accelerated implementation approach of project management processes in smes electronic resourceluis...
TRANSCRIPT
-
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
1/10
2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 1
Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy
Accelerated Implementation Approach of Project Management Processes in SMEs
Lus Cabezas Castillo, Antonio de Amescua Seco, Diana M. Vsquez B
Carlos III Madrid University
Abstract
Effective Project Management is very important for those SMEs that want to compete with other
companies in the global market. Those SMEs working with projects could gain competitive advantage
using Earned Value Management (EVM) technique. Nevertheless the SMEs cannot afford to spend a lot
of time and money in the process of implementing this technique in their companies. It is shown here an
accelerated approach that could help in the implementation of the EVM technique in Small Settings. This
is achieved integrating the IDEAL (McFeeley, 1996) model cycle, and practices recommended for EVM
implementation by the PMI in their standards (PMI, 2008) (PMI, 2005). As recommended by CMMI level
3 (defined process) it has identified phases, activities, roles, inputs and outputs, work products and
measurements needed to carry out the implementation. The resulting steps have been simplified taking
into consideration the Small Setting constraints. The process has been validated through case studies and
surveys in four projects of two very different organizations, measuring different parameters related toprocess improvement. A defined process (with reduced complexity) and PMO are key factors that help
reducing EVM implementation money an time.
IntroductionThe objective
Earned Value Management (EVM) has proven itself to be one of the most effective performance
measurement and feedback tools for managing projects (PMI, 2005). EVM usage at a global level shows
a relatively slow, but steady growth, both in the public and private sectors. A higher growth could be
expected, given the simplicity of the theoretical base and the benefits it produces. It is important to note
that EVM is a technique recommended by the most authorised management practitioners in the world and
by prestigious institutions as the PMI, Project Management Institute.
Some of the processes important to improve are those related with Project Management.A Guide to the
Project Management Body of Knowledge (PMBOK Guide) 4th Edition (PMI, 2008) points out 42
processes distributed in a matrix of five process groups and nine knowledge areas. Every process has
inputs, tolls and techniques, and outputs. Perhaps the most important tool and technique is EVM (PMI,
2005), Earned Value Management, as it requires to perform a good deal of the best practices
recommended. This has been the reason for choosing the implementation of EVM as objective for the
experimentation.
Organization of the paper: First there is a definition of some terms used. It continues with a description of
the experimentation method used, the case studies and the survey. Finally there is a resume of
conclusions. The experience is carried out under the scope of Software Process Improvement for SmallSettings in the University Carlos III of Madrid.
The Small Settings picture
In this work it has been adopted the ESI (SEI, 2006) definition for Small Setting. It considers as such:
small businesses with fewer than 100 people
-
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
2/10
2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 2
Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy
small organizations, within a larger organization, with fewer than 50 people
small projects with fewer than 20 people
Think small first
How Do You Eat An Elephant? One Bite at a Time (Hogan, 2000), or as one International Process
Research Consortium - IPRC sponsor put it, "all improvement happens through small groups."
Both the implementation cost and time of actual SPI CMMI, Project Management processes, or just
EVM, are hard items to be handled by most companies in southern Europe, especially when referring to
the Small Settings.
Carlos III University of Madrid is deeply involved in Software Process Improvement, working in close
collaboration with leading SPI Spanish companies like Zonnect Redes de Ingeniera (www.zonnect.com).
The objective of this research is to apply proven methodologies for the small setting, as part of an overall
strategy that finally helps also the big ones: Think small first, eat an elephant one bite at a time.
The orientation of Carlos III research in this field is taken from:
The policy of the EU through the Framework Programs that deeply promotes R&D in SMEs.
The recommendation and results of the SEI IPRC Project Charter that is promoting the
Improvement of Processes in Small Settings (IPSS), planned to start October 1, 2006.
The best practices recommended by the PMI set of standards.
The accumulated experience and results of the research group.
