acoustic installation procedure

6
Fresh Air & Hot Air Attenuators Sheet on Fresh Air Attenuators Elem Procedure of Isntallation of Fresh & HOT Air Attenuators Step 1: Suitable Size Louver Box is made with Steel Channels.and anchored to wall and Steel Frame Work to House Attenuators-Louver Box. Step 2: Tilted Horzontal Angles are welded within the Louver Box Inside Walls. At a pitch of 100 mm Step 3: The attenuators of 100 mm thicknes are inserted in the channel slot within the Louver Box. Step 4: The Louver element locked by welding angle on the external border of the louver Box. Step 5: MS Sheet is reveted on the outer side of the BOX.

Upload: mazumdarsatyajit

Post on 12-Jan-2016

226 views

Category:

Documents


0 download

DESCRIPTION

Acoustic Works for DG Set

TRANSCRIPT

Page 1: Acoustic Installation Procedure

Fresh Air & Hot Air Attenuators

Sheet on the Louver BOX.

Fresh Air Attenuators Elements

Procedure of Isntallation of Fresh & HOT Air Attenuators

Step 1: Suitable Size Louver Box is made with Steel Channels.and anchored to wall and ground. Steel Frame Work to House Attenuators-Louver Box.

Step 2: Tilted Horzontal Angles are welded within the Louver Box Inside Walls. At a pitch of 100 mm

Step 3: The attenuators of 100 mm thicknes are inserted in the channel slot within the Louver Box.

Step 4: The Louver element locked by welding angle on the external border of the louver Box.

Step 5: MS Sheet is reveted on the outer side of the BOX.

Page 2: Acoustic Installation Procedure

Hot Air Ducting for Radiator

Steel Frame Work

MS Sheet

Inter Connecting Canvas

Procedure Hot air Inter connection with Radiator

Step 1: Suitable Size MS steel Frames are made with the requisite opening for Radiator

Step 2: MS sheet is revetted on the steel frame.

Step 3: Radiator and the framework is connected by way of Canvas

Page 3: Acoustic Installation Procedure

Hot Air Rain Protection Louvers

Single Leaf Acoustic Hinged Doors

Rain Protection Louvers

Procedure for rain Protection Louvers Installation Steel Frame Work

Step 1: Suitable Size MS steel Frames are made fixed on One End of Hot Air Louvers

Page 4: Acoustic Installation Procedure

Step 2: Rain Protection Elements are revetted on these frames