Mechanical Electrical Design (MED), was established By Eng. Abd El Hamid Bakry in 1992, now it's considered one of the top consulting firms in Egypt and Middle East. MED is highly specialized in Electrical & Mechanical Design,Follow up and supervision.

MED concept is to provide efficiently professional Mechanical & Electrical services, with the highest standards, state of art and Effective cost construction way.

Outside Egypt, MED has carried out projects in KSA, UAE, Yemen, Qatar, Jordan, Guienia Bissau, Sudan and Rwanda and has cooperated with reputable National and international consultants, architects& management firms.

MED offers a wide range of services and covers a variety of projects with the aid of the most updated software programs in the following specialization:

• High rise buildings.• Residential complexes.• Hotels and floating hotels.• Resorts.• High-Tech office buildings.• Malls.• Factories and industrial projects.• Hospitals and health care facilities.• Universities and Educational facilities.• Museums and Mosques.• Banks.• Stadiums, clubs and sports Facilities.• District Cooling Plants.

MED MANAGING DIRECTOR

ABD EL HAMID BAKRYMechanical Electrical Design DirectorBirth Date: 1953Nationality: Egyptian

Qualifications: BSC Mechanical Engineering(1978)Faculty of EngineeringCairo University, Cairo, Egypt

Professional Member Ship:• Egyptian syndicate of Engineers.• Egypian Mechanical Engineering Society.• American Society of Heating, Refrigeration & Air conditioning (ASHRAE). • National fire protection Assocation (NFPA).• International Distric Energy Association (IDEA).

Professional Experience :

1982 to 1997, have worked as Mechanical Engineer, Senior Mechanical Engineer& Project Manager in DAR EL HANDASAH CONSULTANTS Cairo and Middle East offices in listed below projects:

• Makkah Haram Extension, Makkah ,Saudi Arabia .• Maintenance programmer for the Holy Mosques, Saudi Arabia.• Malakan water supply and storage, Saudi Arabia.• Bulk 1 Reservoir, Saudi Arabia.• Utility Culvert ventilation, Makkah, Saudi Arabia.• Improvement of tunnels in Makkah, Saudi Arabia. • Madinah Library and Exhibition Hall, Saudi Arabia.• Prophet's Mosque In Madinah, Saudi Arabia.• Technical Assistance For Makkah Committee, Saudi Arabia. • Souk AlSaghir Underpass, Makkah, Saudi Arabia.• Makkah Car-Parks, Saudi Arabia .• Automated People Mover System, Saudi Arabia .

• Water Tunnel, Makkah, Saudi Arabia.• Riyadh Sewage Treatment Plant Phase III, Saudi Arabia..• Kharj Sewage Treatment Plant , Saudi Arabia.• Dualling of Pedestrian Tunnels: Muna, Saudi Arabia.• Madinah Cental Area Redevelopment, Saudi Arabia.• Madinah Hajj StationTerminal and Central Hospital Saudi Arabia. • Mosques of Dammam, Saudi Arabia.• Supply of Irrigation water for Riyadh, Saudi Arabia..• Manakha Tunnel Extension, Madinah Saudi Arabia.• Muna Fire Fighting system, Makkah Saudi Arabia.• Subistitute Mosque, Taif, Saudi Arabia.• Madinah Hajj city and Central hospital Saudi Arabia.• Madinah Mosque Car park, Madinah, Saudi Arabia.• Utility And Service Tunnels, Makkah, Saudi Arabia. • Tunnel Modifications of Makkah, Makkah, Saudi Arabia.• King Abd EL Aziz Hospital in Hasa, Saudi Arabia.• Improvment of Jamart Bridge, Saudi Arabia.• Ground water Development and Management, Yemen.• Water Supply And Sanitation And HealthDevevelopment , Yemen.• Aden Air Port ,Yemen.• Casablanca Environmental Protection Study, Morco• Arab Pharmaceutical manufacturing company.Jordan.• King Hussien medical center, Amman, Jordan. • Bahrain Grand Mosque, Manama, Bahrain.• Government complex, Bahrain.• Maiduguri Water supply, Borno state, Nigeria.• Jos University Master Plan, Plateau state Nigeria.• Tarsus – Pozanti Tag motor way, Adna,Turkey.• Haruieh –Gaziantep Motorway, Turkey.• Multipurpose Cultural center, Istanbul,Turkey.• Beriut Central Dsitric Infrastructure ,Lebanon.• Oil Sevice Center , Angola.• Heliopoils Sheraton Cairo Egypt• Al Ashgar housing Project 6th of October Cairo, Egypt.• Shekiah Zaid Hospital , Egypt• Domiat Housing City; Egypt.• Ein El Souknah Suez, Egypt.• Hammam Military Township,Egypt.• National institute of Heart, Cairo, Egypt.• Armed Air force hospital, Cairo, Egypt.

MECHANICAL ELECTRICAL DESIGN(MED)

A) MECHANICAL WORKA.1) INFRASTRUCTURE:* DISTRICT COOLING AND DISTRICT NETWORKS.*PUMPING STATIONS.* SEWAGE NETWORKS.* WATER & FIRE FIGHTING NETWORKS..* IRRIGATION NETWORKS.* DESALINATION PLANTS.

A.2) INSIDE BUILDINGS:* HEATING, VENTILATION & AIR CONDITIONING.* PLUMBING SYSTEMS.* FIRE FIGHTING SYSTEMS.* KITCHEN EQUIPMENT DESIGN.* LAUNDRY EQUIPMENT DESIGN.* SWIMMING POOLS DESIGN.* BOILERS PUMPING STATIONS.* MEDICAL GASES.

A.3) MECHANICAL TRANSPORTATION SYSTEM:* LIFTS & DUMBWAITERS.* ESCALATORS.

