Activity Benchma Task Task ID Approx. Duration Rehoming 15min/site Site Creation 30min Software Upgrade BTS 10min BSC 480min RNC 480min PAT BTS 240min BSC 120hrs RNC 120hrs Optimization IWO 15min IWO- Other changes

Upload: tongaimutengwa5194

Post on 27-Jan-2016

212 views

Category:

Documents


0 download

DESCRIPTION

AcB

TRANSCRIPT

Page 1: Activity Benchmarks Access

Activity BenchmarksTask Task ID Approx. Duration Prerequisites

Rehoming 15min/site

Site Creation 30min

Software Upgrade

BTS 10min

BSC 480min

RNC 480min

PATBTS 240min site integrated

BSC 120hrs

RNC 120hrs

Optimization IWO 15min flawless DTIWO- Other changes

Site creation, prerouting/crossconnections

RNP+TNP IWOs, site deployment, site creation DTs,neighbour relations DTs (Geran, UTRAN, E-GERAN, E-UTRAN)

site configuration backup, Faults log

OMP backup, OMM backup, Setting OMP boot mode, logservice deployment, export current Network plan data, export current list of alarms

Installation & hardware configuration

Installation & hardware configuration