accelerated implementation approach of project management processes in smes electronic resourceluis...

Upload: henrique-napoles

Post on 03-Jun-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    1/10

    2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 1

    Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy

    Accelerated Implementation Approach of Project Management Processes in SMEs

    Lus Cabezas Castillo, Antonio de Amescua Seco, Diana M. Vsquez B

    Carlos III Madrid University

    Abstract

    Effective Project Management is very important for those SMEs that want to compete with other

    companies in the global market. Those SMEs working with projects could gain competitive advantage

    using Earned Value Management (EVM) technique. Nevertheless the SMEs cannot afford to spend a lot

    of time and money in the process of implementing this technique in their companies. It is shown here an

    accelerated approach that could help in the implementation of the EVM technique in Small Settings. This

    is achieved integrating the IDEAL (McFeeley, 1996) model cycle, and practices recommended for EVM

    implementation by the PMI in their standards (PMI, 2008) (PMI, 2005). As recommended by CMMI level

    3 (defined process) it has identified phases, activities, roles, inputs and outputs, work products and

    measurements needed to carry out the implementation. The resulting steps have been simplified taking

    into consideration the Small Setting constraints. The process has been validated through case studies and

    surveys in four projects of two very different organizations, measuring different parameters related toprocess improvement. A defined process (with reduced complexity) and PMO are key factors that help

    reducing EVM implementation money an time.

    IntroductionThe objective

    Earned Value Management (EVM) has proven itself to be one of the most effective performance

    measurement and feedback tools for managing projects (PMI, 2005). EVM usage at a global level shows

    a relatively slow, but steady growth, both in the public and private sectors. A higher growth could be

    expected, given the simplicity of the theoretical base and the benefits it produces. It is important to note

    that EVM is a technique recommended by the most authorised management practitioners in the world and

    by prestigious institutions as the PMI, Project Management Institute.

    Some of the processes important to improve are those related with Project Management.A Guide to the

    Project Management Body of Knowledge (PMBOK Guide) 4th Edition (PMI, 2008) points out 42

    processes distributed in a matrix of five process groups and nine knowledge areas. Every process has

    inputs, tolls and techniques, and outputs. Perhaps the most important tool and technique is EVM (PMI,

    2005), Earned Value Management, as it requires to perform a good deal of the best practices

    recommended. This has been the reason for choosing the implementation of EVM as objective for the

    experimentation.

    Organization of the paper: First there is a definition of some terms used. It continues with a description of

    the experimentation method used, the case studies and the survey. Finally there is a resume of

    conclusions. The experience is carried out under the scope of Software Process Improvement for SmallSettings in the University Carlos III of Madrid.

    The Small Settings picture

    In this work it has been adopted the ESI (SEI, 2006) definition for Small Setting. It considers as such:

    small businesses with fewer than 100 people

  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    2/10

    2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 2

    Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy

    small organizations, within a larger organization, with fewer than 50 people

    small projects with fewer than 20 people

    Think small first

    How Do You Eat An Elephant? One Bite at a Time (Hogan, 2000), or as one International Process

    Research Consortium - IPRC sponsor put it, "all improvement happens through small groups."

    Both the implementation cost and time of actual SPI CMMI, Project Management processes, or just

    EVM, are hard items to be handled by most companies in southern Europe, especially when referring to

    the Small Settings.

    Carlos III University of Madrid is deeply involved in Software Process Improvement, working in close

    collaboration with leading SPI Spanish companies like Zonnect Redes de Ingeniera (www.zonnect.com).

    The objective of this research is to apply proven methodologies for the small setting, as part of an overall

    strategy that finally helps also the big ones: Think small first, eat an elephant one bite at a time.

    The orientation of Carlos III research in this field is taken from:

    The policy of the EU through the Framework Programs that deeply promotes R&D in SMEs.

    The recommendation and results of the SEI IPRC Project Charter that is promoting the

    Improvement of Processes in Small Settings (IPSS), planned to start October 1, 2006.

    The best practices recommended by the PMI set of standards.

    The accumulated experience and results of the research group.