B) ELECTRICAL WORKB.1) INFRASTRUCTURE:* LOW & MEDIUM VOLTAGE.* POWER DISTRIBUTION NETWORKS.* TELECOMMUNICATION & & SECURITY NETWORKS.* STREET & GREEN AREA LIGHTING.* FIELD & SPORTS LIGHTING.

B.2) INSIDE BUILDING:* POWER DISTRIBUTION.* GENERAL & DECORATIVE LIGHTING.* LOW – CURRENT SYSTEMS.* SPECIAL SYSTEMS FOR HOSPITALS & HOTELS.* COMPUTER NETWORKS.

OUR GROUP IS AROUND 80 EMPLOYEES DISTRIBUTED AS FOLLOWS:

A) Mechanical Team:

B) Electrical Team:

MANAGEMENT

Eng. Abd EL Hamid BakryManaging Director

4 Senior Mech. Eng.(Designers)

9 Senior Mech. Eng.(for site supervision)

12 Draftsmen(Auto-cad)

5 Secretaries& 3 office boys

8 Junior Mech. Eng.(Designers)

Eng. M. KManaging Director

4 Senior Elec. Eng.(Designers)

4 Senior Elec. Eng.(Designers)

8 Junior Elec. Eng.(Designers)

9 Draftsmen (Auto-CAD)

3 Secretaries& 3 office boys

1 Draftsmen (Manual)

OUTLINE OF TECHNICAL SERVICES OFFERED BY MED1. FIELD INVESTIGATION AND DATA COLLECTION.2. PRELIMINARY DESIGNS AND FEASIBILITY STUDIES.3. FUNDAMENTAL DESIGNS AND BUDGET ESTIMATES.4. FINAL CONSTRUCTION WORKING DRAWINGS.5. CALCULATION SHEETS AND COMPUTER FACILITIES.6. TENDER DOCUMENTS INCLUDING GENERAL CONDITIONS OF CONTRACTS, SPECIFICATIONS, BILL OF QUANTITIES AND COST ESTIMATES.7. VALUE ENGINEERING STUDIES.8. SUPERVISION DURING EXECUTION, MATERIAL & SHOP DRAWINGS APPROVALS.9. QUALITY ASSURANCE, SITE INSPECTION AND TESTING.10. TECHNICAL REPORTS AND RECOMMENDATIONS.11. FINAL HANDING OVER AND COMMISSIONING.

EXPERIENCE RECORD

THE FOLLOWING ARE SOME PROJECT DESIGNED BY THE OFFICE IN THE LAST 18 YEARS.

STADIUMS, CLUBS & SPORTS FACILITIES

ABIN Stadium, ABIN, Yemen, (under construction):

It is an open stadium with around 20000 spectators.The main building consists of an indoor Conference Hall for 200 persons, Offices, Cafeteria and VIP Lounge. The site accommodates another three main buildings.

Scope of work: Mechanical & Electrical Working, Drawings, Tender Documents and Site Supervision for: Sports Lighting; General & Outdoor lighting Power; Low-current systems and Score Boards system; Sanitary design; inside & outside buildings as well as systems for the stadium areas; V.I.P lounges and landscape works; Heating; Ventilation And Air conditioning system and Central utility plants. (E/M Budget is around 40 Million U$ Dollar).

STADIUMS, CLUBS & SPORTS FACILITIES

22nd Of May Stadium, Adan, Yemen, (Under construction):

It is an open stadium with around 26000 spectators. The main building contains indoor Conference Hall for 200 persons, Offices, Cafeteria and VIP Lounge, The site accommodate another three main buildings.

Scope of work: Working Drawings, Tender Documents and Site Supervision for: Sports Lighting; General & Outdoor lighting Power; Low-current systems and Score Boards system also including Sanitary design inside & outside buildings as well as systems for the stadium areas; V.I.P lounges and landscape work Heating; Ventilation And Air conditioning system and Central utility plants. (E/M Budget is around 40 Million U$ Dollar)

1

Cairo Stadium Equestrian, Nasr City, Cairo, Egypt:It is an open stadium for Horse Jumping sport, with around 5000 spectator seats, the main building has an indoor Conference Hall for 200 persons, Offices, Cafeteria and VIP Lounge. The site accommodates another three main buildings (Referees, Lockers and Stables buildings). The total connected power is 3 MVA.

Scope of work: Mechanical & Electrical Working, Drawings, Tender Documents and Site Supervision for: Sports Lighting; General & Outdoor lighting Power; Low-current systems and Score Boards system; Sanitary design inside & outside buildings as well as HVAC system for V.I.P lounges (E/M Budget is around 12 Million L.E)

Cairo Stadium Aelodromem, Nasr City, Cairo, Egypt:It is an open stadium for Bicycle Racing sport and some other open play ground sports in the center, with around 8,000 spectator. The main building is two floors containing Offices, Cafeteria, Meeting Rooms and VIP Lounge. The total connected power is 3 MVA.

Scope of work is Mechanical & Electrical Working , Drawings, Tender Documents and Site Supervision for: Sports Lighting; General Outdoor Lighting; Power; Low-Current Systems and Score Boards System; Sanitary design inside & outside buildings as well as HVAC system for V.I.P lounges. (E/M Budget is around 13.5 Million L.E).

El Mansoura City – Social Club, EL Mansoura City – Egypt: It is a Social Club consists of a main Social Building, Restaurants, Gymnasium, Swimming pools, Sports fields and Green Areas. The total connected power is around 2 MVA.