This research is oriented to provide approaches, tools, techniques, and guidance for applying
methodology and best practices in Small Settings both for Process Improvement and Project
Management.
The IDEAL model is being considered a good guidance for all organizations, but the complexity of the
steps/activities recommended is a burden for Small Settings that, generally, do not the money, resources
and material needed. To any prescribed IDEAL step it has been applied a filter, using expert judgement
analysis in order to decide whether the step could be omitted or not in a Small Setting scenario.
Organization of the paper
First there is a definition of terms, with same examples of factors found in projects. It continues with a
description of the method used, followed by some facts on the validation method used and the actual state
of the research. Finally there is a resume of conclusions.
Concepts and Definitions
Definitions
Some concepts used in this work are:
The effect of reducing the average time and/or cost needed to deploy a practice or process.
Acceleration
http://www.zonnect.com/http://www.zonnect.com/http://www.zonnect.com/http://www.zonnect.com/ -
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
3/10
2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 3
Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy
We use SME as a synonymous of Small Setting, as defined by the (SEI, 2006), SEI (2002):
SME
small businesses with fewer than 100 people
small organizations, within a larger organization, with fewer than 50 people
small projects with fewer than 20 people
Small setting represents more than 85% of the whole market. This is the reason why theinstitutions at any level, whether local, national or international, are very interested in giving
these small setting the innovation and competences they need to compete in the global market.
Here is a justification of our interest in this part of the market.
Experimentation Methodology
As important as the tool and technique we want to implement is the operating subject that is going to use
it: a SME. Due to the special characteristics of an SME a special tailoring of the IDEAL model
recommendations has been made. The process followed is the following research phases:
First: a complete IDEAL WBS check list has been made. (Exhibit 1) This WBS isindependent of the size of the company were the improvement is going to been made
Second: This WBS has been augmented including extra activities specially recommended by
several authors (Exhibit 2) (PMI, 2005; Cabezas L. et al, 2007a)
Third: It has been decided whether a particular activity in the WBS was going to be applied
or not to a Small Setting. This has been done using Expert judgement technique. The
chosen activities have defined in writing
Fourth: Experiment 1. Using Expert Judgement it was selected a subset of the Small
Setting WBS in order to measure and analyze how they contribute in the acceleration of the
implementation process.
o Data and Measurements carried out of four case studies in two very not similar Small
Settings.
o Survey
o Analysis and results
Fifth: Experiment 2: Using Expert Judgement it was selected a subset of Experiment 1
WBS in order to compare, using measures and analyses, how a Small setting would perform
in two very different scenarios (with and without a special purpose SaaS Platform with ready
to use process embedded in it).
o Data and Measurements carried out of four case studies in two very not similar Small
Settings, both with and without use of a SaaS platform.o Survey
o Analysis of results
The research moves along a previously defined roadmap, dealing first with EVM implementation
acceleration and second the influence of using a SaaS platform. The model is refined through iteration
and experimentation results.
