Contractor shall coordinate and prioritize its work as to eliminate impact to site access and / or the project schedule.

7. Contractor shall establish rough grade to within ± 1/10 sub-grade, to include proper compaction and

elevations for sidewalks, pavements, drives, curbs, landscape, and / or topsoil areas. Landscape, topsoil and other open areas (excluding ball fields and play areas) to be graded to within +/- 0.20’ of design elevation. Contractor shall furnish and install the backfill for curbs, gutters, and sidewalks to re-establish rough grade.

8. Contractor shall establish rough grade to within ± 1/10 sub-grade, to include proper compaction and

elevations for building pad for acceptance by 03A Contractor. Due to the limited access around the new building pad, portions of the building pad will be initially graded approximately 4-6” high (only at the direction of the CM) to protect building pad sub-grade from damage due to construction traffic. 02A contractor shall include multiple mobilizations for initial grading and final grading of the building pad in order to accommodate 03A/04A/05A contractor access throughout the building pad footprint.

9. Contractor shall furnish and install a complete storm water drainage/SWM system including, but not

limited to, all pipes, inlets, manholes, laterals, headwalls, endwalls, cleanouts, rip rap, geotextile fabric, observation wells, granite blocks, pipe anchors, gratings, bedding materials, foundations, cut off walls with rip rap outlets, under-drains throughout site including at play areas-retaining walls-artificial turf-etc, temporary fence at ponds, storm filters, storm traps, flow splitters, sand filters, underground

Page 48: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 7 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

quantity control facilities, trash racks, trench drains (including those adjacent to building), bio-retention areas and all related devices as required to provide a complete SWM system. Contractor shall flush the entire storm water drainage system at the direction of the Construction Manager and/or any governing agency, if required. Contractor shall provide all temporary SWM/Storm Drain work as indicated or implied by the contract documents and/or required by phasing, and shall remove all temporary work as required. All layout and surveying is the responsibility of this contractor. All as-builts of system must be performed by the Civil Engineer of Record during course of construction. Contractor to include costs of hiring Civil Engineer of Record to perform this service with base bid.

10. Contractor shall furnish and install complete sanitary sewer systems in accordance with local codes

consisting of all piping, manholes, laterals, cleanouts, and all related devices as required. All layout and surveying is the responsibility of this contractor. System flushing of this system shall be the responsibility of this contractor. Contractor is required to coordinate all required inspections for this work.

11. Contractor shall furnish and install a complete water system for potable water service and fire protection service outside the building in accordance with local codes consisting of all piping, manholes, laterals, valves, vaults, cleanouts, hydrants, standpipes and all related fittings as required. This particular utility will be brought into the building by this contractor. The 15A contractor will take responsibility from the first flange within the main building, the 15B contractor will take responsibility at the backflow preventer furnished and installed by the 15A contractor. Coordination of exact location required by the 15A contractor is the responsibility of this contractor. Fire hydrant flushing is the responsibility of this contractor. All layout and surveying is the responsibility of this contractor. Contractor is required to coordinate all required inspections for this work. Contractor includes all temporary water services as indicated by the contract documents for maintaining service to the existing building during construction, and shall remove temporary conditions as indicated or implied. Contractor includes providing one (1) temporary water service for construction area and one (1) temporary water service to CM Construction Trailer.

12. The Contactor shall furnish, install, and maintain a suitable temporary construction access road around the entire perimeter of the new building, as well as access from the Felker Ave entrance at the property line to the building access road. This work is in addition to the SCEs indicated on the contract documents. The Contractor shall remove the temporary road and perform all necessary re-grading and restoration upon receipt of direction from the Construction Manager. Roads shall be adequate to support all construction traffic and equipment. The roads at a minimum

shall be constructed of stabilizing cloth and 8” of adequately sized stone. The roads shall be a minimum of 30’ -0” wide and shall start ± 10’- 0” off of the face of the building. In the event that the stabilized access road is installed at, around, or near any existing or future utilities that may need to be removed, repaired, and / or installed, this Contractor shall remove, adjust, and / or repair sections of these stabilized areas as necessary at no additional cost to Owner or Construction Manager.

13. Contractor shall furnish, install, and maintain suitable construction staging areas at the south, west, and northeast parking areas adjacent to the new building. The combined size of these staging areas shall be 80,000 square feet of surface area. Staging areas shall be adequate to support construction traffic and equipment, and at a minimum constructed of stabilizing cloth and 8” of adequately sized stone. In the event that the stabilized staging area(s) are installed at, around or near any existing or future utilities that may need to be removed, repaired, and / or installed, this Contractor shall remove, adjust, and / or repair sections of these stabilized areas as necessary at no additional cost to Owner or Construction Manager. The Contractor shall remove the temporary staging areas, and perform all necessary re-grading and restoration upon receipt of direction from the Construction Manager

14. Limits of building pads shall extend a minimum of 15’ beyond the building footprint where applicable

around the entire perimeter of the building. Final grades shall be temporarily adjusted as necessary to meet this requirement. At the direction of the Construction Manager, the Contractor shall re-grade around the perimeter of the building to the final grades required by the Contract Documents inclusive of removal of temporary ring road(s) or staging areas. Contractor shall rough grade to required

Page 49: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 8 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

tolerances for slab on grade. Backfilling of all building walls, foundations, and slabs shall be the responsibility of this Contractor. Backfilling of all site wall, segmental retaining walls, site foundations, ands site slabs installed by this contractor shall be the responsibility of this Contractor.

15. Contractor will close or cover all sub-grade or utility excavation at the end of each work day unless

exempted by Construction Manager’s representative. Any unsuitable conditions caused as a result of contractor’s failure to protect trenches or exposed sub-grades will be remedied at contractor’s sole expense and at no cost to the Owner or Construction Manager.

16. Contractor is responsible for re-spread and / or removal of the centrally located spoil stockpile

generated by footings, walls, utilities, electrical excavations, plumbing excavations, geothermal excavations, etc provided there will be no design grade / elevation changes from the contract documents. Contractor is encouraged to perform own takeoff for this work as a full contract document set has been issued for use. Contractor is responsible for removal of any and all excess spoils from site that cannot be re-spread and stay within design parameters.

17. This Contractor shall provide for all site demolition shown or implied on the drawings that is outside

the footprint of the existing main OHHS building to include, but is not limited to, the complete demolition, removal, and disposal of all existing out buildings, existing curb & gutter, asphalt paving & sub-base, concrete paving & sub-base, concrete sidewalks, concrete walls, concrete foundations, underground utilities, fences, gates, rails, exterior athletic equipment, scoreboards, signs, plants, lights, parking bumpers, backstops, courts, decks, wood ramps, tanks, monitoring wells, posts, nets, post footings, field equipment footings, portable classroom footings, and the like. Contractor shall supply and install all plugs shown or required at all utilities that are removed. Contractor shall be responsible for protection, salvage, and relocating the tree(s) and plaque(s) as indicated.

18. The contractor shall with the assistance of the CM coordinate with all public utilities for the removal of the existing services. With approval of Utility Company(s) it is this contractor’s responsibility for the removal from site and or cutting, capping, filling and abandoning in place of all existing utilities.

19. Contractor shall be responsible for providing and maintaining wash racks with portable sediment

tanks/sump pits at all SCEs during construction. Contractor shall also be responsible for providing water and labor to operate the wash rack during the entire project until project completion or allowed removal of wash racks by LAHJ.

20. Contractor is only responsible for the flushing of the water line to achieve a passing test for

chlorination. This contractor is not responsible for a flow test if required by the Fire Marshal; this will be the 15B contractor’s responsibility.

21. This Contractor is responsible for keeping the streets clean of construction debris, mud, dirt etc only if

caused by this contractor’s failure to properly maintain the construction entrance, stoned roadways, access roads, wash rack, etc. Maintenance of roadway debris caused by other contractor’s general neglect to properly use the equipment and facilities provided by this contractor or Construction Manager will be the respective contractor’s debris to clean up and not the responsibility of this contractor.

22. Contractor is responsible for providing a written traffic control plan for CM, Owner, A/E and LAHJ approval for all work performed within the public right-of-way. The plan shall outline all necessary provisions to provide and maintain acceptable public safety and traffic control measures while right-of-way work is performed. This contractor shall be responsible for providing, maintaining, and removing (at completion of work) all said measures per the approved traffic control plan.

Page 50: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 9 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

Site Paving and Concrete Specific Scope: 1. Contractor shall clean off all utility covers, curbs, sidewalks, and any other installed items of asphalt

products in the paved areas. 2. Contractor shall provide all necessary permits, fees, and inspections that may be required.

3. Contractor includes all bonds for Right of Way Work. Contractor shall comply with all MDOT rules

and regulations for the work within Public Right of Way. 4. Contractor shall furnish and place stone fill as required to establish proper elevations. Contractor shall

protect all excavations until approved including protection from freezing and dewatering. 5. Contractor shall furnish and install all sub-base courses, asphalt base (binder) courses, tack coats,

overlay binder coats, overlay protective membranes, overlay protective membrane strips, asphalt surface courses, bitumastic sealant, and joint sealants.

6. During Phase 1 of the project, Contractor to provide temporary staff parking lot as indicated by the

contract documents. Temporary parking lot shall consist of a light duty paving section, and be provided with striping to accommodate 150 parking spaces. At the conclusion of Phase 3, Contractor shall demolish temporary parking lot and restore to permanent conditions as indicated by the contract documents.

7. Prior to commencement of Fall Semester 2011, Contractor shall remove approximately 800 square feet

of parking lot islands, and provide temporary light duty paving patchwork to accommodate relocated bus turning radius at the existing south parking lot.

8. Contractor shall patch and repair any damage to existing roads, adjacent surfaces, and curb and gutter

incurred during the 02A operations. In addition the 02A contractor should assume to repair/replace 5% of the total lf of curb and gutter, sf of sidewalks, and sy of asphalt pavement on the project due to damage caused by others. All work performed for this 5% is to be tracked via ticket and proper backup documentation must be provided to the Construction Manager. In the event 5% is not fully used at project completion, a deduct change order will be issued to the 02A contractor for the unused amount.

9. Construction Manager reserves the right to schedule the installation of the base course of asphalt

paving and then the surface course of asphalt paving as two separate construction events. Contractor shall be responsible for repairing damages, even if caused by others, to the base course asphalt as necessary prior to the installation of the final course asphalt.

10. Contractor shall prepare and provide for all means required to tie in new asphalt to existing asphalt at

all required locations, and to properly patch asphalt where existing curb has been removed. 11. Contractor shall provide patching of existing asphalt in existing roads and on-site driveways/parking

lots as needed for the connection of utilities. Contractor shall saw cut, remove, and dispose of existing asphalt for the water line and geothermal S/R piping. It will be the responsibility of this Contractor to furnish and install the permanent asphalt requirements at this location at the time and direction provided by the Construction Manager.

12. Contractor shall provide all fine grading and proof rolling as necessary prior to the installation of the

sub-base course. 13. Contractor shall provide layout, surveying to allow furnishing and installation of all concrete,

reinforcing, formwork, excavation, backfilling, fine grading, fill, gravel(including granular backfill

Page 51: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 10 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

where called out), weep holes, water stops, perforated PVC under drains at its work (including stone and filter fabric), bio-barriers (where called out), fence sleeves, waterproofing, support chairs, concrete pumping, control joints, expansion joints (zip cap type), expansion filler, weld wire mesh, scoring joints, hot/cold weather protection and the like for all of the following site concrete items:

a. curb and gutter, b. sidewalks (regular and heavy duty including all the way up to the face of

building / face of door and the like), c. turn down slab details with all associated stone, d. platforms / stoops, e. concrete paving and aprons, f. exterior reinforced concrete pad(s), including pads for generator and electrical

transformer, g. concrete work within courtyard, h. concrete paving/steps within mechanical yard area,

concrete for exterior bollards, i. retaining walls (masonry veneer, if applicable, by 04A contractor), j. exterior stairs, cheek walls, and landings, k. exterior ramps and handicapped ramps (including detectable warning surfaces), l. flagpole footings (flag pole and accessories also by 02A contractor), m. concrete for exterior athletic equipment and accessories, n. all concrete work associated stadium grandstands and exterior bleachers o. concrete for exterior furnishings such as benches, bike racks, trash cans, etc, p. concrete associated with tennis courts, q. concrete for track and field, and other athletic specialties, r. footings for scoreboards, s. concrete for fencing and ornamental fencing t. concrete edging for inside track perimeter, u. new school sign footing; masonry and sign by others, v. mow strip(s), including at building, w. concrete footings for exterior masonry piers, x. concrete for footings, planter walls, steps, and walks y. footings, walls, walkways, steps, ramps, and all other concrete for courtyards

within the building footprint, z. and any other site concrete item called out within the drawings and

specifications unless noted otherwise. 14. Concrete work that will be provided by the 03A Contractor (excluded from 02A scope) are as follows:

a. foundations and slabs for new OHHS main building structure, b. footings, walls, slabs and steps for loading dock, c. concrete foundations and slabs for all outbuilding structures, including

1. Concession Building (also referred to as field house) 2. Ticket Booth (also referred to as field house)

15. Concrete work that will be provided by the 16A Contractor (excluded from 02A scope) are as follows:

a. Concrete for site lighting and sports lighting bases, b. Concrete for new secondary electrical duct banks.

16. Contractor shall provide detectable warning pads at all handicapped ramps, crosswalks, depressed

curbs, and other locations as shown by the contract documents. 17. Contractor shall seal all concrete called out to be sealed per the contract documents. Contractor shall

provide one additional coat which will be applied just prior to substantial completion as directed by the Construction Manager.

Page 52: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 11 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

18. Contractor shall protect threaded and / or embedded items to prevent bending, deformation and corrosion. Contractor shall repair or restore all damaged threaded and / or embedded items prior to commencement of installation on these embedded items.

19. Contractor shall receive, unload, inventory, sign for and accept all embedded items furnished by other

Contractors for installation by this Contractor. Contractor shall properly store and protect items furnished by others.

20. Contractor shall coordinate with Mechanical and Electrical Contractors to ensure all rough-ins are

complete prior to concrete work associated to this scope. Contractor shall coordinate with the Construction Manager regarding scheduling of all concrete pours. Contractor shall submit each week to the Construction Manager, in writing, a two (2) week pour schedule for coordination with other trades.

21. Contractor to protect CMU walls and / or adjacent finishes from splashing caused by concrete

placement. If concrete splashes on CMU walls and / or adjacent finishes, then the Contractor shall be responsible for the removal of the splashed concrete.

22. Contractor shall provide as-built elevations shots of the slabs, platforms, ramps, loading areas, mechanical yards, the stage, and any other item installed by this Contactor. Contractor shall provide as-built elevations of all top of footing elevations. Contractor shall provide this as- built information within forty-eight (48) hours after concrete has been poured.