Scope of work: Mechanical & Electrical Working, Drawings, Tender Documents for Electrical, Sanitary and HVAC system (E/M. Budget is around 6 Million L.E)

STADIUMS, CLUBS & SPORTS FACILITIES

2

FACTORIES

FACTORIES

INTERNATIONAL METALS FACTORY, 10th Of Ramadan, Egypt:

It is a production plant of copper cables.

Scope of work: includes the design and Site supervision of electrical , low current , heating, ventilation and air conditioning, industrial cooling water to the production equipment

compressed air system, plumbing, fire fighting systems and external networks. Project includes plant rooms, production building and storage building.

Arabian Ceramics Factory, Saudi Arabia:

It is a new ceramic factory over an area of 300000m2 and having 9 production ceramic production lines.

Scope of work: working drawings & Tender documents and site supervsion for all MEP works with total cost 200,000,000 S.R.

Chipsy Factory Extension (6th of October City), Egypt:

It is an extension to food production factory in 6th of October City consists of welfare building, TC and PC lines and 4 floors administration building

Scope of work: MEP , HVAC, plumbing, fire fighting works and Electrical works. Total cooling load of the project is 300T.R. and 3 MVA.

3

New Medical Supplies, Badr City, Egypt:

It is a plant for manufacturing of pharmaceutical products and all related accessories. The built up area is around 8,000 m2 including a separate 4 floors administration building.

Scope of work: The preparation of working Drawings, Tender Documents and site Supervision for heating, ventilation, air conditioning and motor control system.

FACTORIES

The total connected power is 8 MVA and the project is centrally air conditioned from an air cooled chiller plant 1400 R.T.

Scope of work: Mechanical Works Shop and as - Built Drawings, for heating, ventilation, air conditioning , Sanitary & Fire Fighting Systems.

European Egyptian Pharmaceutical Company-Amriya, Alexandria, Egypt:

It is a pharmaceutical factory consisting of the following buildings: Production building (Two floors each around 8000 m2), Administration building (Four floors each around 1300 m2), Social building (Two floors each around 800 m2) Service building (Two floors each around 400 m2), Substation building (Two floors each around 1000 m2), Mosque (Around 140 m2).

National Pipe Company (N.P.C) Factory (Badr City), Egypt:

It is considered a major factory for production of prestressed concrete pipes (700-2600mm). The total connected load is 3.5 MVA.

Scope of work: Design And Site supervision of Electrical & Mechanical system of the project.

4

FACTORIES

Kaolin Factory, Sinai, Egypt:

It is a Kaolin producing plant for Kaolin bearing silica sand raw material for ceramic industry. The total connected power is 3MVA .Scope of work: Mechanical system, including factory building and power plant station.

Yarning and Callus Factory, Gesr EL Suez Road, Egypt:

The project includes the design of heating, ventilation and air conditioning installations; electrical motor control systems; building management system and external networks;

plumbing and fire fighting systems and external networks. It also includes knitting production farm containing 20 machines; Sewing Halls; Printing areas; Dyeing plant; spin and textile storage areas; Administration and storage buildings. Plant capacity is 1000 TR.

Cairo Cotton, 10th of Ramadan, Egypt:

The project includes the design of heating, ventilation and air conditioning installations, plumbing and fire fighting systems, electrical motor control systems, building management system and external networks.

Also plant rooms, Knitting, production farm containing a 100 machines, Sewing Halls, Printing areas, Dyeing plant ,spin and textile storage areas, Administration building and storage building for Cotton and fabrics. Plant capacity is 4000 TR(E/M Budget is around 160 Million Egyptian pounds).

5

FACTORIES

Daewoo Egyptian Car Making Plant at 6th. Of October City:

It is a plant for DAEWOO cars manufacturing with a built up area around 50000 m2 including 2 separate administration building factory bays and a substation for Transformers. The project is equipped with L.P.G station; Steam generation plant; compressed air generation plant; industrial and deionized water treatment plants.

Scope of work: The preparation of working Drawings, Tender Documents and site Supervision of mechanical system.

Egyptian Can Making Plant at 6th. Of October City:

It is a plant for cans manufacturing with a built up area around 25000 m3 including 2 separate administration building floors and a substation for 6 MVA Transformers. The project is equipped with L.P.G station. Scope of work: the preparation of working Drawings, Tender Documents and site

Ameco Medical, Badr City, Egypt:

It is a plant for manufacturing of Needle syringe products and all related accessories. The built up area is around 10,000 m3 including 4 separate administration building floors.

Scope of work: the preparation of working Drawings, Tender Documents and site Supervision for HVAC system.

Supervision for HVAC system computerized operated system.

6

FACTORIES

Factory 81 –Cairo Egypt:

The project includes the design and site supervision of installations of MEP works; heating, ventilation and air conditioning; plumbing and fire fighting systems and external networks; plant rooms; production building and storage building.

Link Misr New Factory 10th of Ramadan City, Egypt:

The project is a metal production factory of around 2500m2 and three floors administration building. Scope of work: Mechanical Works

Egyptian LNG Factory (EDCO 1) Alexandria Egypt:

Design work for heating, ventilation, air conditioning System, Plumbing and Fire Fighting System including the coordination with intenational process firms.The project consists of three buildings as following:* Maintenance Building.* Control Building. * Warehouse Building.

Egyptian LNG Factory (EDCO 2) – Alexandria Egypt:Design work for HVAC System, Plumbing System and Fire Fighting System.The project consists of three buildings as follows:-

* Compressor Substation Building. * Main Substation Building. * Propane Condenser Substation Building.

7

FACTORIES

Suez Steel Factory, Suez, Egypt:Project of total built up area of 150000 m2. it includes the preparation of sound calculation; fire fighting; MEP, electrical fire alarms; plumbing and air conditioning systems for 24 industrial buildings for steel manufacturing plant.