    This research is oriented to provide approaches, tools, techniques, and guidance for applying

    methodology and best practices in Small Settings both for Process Improvement and Project

    Management.

    The IDEAL model is being considered a good guidance for all organizations, but the complexity of the

    steps/activities recommended is a burden for Small Settings that, generally, do not the money, resources

    and material needed. To any prescribed IDEAL step it has been applied a filter, using expert judgement

    analysis in order to decide whether the step could be omitted or not in a Small Setting scenario.

    Organization of the paper

    First there is a definition of terms, with same examples of factors found in projects. It continues with a

    description of the method used, followed by some facts on the validation method used and the actual state

    of the research. Finally there is a resume of conclusions.

    Concepts and Definitions

    Definitions

    Some concepts used in this work are:

    The effect of reducing the average time and/or cost needed to deploy a practice or process.

    Acceleration

    http://www.zonnect.com/http://www.zonnect.com/http://www.zonnect.com/http://www.zonnect.com/
  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    3/10

    2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 3

    Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy

    We use SME as a synonymous of Small Setting, as defined by the (SEI, 2006), SEI (2002):

    SME

    small businesses with fewer than 100 people

    small organizations, within a larger organization, with fewer than 50 people

    small projects with fewer than 20 people

    Small setting represents more than 85% of the whole market. This is the reason why theinstitutions at any level, whether local, national or international, are very interested in giving

    these small setting the innovation and competences they need to compete in the global market.

    Here is a justification of our interest in this part of the market.

    Experimentation Methodology

    As important as the tool and technique we want to implement is the operating subject that is going to use

    it: a SME. Due to the special characteristics of an SME a special tailoring of the IDEAL model

    recommendations has been made. The process followed is the following research phases:

    First: a complete IDEAL WBS check list has been made. (Exhibit 1) This WBS isindependent of the size of the company were the improvement is going to been made

    Second: This WBS has been augmented including extra activities specially recommended by

    several authors (Exhibit 2) (PMI, 2005; Cabezas L. et al, 2007a)

    Third: It has been decided whether a particular activity in the WBS was going to be applied

    or not to a Small Setting. This has been done using Expert judgement technique. The

    chosen activities have defined in writing

    Fourth: Experiment 1. Using Expert Judgement it was selected a subset of the Small

    Setting WBS in order to measure and analyze how they contribute in the acceleration of the

    implementation process.

    o Data and Measurements carried out of four case studies in two very not similar Small

    Settings.

    o Survey

    o Analysis and results

    Fifth: Experiment 2: Using Expert Judgement it was selected a subset of Experiment 1

    WBS in order to compare, using measures and analyses, how a Small setting would perform

    in two very different scenarios (with and without a special purpose SaaS Platform with ready

    to use process embedded in it).

    o Data and Measurements carried out of four case studies in two very not similar Small

    Settings, both with and without use of a SaaS platform.o Survey

    o Analysis of results

    The research moves along a previously defined roadmap, dealing first with EVM implementation

    acceleration and second the influence of using a SaaS platform. The model is refined through iteration

    and experimentation results.

  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    4/10

    2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 4

    Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy

    Exhibit 1: A sample of IDEAL based WBS

    ACTIVITIES PROPOSED BY IDEAL SS Exp.1 ? Exp. 2 ? REASONING

    A.4.3 Pilot Potential Solutions YES YES YES Measured and analyzed

    Verify the solution in a real project in the organization. YES YES YES Measured and analyzed

    Capture lessons learned and results of pilot to refine the soluti YES YES YES Measured and analyzed

    A.P.1. Establish a Performance Measurement Baseline (PMB) YES YES YES Measured and analyzed

    A.P.1.1. Decompose scope to a manageable level YES YES YES Measured and analyzed

    A.P.1.2. Assign unambiguous management responsibility YES YES YES Measured and analyzed

    A.P.1.3. Develop a time-phased budget for each work task YES YES YES Measured and analyzed

    A.P.4.1. Select EV measurement techniques for all the ta YES YES YES Measured and analyzed

    A.P.5.1. Maintain integrity of PMB throughout the project YES YES YES Measured and analyzed