23. Contractor shall grade all backfill so that water runs away from any structure. 24. Contractor shall furnish and install all moisture retaining covers and curing compounds as required to

complete own work.

25. Contractor includes installation of zip cap expansion joint material, and all associated caulking of own work, inclusive of removing plastic cap and proper preparation prior to application of sealant.

26. Asphalt Binder Escalation: An adjustment will be made to the final Contract Sum if the price of

asphalt binder fluctuates from the prevailing price as quoted here to the actual price on the date of placement. The Contract Sum will be adjusted if asphalt binder fluctuation is above 10% or below negative 10%. Only the differential percent change beyond the above noted 10% will be used.

For the purpose of making these calculations, a monthly price index is maintained by the MD State Highway Administration. This index is the average FOB selling price of asphalt binder at the supplier’s terminal in the State of Maryland. Contract price adjustment will be computed monthly by using the following formula:

F= (PP-Pb)/Pb Where:

F = price increase/decrease of asphalt binder, expressed as a decimal PP = index price of asphalt binder per ton at placement date

Pb = the prevailing index price of asphalt binder per ton in January 2011, as specified by MDSHA.

Contract Price adjustment due to Contractor or Owner when price of asphalt binder does not increase or decrease significantly (i.e.: -0.10 >F>0.10) – Zero Dollars

Page 53: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 12 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

Contract price adjustment is due to Contractor as a cost to Owner when price of asphalt binder increases significantly (i.e. F>0.10) – A= [(F-0.10) x T x Pb] x Tons Contract price adjustment is due to Owner as a credit to Contractor when price of asphalt binder decreases significantly (i.e. F< -0.10) – A= [(F-0.10) x T x Pb] x Tons Where:

A = Addition / Deduction to Contract Sum F = price increase/decrease of asphalt binder, expressed as a decimal T = design target asphalt content as stated in the asphalt manufacturer’s mix design

for base or surface course expressed as a decimal Pb = the prevailing index price of asphalt binder per ton in January 2011 as

specified by MDSHA Tons = ACTUAL Tonnage of Hot Mix Asphalt Base or Surface (Base & Surface Mix

cost increase/decrease will be calculated separately using the design target asphalt contents for each per “T” above), as documented by certified, dated, weighted tickets furnished by the asphalt manufacturer.

Please note that the Contract Price Adjustment does NOT include Overhead & Profit markup, which will not be allowed or required on adjustments due the Contractor or Owner. The Contract Price Adjustment also does not include a state sales tax or bond markup, but these markups/markdowns will be allowed/required on both adjustments due the Contractor and Owner.

Synthetic Running Surface Scope: 1. Contractor to furnish and install synthetic running surface complete, including but not limited to

excavation and preparation of sub-grade, base layer, second and third layers of rubber granules, track surfacing and final line markings.

2. Installing contractor shall be certified by the approved manufacturer and shall only use workmen who are trained and experienced in the installation of the track surface.

3. Track surface shall have a force reduction in the range of 30%-50% inclusive, modified vertical

deformation 0.6mm to 1.8mm inclusive, and be resistant to scuffing and shedding of granules.

4. Contractor to provide a minimum of one year warranty covering materials and installation. Contractor shall repair or replace defective surface at no cost to Owner during the warranty period, as deemed by the Construction Manager.

5. Contractor acknowledges the bituminous concrete base shall cure for a minimum of 14 days prior to

the application of the running track surface. Track surface shall not be placed when ambient temperature is expected to fall below 50 degrees F. Base shall be maintained and protected by contractor during this period.

6. Contractor is responsible for protection of final product until accepted by Owner or Construction

Manager. Fencing Specific Scope: 1. Contractor shall furnish and install all site fencing related items to include, but is not limited to, posts,

rails, braces, bracing assemblies, galvanizing, powder coating, bottom tension wire, continuous top rails, continuous bottom rails, continuous mid rails, fabric, terminal posts, line posts, gate posts, hinge

Page 54: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 13 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

posts, terminal & gate post bracing assemblies, stretcher bars, sleeves, non-shrink grout, gates, hardware, accessories, tie wire, grounding, padlocks, knox boxes and/or knox locks, excavation for posts, concrete formwork/sonatubes, concrete for posts, fence line grading, and the like for a complete scope of work.

2. Contractor to review specifications to ensure all applicable pieces and parts are Polyester powder

coating equivalent to LifeCoat LCX by P&H Tube; color to be Black. Submit color for final approval by Architect.

3. Contractor shall furnish and install fence/gate assemblies throughout entire site, to include, but is not

limited to, the following locations: parking lots, bus loop, perimeter fencing, athletic fields, retaining walls, backstops, play areas, tennis courts, basketball courts, ball fields, dugouts (including vinyl coated steel wire fencing and gates within dugout structure), and all other locations throughout site.

4. Contractor shall furnish and provide layout for the sleeves needed for the fence posts located on top of concrete walls and segmented walls (if applicable).

5. Contractor to include all mow strips at own work.

6. Contractor to include one lock with two keys for each gate; locks to be “Steel Secrete Service” per

specifications.

7. Contractor to provide warranty for ten years for all coated fencing against peeling, cracking and corrosion.

Retaining Wall Specific Scope: 1. Contractor shall furnish and install all site retaining walls including Cast in Place Concrete, modular

concrete and segmented block. Contractor to include excavation, compaction, drainage, damp-proofing systems, waterproofing systems, drainage systems, connections to storm systems where applicable, sheeting/shoring, accessories, adhesives, backfill, final grading etc. for a complete system. Contractor responsible to coordinate rail installation as well. Contractor includes multiple mobilizations as required to meet the CPM schedule. Contractor acknowledges all rails at top of retaining walls are to be located within the top cap of the retaining wall.

2. Contractor includes professional design engineer for designing of all segmental block retaining walls,

and associated railings within retaining walls. Design shall be coordinated with all other site work impeding tie-back/support systems.

Site Amenities Specific Scope: 1. Contractor shall furnish and install all site amenities, to include but limited to trash receptacles,

benches, benches at ball field, benches for softball field, flag poles, and bike racks etc. Contractor shall provide all core drilling, anchoring materials, and the like to complete the installation of the items. Contractor to coordinate installation of foundations required for these items with the Site Concrete Contractor.

2. All furnishings are to be installed level, plumb and true and securely anchored or positioned at

locations as indicated on drawings.

3. Contractor shall furnish and install all steel bollards throughout site as indicated by the contract documents. Comply with DIV 5 requirements for steel material. Installation includes all excavation, concrete, sleeving, sealants, etc for a complete installation.

Page 55: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 14 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

4. Contractor shall furnish and install all exterior steel railings as indicated by the contract documents,

including railings at exterior stairs, ramps, retaining walls, and all other areas throughout the site and building exterior. Contractor shall comply with DIV 5 requirements for steel material, and shall be powder coated as indicated by the contract documents. Installation includes all excavation, sleeving, sealants, etc for a complete installation.

Site Athletic Equipment: 1. Contractor to furnish and install all exterior athletic equipment including but not limited to baseball

and softball field equipment complete, soccer and football goals complete, tennis court equipment complete, exterior scoreboards complete (inclusive of foundations and galvanized steel supports; electrical by others), track & field equipment complete, discus throwing ring, shot put throwing ring, shot put toe board, triple and long jump take off systems, edging, fasteners etc.

2. Contractor to include salvaging and re-installation of baseball field scoreboard, and football clock.

3. The 6A Contractor to furnish and install all interior gymnasium equipment at main and secondary gymnasium including but not limited to basketball equipment, volleyball equipment, badminton equipment, divider curtains, safety pads, interior scoreboards, batting cages and netting, mat movers, etc.

4. All foundations for exterior gymnasium equipment including pole vaulting equipment, exterior football scoreboard, exterior baseball and competition softball scoreboards, exterior soccer goals, football goals, baseball and softball foul poles are being furnished and installed by this Contractor, unless attachment is to structure being furnished by others.

5. Contractor includes all excavation, backfill and concrete for all equipment being provided by this scope.

6. Contractor includes coordination with other contractors for placement of all sleeves, inserts, anchors

etc for items furnished and installed under this scope of work.

7. Electrical feeds and connections for equipment is by others, Contractor is responsible for coordination of MEP requirements.

8. Contractor includes all track and field event surfacing systems inclusive of stone, underdrains, asphalt

base, resilient running track base mat / structural spray surfacing system for the track and the associated field event runways.

9. Contractor includes all line markings as approved by the Architect, in accordance with track and field standards.

Artificial Turf Specific Scope: (Alternate) 1. Contractor shall furnish and install the artificial turf system complete including but not limited to,

subgrade compaction, stone/under drain system and edge detailing, and finish carpet surface.

2. Contractor shall have minimum experience of five completed field installations of soccer or football fields of 65,000 sf or more. Contractor to provide specifics on installations including the exact name of the product used, client contact names, addresses, telephone numbers and age of installations.

Page 56: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 15 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

3. Contractor shall provide an experienced project supervisor, who possesses a minimum of five (5) years experience supervising projects of similar scope, size and complexity.

Tennis Court Surfacing and Nets Scope: 1. Contractor to furnish and install tennis courts as indicated on drawings in number, size and locations as

shown. Contractor includes preparation of base pavement, footings, game lines, net posts, and nets.

2. Court surface shall be uniform in texture and color, in accordance with grades, cross sections and pitch as designed, and free of all depressions and ridges.

3. Installing contractor must be certified by the approved manufacturer, and shall only use workmen who

are trained and experienced in the installation of the court surface.

4. Contractor will not store surfacing or color material in direct sunlight. Contractor shall prevent materials from freezing.

5. Contractor includes court surfacing, tennis net posts and sleeves, tennis net tie downs, tennis nets,

fencing inclusive of windscreens, game lines, court surface base, concrete foundations, tennis backboards etc.

Landscaping Specific Scope: 1. Contractor shall strip, screen, stockpile, protect, test, amend and stabilize all topsoil as required by the

contract documents and governing jurisdiction having authority requirements. Contractor shall re-spread topsoil in all areas provided the topsoil meets project standards as indicated on drawings. Topsoil on ball fields shall be motor graded to within plus/minus 1/10 of a foot of the design elevation. Maximum size of screen shall be ¾” sieve. Topsoil shall be a 4-8 inch layer (or as specified), lightly compacted to minimum thickness of 4 inches (or as specified). Contractor shall supply tested, screened, amended topsoil from off-site if and / or when the onsite quantities are insufficient. Contractor to test and make all amendments to bring material within project specifications. It is the contractor’s responsibility to submit test results to Construction Manager for approval with required recommendations to bring material within project specifications, prior to the start of any topsoil work. This requires the Contractor to hire a third party independent testing agency.

2. Contractor shall layout all landscaping with flagging, and shall receive approval from the landscape

architect, architect and PGCPS prior to installation. Contractor shall provide and install all landscape plantings to include, but is not limited to, all guarantees, certificates, submittals, plants, trees, shrubs, topsoil amendments, sand (if required), organic matter, planting soil mix, anti-desiccant, tree paint, herbicide, fertilizer, stakes for supporting trees, wires for guying trees, mulch, and the like to complete all landscape plantings shown or implied within the drawings and specifications. Contractor shall furnish water and necessary temporary or permanent irrigation equipment per the specifications.

3. Contractor shall provide and install all seeding and sod to include, but is not limited to, guarantees,

certificates, submittals, delivery, storage, topsoil testing and amendments, sand (if required), organic matter, seed mixtures, sod types, mulch, hydraulic seeding, sod stakes, water, protection, restoration, cleaning, maintenance, turf inspections / reviews by a qualified turf agronomist, and the like to complete all seeding and sod shown or implied within the drawings and specifications. Contractor shall furnish water and necessary temporary or permanent irrigation equipment per the specifications.

4. Contractor shall provide and install all forest conservation requirements to include, but is not limited

to, all arborist reports, root pruning, tree protection signs, deep-root fertilization, crown reduction, watering, vertical mulching, and all other items outlined within the Forest Conservation Drawings and as required by the County Forester.

Page 57: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 16 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

5. Contractor shall provide and install all maintenance requirements to include, but is not limited to,

maintaining all plants and turf in a healthy condition. Contractor shall provide for all pruning, cutting, watering, fertilizing, cultivating, weeding, mulching, tightening / repairing of staking, setting plants to proper grades or upright in position, restoration of the planting saucer, and furnishing / applying sprays and other items as necessary to keep the plantings free of insects and disease and in a thriving condition. Maintenance shall begin immediately after each planting is completed and shall continue for a period of twelve (12) months following project substantial completion. Contractor shall furnish own water and irrigation equipment and irrigate areas as required throughout this period.

6. Contractor includes independent third party testing of all topsoil material and associated

recommendations and amendments to bring material to within project specifications. Contractor to submit all tests and recommendations prior to the start of topsoil work for approval.

7. Contractor includes all mulching, pretreatment of mulched areas, inclusive of mulch walkways,

maintence of mulching etc.

8. Contractor includes all portable drip irrigation bags as required.

9. Contractor includes monthly turf inspections by a qualified turf agronomist for a period of one (1) years following project substantial completion.

10. Contractor shall provide skinned infield mix as indicated by the contract documents.

11. Contractor shall provide all blue stone dust for warning track, BB/SB field dugouts, and all other areas as indicated.

Road and Parking Accessories Specific Scope:

1. Contractor shall adhere to all Maryland Department of Transportation State Highway Administration’s

current Standard Specifications for Construction Materials and the ANSI D6.1-1971 Manual on Uniform Traffic Control Devices for Streets and Highways.

2. Contractor shall adhere to the product delivery, storage, handling, project conditions,

products/materials, surface preparation, application, protection, and restoration requirements outlined within the project specifications and drawings.

3. Contractor shall coordinate and work with the Construction Manager with regard to the Fire Marshal’s

requirements.

4. Contractor shall adhere to the sign location and installation requirements outlined within the project specifications and drawings.

5. Contractor shall layout and paint all parking lot striping to include, but is not limited to all parking

spaces, regular handicapped spaces, van accessible spaces, para-hatch areas at handicapped spaces, bus spaces, traffic arrows, center lines, stop bars, and pedestrian crosswalks and other stenciled markings. This includes striping/markings for all temporary parking spaces and walkways.

6. Contractor shall furnish and install all concrete wheel stops and fire lane curbing paint and associated

stenciling. Wheel stops are to be provided at all parking spaces that do not terminate at new concrete curb (temporary parking lot excluded).

7. Contractor shall furnish and install all posts and signs for site including but not limited to handicapped signs, van handicapped signs, drug free school zone signs, do not enter signs, student drop off signs,

Page 58: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 17 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

fire lane signs, no parking anytime signs, buses only signs, staff parking signs, one way signs, no U-turn signs, reserved only signs, etc.