Hi Farm Factory For Medical Applications, Cairo, Egypt:Scope of work: Plumbing and Air conditioning system for a pharmaceticalmanufacturing plant.

Alexandria Carpet Factory, Alexandria, Egypt:It is a carpet production factory of 2000 m2 built up area.Scope of work: Air Conditioning System.

ABI Pharmaceutical Company 10Th Of Ramadan, Egypt:A medical supplies equipment factory over a built- up area of 3000 m2. The total connected power is 1 MVA with 400 T.R sir cooled chiller plant.

Factory 18, Cairo, Egypt:The project includes the design and installations of MEP works; Heating; ventilation and air conditioning; plumbing and fire fighting systems and external networks; plant rooms; production building and storage building.

ABB Factory, Cairo, Egypt:It is as Transformers production plant and Office Building.

Scope of work: Design and supervision of the ventilation air conditioning system, and fire fighting systems.

ALex Fiber, Alexandria, Egypt: A factory for making pets and dolls from fibers and textiles

Scop of work: All MEP work.

Luna Factory, 6th of October, Egypt : A cosmetics producing factory with built up area 10000 m2

Scope of work: Mechanical work.

8

BUILDINGS

Dar Al Kuttub Al Misreyyah, (Bab El- Kahlak), Cairo, Egypt:

Design of the ventilation and the air conditioning system and fire fighting system for the following building areas: Reinforced Shields; Main Reading Hall; Technical Library Section; OPAC; Book Exhibition; History of Arabic Calligraphy, Amphitheater; Lecture Hall; Research Hall; Computer Information Center & Stacks for Arabic Calligraphy; Papyrus Hall; Department

Head of Microfilm; Administrative Office for Microfilm; Microfilm Unit CD-Roms Hall; Internet & Cable Systems; Stacks & Manuscripts Stacks; Stacks Preparation; Dark Rooms; Sterilization Unit; Verification Center & Research Area for Stacks.

Dar Al Kuttub Al Misreyyah, (Kornish El Nil), Cairo, Egypt:

Design of the ventilation and air conditioning system and fire fighting system for the following areas: Library Hall; Microfilm Hall; Information Center; Camera Hall; Research Hall; Documented Study & Research Center; Biological Lab; Chemical Lab; Patch Lab, Hand Fitting & Repair Lab; Cladding workshop.

BUILDINGS

El Tanani Office Building, New cairo, Egypt:

A project includes 6 floors office building & show rooms with total connected power of 2 MVA & 400 R. Ton air cooled chiller plant.

Scope of work: Working Drawings, Tender Documents for MEP work.MEP Budget: ( Approximately 25 M-EGP )

9

BUILDINGS

Escowa Building, Beirut, Lebanon:

Maintenance programmes for the Escowa Building, Beirut, Lebanon, comprehensive maintenance management system including assets lists; planned maintenance instruction; for a 13-story building; usable space comprising exhibition halls; 5 story parking garage; office building of 8 stories including air conditioning system of 1500 T.R. .

Escowa Building, Beirut Lebanon ( Extension )Design review for a 13-story building, usable space comprising exhibition halls, 5 story parking garage, office building of 8 stories including air conditioning system of 1500 T.R. .

ABC Head Quarter, Tarek Nour, Smart Village , Cairo Egypt (Under construction):

6 floors office building accommodating around 1000 employees with all modern intelligent systems. The total connected load is 2 MVA with 500 T.R cooling plant capacity.

Kuwait Diplomatic Head Quarter-Cairo, Egypt (Under Construction):

The project is considered the new Kuwait Embassy in Egypt covering around 2500m2 built-up area directly on the Nile side, accommodating the Embassy Assembly & Consulate offices,distributed on the first 6 floors as well as another three floors for residential facilities, the building

is fully equipped with all modern High-Tec facilities and an Air-cooled chiller plant of around 600 T.R Scope of work: Mechanical working drawings, Tender Documents for Sanitary, Fire Fighting and HVAC systems(E/M Budget is around 18 Million LE).

Scope of work: MEP, Mechanical and Electrical system of the project.

10

BUILDINGS

AL Raha Abu Dhabi, United Arab Emirates (Under construction):

5 Residential towers from 12 to 16 floors with common basement and ground floors. The total connected power is 11 MVA with district cooling HVAC system.Scope of work: Working drawings and tender documents of all MEP work.

EL-Dhafra, Abu Dhabi, United Arab Emirates (Under construction):

A residential LEED certified tower, 28 floors with built-up area of 24000 m2, the total connected load is 4.5 MVA with district cooling HVAC system.Scope of work: Working drawings and tender documents for all MEP work.

Raya Holding New Head Quarter, 6th Of October City ,Egypt:

7 Floors office building for Raya company with total connected power of 4.5 MVA and 1000 T.R air cooled chiller plant.

EL Mansoury Tower Dubai, United Arab Emirates:

28 Floors with built-up area of 24000 m2 , the total connected load is 4.5 MVA with district cooling HVAC system. Scope of work: working drawings and tender documents for all MEP work.

11

BUILDINGS

`Al Maydan, Dubai, United Arab Emirates:

28 floors and 4 basements with built-up area of 24000 m2. The total connected load is 4.5 MVA with district cooling HVAC system. Scope of work: working drawings and tender documents for all MEP work.

Administration building, 10th of Ramadan, Cairo, Egypt:

A project including Mechanical works, Plumbing and air conditioning services for a 6 floors office building.

The Peridot, Dubai, United Arab Emirates:

A residential LEED certified tower, 12 floors and two basements with built-up area of 24000 m2. The total connected load is 4.5 MVA with a central air conditioning cooling HVAC system.

Scope of work: Working drawings and tender documents for all MEP work.