-
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
4/10
2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 4
Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy
Exhibit 1: A sample of IDEAL based WBS
ACTIVITIES PROPOSED BY IDEAL SS Exp.1 ? Exp. 2 ? REASONING
A.4.3 Pilot Potential Solutions YES YES YES Measured and analyzed
Verify the solution in a real project in the organization. YES YES YES Measured and analyzed
Capture lessons learned and results of pilot to refine the soluti YES YES YES Measured and analyzed
A.P.1. Establish a Performance Measurement Baseline (PMB) YES YES YES Measured and analyzed
A.P.1.1. Decompose scope to a manageable level YES YES YES Measured and analyzed
A.P.1.2. Assign unambiguous management responsibility YES YES YES Measured and analyzed
A.P.1.3. Develop a time-phased budget for each work task YES YES YES Measured and analyzed
A.P.4.1. Select EV measurement techniques for all the ta YES YES YES Measured and analyzed
A.P.5.1. Maintain integrity of PMB throughout the project YES YES YES Measured and analyzed
A.P.2. Measure and analyze performance against the baseline YES YES YES Measured and analyzed
A.P.2.1. Record resource usage during project execution YES YES YES Measured and analyzed
A.P.2.2. Objectively measure the physical work progress YES YES YES Measured and analyzed
A.P.2.3. Credit earned value according EV Techniques YES YES YES Measured and analyzed
A.P.2.4. Analyze and forecast cost /schedule performance YES YES YES Measured and analyzed
A.P.2.5. Report performance problems and /or take action YES YES YES Measured and analyzed
A.4.4 Select Solution Providers NO NO NO Not relevant for Small Setting Exhibit 2: Activities in de WBS directly related to EVM
Case studies, scenarios and survey
Description of the SMEs used in the case studies:
One SME is a very small EBCT (Science and Technological Base Company), with a total staff of 20
people. All have high level of formal education, some are PhD degrees. Nonetheless, around 50% of them
have only work experience in the academic world. They are under time pressure for succeeding in two
ambitious R&D projects, with fixed deadlines. The SME was constituted one year ago, and most of the
staff (Lawyers, Telecommunications, Industrial and Aeronautical engineers, Software Development
engineers, Business Administration, Sociology, etc) were hired in the last six months. The end users are
very motivated as they constitute what is understood as a Living Laboratory
The other SME is the IT Department of an Organization belonging to a Governmental Institution. As suchis a Small Setting both because the project involves less than 20 people, and because this IT Department
is small organization, within a larger organization, with fewer than 50 people. Nearly all are long standing
public employees with an average of 15 years in the company, working from 8:00 to 15:00. They are not
accustomed to work under pressure, and these projects are no exception. The subcontracting company
carries out the biggest burden of the project, working long hours till 18:00. They work under time and
material type of contract. The end users form a special part of the project as they are the people that
validate the project results and usually are very slow producing the validation reports.
-
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
5/10
2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 5
Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy
The Case Studies are the four projects. All these projects are monitored and controlled using EVM with
regular weekly meetings were the EVM reports supply the main performance information on the project
progress. (Exhibit 3)
The survey is constructed with a standard set of questions aimed to asses the project manager and sponsor
consideration at project start, middle and end.
PROJECT ACRONIM
COMPANY ACRONIM
FULL PROJECT NAME
CONSTRAINTS
Documentation supplie d
to team members
End User Team (people)
Main Subcontractor Team
N. of Subcontracting firms
Own Staff Project Team
BAC . Budget At
Completion (man hours)
PD -Planned Duration
(weeks)
Fixed Deadline Mix Project team
(consultants and key
users). Only
subcontraccting project
team is measured
Fixe d Deadline Onl y own Staff . Cost is not
measured, only duration
maters
9.286 2.533 6.964 4.555
4 1
Overall project vision
Individual tasks, effort
expected, start and
finish dates planned
Project WBS and
Schedule
Overall project vision
Individual tasks, effort
expected, start and
finish dates planned
Project WBS and Schedule
32 19 32 17
10 15
6 8 6
1
10
6
3
INA LQT INA
LQT SUGAR Universal
Guiding System in Close
Environments for
persons with visual
deficiencies
Phase 2 of
Aeronavegability
Documentation Portal
Phase 1 of LQT Elder
Cluster Integral Support
Platform for the
Independent life of
Elder people
FI/ISPS
Closing/Opening/Report
ing Modifications in SAP
ERP
4 6 4
12
SUG CAG EL1 AE2
LQT
8
Exhibit 3: Summary table of Projects used in as Case Studies