Grandstands Specific Scope: 1. Contractor to design, fabricate, furnish and install all grandstands/bleachers in conformance with

required structural performance inclusive of excavations, form, pouring and backfilling of foundations, form and pouring slabs and sidewalks.

2. Contractor to include field measurements of actual finished grade prior to the start of fabrication.

3. Contractor to include complete grandstand system including but not limited to, structural steel shapes, uncoated and galvanized steel sheets, steel tubing, aluminum extrusions cast or extruded aluminum end caps, fasteners, aluminum seat and foot boards, decking system, aluminum riser boards, steps, ramps, guard rails, hardware and accessories, and foundations and any other incidental work for a complete and operational installation.

4. Contractor to include complete press box inclusive of structure, flooring, wall structure, exterior finish,

roof structure, doors, windows, countertops, painting, caulking, electrical, observation deck and special warranty and any other incidental work for a complete and operational installation.

5. Contractor to include all relevant coordination with other trades as site lay down area will be extremely

limited at time of install. Geothermal Well Field Specific Scope: 1. Contractor is responsible for all work associated with the geothermal field, including but not limited to

wells, well casings, vertical and horizontal distribution and return piping, fittings, flanges, valves, etc. up to the building (turned up and capped above slab within the new building per detail 1/M905), site vaults, manifolds within vaults, anti-bouyancy devices, grout, stone, fill, insulation, utility warning tape, and all other work indicated or implied by the contract documents for a complete geothermal well system.

2. Contractor shall coordinate with 03A Concrete Contractor for work extending into the building foundation / through slab. Contractor shall provide all sleeves/waterstops for penetrations, and layout drawing for embedded work within concrete foundations/slabs. It is the Geothermal Contractor's responsibility to coordinate and check this work directly with the Concrete contractor.

3. Permanent HVAC equipment will be utilized for temporary climate control as directed by the CPM

Schedule. The permanent equipment shall remain in operation following start-ups, as directed by the Construction Manager. The Contractor shall perform regular maintenance on all equipment as necessary to maintain equipment in “like new” condition. Any costs associated with an extended warranty due to early start up are to be included in the base bid.

4. Contractor will be responsible for all Sediment Erosion Control (SEC) measures, excavation, grading,

backfill and any other item associated with exterior work provided under this package. Contractor will dispose offsite excavation/drilling spoils. Contractor will dewater excavations as necessary to maintain progress for work in this package. Upon completion of work contractor will restore all limits of disturbance of this package to original grade prior to start of work.

5. Drawings are shown diagrammatically and are not intended to show every fitting, valve, offset etc.

Contractor is to provide equipment, piping, and devices necessary to make a complete and operating system.

Page 59: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 02A - Sitework Page 18 of 18 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

6. Contractor shall provide layout drawing of all geothermal well field work, coordinated with existing

and new utilities. Contractor shall account for proper clearances between geothermal wells and well piping with other utilities such as water, sewer, storm, and underground electric lines.

7. Contractor to include all fire saffing and or fire caulking of all own penetrations regardless of timing

with installation of walls, floors, and slabs installed by others. SPECIAL CONSIDERATIONS: 1. UNCLASSIFIED TO DESIGN SUB-GRADE: Excavation and/or drilling work under this

contract is unclassified to design sub-grade, and includes but not limited to, excavation and removal of soil, shale, rock, fill, abandoned utilities, abandoned tanks, abandoned wells, abandoned structures, and any and all other subsurface conditions encountered in the contract area to this trades lowest design elevation in same area. The Contractor shall make his own soil and subsurface investigations, examination, tests, and exploratory borings of existing subsurface conditions to determine the nature of the soil conditions underlying the project site and thereby assuming all responsibility in excavating for this project without recourse to subsurface information obtained from the engineer, or indirectly from the Owner. The risk of unanticipated soil conditions from current elevations to this trades lowest design elevation in same area is solely the Contractor’s. No extra or additional compensation or use of unsuitable soils allowance for excavation or claim otherwise will be made or paid under this contract until added excavations below this trades lowest design elevation in same area is required. Contractor is responsible for furnishing and placing any import fill material that may be required to complete the work.

2. UNSUITABLE SOILS ALLOWANCE: Contractor shall carry an allowance of 40,000 cubic yards within the base bid amount to address unclassified, unsuitable soils below lowest designed sub-grade elevation. The allowance represents the quantity of material anticipated to be excavated, removed, and replaced with imported structural fill suitable for the building pad, including placement and compaction in accordance with specification requirements. Contractor shall provide a cubic yard unit price with the bid (see bid form). Actual compensation for replacement of unsuitable soils (below lowest designed sub-grade elevations) through use of the allowance will be based on actual quantities verified in the field by the Construction Manager. If the actual work performed is less than 40,000 cubic yards, the unused allowance quantity multiplied by the unit price will determine the credit amount due by the Contractor. If the actual work performed is more than 40,000 cubic yards, the additional compensation due (via change order) to the Contractor will be determined by the additional quantity of cubic yards multiplied by the unit price, with no additional mark-ups allowed.

END OF SCOPE 02A

Page 60: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 03A – Concrete Page 1 of 4 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

WORK SCOPE CATEGORY 03A CONCRETE The work of this bid category includes but is not limited to providing all labor, equipment, materials, scaffolding, hoisting and incidentals to complete all Concrete work in accordance with the specifications, drawings and applicable codes. All work is to be performed as shown on the plans and / or specified under the following technical sections: SECTION All of Division 0

NAME

03300 Cast-in-Place Concrete 03360 Polished Concrete Floor Finishes 05810 Expansion Joint Cover Assemblies (as it relates to this scope)

(as it relates to this scope)

07135 Self-Adhering Sheet Waterproofing (as it relates to this scope) 07210 Building Insulation (as it relates to this scope) 07920 Joint Sealants (as it relates to this scope) ALL OTHER SPECIFICATION SECTIONS - FOR COORDINATION PURPOSES Geotechnical Report issued by GROTECH Engineers for informational purposes. In addition to the above, trade contractors are to include, but are not limited to, AIA Documents and various other Technical Specifications interfacing with this work. The Contractors are required to review the work descriptions of the other categories so as to not misunderstand the scope responsibilities. The Contractors are also bound to the HESS Safety Manual and the HESS Trade Contractors Procedures Manual for Oxon Hill High School Modernization for the administration of the contract.

Contractor is responsible for General Scope of Work listed elsewhere in this specification section. General Scope:

THE SPECIFIC SCOPE OF WORK IS TO INCLUDE

, but is not limited to, the following items:

Concrete Specific Scope:

1. All cast-in-place concrete associated with the main building, team room additions, loading dock, concessions / ticket booths (also referred to as field house) structures are part of this contract package, unless otherwise noted within this scope.

2. Site concrete outside the building and outbuilding perimeters will be performed by the 02A contractor, and is not part of this contract package, unless otherwise noted within this scope.

3. Contractor to include excavation, concrete, rebar, and labor to pour temporary foundation for mockup

panel(s).

4. Contractor shall seal and or apply hardener for all concrete called out to be sealed and or hardened per the contract documents. Contractor shall provide one additional coat and cleaning of surface prior to application, which will be applied just prior to substantial completion as directed by the Construction Manager.

5. Contractor shall furnish and install all concrete on metal floor and roof decks as required by the

Contract Documents, including all temporary shoring and bracing required to support the load imposed by the Contractor’s work and to prevent excess deflection of the structure. Contractor shall form all openings through decks and slabs as shown on the drawings and as required by others. Contractor shall grout all base plates. Contractor shall provide its own layout for any of its openings being formed.

Page 61: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 03A – Concrete Page 2 of 4 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

6. Contractor shall furnish and install all perimeter rigid insulation under slab on grade and at inside face of foundation walls.

7. Contractor shall include second tier professional surveying services for anchor bolt layout and

verification after bolts are set. The as-built survey of anchor bolts to be completed and submitted to Construction Manager four (4) weeks prior to the start of steel, to allow ample time for corrections.

8. Contractor shall coordinate, layout and protect threaded embedded items to prevent bending,

deformation and corrosion. Contractor shall repair or restore all damaged threaded embed items prior to commencement of steel erection.

9. Contractor shall furnish and install all locker bases, including embedded treated wood sleepers. 10. Contractor shall receive, unload, inventory, sign for and accept all embedded items furnished by other

Contractors for installation by this Contractor. Contractor shall properly store and protect items furnished by others.

11. Contractor shall install only all anchor bolts, base plates, leveling plates, bearing plates, inserts,

sleeves, clips, and reglets required by the Contract Documents. Contractor to include grouting of base plates.

12. Contractor shall coordinate with Mechanical and Electrical Contractors to ensure all rough-ins are

complete prior to slab, deck, and wall pours. Contractor shall coordinate with the Construction Manager regarding scheduling of all concrete pours. Contractor shall submit each week to the Construction Manager, in writing, a two (2) week pour schedule for coordination with other trades.

13. Contractor shall be responsible for all excavation and backfill work required for the installation of

concrete foundations, walls, and slabs. Contractor shall provide all pumping, dewatering, temporary bracing and shoring for its concrete work and temporary protection necessary to complete its work, and as required by the Contract Documents. Contractor shall maintain foundations free of water, mud, and the like until masonry operations have commenced, at which time it becomes the mason’s responsibility until backfill operations commence in each area. Contractor shall be responsible for backfilling to sub-grade and compacting of interior and exterior foundations, slabs, and walls. Contractor shall be responsible for all fine grading required to perform all its work. The Contractor shall dispose of his excavation and / or grading spoils in a central location as directed by Construction Manager.

14. Contractor includes all reinforcing bar, wire, chairs, etc for this work. 15. Contractor shall slope slabs to floor drains as required. 16. Contractor shall furnish and install all concrete, reinforcing, formwork, excavation, backfilling, fine

grading, fill, gravel (including granular backfill where called out), weep holes, water stops, sleeves, support chairs, concrete pumping, hot / cold weather protection and the like for all of the following:

a) footings / foundations, b) slabs-on-grade, c) elevated slabs / slabs-on-metal deck, d) interior walls, e) piers, f) CIP Concrete portals/lintels g) grade beams, h) slab haunches, i) housekeeping / equipment pads,

Page 62: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 03A – Concrete Page 3 of 4 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

j) pits, k) elevator pits, l) orchestra pits, m) interior stairs/ramps, n) platforms and or stage, o) loading dock (including stairs), p) concrete retaining walls (building related), q) outbuildings r) trash room, s) exterior stairs adjacent to building structure t) recycle room, u) slab depressions, note some depressions will be only if alternates are

accepted,, v) and any other building concrete item called out within the drawings and

specifications. 17. Contractor shall furnish and install the fine grading, gravel, vapor barrier and retarders, expansion

joints, control joints, including all required scoring patterns. 18. Contractor shall also furnish and install all concrete and reinforcing steel for all pipe penetrations that

penetrate its work per structural details. Contractor acknowledges steel sleeves for pipe penetrations through floor slabs are to extend above finish floor elevation a minimum of two inches, and includes all costs associated with properly hand finishing around said sleeves.

19. Contractor to protect CMU walls and / or adjacent finishes from splashing caused by concrete

placement. If concrete splashes on CMU walls and / or adjacent finishes, then the Contractor shall be responsible for the removal of the splashed concrete.

20. Contractor shall provide as-built elevations shots of the slabs, platforms, ramps, and any other item

installed by this Contactor. Contractor shall provide as-built elevations of all top of footing elevations. Contractor shall provide this as- built information within forty-eight (48) hours after concrete has been poured.

21. Contractor shall provide all hoisting required for its work. 22. Contractor shall supply and install all concrete and reinforcing mesh at all metal pan stairs and metal

stair landings. Contractor to remove all over-pour on underside of stairs to allow for painting. Include wash down of cleaning or protecting agents to allow painting operation to begin.

23. Contractor shall complete the installation of all anchor bolts and leveling plates promptly upon

completion of supporting foundations in each building area. 24. Contractor shall provide for all floor slabs to be level and ready to receive specified floor finish.

Contractor shall coordinate with finish schedule to achieve this. 25. Contractor shall grade all backfill so that water runs away from any structure. 26. Contractor shall furnish and install all necessary formwork, construction joints, diamond joints, control

joints, isolation joints, expansion joints, waterproof seals, welded wire fabric, removable plastic or hardboard pre-formed strips, roofing felts, and vapor barriers. Contractor to carefully layout construction joints and control joints with finish schedule to allow for patterns to match architectural layout. Contractor shall coordinate with the 09A Contractor for proper locations and width of block-outs for floor expansion joints, and will be responsible to patch concrete slabs following installation of expansion joints (expansion joints will be set by 09A Contractor).

Page 63: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 03A – Concrete Page 4 of 4 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

27. Contractor shall furnish and install all moisture retaining covers and curing compounds as required to

complete its work. 28. Contractor shall rub and finish all exposed concrete walls installed by this contractor. 29. Contractor shall provide for all excavation and backfill of own work. 30. Contractor to coordinate building retaining/foundation walls with earthwork contractor. This

contractor is responsible for proper backfilling of building retaining/foundation walls. 31. Contractor shall install all pipe bollards supplied by others. Contractor to include concrete in pipe

bollards. Contractor to include multiple mobilizations for this scope of work. 32. Contractor includes installation and maintenance of fall protection at slab block outs and diamonds.

Contractor to coordinate with masonry and steel contractor for removal of protection to allow for installation of their work.

33. Contractor includes below grade waterproofing of all below grade walls such as elevator pits, orchestra

pits, etc.

34. Contractor includes all damp-proofing applied to concrete surfaces provided by this contractor.

35. Contractor includes caulking of own work, inclusive of plastic “zip cap” type expansion material for clean sealant joint.

36. Contractor includes providing fluid applied vapor permeable air barrier membrane at all concrete-to-concrete joints as specified. Concrete-to-Masonry and other dissimilar materials shall be installed by other respective trades.

SPECIAL CONSIDERATIONS:

1. The Construction Manger has assumed slab on grade will be placed in no more than twenty (20) pours. In the event Contractor requires more than twenty (20) pours, Contractor to arrange with Construction Manager’s Testing Agency for performance of floor levelness and floor flatness testing for all pours past pour twenty. All costs for this additional testing are the responsibility of this Contractor. Failure to properly coordinate the additional testing will result in the Construction Manager performing this service at the Contractor’s expense.

Added by Addenda #3

1. 3A contractor is responsible for installation of the polished concrete and polished concrete decorative floor finish in lieu of vct, identified in alternate #7. The filled-and-polished ground face units for base will be provided and installed by the 4A contractor.