Khartoum Buildings, Sudan:

4 residential towers 13 floors each with common basement and ground floor, including shops, gym and car parking with district cooling HVAC system with total area of 3800 m2.

Scope of work: working drawings and tender documents of all Mechcanical work. Electrical Motor control centers and Building Mangement System .

12

BUILDINGS

Ramla Office Building:Design of the ventilation and air conditioning system, plumbing and fire fighting systems for a tower at Nile side banks .

Scope of work: Mechanical working drawings, Tender Documents Sanitary, Fire Fighting and HVAC systems.

Misr Insurance, Cairo, Egypt:The project is a 16 floors with 18000m2 built –up area accommodating 1000 employees. The total connected powers is 4 MVA, with 1200 T.R air cooled chiller plant.

Buraidah Buildings Saudi Arabia:A group of residential towers in Saudi Arabia consisting of 5 residential towers from 6 to 7 floors with common basement and ground floors. The total connected power is 11 MVA. Scope of work: working drawings and tender documents of all MEP work.

El Riyadh Palaces, Riyadh, Saudi Arabia:MEP design for a palace compound at Riyadh of 20000 m2 built up area.

AL-Ashraff Syndicate Building, Cairo, Egypt:

A 6 floors, Office building for Al-Ashraff syndicate with total connected power of 1MVA.

Scope of work: working drawings, tender documents and site supervision for all MEP works with total budget of 6,000,000 EGP.

El-Sweedy Office Building, Cairo, Egypt:

The project consisting of 6 floors adminstration office building and two basements.

Scope of work: includes Plumbing and air conditioning, Building mangement system and Electrical Motor Control Centers .

13

BUILDINGS

Mixta Complex, 6th of October City, Egypt:A group of residential of 8 towers.

Scope of work: MEP district utilities, for all MEP work.

Troops House Project, Cairo, Egypt:Design and construction review of troops house air-conditioning System including public areas, 3 restaurants, 3 exhibition halls, kitchen area, cold rooms and 100 rooms hotel.

Mina Garden City, 6th of October City, Cairo, Egypt:Design for a 10,000 m2, 3-story building comprising exhibition halls; shopping areas; Health Club; Bowling Center; Gymnasium; Multipurpose sports hall...etc. Air conditioning system is of 1000 T.R. .

Egyptian Petroleum Company, Main Office, Cairo, Egypt:Upgrading of the air conditioning system of Egyptian Petroleum Company, Main Office of 800 T.R. cooling capacity of the main company Adminestration Building.

Specialty Laboratory, Cairo, Egypt:The project consists of supply of specialty services for laboratory area including Plumbing and Service networks.

Office Building Cairo, Egypt:A project includs plumbing and air conditioning services of an office building of 6 floors at 10 Th. of Ramadan city.

Arabic Theater, Giza, Egypt: ( Air conditioning of a theatre ), of 10000 m2 have a central air conditioning plant.

West Delta Regional Control Center, El Behira Egypt:It is a power supply project covering around 4,000 m2 including a separate 5 floors and includes central air conditioning system of 255 T.R. cooling capacity.

Damac:A project including Plumbing and air conditioning services for a 6 floors office building and two basement.

14

MALLS AND SHOPPING CENTERS

Alexandria City Center ( Alexandria), Egypt:

1 story 28,000 m2 building City Center. The building comprises of exhibition halls, shopping areas, ground parking garage area and includes central air conditioning system of 3000 T.R. cooling capacity.

Scope of work: fire fighting; plumbing; ventilation and air conditioning systems; and central plant rooms; motor control centers and building management system for mechanical and electrical systems.Total MEP cost is around 400 Million Egyptian pounds.

MALLS AND SHOPPING CENTERS

Golf City Mall, EL Obour City, Cairo, Egypt:

3 Floors multidiscipline mall, with total built-up area of around 40,000 m2. The project accommodates a Carrefour hyper market, 6 cinemas and shopping center

Scope of work: MEP services; fire fighting; ventilation and air conditioning systems central Air conditioning system of 2400 T.R. cooling capacity; electrical power supply and low current systems total connected power is 4.5 MVA.

15

MALLS AND SHOPPING CENTERS

CARREFOUR Golf City (Obour City), Cairo, Egypt:

It is a shopping mall of 16000 m2 area.

Scope of work: central air conditioning of 750 T.R. cooling capacity; Plumbing & fire fighting system; motor control centers and building management system for mechanical and electrical systems.

Carrefour Dandy Mall, Alexndria Desert Road, Cairo, Egypt:

It is a shopping mall of 16000 m2 area.

Scope of work: central air conditioning, Plumbing & fire fighting systems cooling capacity is 1150 T.R..

ALEXINDRIA CITY CENTER, Part C ALEXINDRIA, Egypt:

Part “C Extension: It is an extension to the existing Alexandria city center building, The extension area is of around 8000 m2 including food courts, magic plants, pooling area.

Scope of work: All services: air conditioning, plumbing and fire fighting. systems, motor control centers and buildingmanagement system for Mechanical and Electrical including the connections to central air conditioning, Plumbing & Fire Fighting Systems, Building Mangement System. The extension cooling capacity is 450 T.R..

16

MALLS AND SHOPPING CENTERS

Bonyan, 6th Of October City, Egypt:

The project is an 22500 m2 administration building consists of 6 towers including offices, restaurants, retails, nursery areas.

Scope of work: include Mechanical, plumbing and fire fighting.District Air Conditioning plant of 1600 T.R cooling Capacity using absorption chiller system.

Nile Mall, Cairo, Egypt:

The project is a 4,000 m2 consisting of 4-story. The building comprising exhibition halls, 4 floors of shopping areas, under ground parking garage area.