    A.P.2. Measure and analyze performance against the baseline YES YES YES Measured and analyzed

    A.P.2.1. Record resource usage during project execution YES YES YES Measured and analyzed

    A.P.2.2. Objectively measure the physical work progress YES YES YES Measured and analyzed

    A.P.2.3. Credit earned value according EV Techniques YES YES YES Measured and analyzed

    A.P.2.4. Analyze and forecast cost /schedule performance YES YES YES Measured and analyzed

    A.P.2.5. Report performance problems and /or take action YES YES YES Measured and analyzed

    A.4.4 Select Solution Providers NO NO NO Not relevant for Small Setting Exhibit 2: Activities in de WBS directly related to EVM

    Case studies, scenarios and survey

    Description of the SMEs used in the case studies:

    One SME is a very small EBCT (Science and Technological Base Company), with a total staff of 20

    people. All have high level of formal education, some are PhD degrees. Nonetheless, around 50% of them

    have only work experience in the academic world. They are under time pressure for succeeding in two

    ambitious R&D projects, with fixed deadlines. The SME was constituted one year ago, and most of the

    staff (Lawyers, Telecommunications, Industrial and Aeronautical engineers, Software Development

    engineers, Business Administration, Sociology, etc) were hired in the last six months. The end users are

    very motivated as they constitute what is understood as a Living Laboratory

    The other SME is the IT Department of an Organization belonging to a Governmental Institution. As suchis a Small Setting both because the project involves less than 20 people, and because this IT Department

    is small organization, within a larger organization, with fewer than 50 people. Nearly all are long standing

    public employees with an average of 15 years in the company, working from 8:00 to 15:00. They are not

    accustomed to work under pressure, and these projects are no exception. The subcontracting company

    carries out the biggest burden of the project, working long hours till 18:00. They work under time and

    material type of contract. The end users form a special part of the project as they are the people that

    validate the project results and usually are very slow producing the validation reports.

  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    5/10

    2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 5

    Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy

    The Case Studies are the four projects. All these projects are monitored and controlled using EVM with

    regular weekly meetings were the EVM reports supply the main performance information on the project

    progress. (Exhibit 3)

    The survey is constructed with a standard set of questions aimed to asses the project manager and sponsor

    consideration at project start, middle and end.

    PROJECT ACRONIM

    COMPANY ACRONIM

    FULL PROJECT NAME

    CONSTRAINTS

    Documentation supplie d

    to team members

    End User Team (people)

    Main Subcontractor Team

    N. of Subcontracting firms

    Own Staff Project Team

    BAC . Budget At

    Completion (man hours)

    PD -Planned Duration

    (weeks)

    Fixed Deadline Mix Project team

    (consultants and key

    users). Only

    subcontraccting project

    team is measured

    Fixe d Deadline Onl y own Staff . Cost is not

    measured, only duration

    maters

    9.286 2.533 6.964 4.555

    4 1

    Overall project vision

    Individual tasks, effort

    expected, start and

    finish dates planned

    Project WBS and

    Schedule

    Overall project vision

    Individual tasks, effort

    expected, start and

    finish dates planned

    Project WBS and Schedule

    32 19 32 17

    10 15

    6 8 6

    1

    10

    6

    3

    INA LQT INA

    LQT SUGAR Universal

    Guiding System in Close

    Environments for

    persons with visual

    deficiencies

    Phase 2 of

    Aeronavegability

    Documentation Portal

    Phase 1 of LQT Elder

    Cluster Integral Support

    Platform for the

    Independent life of

    Elder people

    FI/ISPS

    Closing/Opening/Report

    ing Modifications in SAP

    ERP

    4 6 4

    12

    SUG CAG EL1 AE2

    LQT

    8

    Exhibit 3: Summary table of Projects used in as Case Studies

    Factors, variables and measurements

    For every case study distinction is made between Factors, Variables, Measurements, Comments, and

    Indexes

    For Factor are Environmental parameters, characteristics, constraints, that characterizes a particular

    project. Some examples: budget, personnel skills, language barriers, time to finish, organization

    constraints, etc. Factors are catalogued, analyzed and documented (Heales, 2002; Kemerer, 1999;