END OF SCOPE 03A

Page 64: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 04A Masonry Page 1 of 4 15 June 2011 Revised per Addendum #1 dated 13 July 2011 Revised per ADD#3 26 July 2011 3

00800

WORK SCOPE CATEGORY 04A - Masonry The work of this bid category includes but is not limited to providing all labor, equipment, materials, scaffolding, hoisting and incidentals to complete all Masonry work in accordance with the specifications, drawings and applicable codes. All work is to be performed as shown on the plans and / or specified under the following technical sections: SECTION Division 0

NAME

Division 1 02300 Earthwork (as it relates to this scope) 04200 Unit Masonry 05810 Expansion Joint Cover Assemblies (as it relates to this scope) 07135 Self-Adhering Sheet Waterproofing (as it relates to this scope) 07272 Fluid-Applied Membrane Air Barriers 07841 Through-Penetration Firestop Systems ALL OTHER SPECIFICATION SECTIONS – FOR COORDINATION PURPOSES Geotechnical Report issued by GEOTECH Engineers, Inc. for informational purposes. In addition to the above, trade contractors are to include, but are not limited to, AIA Documents A201 and A401, and various other Technical Specifications interfacing with this work. The Contractors are required to review the work descriptions of the other categories so as to not misunderstand the scope responsibilities. The Contractors are also bound to the HESS Safety Manual and the HESS Trade Contractors Procedures Manual for Oxon Hill High School Replacement for the administration of the contract.

Contractor is responsible for General Scope of Work listed elsewhere in this specification section. General Scope:

THE SPECIFIC SCOPE OF WORK IS TO INCLUDE

, but is not limited to, the following items:

Masonry Specific Scope: 1. Contractor includes full mockup panel for craftsmanship for Architect / Owner review and approval.

Once approved, the mockup will be the standard for installation.

2. Contractor shall furnish and install all masonry work required by the Contract Documents, including, but not limited to, all brick, block, architectural pre-cast concrete (plant cast), mortar, grout, masonry fill, parging, mortar washes, masonry reinforcement (vertical and horizontal), masonry and cast stone steel reinforcement bars, joint reinforcement, masonry lintels, ties and masonry anchors, point up, insulation (compressible, rigid, perlite, and the like for sound ratings) contiguous to this Contractor’s work, masonry fire walls, masonry portal frame columns, column isolation, isolation strips, building paper, flashing, pre-molded control joints, weeps, flashings, mortar netting, samples, mock-ups, masonry cleaners, sealers, and damproofing and/or

waterproofing, spray applied vapor barrier, head of wall fireproofing, elevated slab edge to masonry wall fireproofing, and or smoke barriers, interior and exterior control joint caulking, final cleaning and washdown inclusive of louver , window, curtainwall, storefront frame and glass protection and all other items required for a complete Masonry scope of work.

Page 65: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 04A Masonry Page 2 of 4 15 June 2011 Revised per Addendum #1 dated 13 July 2011 Revised per ADD#3 26 July 2011 3

00800

3. Contractor shall install only all loose angle lintels, beam lintels, anchor bolts (embedded in masonry), and the like that are supplied by others. Contractor to include installation of elevator hoist beam. Contractor shall grout all bearing / leveling plates at all CMU walls.

4. Contractor shall coordinate the install of all hollow metal frames located within masonry walls

furnished and set by the 09A contractor. This contractor shall ensure hollow metal frames remain installed plumb, level, square, and true to line until the frame is completely enclosed in masonry and accepted by the Construction Manager. Contractor shall be responsible for any repair or damage costs to the hollow metal frames.

5. Contractor to include grouting of hollow metal frames. 6. Contractor shall furnish and install all build in place expansion joints (rated, non-rated, expand-o flash

joint covers, and the like) and accessories located at and within masonry walls. 7. Contractor includes furnish and install all Knox boxes located within masonry walls. Contractor to

coordinate with local fire dept for approval and installation. 8. Contractor shall be responsible for installation of all openings within masonry walls where required by

other trades. 9. Any wall penetration required by other trades which has a diameter or horizontal dimension greater

than 12” shall require a lintel be installed. All indicated steel lintels will be furnished by others. In the event a lintel is not called to be steel, it is assumed to be a masonry lintel, furnished and installed by this contractor.

10. In the event an opening is required in a masonry wall and is not properly coordinated between the other

trades and the 04A contractor, via a field use drawing, it is the other trades sole responsibility to implement the required fix. All costs to either saw-cut, or tooth cmu to allow for the opening is the responsibility of the other trades. In the event this contractor has missed the indicated opening, or has miss-sized the opening, the costs required for the fix is the responsibility of this contractor.

11. Contractor shall furnish and install all grouting where required for hollow metal frames, bearing plates,

sills, bond beams, wall reinforcing, and other areas that are required. 12. Contractor shall fill all openings, including top of wall conditions, at full height masonry walls and

provide all fire-safing and / or and/or fire stopping, and / or insulation as required, inclusive of elevated slab edge conditions short of masonry walls.

13. Contractor shall provide several mixing stations and / or staging areas as needed for the phasing of the

project. Contractor includes relocation(s) of mixing station(s) and staging areas as required for construction sequencing / logistics per the direction of the Construction Manager.

14. Contractor will furnish and install all temporary walls bracing of masonry walls inclusive of braces and

footings in accordance with MOSH standards and/or good practice. All masonry walls are to be braced at all times until steel joists and deck are set in place and inspected. Contractor to coordinate bracing with concrete contractor pour schedule. Contractor to provide engineered wall bracing drawings and calculations for record and coordination purposes.

15. Contractor shall perform all dewatering and mucking out as required to perform its work, including

cleaning of footings.

Page 66: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 04A Masonry Page 3 of 4 15 June 2011 Revised per Addendum #1 dated 13 July 2011 Revised per ADD#3 26 July 2011 3

00800

16. Contractor shall coordinate with other trades to allow them to properly set items to be embedded in masonry.

17. Contractor shall scrape and wash-down all walls and floors of excess materials generated by it work. 18. Contractor shall furnish and install all waterproofing, dampproofing, and air barrier

that is applied to its work.

19. Contractor includes the installation of 500 LF steel lintels, angles, and / or plates that may not be shown on the drawings, but may be required during construction.

20. Contractor shall layout all CMU foundations and walls, elevations, and the like to complete its scope

of work. Brick points will be provided by the Construction Manager at no more than 25’ intervals.

21. Contractor shall point up around all mechanical openings, electrical openings, sleeves, and the like located in masonry walls.

22. Contractor shall protect and maintain all architectural pre-cast concrete protection. 23. Contractor includes daily covering of head of wall conditions to prevent infiltration. This includes

areas which receive precast caps are set and not yet caulked due to weather conditions.

24. Contractor includes complete additional washdown prior to substantial completion to eliminate any efflorescence at no cost to the owner.

25. Contractor to include all temporary heating measures to perform all of own work.

26. Contractor to furnish and install all Architectural Precast Concrete. Contractor includes engineered

shop drawings and calculations for all APC. Contractor includes all inserts, attachment and anchorage devices / hardware, clips, angles, welding, and caulking for a complete installation of APC.

27. Contractor to coordinate with 09A, 15A, 15B, and 16A contractor for installation of access doors

furnished and installed by other contractors. This contractor to include cutting of all masonry to allow for installation of access doors by the 09A Contractor.

28. Contractor to furnish and install all exterior rigid insulation on masonry backup walls, including but

limited to behind, brick, precast, cast stone, finish block, and metal panel areas. Contractor to coordinate with exterior framing being provided by 09A contractor.

Added by Addenda 1:

1. This contractor is responsible for the masonry work identified on G-002. The 9A contractor is responsible for the demolition shown on G-002.

Added by Addenda 3

1. Removed air barrier responsibility. Line item 18, above, strike air barrier reference. 2. 4A Contractor is responsible to provide and install the filled-and-polished ground face units at

base where indicated at walls as identified in Alternate #7.

Page 67: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 04A Masonry Page 4 of 4 15 June 2011 Revised per Addendum #1 dated 13 July 2011 Revised per ADD#3 26 July 2011 3

00800

END OF SCOPE 04A

Page 68: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09A Drywall, Carpentry, & Painting 15 June 2011 Page 1 of 5 Revised per ADD#3 26 July 2011 3

00800

WORK SCOPE CATEGORY 09A – Rough Carpentry, Doors, Frames, Hardware, Drywall, Ceilings, and Painting

The work of this bid category includes but is not limited to providing all labor, equipment, materials, scaffolding, hoisting and incidentals to complete all Rough Carpentry, Frames, Doors, Hardware, Drywall and ACT, Impact Resistive Material, and Painting work in accordance with the specifications, drawings and applicable codes. All work is to be performed as shown on the plans and / or specified under the following technical sections: SECTION Division 0

NAME

Division 1 05400 Cold–Formed Metal Framing 05500 Metal Fabrications (for coordination purposes) 05810 Expansion Joint Cover Assemblies 06100 Rough Carpentry 07210 Building Insulation (as it relates to this scope) 07272 Fluid-Applied Membrane Air Barriers (Added by Addenda #3) 07841 Through-Pentration Firestop Systems (for coordination purposes)

07901 Joint Sealants (as it relates to this scope) 08114 Steel Doors and Frames 08211 Flush Wood Doors 08255 FRP Flush Doors 08305 Access Doors (as it relates to this scope) 08710 Finish Hardware 09255 Gypsum Board Assemblies 09265 Gypsum Board Shaft Wall Assemblies 09500 Wood Fiber Acoustical Panels 09511 Acoustical Panel Ceilings 09800 Special Coatings 09841 Specialty Acoustical Wall Panels 09900 Painting Division 6 Specialties (for coordination purposes) Division 15 Mechanical (for coordination purposes) Division 16 Electrical (for coordination purposes) ALL OTHER SPECIFICATION SECTIONS – FOR COORDINATION PURPOSES Geotechnical Report issued by GEOTECH Engineers, Inc. for informational purposes. In addition to the above, trade contractors are to include, but are not limited to, AIA Documents A201 and A401, and various other Technical Specifications interfacing with this work. The Contractors are required to review the work descriptions of the other categories so as to not misunderstand the scope responsibilities. The Contractors are also bound to the HESS Safety Manual and the HESS Trade Contractors Procedures Manual for Oxon Hill High School Replacement for the administration of the contract.

Contractor is responsible for General Scope of Work listed elsewhere in this specification section. General Scope:

THE SPECIFIC SCOPE OF WORK IS TO INCLUDE

, but is not limited to, the following items:

Page 69: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09A Drywall, Carpentry, & Painting 15 June 2011 Page 2 of 5 Revised per ADD#3 26 July 2011 3

00800

Drywall, Rough Carpentry, Acoustical Assemblies, Ceilings, and Painting:

1. Contractor shall furnish and install cold formed metal framing, insulation, drywall, and acoustical assemblies, ceiling tiles, interior wall panels, and the like work required by the Contract documents, including, but not limited to, all gypsum board, acoustical ceilings, translucent ceiling panels, grid suspension systems, acoustical treatment, acoustical panels, “Clouds”, cementitious wood fiber panels, cold formed metal framing, C-shaped loading bearing metal framing, metal stud kickers, metal furring, metal blocking, gypsum sheathing, dense glass, dense dek masonry back-up, acoustical joint sealers, acoustical sealants, hat channel, metal furring, drywall accessories, firestopping (as it relates to this Contractor’s work), fire caulking (as it relates to this Contractor’s work), sound caulking (as it relates to this Contractor’s work), shaft wall assemblies, framing components for suspended / furred ceilings, corner bead, edge trim, control joints, access panels (including those provided by other trades), priming, painting and

building insulation.

2. Contractor is to furnish and install all wood blocking which is exterior to the building as well as all wood blocking located within metal studs which is covered by drywall, dens-glass, or sheathing. This includes but not limited to lumber, wood structural panels, fire retardant treated materials, dimensional lumber, miscellaneous lumber, sheathing, etc. Contractor to coordinate with other trades for final locations and requirements.

3. Contractor shall coordinate with other Contractors on location of all work installed in partitions and

ceilings. Contractor shall ensure that all required inspections have been made prior to closing walls and ceilings.

4. Contractor shall be responsible for the layout of all work in this Contract Package. The Contractor

shall layout all partitions. 5. Contractor shall perform all welding required to complete its work. 6. Contractor shall furnish and install all light gauge metal bent plates, angles, plates, clip angles, and the

like as required for attaching studwork to the structure. 7. Contractor shall inspect all drywall work with a droplight before and after the prime coat of paint, and

perform all necessary point–up. 8. Contractor to include drywall expansion / control joints as recommended by manufacturer if not

specified elsewhere. 9. Contractor will furnish and install all expansion joint system assemblies complete, inclusive of floor,

wall and ceilings. Roof expansion joints are by the 07A Contractor. Exterior expansion joints located in masonry are by the 04A Contractor. Contractor to coordinate with the 03A contractor prior to slab pours.

10. Contractor will coordinate with the 04A contractor for installation of hollow metal frames located in

masonry walls. This Contractor shall ensure hollow metal frames are set plumb, level, square, and true to line. The 04A Contractor shall be responsible for maintaining hollow metal frames until the frame is completely enclosed in Masonry and accepted by the Construction Manager or this contractor for installation of doors, slabs, and finish hardware.

11. Contractor to furnish and install all acoustical ceiling assemblies. Contractor shall furnish all acoustic

tile cut-ins for other trade Contractors. Contractor shall coordinate furnishings and installation of cut tile with the Construction Manager. Contractor shall coordinate installation and arrangement of ceilings system with affected trade contractors through the Construction Manager. The 15B Contractor

Page 70: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09A Drywall, Carpentry, & Painting 15 June 2011 Page 3 of 5 Revised per ADD#3 26 July 2011 3

00800

shall coordinate and verify sprinkler head locations prior to cutting tile or installing grid by the 09A Contractor.

12. Contractor to include protection of acoustical treatments after installation.

13. Contractor shall furnish and install all batt, spray, and acoustic insulation. 14. Contractor shall coordinate all embedded items incorporated in this work including, but not limited to,

mechanical and electrical equipment for proper alignment, leveling, and access. 15. Contractor includes “tenting” of light fixtures if required by code. 16. Contractor includes all reasonably inferred chases and bulkheads for mechanical piping shown on both

architectural and mechanical drawings. 17. Contractor shall replace all damaged ceiling tile prior to acceptance of the ceiling systems at no

additional cost. Contractor shall provide maintenance stock material as specified at no additional cost.

18. Contractor shall provide ventilator when installing drywall to reduce dust and humidity. 19. Contractor shall provide drywall point-up between prime and finish paint coats. Point-up to be

inspected by the Construction Manager and this contractor prior to final coat of paint. 20. Contractor shall furnish and install infill with metal stud and drywall and fire sealant where applicable,

where masonry walls cannot extend to deck. 21. Contractor shall provide a Level 5

Level 4 drywall finish. Therefore, point-up of drywall should be minimal after priming of the surface. Excessive point-up or poor quality workmanship will not be tolerated. Butts joints are to be taken out 24” minimum, factory joints 12” minimum. No board joints are to break at window or doorjambs.