Scope of work: fire fighting, ventilation and air conditioning system, motor control centers and central air conditioning system of 2000 T.R. cooling capacity.

MAADI CITY CENTER CAIRO, EGYPT:

The project is 20000 m2 area extension to the existing Maadi City Center Mall.

Scope of work: Air conditioning , plumbing and fire fighting , motor control centers and building managment

system for mechanical and electrical systems and the connection to central air conditioning plant and Plumbing & fire fighting system. The extension cooling capacity is 1150 T.R. cooling capacity.

17

MALLS AND SHOPPING CENTERS

Donuts Shops:

Design for air conditioning and follow up and supervision of Donuts shops.

Sainsbury Hyper Market: Nasr city Egypt:3000 m2 hyper market with 2 MVA total connected powers and 500 T.R air cooled chiller plant.

Babel Gardens, Cairo, Egypt:Design for a 78,000 m2, 13-story building. Building conteins exhibition halls, 5 floors of shopping areas, 2 floors under ground parking garages, 5 story residential area. The project includes central air conditioning system of 6000 T.R. Cooling capacity.

Wonder Land Cinema Complex, Nasr City, Cairo, Egypt:

The project is a three floor complex containing six cinemas with total capacity of around 2000 spectators as wall as all required recreational facilities .

Scope of work : preparation of working drawings, Tender Documents and site Supervision for HVAC and fire fighting systems.

City Scape, City Mall, 6th Of October,Egypt:

The project is a 4,000 m2, 4-story building. Building comprises exhibition halls, 4 floors shopping areas and under ground parking garage area.

Scope of work: central air conditioning system of 2000 T.R. cooling capacity, fire fighting ventilation and Building Mangement systems.

18

MUSEUMS

Hurghada Museum, Hurghada, Egypt:

The project consist of exibition halls that displays of pre-hestoric era, Displays of Pharonic era, Displays of the Greek era, Displays of Roman era, Displays of Coptic era, Displays of islamic era, Modern displays, Hertiage Displays

Islamic Museum at (Bab El- Khalak), Cairo, Egypt:

The musuem house has different types of Islamic Displays of different times like marble displays,ceramic and glass displays, wooden displays, wooden mehrabs, windows, chairs, doors and flooring, carpets and weave clothes.

Scope of work: Desgin of the MEP service, Ventilation and air conditioning system. Motor control centers , building managment system for the Mechanical and Electrical system and fire fighting system.

MUSEUMS

Revolution Leaders House Museum, Cairo, Egypt:

The Musuem House Exibition halls having the revoloution rare document.

Scope of work: Design of ventilation and air conditioning system, motor control system and building management system for the mechanical and electrical systems and fire fighting system it is one of the most attractive design projects.

Scope of work: Design of ventilation and air conditioning system. Motor control system and building management system for the mechanical and electrical system and fire fighting system.

19

MUSEUMS

Ancient Egyptian tombs, Luxor, Egypt:

Ventilation and environmental system studies. A preliminary study for the improvement of ventilation system and remote monitoring of tombs environment using wireless building management system with wireless antenna.

Alexandria National Museum , Alexandria, Egypt:

One of the main museums that house the Pre-Historic era , Displays of Pharaonic era, Displays of Greek era, Displays of Roman era, which were submerged under Alexandria sea side and were lately restored.

Scope of work: Design of air conditioning system, motor control centers and building management system for the mechanical and electrical systems .

20

HOSPITALS

The Hammad Medical Tower Hospital, Doha Qatar:

The project is a 3 floors building with 40,000 m2 built up area, the hospital is serving around 125 beds and a complete Out-Patient Clinics. In addition, the GSH includes three Operating rooms, Intensive care unit for 5 beds, Diagnostic X-Ray and Ultrasonic Department, Hemo dialysis Department for 6 units and a Maternity.

Dr. Ahmed Okasha-Mental Health Hospital, New Cairo, Egypt:

The project is considered as a mental health resort serving around 100 beds. The building is a four floors with total built-up area of around 7000 m2, accommodating all up to date mental health care equipment.

Al Salab Hospital Nasr city, Egypt:

The project consists of 6 Operation Rooms, Intensive Care Units and around 100 beds. The building is a four floors with total built-up area of around 7000m2, accommodating all up to date medical equipment including Operation Rooms, Recovery Rooms, kitchen and laundry services, with medical gas system, chiller plant, and electrical system.

Scope of work: Mechanical Working Drawings and Tender Documents for, Sanitary, HVAC & Fire Fighting systems. (E/M budget is around 10 Million LE).

HOSPITALS

Scope of work: Mechanical works , central medical gas system to the latest HTM 2022 standards, fire fighting system . air conditioing plant capacity is 1000 TR .

21

El-Mansoura Radiology Treatment Hospital, Mansoura, Egypt:

The Hospital is serving around 200 beds and including special Operation Rooms, Recovery Rooms, Intensive Care Units, Isolation Rooms, and X-Ray department.

Dar-El-Mona for Child Care, Giza, Egypt:

The project is a mentally retardant child-care hospital consisting of three connectedbuildings; each is a four floors, as well as sports, social & educational facilities. The chiller plant is an air-cooled plant with 800 TR capacities.

Katameya Clinic, Cairo, Egypt:

The project is a 5 floor building hospital including Operation Rooms, Operation Recovery Rooms, cafeteria and doctors offices

Scope of work: all MEP systems including electrical HVAC, plumbing, fire fighting and Medical gas systems using bulk oxygen tank.

Al Safwa Hospital 6 October, Egypt:The project is considered a health resort serving about 100 beds: The building is four floors with total built-up area of around 7000m2, accommodating all up to date equipment including Operation Rooms, Recovery Rooms, kitchen and laundry services.