    Khosrowpour-pour, 2005). For the sake of the experiments the factors considered are the following

    (Exhibit 4):

  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    6/10

    2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 6

    Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy

    ACRONIM DESCRIPTION

    PCO Project Cost Overrun

    RPD Real Project Duration

    F-CPI Final Cost Performance Index

    F-SPIt Final Schedule Performance Index time based

    BQ Baseline Quality (0 to 5)

    p Schedule Adherence

    CPI 1/3 Cost Performace Index at 1/3 of project Planned Duration

    CPI 2/3 Cost Performace Index 2/3 of project PD

    CPI 3/3 Cost Performace Index at 3/3 of project PD

    SPIC 1/3 Schedule Perfomance Index cost based at 1/3 project PD

    SPIC 2/3 Schedule Perfomance Index cost based at 2/3 project PD

    SPIC 3/3 Schedule Perfomance Index cost based at 3/3 project PD

    SPIT 2/3 Schedule Perfomance Index time based at 2/3 project PD

    SPIT 3/3 Schedule Perfomance Index time based at 3/3 project PD Exhibit 4: Summary of factors considered

    Variables, in the context of these experiments, are case study data that changes for whether a SaaS

    platform is used or not. They are used mainly in Experiment 2. (Exhibit 5)

    ACRONIM DESCRIPTION

    C-EVM Estimated Cost of EVM Implementation

    C-PMC Estimated Cost of Project Monitoring and Control (PMC)

    D-EVM Estimated Time needed for EVM Implementation

    D-PMC Estimated time needed for PMC

    D-EVM Real amount of Time employed for EVM implementation

    D-PMC Real amount of time employed for PMC

    C-EVM Real Cost of EVM Implementation

    C-PMC Real Cost of Project Monitoring and Control Exhibit 5: Summary of variables used

    Measurement, in the context of these experiments, is the data obtained through objective measurementsmade during the life of the project. These data are independent of the project method used for monitoring

    and control, and depend only on case study project performance. (Exhibit 6)

    Exhibit 6: Summary of measurements made

  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    7/10

    2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 7

    Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy

    Comments are explanatory information that help to understand the Case Study scenario. Indexes are

    calculated numbers that categorize the results. The indexes are normalized to 1. These indexes are used

    for experiment 2. (Exhibit 7)

    ACRONIM DESCRIPTION

    Ip Performance indicator, relationship between objectives

    reached, time employed and resources in regards an

    established plan.

    Is Satisfaction index, that measures the degree of confort

    and end user acceptance. Survey result

    Ile Leaning easiness. Consideration of end user on the

    learning of tools and techniques proposed Exhibit 7: Indexes used

    Analysis of results

    For every case study distinction is made between Factors, Variables, Measurements, Comments, and

    Indexes. Measurements and analysis has been carried out during the life cycle of the project, and the

    calculated results have been updated with every measurement made.

    First of all, it has been compared Indexes of the four study cases, obtained through surveys on the project

    manager and sponsor. The results obtained are shown in the following graphic (Exhibit 8).

    Ile

    0,40

    0,50

    0,60

    0,70

    0,80

    0,90

    1,00

    1,10

    SUG CAG EL1 AE2

    Value

    CaseStudy

    Ile start

    Ile end

    0,40

    0,50

    0,60

    0,70

    0,80

    0,90

    1,00

    1,10

    1,20

    1,30

    SUG CAG EL1 AE2

    Value

    Case Study

    IpIp start

    Ip end

    Is

    0,40

    0,50

    0,60

    0,70

    0,80

    0,90

    1,00

    1,10

    SUG CAG EL1 AE2

    Value

    CaseStudy

    Is start

    Is end

    Exhibit 8: Illustration on Indexes analysis

  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    8/10

    2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 8

    Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy

    The indexes have been calculated averaging the PM and Sponsor responses in each case study. It can be

    observed that the indexes obtain better numbers at the end of the project that at the beginning, fact that

    was in some way predictable due to the education obtained through the project life.