22. Contractor to coordinate with 15A, 15B, and 16A contractor for installation of access doors furnished and installed by other contractors. This contractor to include cutting of all drywall and additional framing to allow for installation of access doors.

23. Fire stopping of all penetrations is to be performed by the contractor making the respective penetration,

ie by 15A, 15B, and 16A.

24. The 04A Contractor is to furnish and install all exterior rigid insulation on masonry backup walls, including but limited to behind, brick, precast, cast stone, finish block, and metal panel areas. The 4A contractor to coordinate with exterior framing being provided by 09A contractor. All other rigid insulation which is contiguous to this contractors work is to be provided by this contractor.

Doors, Frames, Hardware Specific Scope:

1. Contractor shall furnish and install all hollow metal door frames (including sidelights, borrowed lights, transom frames, and architectural stick assemblies), FRP flush doors, hollow metal window frames, hollow metal doors, pre-finished wood doors, and finish hardware (including but not limited to all hinges, continuous hinges, locks, latch sets, deadlocks, exit devices, removable mullions, door closers, electro-magnetic locks, power supplies, key switches, power door operators, overhead stops, overhead holders, push plates, pull plates, anti-vandal pulls, kick plates, armor plates, flush bolts, floor stops, wall stops, thresholds, astragals, weatherstripping, gasketing, door silencers, key cabinets, and the like). Contractor shall adhere to the requirements of the contract documents with regard to quality

Page 71: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09A Drywall, Carpentry, & Painting 15 June 2011 Page 4 of 5 Revised per ADD#3 26 July 2011 3

00800

assurance, regulatory agencies, submittals, samples, products, warranties, factory finishing, key control systems, keys/keying, and the like.

2. Contractor to provide (1) 3’ x 7’ hollow metal frame for installation within masonry mockup panel. 3. The electrical contractor shall provide all power wiring, junction boxes, conduit, rectifiers, and

transformers. 4. This Contractor to furnish all door hardware to the 08A contractor for installation by the 08A

contractor for all aluminum doors and frames. The 08A contractor will not be providing their own hardware.

5. Final keying for all door hardware provided by this contractor will be performed by this contractor,

inclusive of storefront doors and overhead doors.

Painting Specific Scope:

1. Contractor to include all interior and exterior prepping, priming, and painting of all materials as called out in specifications and construction documents including but not limited to steel, galvanized metals, aluminum, concrete, masonry, wood, gypsum, etc.

2. Contractor to include stenciling/labeling of all fire walls as directed by contract documents and by

local jurisdiction. 3. Contractor to include light sanding of walls between primer, first and second coats when applicable. 4. Contractor to include painting of mechanical and electrical work to include but limited to when

applicable, uninsulated metal piping, uninsulated plastic piping, pipe hangers and supports, tanks without factory finishes, visible portions of internal portion of metal ducts without liner, behind all diffusers and grilles, exposed ductwork, all mechanical equipment without a factory finish, all electrical equipment without a factory finish, exposed conduits, etc

5. Stencil and or hanging identification of mechanical piping and or equipment and or electrical conduit

or equipment is the responsibility of the respective MEP contractor. Painting only is the responsibility of this contractor. Contractor to confirm requirements but at a minimum will include painting of exposed piping as follows:

i. Domestic Cold Water Piping Dark Blue

ii. Processed Water Green iii. Dual Temperature Water (2 Pipe) Light Green iv. Natural Gas Yellow v. Refrigerant Piping Black

vi. Domestic Hot Water (140) Orange vii. Domestic Hot Water (110) Beige

viii. Domestic Hot Water Recirc Brown ix. Breeching and Heating Ducts White x. Mechanical and Electric Room Floors Rust

xi. Fire Alarm Conduit Red xii. Sprinkler Piping Red

xiii. Interior of Data Work Boxes Purple

Page 72: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09A Drywall, Carpentry, & Painting 15 June 2011 Page 5 of 5 Revised per ADD#3 26 July 2011 3

00800

6. Contractor to include sealing and or hardeners of all exposed concrete floors. Contractor to apply product one time immediately prior to substantial completion. Contractor to include cleaning of floors to manufacturer’s standard prior to application.

7. Contractor to include all block filler applications. Two coats minimum. 8. Contractor to include painting of all exterior rails, lintels, exterior exposed non prefinished materials. 9. Contractor to include proper preparation for painting of all galvanized materials. 10. Contractor to include all cleaning of surfaces as dictated in the specifications prior to application of

product. 11. Contractor to include caulking of HM frames both door and window including head of door frame(s) to

adjacent surfaces. This is to include both sides of interior and exterior frames. 12. Contractor to include caulking of drywall to block and or concrete surfaces. 13. Contractor to include caulking of interior architectural trim prior to final finish application. 14. Contractor shall be responsible for all minor touch-up and repainting work caused by installation of

adjacent work. 15. Contractor to provide a paint schedule for submittal to the Architect, Owner, and Construction

Manager.

16. Contractor is responsible for any rework as a result of dirt blown into finish, unless notice is given to the Construction Manager prior to beginning work that the site is in need of cleaning.

17. Contractor to include any masking off of materials as required to properly protect other finished

materials. Contractor to product adjacent finished surfaces. Overspray to be cleaned at this contractor’s expense.

1. Strike drywall finish level 5(see line item 21 above) Added by Addenda #3:

2. Contractor shall provide drywall level 4 finish. 3. 9A contractor is responsible for all fluid applied membrane air barriers (specification section 07272)

identified on contract drawings. The 4A contractor is not responsible for the air barrier installation.

END OF SCOPE 09A

Page 73: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09B Flooring Page 1 of 5 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

WORK SCOPE CATEGORY 09B – Flooring The work of this bid category includes but is not limited to providing all labor, equipment, materials, scaffolding, hoisting and incidentals to complete all Flooring work in accordance with the specifications, drawings and applicable codes. All work is to be performed as shown on the plans and / or specified under the following technical sections: SECTION Division 0

NAME

Division 1 03360 Polished Concrete Floor Finishes (Alternate) 07901 Joint Sealants (as it relates to this scope) 09310 Ceramic Tile 09401 Precast Terrazzo 09640 Wood Flooring 09660 Resilient Flooring 09671 Resinous Flooring 09680 Carpeting ALL OTHER SPECIFICATION SECTIONS – FOR COORDINATION PURPOSES Geotechnical Report issued by GEOTECH Engineers, Inc. for informational purposes. In addition to the above, trade contractors are to include, but are not limited to, AIA Documents A201 and A401, and various other Technical Specifications interfacing with this work. The Contractors are required to review the work descriptions of the other categories so as to not misunderstand the scope responsibilities. The Contractors are also bound to the HESS Safety Manual and the HESS Trade Contractors Procedures Manual for Oxon Hill High School Replacement for the administration of the contract.

Contractor is responsible for General Scope of Work listed elsewhere in this specification section. General Scope:

THE SPECIFIC SCOPE OF WORK IS TO INCLUDE

, but is not limited to, the following items:

Ceramic Tile Specific Scope:

1. Contractor to furnish and install all floor and wall tile, ceramic mosaic, porcelain, quarry, glazed and unglazed wall tile , stone thresholds, and accessories including but not limited to thinset material, thick set material, reducer strips, transition strips, base, shower receptors, waterproofing and/or vapor retarders etc.

2. Contractor to coordinate slab depressions with Concrete Contractor. 3. Contractor to coordinate base requirements with the 06A contractor for cabinetry and built in shelving. 4. Contractor to coordinate patterns of materials furnished under this contract with the construction

documents. 5. Contractor to include proper treatment of control joints within slabs prior to laying of floors. 6. Contractor to include caulking of control joints within own work. 7. Contractor to include 100% flash patching and leveling of all floors to receive materials under this

scope of work.

Page 74: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09B Flooring Page 2 of 5 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

8. Grinding of floors is not part of this package and is to be assumed by the 03A Contractor provided this

contractor gives proper notice of unacceptable conditions two weeks prior the start of work.

9. Contractor includes waterproofing of slabs prior to installation of flooring for second and third floor applications as specified. Contractor includes water testing of slabs as specified prior to the installation of tile.

10. Contractor to include tile cleaning and grout sealer prior to protection of floors.

11. Contractor includes crack isolation membrane if required. 12. Contractor to include protection of installed products with craft paper. Contractor to include removal

of protection and placement into dumpster provided by Construction Manager at project completion

Terrazzo Specific Scope:

1. Contractor to furnish and install all Precast Terrazzo and accessories at the Rotunda, including but not limited moisture tests, floor treatments, flexible reinforcing membrane, crack suppression membranes, joint, edge and termination strips, metal divider strips, backing for terrazzo base (cement board), abrasive strips, patterns and color(s), etc

2. Contractor to include precast terrazzo stair treads, with proper nose detail and abrasive strips, and precast terrazzo base units.

3. Contractor to include mockups and samples as specified. 4. Contractor to coordinate with the 5A Contractor before and during stair installation. 5. Contractor to coordinate patterns and colors of materials furnished under this contract with the

construction documents and existing materials. Contractor to provide samples to be submitted for approval.

6. Contractor to include sealing of precast terrazzo. 7. Contractor to assume multiple colors and patterns to be used.

8. Grinding of floors is not part of this package and is to be assumed by the 03A Contractor provided this

contractor gives proper notice of unacceptable conditions two weeks prior the start of work. 9. Contractor to include protection of installed products with craft paper. Contractor to include removal

of protection and placement into dumpster provided by Construction Manager at project completion.

Resinous Flooring Specific Scope:

1. Contractor to furnish and install all resinous flooring and accessories including but not limited moisture tests, floor treatments, flexible reinforcing membrane, control joint treatments, crack suppression membranes, joint, edge and termination strips, metal divider strips, abrasive strips, patterns and color(s), etc

2. Contractor to coordinate slab depressions with Concrete Contractor.

Page 75: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09B Flooring Page 3 of 5 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

3. Contractor to coordinate patterns and colors of materials furnished under this contract with the construction documents and existing materials. Contractor to provide samples to be submitted for approval.

4. Contractor to include proper treatment of control joints within slabs prior to installation of resinous flooring.

5. Contractor to include caulking of control joints within own work, inclusive of perimeter.

6. Contractor to include 100% flash patching and leveling of all floors to receive materials under this scope of work.

7. Grinding of floors is not part of this package and is to be assumed by the 03A Contractor provided this contractor gives proper notice of unacceptable conditions two weeks prior the start of work.

8. Contractor includes crack isolation membrane if required

9. Contractor to include waterproofing behind integral cove base prior to installation of flooring as specified.

10. Contractor to include protection of installed products with craft paper. Contractor to include removal of protection and placement into dumpster provided by Construction Manager at project completion.

Carpet and Vinyl Specific Scope:

1. Contractor to furnish and install both roll and tile carpet and accessories including but not limited to mastic, reducer strips, transition strips, base, etc.

2. Contractor to furnish and install tile resilient flooring and accessories including but not limited to mastic, reducer strips, transition strips, cove and straight base, etc. inclusive of rubber floor tile, vinyl composition floor tile, slip retardant vinyl composition floor tile, cushioned rubber flooring

3. Contractor to coordinate base requirements with the 06A contractor for cabinetry and built in shelving. 4. Contractor to furnish and install resilient stair tread/nosings and accessories as indicated. 5. Contractor to furnish and install resilient molding accessories. 6. Any unclear situation(s) within the construction documents with regards to base is assumed to be base

provided by this contractor. 7. Contractor coordinate patterns of materials furnished under this contract with the construction

documents. 8. Contractor to include caulking of door jambs to resilient flooring. 9. Contractor to include proper treatment of control joints within slabs prior to laying of floors. 10. Contractor to include 100% flash patching and leveling of areas to receive carpet or resilient flooring.

11. Grinding of floors is not part of this package and is to be assumed by the 03A Contractor provided this

contractor gives proper notice of unacceptable conditions two weeks prior the start of work.

Page 76: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09B Flooring Page 4 of 5 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

12. Contractor to include protection of installed products with self sticking plastic at carpet areas and craft paper at resilient areas. Contractor to include removal of protection and placement into dumpster provided by Construction Manager at project completion.

Wood Flooring Specific Scope:

1. Contractor to furnish and install all wood flooring, wood sports flooring, wood dance flooring, wood flooring at stairs etc. Contractor to include but not limit to membranes, sleepers, plywood, adhesives, subflooring, maple flooring, fasteners, finishing materials, perimeter base, adhesives etc.

2. Contractor to coordinate with Concrete contractor for inlaid requirements for proper installation of

wood flooring at stair area. 3. Contractor to coordinate slab depressions with Concrete Contractor. 4. Contractor to include proper treatment of control joints within slabs prior to laying of floors. 5. Contractor to include any incidental caulking associated with this scope for a complete finished

product. 6. Contractor to include floor cleaning prior to protection of floors. 7. Contractor to include incidental flash patching and leveling of areas to receive wood flooring.

8. Grinding of floors is not part of this package and is to be assumed by the 03A Contractor provided this

contractor gives proper notice of unacceptable conditions two weeks prior the start of work. 9. Sports flooring to be layed parallel with long dimension of space unless noted otherwise.

10. Dance flooring to be layed parallel with long dimension of space unless noted otherwise. 11. Contractor to include all nosings, edging, corner treatments, transition strips and any other accessories

required for a complete installation of this work. 12. Contractor to include athletic stripping. Contractor to submit final layout drawings for approval prior

to start of flooring. 13. Contractor to include temporary equipment to bring temperature and humidity into acceptable ranges

for installation of flooring. Contract to include temporary barricades as necessary. 14. Contractor to include protection of installed products with craft paper after proper cure time of

finishes. Contractor to include removal of protection and placement into dumpster provided by Construction Manager at project completion.

EXCLUDED FROM THIS CONTRACTOR WORK is

:

1. Testing costs unless specifically called for in this scope, a result of negligence, poor workmanship, or failure of work to meet the requirement of the documents

Added by Addenda #3

Page 77: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 09B Flooring Page 5 of 5 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

1. The 9B contractor shall provide a credit for VCT flooring as identified in Alternate #7.

The 3A contractor is responsible for the installation of the polished concrete and polished concrete decorative floor finish. The 4A contractor is responsible for the filled-and-polished ground face units.