Scope of work: all mechanical systems including HVAC, plumbing, fire protection and Medical gas system.

Applicants Syndicate Hospital Cairo, Egypt:Mechanical, Medical piping, fire fighting system and air conditioning system of 300 T.R cooling capacity for 100 room hospital.

Scope of work: MEP systems design including HVAC, plumbing, fire protection systems and Medical gas system.

Scope of work: Design review and owner representative for air conditioning system, on site to cover all the MEP work. (E/M Cost is around 25 Million LE).

HOSPITALS

22

TOURISTIC RESORT & HOTELS

Rainbow Hotel, Sharm Elsheikh, Egypt:

Design of MEP services of a five stars hotel with 260 guest rooms and 50 chalets with all related facilities, restaurants, multi purpose halls, swimming pools.

Scope of work: MEP service, Electrical, low current air conditioning systems, kitchen, laundry, utility networks including rain water

network, drainage system network, automatic fire fighting system, swimming pools, plumbing work includes a pressurized domestic cold and hot water system, sewage and desalination plants.

Beach Restaurant Makady Bay, Egypt:

5 Stars hotel consisting of 550 guest rooms, public area restaurants, multi purpose halls, swimming pools.

Scope of work: includes completion of the hotel MEP services, Electrical, Air Conditioning System, Kitchen, Laundry, Utility Networks including drainage system network, Automatic fire fighting system,swimming pools and air

TOURISTIC RESORT & HOTELS

Conditioning Plant . Plumbing work includes a pressurized domestic cold water system, sewage and desalination plants.

23

TOURISTIC RESORT & HOTELS

Sharming Hills, Sharm Elsheikh Egypt:

Design of MEP services of a five stars hotel, 260 guest room hotel, with all related facilities, restaurants, multi purpose halls, swimming pools.

Scope of work: Design and supervision the MEP service Electrical,low current, air conditioning system, kitchens, laundry, utility networks, drainage system network, automatic fire fighting system, swimming pools. Plumbing work includes a pressurized domestic cold and hot water system, sewage and desalination plants.

Fantasia Resort:

Five stars resort, including villas, kids club, and SPA.

Scope of work: includes Design and Site supervision of MEP systems of the hotel service, Electrical, low current, air conditioning system, kitchens, laundry, utility networks including rain-water network, drainage system network, automatic fire fighting system, swimming pools. Plumbing work includes a pressurized domestic cold and hot water system.

Taba Resort, Taba, Egypt:

The project covers an area of around 111000 m2 which consists of Main hotel building, time share units, staff housing, the project will accommodate 365 guest rooms, including restaurants, sports area, and health club.

Scope of work: Preparation of Working Drawing, Tender Documents, Site Supervision and Participating Construction Management responsibilities for HVAC systems as well as Infrastructure Network.

24

Park Hyatt, Cairo, Egypt:

Design and site supervision of 5 Stars hotel consisting of 220 guest rooms, Royal Suits, Presidentieal Suits, Restaurants, multi purpose halls, swimming pools. Scope of work: includes upgrading of the hotel services, air conditioning system, kitchen, laundry, utility networks including rain-water network, drainage system network, automatic fire fighting system, swimming pools. Plumbing including electrical, motor control centers and building management Total MEP Budget 45 million U.S.D.

Al-Dina Resort Hurghada Egypt:

Five stars resort, including villas, kids club, and SPA.

Scope of work :MEP design of the hotel system, electrical ,low current air conditioning system, kitchen, laundry, utility networks including rain-water network, drainage system network,

TOURISTIC RESORT & HOTELS

Nefertary Resort Safaga , Egypt:

Design and site supervision of 4 Stars hotel, consisting of 1000 guest rooms, restaurants, multi purpose halls, swimming pools.

Scope of work: Design and site supervision of the hotel service, electrical, low current, air conditioning systems, kitchen, laundry, utility networks including rain-water network, drainage system network, automatic fire fighting system,

swimming pools. Plumbing work includes a pressurized domestic cold and hot water system, sewage and desalination plants.

automatic fire fighting system, swimming pools. Plumbing work includes a pressurized domestic cold and hot water system, sewage and desalination plants.

25

TOURISTIC RESORT & HOTELS

Oberoi Hurgadah, Egypt:

Redesign of the infrastructure networks, fire fighting, domestic water, drainage and plant rooms of 5 star hotel including resturants,104 clusters, utility area, sewage treatment and reverse osmosis plant main swimming pool, design and construction suppression.

Sharm City, Sharm El Shekih, Egypt:

The project includes the design of Plumbing systems for village , housing, residential buildings, super market and office areas for sharm city at Sharm El Sheikh.

Grand Makadi Hotel, Hurghada, Egypt:

Site supervision & management of heating ventilating and air conditioning system – for a main building of (14000 m2 and 330 guest rooms & suits and 3 Restaurants) using Distric cooling plant. The total cost of the project 90 million pounds.

Safir Hotel, Cairo, Egypt:

Renovation project and site supervision of 5 Stars hotel, consisting of guest rooms, restaurants, multi purpose halls and swimming pools. Scope of work: Mechanical design and supervision of air conditioning system, kitchen, laundry,

utility networks including rain-water network, drainage system network, automatic fire fighting system, swimming pools, plumbing work including electrical, motor control centers and building management system.

26

TOURISTIC RESORT & HOTELS

MovenPic El Ein Resort, Suez, Egypt: Design and Site supervision & management of heating ventilating and air conditioning system for a main building of (18000 m2 and 172 Guestrooms & units, 2 Restaurants and 4 Ball rooms) 475 Ton capacity. The total cost of the project 40,000,000 pounds.