Factors, variables and measurements
For every case study distinction is made between Factors, Variables, Measurements, Comments, and
Indexes
For Factor are Environmental parameters, characteristics, constraints, that characterizes a particular
project. Some examples: budget, personnel skills, language barriers, time to finish, organization
constraints, etc. Factors are catalogued, analyzed and documented (Heales, 2002; Kemerer, 1999;
Khosrowpour-pour, 2005). For the sake of the experiments the factors considered are the following
(Exhibit 4):
-
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
6/10
2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 6
Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy
ACRONIM DESCRIPTION
PCO Project Cost Overrun
RPD Real Project Duration
F-CPI Final Cost Performance Index
F-SPIt Final Schedule Performance Index time based
BQ Baseline Quality (0 to 5)
p Schedule Adherence
CPI 1/3 Cost Performace Index at 1/3 of project Planned Duration
CPI 2/3 Cost Performace Index 2/3 of project PD
CPI 3/3 Cost Performace Index at 3/3 of project PD
SPIC 1/3 Schedule Perfomance Index cost based at 1/3 project PD
SPIC 2/3 Schedule Perfomance Index cost based at 2/3 project PD
SPIC 3/3 Schedule Perfomance Index cost based at 3/3 project PD
SPIT 2/3 Schedule Perfomance Index time based at 2/3 project PD
SPIT 3/3 Schedule Perfomance Index time based at 3/3 project PD Exhibit 4: Summary of factors considered
Variables, in the context of these experiments, are case study data that changes for whether a SaaS
platform is used or not. They are used mainly in Experiment 2. (Exhibit 5)
ACRONIM DESCRIPTION
C-EVM Estimated Cost of EVM Implementation
C-PMC Estimated Cost of Project Monitoring and Control (PMC)
D-EVM Estimated Time needed for EVM Implementation
D-PMC Estimated time needed for PMC
D-EVM Real amount of Time employed for EVM implementation
D-PMC Real amount of time employed for PMC
C-EVM Real Cost of EVM Implementation
C-PMC Real Cost of Project Monitoring and Control Exhibit 5: Summary of variables used
Measurement, in the context of these experiments, is the data obtained through objective measurementsmade during the life of the project. These data are independent of the project method used for monitoring
and control, and depend only on case study project performance. (Exhibit 6)
Exhibit 6: Summary of measurements made
-
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
7/10
2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 7
Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy
Comments are explanatory information that help to understand the Case Study scenario. Indexes are
calculated numbers that categorize the results. The indexes are normalized to 1. These indexes are used
for experiment 2. (Exhibit 7)
ACRONIM DESCRIPTION
Ip Performance indicator, relationship between objectives
reached, time employed and resources in regards an
established plan.
Is Satisfaction index, that measures the degree of confort
and end user acceptance. Survey result
Ile Leaning easiness. Consideration of end user on the
learning of tools and techniques proposed Exhibit 7: Indexes used
Analysis of results
For every case study distinction is made between Factors, Variables, Measurements, Comments, and
Indexes. Measurements and analysis has been carried out during the life cycle of the project, and the
calculated results have been updated with every measurement made.
First of all, it has been compared Indexes of the four study cases, obtained through surveys on the project
manager and sponsor. The results obtained are shown in the following graphic (Exhibit 8).
Ile
0,40
0,50
0,60
0,70
0,80
0,90
1,00
1,10
SUG CAG EL1 AE2
Value
CaseStudy
Ile start
Ile end
0,40
0,50
0,60
0,70
0,80
0,90
1,00
1,10
1,20
1,30
SUG CAG EL1 AE2
Value
Case Study
IpIp start
Ip end
Is
0,40
0,50
0,60
0,70
0,80
0,90
1,00
1,10
SUG CAG EL1 AE2
Value
CaseStudy
Is start
Is end
Exhibit 8: Illustration on Indexes analysis
-
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
8/10
2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 8
Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy
The indexes have been calculated averaging the PM and Sponsor responses in each case study. It can be
observed that the indexes obtain better numbers at the end of the project that at the beginning, fact that
was in some way predictable due to the education obtained through the project life.
Conclusions
It has been possible to conclude, according the use of the accelerated Process used, that there is an
increase in all the indexes (from start to end surveys). This implies that there is a positive contribution of
the accelerated Process for Implementing EVM in all the Case Studies. One curiosity is that the Company
(LQT) with a lot of academic knowledge behaves more positively towards the use of the agile process,
being the governmental Small Setting (INA) with a lot of civil servants that were more reluctant to use it.