END OF SCOPE 09B

Page 78: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 1 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

WORK SCOPE CATEGORY 16A - Electrical The work of this bid category includes but is not limited to providing all labor, equipment, materials, scaffolding, hoisting and incidentals to complete all Electrical work in accordance with the specifications, drawings and applicable codes. All work is to be performed as shown on the plans and / or specified under the following technical sections: SECTION Division 0

NAME

Division 1 02220 Selective Demolition (as it relates to this scope) 02221 Building Demolition (as it relates to this scope) 02300 Earthwork (as it relates to this scope) 05120 Structural Steel (for coordination purposes) 05210 Steel Joists (for coordination purposes) 05310 Steel Deck (for coordination purposes) 07540 Thermoplastic Membrane Roofing 07552 Modified-Bitumen Roofing (for coordination purposes) 07841 Through-Penetration Firestop Systems (as it relates to this scope) 07901 Joint Sealants (as it relates to this scope) 08305 Access Doors and Frames

08710 Finish Hardware (for coordination purposes)

10200 Louvers and Vents (for coordination purposes) 10416 Scoreboards 10652 Operable Partitions (for coordination purposes) 11063 Stage Rigging Equipment 11065 Stage Lighting Equipment 11067 Stage Production AV Equipment 11132 Projection Screens (for coordination purposes) 11160 Loading Dock Equipment 11172 Solid Waste Handling Equipment (for coordination purposes) 11400 Foodservice Equipment (for coordination purposes) 11452 Residential Appliances (for coordination purposes) 12340 Educational Casework (for coordination purposes) 12345 Laboratory Casework and Fixtures (for coordination purposes) 12352 Media Center Casework and Equipment (for coordination purposes) 12710 Fixed Audience Seating (for coordination purposes) 12715 Lecture Room Seating (for coordination purposes) 13100 Lightning Protection 13125 Grandstands and Bleachers (for coordination purposes) 13845 Lighting Controls 13852 Digital, Addressable Fire-Alarm System 13921 Electric-Drive, Centrifugal Pumps 14210 Electric Traction Elevators (for coordination purposes) Division 15 (for coordination purposes) 16051 Common Work Results for Electrical 16055 Overcurrent Protective Devise Coordination 16060 Grounding and Bonding 16073 Hangers and Supports for Electrical Systems 16075 Electrical Identification 16120 Conductors and Cables 16130 Raceways and Boxes 16140 Wiring Devices 16145 Lighting Control Devices 16211 Electricity Metering

Page 79: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 2 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

16231 Engine Generators 16269 Variable Frequency Controllers 16410 Enclosed Switches and Circuit Breakers 16415 Transfer Switches 16420 Enclosed Controllers 16441 Switchboards 16442 Panelboards 16461 Low-Voltage Transformers 16491 Fuses 16511 Interior Lighting 16521 Exterior Lighting 16526 Exterior Athletic Lighting 16555 Stage Lighting System Installation, Conduits, & Wiring 16755 Rigging Systems Conduits & Machine Connections 16760 Stage A/V Systems Conduits 16995 Electrical Systems Commissioning 16996 Electrical Testing Requirements 16997 Sample Pre-function Check Lists - Electrical 16998 Sample Function Test Procedures - Electrical 17100 Telecommunications Pathways and Spaces 17150 Structured Cabling Requirements 17210 Network Communications Equipment (for Informational Purpose 317325 Auxiliary Sound Systems

)

17400 Video Distribution System 17440 Video Devices (for Informational Purposes3

17740 Intercom and Master Clock Systems )

17550 Audio Equipment 17920 Access control and Intrusion Detection 17930 Video Surveillance System ALL OTHER SPECIFICATION SECTIONS – FOR COORDINATION PURPOSES Geotechnical Report issued by GEOTECH Engineers, Inc. for informational purposes. In addition to the above, trade contractors are to include, but are not limited to, AIA Documents A201 and A401, and various other Technical Specifications interfacing with this work. The Contractors are required to review the work descriptions of the other categories so as to not misunderstand the scope responsibilities. The Contractors are also bound to the HESS Safety Manual and the HESS Trade Contractors Procedures Manual for Oxon Hill High School Replacement for the administration of the contract. .

Contractor is responsible for General Scope of Work listed elsewhere in this specification section. General Scope:

THE SPECIFIC SCOPE OF WORK IS TO INCLUDE

, but is not limited to, the following items:

Electrical Specific Scope:

1. Contractor shall furnish, install, and maintain adequate temporary lighting, as specified by MOSH and OSHA codes, and adequate electrical service for all trades regardless of status of permanent power from utility company. In the event permanent services are not available, Contractor shall furnish, install, fuel, and maintain temporary generators to provide adequate temporary lighting.

Page 80: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 3 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

2. Contractor shall furnish and install dedicated temporary requirements for connection of all trades equipment such as masonry contractor’s saw, tile contractor’s saw, and elevator equipment. Contractor shall furnish, install, fuel and maintain temporary generators until service from the utility company can be established.

3. Contractor shall furnish and install all electrical work indicated in the Contract Documents, including, but not limited to, fire alarm systems complete, electrical systems complete, public address systems complete, sound systems, video projection/production systems, music systems complete, and any other Division 11, 12, 13, 16, and 17 systems. These systems shall include, but are not limited to, all primary service, secondary service, raceways, outlet boxes, pull boxes, junction boxes, wire ways, wiring, cables, wiring devices, receptacles, switches, hangers, supports, identification inclusive of painting of conduits per the specifications, contactors, time clocks, wall mounted clock with cage in gymnasium, photocells / photo-controls, connections to equipment, switches, panel boards, transformers, switchboards, service entrance surge suppression, grounding, lightning protection as indicated, emergency stand-by generators, dimming systems, controls, conduit, spare conduit with pull string where called out, automatic and / or push button door openers, power / data requirements for exterior signage, kilns, battery chargers, emergency cut-offs, gym control panels, fire hydrant supervision, light guards/cages, and the like for the complete installation of all systems unless noted otherwise elsewhere.

4. If at any time during the course of construction, permanent utilities which are being used for

construction need to be terminated, regardless of length of time, this Contractor shall (A) furnish, install, and maintain temporary generators until service from the utility company can be reestablished, to allow for school operations or other trades to continue work uninterrupted, or (B) schedule shut-offs, switch-over(s) off hours. At which time they are to be coordinated with Construction Manager a minimum of seven (7) days in advance.

5. Contractor shall coordinate with the Concrete Contractor and the Masonry Contractor to provide all

required embedded items, including, but not limited to, sleeves, conduit, device boxes, panel boxes, and the like included in this scope. The Contractor shall be responsible for the proper location and installation of all embedded items. Note surface applied/exposed conduits, boxes, etc will not be allowed unless specifically approved via RFI prior to installation. This includes control wiring, conduit and boxes.

6. In the event an opening is required in a masonry wall and is not properly coordinated between this and 04A contractor, via a field use drawing, it is this contractor’s sole responsibility to implement the required fix. All costs to either sawcut, or tooth cmu to allow for the opening is the responsibility of this contractor. In the event the 04A contractor has missed the indicated opening, or has miss-sized the opening, the costs required for the fix is the responsibility of the 04A contractor

7. Contractor shall furnish and install complete power connections and final connections for all equipment installed under this scope and other trades scopes including, but not limited to, food service equipment, miscellaneous equipment and appliances, casework, specialties, toilet accessories, motorized partitions, motorized projectors, electric hardware, stage equipment, theatre equipment, television equipment, athletic equipment / devices, electrical equipment, mechanical equipment, shop equipment, pumps, motors, panels, appliances, and the like as required by the Contract Documents. The Contractor shall check and verify that the power it is providing (amperage, voltage, etc.) matches the power requirements of the equipment it is connecting to. The Contractor shall report any deviations to the Construction Manager prior to making the connection.

8. Contractor shall coordinate with Mechanical Contractor and any other trades regarding motor starters including final connections for all mechanical equipment. Electrical Contractor shall furnish and install for all trades all motor starters, control panels, fuses, contactors, safety switches, disconnect switches, and controls when stated in the specifications or drawings and is not specifically assigned to

Page 81: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 4 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

others by the Contract Documents. Where it is unclear as to the intent of the drawings or specifications as to who furnishes the required equipment of other trades, it shall be the responsibility of this Contractor to provide the required equipment.

9. Contractor shall furnish and install a complete fire alarm system as indicated by the Contract Documents. Contractor shall furnish and install all required electrical connections to all alarm devices, including but not limited to, water gongs, flow switches, connections to electric door hardware, and tamper switches installed by others. Contractor includes coordination and conduits to feed to protective covers, exterior bleachers (grandstands), and if required to be tied to the main building fire alarm system. This contractor has all F/A connections and programming of all devices. Contractor also includes all inherent off hour work required for this scope item.

10. Contractor includes coordination and installation all power requirements and/or fire alarm connections for all prefabricated display cases, display surfaces, bulletin boards, protective covers, operable panel partitions, miscellaneous equipment, theater rigging, fire curtains, stage curtains, cyclorama curtains, commercial laundry and dry cleaning equipment, motorized projection screens, projection screens, solid waste handling equipment, food service equipment, ansul systems, residential equipment, photo laboratory equipment, gymnasium equipment (indoor and outdoor), applied technology and engineering laboratory furnishings and equipment, laminated casework, wood casework, fixed audience seating, telescoping stands, exterior bleachers for complete and fully functional systems

11. Contractor shall furnish and install all exterior work, conduit ducts, and / or duct banks, including but not limited to, electrical, phone, CATV, fiber optic, spares, transformer pads, manholes, concrete, and the like as required. Contractor shall also furnish and install all concrete and accessories for the site lighting package and stadium lighting packages. Contractor shall be required to furnish and install all concrete related to the work of this scope, including, but not limited to encasement of underground conduits, anchor bolts, reinforcing steel, and light pole bases. Contractor shall note that the interior housekeeping and equipment pads will be provided by the Concrete Contractor. The coordination and layout of the interior housekeeping and equipment pads for this Contractor will be provided by this Contractor. In the event a concrete pad is required for this contractors equipment but not shown on the drawings, this Contractor will be responsible to install this concrete work complete. Contractor shall furnish and install all exterior equipment foundations and pads. Contractor shall coordinate this work with the Construction Manager, Owner and all applicable Utility companies. Contractor shall perform all excavating and backfilling required for all work outlined in this section.

12. Contractor includes power to all interior and exterior scoreboards at all locations.

13. Contractor includes test pitting for location of existing service to existing facility. Contractor includes all temporary measures and rerouting of existing service to allow for new parking areas to be put on grade as this work preceeds the abandonment of existing facility.

14. Contractor to bring conduit, exterior weatherproof junction boxes, wiring, and final termination for power to Field Houses and, Exterior Bleaches (Grandstands).

15. Contractor will coordinate with all equipment and appliance Contractors, to ensure that proper rough-ins and receptacles are provided under this Contract.

16. The permanent HVAC equipment will be utilized for temporary climate control as directed by the CPM Schedule. The permanent equipment shall remain in operation following start-ups, as directed by the Construction Manager. Contractor shall perform regular maintenance on all equipment as necessary to maintain equipment in “like new” condition. Contractor shall complete all work necessary to properly electrify (on a temporary and/or permanent basis) the equipment for its use as described above. The use of permanent electrical equipment to provide power shall not alter required warranties.

Page 82: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 5 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

The required warranty for all equipment commences on the date of substantial completion. Any costs for extended warranty due to early start up are to be included in this Contractor’s base cost.

17. Contractor shall furnish and install all sound caulking, firesaffing and fire caulking at all penetrations

this Contractor makes through walls, ceilings, and / or slabs, inclusive of exterior perimeter of pathways

18. Contractor shall coordinate placement of conduit under slab on grade with the Mechanical Contractor,

Concrete Contractor, and Construction Manager.

19. Contractor shall be responsible for all excavation, grading, backfill, approved compaction, and any other item associated with its interior and exterior work provided under this package. Contractor shall dispose of its excavation spoils to a central location as directed by the Construction Manager. Contractor shall be responsible for dewatering its excavations as necessary to maintain progress for its work. Contractor is responsible for the excavation and backfill for all its work and is responsible for restoring all excavations to their original grade and compaction. If in the event this Contractor must perform an excavation operation for reason caused by itself after the stone base of the concrete slab has been installed, it will be the responsibility of this Contractor to repair the stone base for the concrete slab, replace any stone base that may have been contaminated by this Contractor’s excavation operations, and bring this area back to its original grade prior to this Contractor’s excavation.

20. This contractor to coordinate with demolition contractor and utility company to ensure proper shut down of active utilities prior to the start of demolition of the existing facility and outbuildings.

Disconnect responsibilities are as follows:

Service Action U/G Infrastructure Removal Domestic Water Excavate and Cap – 15A 02A Contractor Fire Sprinkler Excavate and Cap – 15A 02A Contractor Sanitary Sewer Excavate and Cap – 15A 02A Contractor Storm 02A Contractor Gas Meter Removal – Utility Company 02A Contractor Telephone / Cable Discontinue Service –PGCPS 02A Contractor Electrical Pull Fuses / Transformer – Pepco 02A Contractor

Rodent Removal 02B Contractor

21. Contractor is responsible to verify size, quantity and final routing of underground conduits for cable and telephone prior to installation, with respective utility company at no additional cost to the owner or construction manager.

22. The Sprinkler System Contractor and the Electrical Contractor shall submit concurrently to the Fire Marshall and any other jurisdiction having authority, a coordinated sprinkler system/fire alarm system submittal in accordance with the Fire Marshall’s and any other jurisdictions having authority requirements. The Contractors shall provide the required coordinated submittal in its entirety within one hundred and twenty (120)days of receiving a Letter of Intent, Notice to Award, or the Contract, whichever is issued first.

23. Contractor shall submit coordinated layout drawings for all electrical work installed by this contractor, coordinated with Contractors who have an impact on the work i.e., Sprinkler, Mechanical, Drywall, Masonry, Concrete, Steel, etc. Contractor shall coordinate all underground, mechanical rooms, electrical rooms, above ceiling work with the other Contractor(s).

Contractor shall complete coordination drawings before fabrication and installation of its material, system or equipment can begin. All Trades shall complete these coordination drawings within

Page 83: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 6 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

timeframe listed below as to allow review and resolution of conflicts without impacting the project schedule. The Construction Manager will act as the BIM Manager on the project. This trade contractor shall develop a Building Information Model within the Division 5 work components as outlined within the technical sections listed, to be used within a Federated Model consisting of linked but distinct components of other trades for the purpose of trade coordination. The level of detail of the BIM provided by this trade contractor shall be equal to a fabrication model, and shall be used as the basis of the detailed design for shop drawings/design connections. The same division 5 model will be used for fabrication, coordination and erection/installation. All trade fabrication models shall be coordinated by the BIM Manager using Navisworks Manage. All software shall be compatible with Revit, AutoCAD and Navisworks. As soon as practicable, all appropriate project participants shall meet, to develop and execute the project's BIM execution plan. Below is the estimated timeframe to complete this task:

Contractor Timeframe to Complete 05A 30 calendar days 15A 45 calendar days (starts after finish of 05A model) 15B 30 calendar days (starts after 15 calendar days of the start of 15A model) 16A 45 calendar days (starts after finish of 05A model) Team Review (CM, 05A. 15A, 15B, 16A) will happen simultaneously as the models are being

uploaded of different sections/floors and shall be finished after 15 calendar days of the last model upload.