    Conclusions

    It has been possible to conclude, according the use of the accelerated Process used, that there is an

    increase in all the indexes (from start to end surveys). This implies that there is a positive contribution of

    the accelerated Process for Implementing EVM in all the Case Studies. One curiosity is that the Company

    (LQT) with a lot of academic knowledge behaves more positively towards the use of the agile process,

    being the governmental Small Setting (INA) with a lot of civil servants that were more reluctant to use it.

    The result shown here, are going to be double checked with further surveys.

    The conclusions reached during the experimentation can be summarizes as follows:

    1. It is good to have a Defined Process to accelerate the EVM implementation in an SME, but the

    formal processes have to go under a high simplification. The defined process is important also

    because it is a good help having beforehand in writing what has to be done.2. The success depends also of the existence of a PMO, manned at least with a part time person. This

    helps to consolidate the performed actions and provides continuity with other projects.

    3. The use of a SaaS platform introduces a further acceleration as it minimizes the time and cost of

    some of the tasks to be performed, and obliges the continuity of the periodic actions. Nevertheless

    the effect of the PMO cannot be forgotten. At least an part time PMO should be always present.

    References

    Cabezas L, Fernndez B., Amescua A., Lpez-Cortijo R, Jimnez F., Cabezas P., Lpez S. (2007a)

    EVM, Teoria, Practica e Implementacin, Instituto Nacional de Tecnica Aeroespacial, Madrid,

    Spain, November 2007

    Cabezas L., de Amescua Seco, A. & Lpez-Cortijo, R.(2007b) EVM implementation accelerator forsmall settings. PMI Global Congress EMEA. Budapest, Hungary, 2007

    Heales, J (2002, November), A model of factors affecting an information system's change in state,

    Journal of Software Maintenance: Research and Practice, 14 (6) 409-427

    Kemerer, C & Slaughter, S (1999, July)) An Empirical Approach to Studying Software Evolution,IEEE

    Transactions on Software Engineering 25(4493 - 509

    Khosrowpour-pour, M. (2002).Advanced topics in information resources management; V.4.; Hershey,

    PA: IGI Publishing.

    McFeeley, B. (1996) IDEAL:A Users Guide for Software Process Improvement. Software Engineering

    Institute (SEI) : Carnegie Mellon University Pittsburgh, Pennsylvania. CMU/DEI-96-HB-001.

    February 1996.

    PMI (2003) Organizational Project Management Maturity Model (OPM3) Knowledge Foundation.

    Newtown Square, Pennsylvania: Project Management Institute.PMI (2005) Practice Standard for Earned Value Management.Newton Square, PA: Project Management

    Institute.

    PMI (2008)A Guide to the Project Management Body of Knowledge. Fourth Edition.Newton Square,

    PA: Project Management Institute.

    SEI (2002), Capability Maturity Model Integration(CMMI SM), Version 1.2; Continuous

    Representation; CMU/SEI-2002-TR-028, Carnegie Mellon University

    SEI (2006),Improving Processes in Small Settings (IPSS), A White Paper; The International Process

    Research Consortium (IPRC), Software Engineering Institute.http://www.sei.cmu.edu

    http://www.sei.cmu.edu/http://www.sei.cmu.edu/
  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    9/10

    2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 9

    Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy

    Solomon, P.J. (2005,August) Performance-based earned value. Northrop Grumman Integrated Systems.

    Crosstalk: The Journal of Defense Software Engineering. Available at

    http://www.stsc.hill.af.mil/CrossTalk/2005/08/0508Solomon.html

    http://www.stsc.hill.af.mil/CrossTalk/2005/08/0508Solomon.htmlhttp://www.stsc.hill.af.mil/CrossTalk/2005/08/0508Solomon.htmlhttp://www.stsc.hill.af.mil/CrossTalk/2005/08/0508Solomon.html
  • 8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas

    10/10

    This material has been reproduced with the permission of the copyright owner.Unauthorized reproduction of this material is strictly prohibited. For permission to

    reproduce this material, please contact PMI or any listed author.