The result shown here, are going to be double checked with further surveys.
The conclusions reached during the experimentation can be summarizes as follows:
1. It is good to have a Defined Process to accelerate the EVM implementation in an SME, but the
formal processes have to go under a high simplification. The defined process is important also
because it is a good help having beforehand in writing what has to be done.2. The success depends also of the existence of a PMO, manned at least with a part time person. This
helps to consolidate the performed actions and provides continuity with other projects.
3. The use of a SaaS platform introduces a further acceleration as it minimizes the time and cost of
some of the tasks to be performed, and obliges the continuity of the periodic actions. Nevertheless
the effect of the PMO cannot be forgotten. At least an part time PMO should be always present.
References
Cabezas L, Fernndez B., Amescua A., Lpez-Cortijo R, Jimnez F., Cabezas P., Lpez S. (2007a)
EVM, Teoria, Practica e Implementacin, Instituto Nacional de Tecnica Aeroespacial, Madrid,
Spain, November 2007
Cabezas L., de Amescua Seco, A. & Lpez-Cortijo, R.(2007b) EVM implementation accelerator forsmall settings. PMI Global Congress EMEA. Budapest, Hungary, 2007
Heales, J (2002, November), A model of factors affecting an information system's change in state,
Journal of Software Maintenance: Research and Practice, 14 (6) 409-427
Kemerer, C & Slaughter, S (1999, July)) An Empirical Approach to Studying Software Evolution,IEEE
Transactions on Software Engineering 25(4493 - 509
Khosrowpour-pour, M. (2002).Advanced topics in information resources management; V.4.; Hershey,
PA: IGI Publishing.
McFeeley, B. (1996) IDEAL:A Users Guide for Software Process Improvement. Software Engineering
Institute (SEI) : Carnegie Mellon University Pittsburgh, Pennsylvania. CMU/DEI-96-HB-001.
February 1996.
PMI (2003) Organizational Project Management Maturity Model (OPM3) Knowledge Foundation.
Newtown Square, Pennsylvania: Project Management Institute.PMI (2005) Practice Standard for Earned Value Management.Newton Square, PA: Project Management
Institute.
PMI (2008)A Guide to the Project Management Body of Knowledge. Fourth Edition.Newton Square,
PA: Project Management Institute.
SEI (2002), Capability Maturity Model Integration(CMMI SM), Version 1.2; Continuous
Representation; CMU/SEI-2002-TR-028, Carnegie Mellon University
SEI (2006),Improving Processes in Small Settings (IPSS), A White Paper; The International Process
Research Consortium (IPRC), Software Engineering Institute.http://www.sei.cmu.edu
http://www.sei.cmu.edu/http://www.sei.cmu.edu/ -
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
9/10
2010 L. Cabezas Castillo, A. de Amescua Seco, D. M. Vsquez B 9
Originally published as part of Proceedings PMI Global Congress 2010 Milan, Italy
Solomon, P.J. (2005,August) Performance-based earned value. Northrop Grumman Integrated Systems.
Crosstalk: The Journal of Defense Software Engineering. Available at
http://www.stsc.hill.af.mil/CrossTalk/2005/08/0508Solomon.html
http://www.stsc.hill.af.mil/CrossTalk/2005/08/0508Solomon.htmlhttp://www.stsc.hill.af.mil/CrossTalk/2005/08/0508Solomon.htmlhttp://www.stsc.hill.af.mil/CrossTalk/2005/08/0508Solomon.html -
8/11/2019 Accelerated Implementation Approach of Project Management Processes in SMEs Electronic ResourceLuis Cabezas
10/10
This material has been reproduced with the permission of the copyright owner.Unauthorized reproduction of this material is strictly prohibited. For permission to
reproduce this material, please contact PMI or any listed author.