Total duration of the BIM coordination process is 90 calendar days. This time frame is inclusive of all models that are required by any sub contractor of the above

mentioned trade contractor. A detailed BIM schedule will be developed after the BIM kick off meeting and shall be part of the

BIM Execution Plan.

Any installation that is improperly performed due to failure to properly coordinate work will be corrected in the field at no additional cost to Owner or Construction Manager.

24. Contractor shall coordinate with Concrete Contractor regarding underground work, mechanical openings, and embedded items. Contractor shall coordinate with Masonry Contractor, Steel Contractor, and Drywall Contractor regarding duct-banks, raceways, and conduit sleeves. Contractor shall provide field layout duct-banks, raceways, and conduit sleeves. Contractor shall provide all sleeves required for its penetrations. Contractor shall provide coordination drawings showing all duct-banks, raceways, and conduit sleeves and dimensional layout of these penetrations for all steel penetrations for incorporation into the Steel Contractors steel fabrication shop drawings. Contractor shall provide all coordination drawings for concrete, masonry, and steel within Thirty (30) days of receiving a Letter of Intent, Notice to Award or the Contract, whichever is issued first.

25. Contractor shall coordinate box outs directly with the Masonry Contractor where possible. When not possible contractor is responsible for neatly core drilling or cutting masonry walls where its work will pass through masonry walls.

26. Contractor to coordinate with concrete contractor for floor penetrations. When not possible contractor is responsible for neatly core drilling through concrete. Where floor removal is required, Contractor

Page 84: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 7 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

will replace floor slabs removed by this Contractor in the manner specified, if work must be done out of concrete pour sequence.

27. Contractor shall furnish and install all required escutcheons, pedestals, and the like for complete finish trim for this Contractor’s work in all ceilings, walls, floors, millwork, casework, and the like.

28. Contractor shall furnish and install all specified backing and supports for fixtures and equipment, including telephone and security equipment and backboards, and all cabinets necessary for this Contractor’s work. This includes plywood.

29. Contractor shall furnish and install the Emergency Generator, including electrical connections, accessories, connections to, pumps, and transfer switches, exhaust piping and tanks.

30. Contractor shall design, furnish, and install a complete Fire Alarm System with shop drawings and wiring interface of various pieces of equipment to be controlled as detailed in the specifications, drawings, and equipment data. Fire Alarm System and Sprinkler System zones must

match and/or coincide. This Contractor shall design, furnish, and install the system to meet with every one of the following standards that are the minimum: State Fire Marshall, County Fire Department, Applicable Safety Codes, BOCA Codes, ANSI Elevator Codes, National Fire Protection Association Standards, and National Electrical Code, Article 760. Contractor shall coordinate with the Mechanical Contractor before any work on this system can commence. Contractor to furnish to Mechanical Contractor duct-smoke detectors for installation, final connections and tie in with fire alarm system is by this contractor.

31. Contractor shall provide the Construction Manager with a copy of the latest edition of the NECA labor-pricing manual at no additional cost.

32. This Contractor shall provide all labeling and identification required for its work inclusive of painting and stenciling of conduits as required per the specifications.

33. Contractor will survey the entire building prior to substantial completion in order to allow Contractor to replace any failed lamps and ballasts within two weeks following substantial completion and / or at the direction of the Construction Manager at no additional cost to Owner or Construction Manager.

34. Contractor shall furnish and install all miscellaneous steel and support hanger steel required for ceiling and / or wall mounted equipment it is installing, including light fixtures, specialty fixtures, panels, transformers, and the like. Contractor shall furnish and install prime coat painting for all unprotected support and hanger steel.

35. Contractor shall review all casework, mechanical equipment, shop equipment, signage, theatre equipment, stage equipment, appliance, equipment submittals, shop drawings, and product data to assure that all electrical components are compatible and operable with the electrical system (including the fire alarm system). Contractor shall provide to the Construction Manager written verification of its review and bring forward in writing any discrepancies found within this data within three (3) weeks after receiving this data. If discrepancies are not reported within that time frame, the Contractor shall be responsible for any costs associated with those discrepancies. Non-conformance to this requirement shall not be cause for schedule delay.

36. Contractor shall furnish and install all outlets, wire mold, and other electrical devices / components required for casework and millwork. Cutouts for this work will be provided by others. This Contractor shall provide templates for locating and completing these cut outs to the Millwork Contractor.

37. If documents call for “empty conduit” or any version thereof, this contractor has included “empty conduit”, clips, anchoring, hangers, etc, and associated pull string(s) and blank cover plate.

Page 85: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 8 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

38. Contractor shall furnish and install all Control Systems electrical requirements outlined on in the

drawings and specifications.

39. Contractor shall furnish and install equipment and devices with sufficient space to allow for proper operation, maintenance, and removal as needed. Relocation of equipment and / or devices to provide access will be at the expense of the Contractor if its work is found not to be in compliance.

40. Contractor shall include relocation of existing electrical utilities, light poles etc as indicated on Contract Documents.

41. Contractor shall furnish and install all conduit, wire and electrical signage regardless of voltage for building and site, inclusive of school sign/directory at entrance.

42. The 16A Contractor will install only, furnished by the 06A contractor; all electric hand dryers, associated anchors and fasteners.

43. Permanent Service:

Contractor to include excavation, installation of conduits and associated sweeps concrete, photo documentation, backfill, compaction, end staking, etc for primary electric service installation. Pepco includes setting of transformer. This contractor includes transformer pad, and secondary ductbank to building. All primary and secondary wire will be pulled and terminated by Pepco. Contractor includes in its entirety all interior and exterior, football field lighting, fire alarm system, public address and music equipment, school intercom and programming equipment, security systems, sound systems, clock systems, Video Projection / Production Systems , etc.

44. Contractor includes wiring and step down transformers and or power supplies for all electrified door hardware. Actual hardware at door is furnished and installed by the 09A contractor. This contractor to coordinate routing of conduits within door frames during frame installation.

45. Contractor has final connection of equipment being provided by other located within the main

building, grandstand, field house, and other outbuildings as specified. Contractor to coordinate with 06A, 15A, and 15B contractors respectively for a clear understanding of equipment being provided by other trades.

For coordination purposes with equipment furnished by other trades, and or PGCPS, below is a brief summary to include but no limiting toItem

: Furnish Install Final Electrical

Connection All high voltage wiring 16A 16A 16A Conduits, raceways and interconnecting boxes 16A 16A 16A Wire Pathways 16A 16A 16A High Voltage Wire testing and labeling 16A 16A 16A Labeling of conduits and back boxes 16A 16A 16A Junction Boxes 16A 16A 16A Power Terminations (High Voltage) 16A 16A 16A Primary and Secondary Conduits 16A 16A 16A Primary and Secondary Conductors Pepco Pepco BGE Transformer Pad and Transformer Switch Pad 16A 16A BGE Transformer Pepco Pepco BGE Overhead Coiling Doors 06A 06A 16A Display Cases 06A 06A 16A Exterior Directory 16A 16A 16A Operable Panel Partitions 06A 06A 16A

Page 86: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 9 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

Theatre Rigging 16A 16A 11E Projection Screens 06A 06A 16A Solid Waste Handling Equipment 06A 06A 16A Food Service Equipment 06A 06A 16A Residential Equipment 06A 06A 16A Passenger Elevators 06A 06A 16A Fire Alarm System 16A 16A 16A Theatrical Systems Lighting 16A 16A 16A Theatrical Systems dimming system wiring 16A 16A 16A Theatrical Dimmer Racks or cabinets 16A 16A 16A Theatrical Control devices 16A 16A 16A Theatrical Rigging Pipes 16A 16A 16A Sound Systems 16A 16A 16A Video Projection/Production Systems 16A 16A 16A Clock and Program Control 16A 16A 16A Public Address and Music Equipment 16A 16A 16A School Intercom and Program Equipment 16A 16A 16A Security System 16A 16A 16A Power Supply for Door Hardware 16A 16A 16A Electrified Door Hardware 09A 09A 16A Video, Cable, Data, Telephone Concealed Conduit 16A 16A 16A

46. Contactor includes furnish of all access doors required for own work. Access doors to be installed by

09A Contractor at both Masonry and Drywall locations.

Stage Rigging, Stage Lighting, & Stage Production AV Equipment Specific Scope:

1. Contractor to furnish and install a complete and operational Stage Rigging, Stage Lighting and Stage Production AV system for the Auditorium, Black Box, and TV Studio that includes but not limited to all wiring, plates, connections and miscellaneous equipment, lighting, coordination, provisions, inspections, testing, instructions, warranties, materials, transportation, field dimensioning, sound system and sound system testing

, motorized and automated hoists, motorized batten hoisting equipment and systems, mechanical back up brakes, overload and underload detection, loft blocks, schedule 40 black iron pipe battens, motorized batten hoisting system automated control center (ACC), ACC software, ACC wheel chair accessible, password protection, CPU control, emergency stops, hardware, forged cable clips, compressible copper swage fittings, copper sleeves, turnbuckles with jam nuts, tapping of dead ends of all wire ropes, final adjustments, testing and inspections inclusive of load testing, Professional Engineered Stamped drawings, and any other incidental work for a complete and operational system.

2. Contractor to review base drawings for coordination of turn-key Stage Rigging System with conduits, junction boxes and electrical per the drawings.

3. Contractor to coordinate all rigging structural requirements with the 05A contractor prior to the

fabrication of structural steel. Contractor to verify field installation prior to fabrication of rigging system.

4. Contractor to furnish and install all stage curtains as indicated and or specified including but not

limited to coordination with supplied theater rigging, all theater curtains, curtain track and hardware, fabrics, legs, borders, cycloramas, main curtains all vertical seams (no horizontal seaming will be allowed), labeling, draw curtains, border curtains, leg curtains, pipes and tracking, clamps, eyebolts,

Page 87: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

HESS Construction + Engineering Services Oxon Hill High School Replacement

Package 16A - Electrical Page 10 of 10 15 June 2011 Revised per ADD#3 26 July 2011 3

00800

schedule 40 black iron for dead hung borders and legs and any other incidental work for a complete and operational system.

5. Principal structural steel work unless noted herein is by the 05A contractor. This contractor is to coordinate all structural requirements with the 05A contractor prior to fabrication of structural steel. Contractor to verify field installation prior to fabrication of stage curtains.

6. Contractor includes all incidental caulking relating to this work.

SPECIAL CONSIDERATIONS:

1. Construction Managers Trailer:

Contractor includes permits, bonds, utility company connection fees, labor and material and all miscellaneous costs to supply and install a 120 /208V 200AMP electrical and cable service to the Construction Managers Office Trailer. This service will be inplace for Construction Manger will downsize and demobilize trailer complex and replace with smaller office trailer relocated onsite. Electrical Contractor is responsible for all relocation and reconnection costs. In the event permanent services are not initially available for either location, Contractor shall furnish, install, fuel, and maintain temporary generators until service from the respective utility company can be established. Once established, Contractor is responsible for monthly service bills until project completion. In the event they cannot be established, Contractor is responsible for all costs to furnish, install, fuel, and maintain temporary generators until project completion. Contractor includes installation of and final connection of heat tape for temporary office furnished by 15A contractor. Contractor includes final disconnect and disposal of service at project completion.

2. Temporary Power to Site:

Contractor includes permits, bonds, utility company connection fees, labor and material and all miscellaneous costs to supply and install a minimum of 277/480V 3 Phase 400 AMP service with distribution points at 120 / 208 V located at such points that no electrical cords will be over 100 lf in length and as approved by the Construction Manager. This service will be inplace for the duration of the project. In the event permanent services are not initially available for either location, Contractor shall furnish, install, fuel, and maintain temporary generators until service from the respective utility company can be established. Once established, Contractor is responsible for monthly service bills until project completion. In the event they cannot be established, Contractor is responsible for all costs to furnish, install, fuel, and maintain temporary generators until project completion. Contractor includes final disconnect and disposal of service at project completion.

3. Power Requirements at Phase 1 Completion

: Contractor shall provide all power, communications, data, and fire for the Fieldhouse, press box, site lights, sports lights (if Alternate is accepted), and scoreboards at the completion of phase 1, as these area’s will be occupied. If the permanent service is not available this contractor is responsible for bringing temporary service to facilitate.

Added by Addend #3

1. Technology infrastructure and equipment shall be divided into two bid packages. 17A work shown on schedule T-001will be furnished and installed by the 16A Contractor. The 17B work will be bid at a later date.

END OF SCOPE 16A

Page 88: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

CERAMIC TILE TYPE SCHEDULE 8 X 8 PORCOXON HILL HIGH SCHOOL PAVER

WAINSCOT FULL WALLNUMBER SPACE TO 48" AFF TO CLGA108 WHIRLPOOL X X XA129 WHIRLPOOL X X XB112 OFF SHOWER X X XB113 OFF SHOWER X X XB121 STAFF TOILET X X XB134 F REST ROOM X X XB135 M REST ROOM X X XC123 EMP TOILET X X XC131 TOILET X X XC134 TOILET X X XC135 LAUNDRY XC145 LAVATORY X X XC146 SHOWER X X XC150 REST ROOM X X XD109 TOILET X X XD111 TOILET X X XD113 TOIL/CHNG X X XD122 TOIL/CHNG X X XD123 TOIL/CHNG X X XD127 TOIL/CHNG X X XD128 TOIL/CHNG X X XE119 TOIL/CHNG X X XE120 TOIL/CHNG X X XF110 STAFF RESTRM X X XF116 M REST ROOM X X XF117 F REST ROOM X X XF119 F REST ROOM X X XF120 M REST ROOM X X XF126 STAFF RESTRM X X XF155 WC X X XF157 STAFF TOILET X X XF168 TOILET X X XF172 TOILET X X XF182 STAFF TOILET X X XF185A PATIENT TOIL X X XF185B PATIENT TOIL X X XF196A TOILET X X XF196B TOILET X X XF203 STAFF TOILET X X XF206 F REST ROOM X X XF207 M REST ROOM X X XF214 STAFF RESTRM X X XF215 STAFF RESTRM X X XF217 M REST ROOM X X XF218 F REST ROOM X X XF222 STAFF TOILET X X XF227 REST ROOM X X XF303 STAFF RESTRM X X XF306 F REST ROOM X X XF307 M REST ROOM X X XF314 STAFF X X XF315 STAFF X X XF317 M REST ROOM X X XF318 F REST ROOM X X XF322 STAFF RESTRM X X XG104 TOILET X X XG113 TOILET X X XG150 TOILET X X XG153 TOILET X X XH101 TICKETS XH102 CONCESSIONS XH103 TOILET X XH104 MALE LOCKER XH105 SHOWER X X XH106 TOILET XH108 F REST ROOM XH109 SHOWER X X XH110 FEMALE LOCKER XH111 TOILET X

QUARRY TILE BASE AND FLOOR AS INDICATED IN FINISH SCHEDULE.

8 X 8 GLAZEDWALL TILE

FLOOR BASE

END OF SECTION 09310 09300-12

Page 89: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

OX

ON

HIL

L H

IGH

SC

HO

OL

REVISONS:

INTERIOR PLAN

BID SET

A-958

0600COMM. NO.:

06/15/2011DATE:

PRIN

CE

GEO

RGE'

S C

OU

NTY

BO

ARD

OF

EDU

CA

TIO

N

PRIN

CE

GEO

RGE'

S C

OU

NTY

, MA

RYLA

ND

& ELEVATIONSMISC. SPACES

Professional Certification:I certify that these documents were

prepared or approved by me, and that Iam a duly licensed Architect under the

laws of the State of Maryland,license number 3650,

expiration date 3/24/12.

A-958A

PLAN: HEALTH RM (RES) D-108, SPEECH D-110, INSTRUCTIONAL KITCHEN D-122 & CLASSRM(RES) D-114SCALE:1/4" = 1'

0 2 4 8

3

A-958

ELEV: CLASSRM (RES) D-114SCALE:1/4" = 1'

0 2 4 8

E

A-958

ELEV: CLASSRM (RES) D-129SCALE:1/4" = 1'

0 2 4 8

B

A-958

PLAN: CLASSRM'S (RES) D-125, D-129 & LAUNDRY D-126SCALE:1/4" = 1'

0 2 4 8

2

A-958

A-958 CPLAN: OT/PT/MOVE RM D-119SCALE:1/4" = 1'

0 2 4 8

4

A-958

CW

-B24

(R)

AP-001

CW

-W36

CW

-B24

(L)

CW

-W24

(L)

CW

-B30

(S)

CW

-B30

(S)

CW

-W24

x24(

R)

AP-006KITCHENETTE/TEACHER'S LOUNGE

F-213

F-216F-214

STAFFREST FM

F-215

STAFFREST FM CLEAR

AP-

00

1

AP-

00

6

EC

TB 4X8

EC

ELEV: KITCHENETTE/TEACHERS LOUNGE F-213 & F-313SCALE:1/4" = 1'

0 2 4 8

A

A-958

LAUNDRY

D-126

T/CHNG RM

D-127

CLASSROOM (RES)

D-125CLASSROOM (RES)

D-129

T/CHNG RM

D-128

CORRIDOR LOCKERS (TYP)

CHCH

EC AW

MIR

-1

TB 4X8

CW-001 CW-001 CW-001 CW-001

CW-0

02C

W-0

02

CH CH

EC

AW

MIR

-1

TB 4X8

CW-001 CW-001 CW-001

CW-0

02C

W-0

02

CW-001

EC

EC

AP-003

L-001 (55)EC

TB 4

X8

CW-003CW-003

CW-0

03

CW-0

03

AP-004

SPEECH

D-110

INSTRUCTIONAL KIT

D-112

HEALTH RM (RSE)

D-108

CORRIDOR

TOILET

D-109

TOILET/CHANGING

RM

D-113

CLASSROOM (RES)

D-114

TOILET

D-111

MB 4X20 TB 4X8TB 4X8

TB 4

X8

MB

4X8

EC

AW

MIR

-1

TB 4X8

AP-

00

8

AP-

00

1

AP-

00

2

AP-005

MB

4X8

MB

4X8

EC

EC

CHCH

CW-001

EC

AW

MIR

-1

TB 4X6

CW-0

02C

W-0

02

CW-001CW-001CW-001

AP-

00

1

TB 4X6

EC

L-001 (9)L-001 (43)

TB 4

X8

TB 4X6

CW-0

03C

W-0

03

CW-0

02C

W-0

02

CW-0

03

6

OT/PT/MOVE RM

D-119

UP

EXER

CIS

E M

ATST

ACK

OF

4

THER. BALL

MA

TM

AT

MA

TM

AT

CH

CH

TB 4

X6

CW-002

EC

L-001 (11)

PLAN: KITCHENETTE/TEACHERS LOUNGE F-213 & F-313SCALE:1/4" = 1'

0 2 4 8

1

A-958

CW

-W24

(L)

CW

-W36

EC

CW-002

CW-0

03 CW-002

CW-0

03

CW

-B30

(S)

CW

-B30

(S)

CW

-W30

(S)

CW

-W30

CW

-B12

(D)

CW

-W12

(R)

Classrm D-129

EC

CW-002 CW-002

CW

-B30

(S)

CW

-B30

(S)

CW

-W30

(S)

CW

-W30

CW

-B12

(D)

CW

-W12

(R)

TB 4'X8'

Classrm D-125 ELEV: CLASSRM (RES) D-125SCALE:1/4" = 1'

0 2 4 8

C

A-958

CW-002 CW-002

CW

-B30

(S)

CW

-B30

(S)

CW

-W30

(S)

CW

-W30

CW

-B12

(D)

CW

-W12

(R)

TB 4'X6'

CW-0

03

Classrm D-114

AW

CW

-B30

(S)

CW

-B30

(S)

CW

-W30

(S)

CW

-W30

LaundryELEV: LAUNDRY D-126SCALE:1/4" = 1'

0 2 4 8

D

A-958

CW

-B30

(S)

CW

-W30

(S)

CW

-BC

21(L

)

CW

-BC

21(R

)C

W-W

21(R

)

CW

-W21

(L)

Speech

CW

-B30

(S)

CW

-W30

(S)

AP-001

CW

-BC

21(L

)C

W-W

21(L

)

instructional Kit

CW

-B30

(S)

CW

-B30

(S)

CW

-B36

CW

-B36

CW

-B12

(D)

CW

-B12

(D)

CW

-W12

(R)

CW

-W30

(S)

CW

-W30

(S)

CW

-W36

CW

-W36

CW

-W12

(L)

CW

-W12

(L)

instructional Kit

AP-0

08AP

-002

AC

W-W

3014

instructional Kit

CW

-B24

(R)

CW

-B24

(L)

CW

-B36

CW

-W36

CW

-W24

(L)

CW

-W36

GYM TICKETS

LAUNDRY

B-143

UNIFORM STOR

B-145

PASSAGE

B-144AP-004A

AP-003A

PROVIDE 8' LONG 3 5/8" STUD PARTITIONFOR BACK TO BACK SHELVES

SHELF W/ ROD (TYPICAL) -SEEDETAIL THIS SHEET

ELEV: SPEECH D-110SCALE:1/4" = 1'

0 2 4 8

F

A-958

ELEV: INSTRUCTIONAL KITCHEN D-112SCALE:1/4" = 1'

0 2 4 8

H

A-958

ELEV: HEALTH RM (RES) D-108SCALE:1/4" = 1'

0 2 4 8

J

A-958

ELEV: INSTRUCTIONAL KITCHEN D-112SCALE:1/4" = 1'

0 2 4 8

I

A-958

PLAN: LAUNDRY B-143 & UNIFORM STG B-145SCALE:1/4" = 1'

0 2 4 8

5

A-958

CW

-B30

(S)

CW

-W30

(S)

ot/pt/move

CW

-W24

(R)

CW

-BC

24(R

)

ELEV: OT/PT/MOVE RM D-119SCALE:1/4" = 1'

0 2 4 8

GA-958

CW-B36

CW-B36

CW-B30(S)

CW-W

36

CW-W

36

CW-W

30(S)

AP-

004

AP-004

AP-

003

AP-300A

SHELF & ROD

ELEV: LAUNDRY B-143SCALE:1/4" = 1'

0 2 4 8

K

A-958

2'-1

0"

4'-0

"

4'-0" 1'-2"

CW-005

5'-6

" AFF

1'-6"

3/4" PLYWD SHELVING W/HARDWD NOSING

SHEL158-WH, CLOSET SHELF & ROD SUPPORT BRACKET (CLOSETBAY.COM)@ 4'-0" O.C.

SHELF W/ ROD (TYP.)

HEALTH CLASS/LAB

D-209

UP

L-001 (8)

EC

SE

TB 4

X6

MB

4X20

TB 4

X4

TB 4

X20

PS-8

CW-002CW-001 CW-001 CW-001

MB 4X8 AW

ECCW-003CW-003

PLAN: HEALTH CLASS/LAB D-209SCALE:1/4" = 1'

0 2 4 8

6

A-958

CW-002

CW-0

03

CW-0

03

CW-0

01

CW-0

01

CW-0

01

CW-BC21(R)

CW-B30(S)

CW-B30(S)

CW-W

30(S)

CW-W

21(R)

CW-W

30

AW

EC

MB 4'X8'

ELEV: HEALTH CLASS/LAB D-209SCALE:1/4" = 1'

0 2 4 8

L

A-958

PENCIL SHARPNER (NIC)

4"X4"X1" HARDWOOD BLOCKWITH 1/4" BEVELED EDGES

3'-6

" AFF

AW-1

A-958D

A-958B

A-958

L

A-958 E

A-958

H

IA-958

F

A-958J

A-958 G

A-958K

MISC. DETAILS (SCALE 3/8" = 1'-0")

CLASSRM'S (RES) D-121 & D-124 SIMILAR

3ADDENDUM #307/26/2011

ADDENDUM DRAWING AD3-01

SHEET A-958 ADDED TO BID SET 3

Page 90: ADDENDUM #3 - HESS · 2014-08-01 · Section 00210 – BID FORM a. Replace. ... column 3N west to W12x26 steel beam to read "W10x15". ... asphalt cement index is currently $630.00

OX

ON

HIL

L H

IGH

SC

HO

OL

REVISONS:

BID SET

A-976

0600COMM. NO.:

06/15/2011DATE:

PRIN

CE

GEO

RGE'

S C

OU

NTY

BO

ARD

OF

EDU

CA

TIO

N

PRIN

CE

GEO

RGE'

S C

OU

NTY

, MA

RYLA

ND

LOBBY/PREFUNCTION

INTERIORELEVATIONS

Professional Certification:I certify that these documents were

prepared or approved by me, and that Iam a duly licensed Architect under the

laws of the State of Maryland,license number 3650,

expiration date 3/24/12.

A U D I T O R I U MA U D I T O R I U M

12" ALUMINUM LETTERS12" ALUMINUM LETTERS

GRANITE BENCH (SEE G/A-975)

GRANITE BENCH (SEE G/A-975)

IGF-C (3 COURSES)

IGF-C (2 COURSES)IGF-C (2 COURSES)IGF-C (2 COURSES)IGF-C (2 COURSES)IGF-A (4 COURSES)

IGF-A IGF-A IGF-A

IGF-AIGF-A

LOBBY/PREFUNCTION NORTH INTERIOR ELEVATIONScale: 1/8" = 1'-0"

1

A-976

LOBBY/PREFUNCTION NORTH INTERIOR ELEVATIONScale: 1/8" = 1'-0"

1

A-976

T H E A T E R

12" ALUMINUM LETTERS

IGF-BIGF-A (4 COURSES)

IGF-C (3 COURSES)

IGF-C (2 COURSES)

EWCEWCEWC EWC

DISPLAY CASE (SEE H/A-975)

LOBBY/PREFUNCTION SOUTH INTERIOR ELEVATIONScale: 1/8" = 1'-0"

2

A-976

INTERIOR MATERIAL KEYMASONRY:IGF-A - 8" X 16" TRENWYTH/PRAIRIE STONE "DOVER GREY" GROUND-FACE CMUIGF-B - 8" X 16" TRENWYTH/PRAIRIE STONE "NATURAL-A" GROUND-FACED CMUIGF-C - 8" X 16" TRENWYTH/PRAIRIE STONE "BUTTERSCOTCH" GROUND-FACE CMU

CONTINUOUS WIRE MOLD FOR CABLE

3/4" x 3-1/2" x 28" HI PLYWOOD LEG SUPPORT@ 3'-0" 0.C.

4"X 6" CUT OUT CABLEPORT

30"

3" CABLE ACCESS GROMMETS 2 PER STATION TYP.

2'-6"2"

5/8" 5/8" 3'-0" O.C. (TYP.)

1 1/4" PLYWOOD LEG

3" GROMMET HOLES

EDGE OFCOUNTER

WALL

3/4" x 3" CONTINUOUSSTRIP OF PLYWOODGLUED TO BOTTOM OF COUNTER

3/4" PLYWOOD COVERED W/P.LAM. ONALL EXPOSED SURFACES

3/4" X 12" CONTINUOUSPLYWOOD STRIPFOR FUTUREKEYBOARD

3"

WALL

RUBBER BASE AS SCHEDULED

1"16"

1 1/2" CONTINUOUS PVC EDGING

1-1/4" PLYWOOD LEG WITH P.LAM.ON EXPOSED SURFACES 3'-0" O.C. (TYP)

2'-0

"

MIN. 8" DEEPCABLE TROUGHBETWEEN SUPPORTS

3/4"x 6" PLYWOOD LEDGERBETWEEN SUPPORTS

3/4" x 12" CONTINUOUSSTRIP OF PLYWOODALONG COUNTER EDGEFOR KEYBOARD

3/4" x 3" x 28" HIPLYWOOD LEG SUPPORT

3/4" x 6" CONTINUOUSPLYWOOD LEDGER

28 1

/2"

1 1/

2"

3" X 3" X 5/16"STL ANGLESPANNING BETWEEN TWOBEAMS & WELDED TO TOP & BOTTOM

3" IPS STL PIPE X LENGTH AS REQUIRED, WELDED TOANGLES

2" WIDE ACCESS CUTOUT

1/2" X 4" STL PLATE WITH9/16" HOLE CENTERED

1/2" X 4" LONG FORGED STLEYE-BOLT W/ NUTS & LOCKWASHERS

METAL ESCUTCHEON

LAY-IN CEILING

SAFETY ROTATION DEVICESOUTHPAW ENTERPRISES, INC.EYE BOLT MODEL 7000-1SAFETY SNAP MODEL 100SAFETY ROTATION DEVICEMODEL 2000

CONC SLAB ON MET'L DECK

DETAIL @ CEILING HOOK/SUPPORTScale: 3/4" = 1'-0"

B

A-976

3ADDENDUM #307/26/2011

ADDENDUM DRAWING AD3-02

DETAILS A & B ADDED3

CONTINUOUS COUNTER DETAILScale: 3/4" = 1'-0"

A

A-976