Porto Marina, Marina resort, North Coast, Egypt:

The project consists of:9 attached residential towers, 12 floors with around 1000 flats.An apartment hotel, 12 floors serving around 120 units.

Five stars 250 Guest Hotel Rooms with an international health club.

Scope of work: working drawings and tender documents and site supervision for all air conditioning and ventilation work.

Makady Palace Hotel, Hurghada, Egypt:

Site supervision & management of heating ventilating and air conditioning system for a main building of (15000 m2 and 550 guestrooms & suits and 7 Restaurants). The total cost of the project 130 million pounds.

27

Cairo Sheraton, Giza, Egypt: The project is 5 Stars hotel consisting of (Two tower ) of 14000 m2 and 330 guest rooms & suits and 3 Restaurants. Design and site supervision of guest rooms, restaurants, multi purpose hall and swimming pools.

Scope of work: Design; Site supervision & management of heating ventilating and

air conditioning system; electrical motor control centers and Building managementand renovation of the hotel services like Kitchen, laundry, utility networks including rain-water network, drainage system network, automatic fire fighting system, swimming pools; Plumbing work include a pressurized domestic cold water system.

TOURISTIC RESORT & HOTELS

Conrad Hotel, Cairo, Egypt:

Renovation of public area and Mechanical system, air conditioning, fire fighting and plumbing systems, with total budget of 20,000,000 L.E.

Porto El sokhna, Marina Resort, North Coast, Egypt:

The project consists of Three residential Towers 24 floors with around 1800 flats Two floors shopping mall Beach hotel 125 Guest rooms.

Scope of work: working drawings and tender documents for all air conditioning and ventilation

28

TOURISTIC RESORT & HOTELS

Sofitel Hotel, Cairo, Egypt:

Design Reviewand client repersanta of 5 Stars hotel consisting of guest rooms, restaurants, multi purpose halls swimming pools. Scope includes design review of upgrading of the hotel services, air conditioning system, kitchen, laundry, chilled water networks.

Libya Hotel, Guniea, Bisau:

Design and site supervision of 5 Stars hotel consisting of guest rooms, restaurants, multi purpose halls swimming pools.

Scope of work: Upgrading the hotel MEP services air conditioning system kitchen, laundry, utility networks including rain-water network, drainage system network, automatic fire fighting system, swimming pools. Plumbing work includes a pressurized domestic cold water system and Electerical system.

Katameya Dunes, Cairo, Egypt:

A compound of 15000 m2 surface area containing 128 hotel bed rooms, 24 suites, 380 villas.

Scope of work: Mechanical, Plumbing, fire fighting system, swimming pools, Boiler room, air conditioning, parking ventilation, Electrical, motor control centers and building management System.

29

TOURISTIC RESORT & HOTELS

La Goon Beach Resort, El Sokhna Egypt:

A touristic resort accommodating 30 VIP villas,120 challets, 50 guest rooms , 3 stars Hotel with all related facilities .The total connected power is 3 MVA. Scope of work: working drawings. Tender documents and site supervision for all Mechanical works.

Cascades, Soma Bay, Hurghada, Egypt:

300 guest rooms, five stars Hotel with an international health club, French Health and treatment Spa, and golf course. The total connected power is 4 MVA with 1000 T.R air cooled chiller plant.

Scope of work: working drawings and tender documents for all air conditioning and ventilation work.

30

Paradise Resort, Ras Sedr, Sinai, Egypt:

(Executed 2000); The Project is a touristic resort covering an area of around 150,000 m2 and accommodating 100 Guest Rooms.Hotel, Private Villas & Chalets, small Recovery Hospital, Indoor & Outdoor Recreational Activities and four Swimming Pools. Work Drawings, Tender Documents and Site Supervision, Sanitary, Fire Fighting and HVAC systems.

TOURISTIC RESORT & HOTELS

Boutique Hotel, Zamalek, Cairo, Egypt:

5 floors, 30 suits, 6 stars hotel on the Nile side with total connected power of 1 MVA and 300 T.R air cooled chiller plant.

Scope of work: working drawings & Tender Documents (Mechanical systems).

Movenpick Ghaza, ghaza, Palestine:

200 guest rooms, 5 stars Hotel with 4 MVA connected power&400 T.R AC plant.

Scope of work: working drawings & Tender Documents (Mechanical Systems)With budget of 8,000,000 $.

Accor hotel, Stella, Hurghada, Egypt:

500 guest rooms, five stars Hotel ,600 Chalet,60 villas and all related facilities with 8 MVA connected power.

Scope of work: working drawings, Tender documents and site supervision for all mechanical works.

Stella De Marie, El Sokhna, Egypt:

Five stars Hotel and an international health club with 4 MVA connected power and 800 T.R water cooled chiller.

Scope of work: working drawings. Tender documents and site supervision for all mechanical work.

31

TOURISTIC RESORT & HOTELS

Meridian, Sharm, Egypt:Design and site supervision of 5 Stars hotel consisting of guest rooms, restaurants, multi purpose halls, swimming pools. The hotel has Central Air conditioning plant, kitchen, laundry, utility networks including rain-water network, drainage system network, automatic fire fighting system, Plumbing work includes a pressurized domestic cold water system.

Windsor Hotel - Hurghada - Red Sea, Egypt:The project covers an area of around 300,000 m2 which consists of 6 zones the Main Hotel building, VIP Village, times Share units, staff housing and the Electromechanical plants. The project will accommodate around 1000 Guest Rooms, around 12 Restaurants, Casino, Roman Theater, Sports area, Health Club, Bowling, Gymnasium, Multipurpose halls. The Main building & village units are connected to a centralized water cooled chiller plant around 2500 T.R.. The staff housing units are connected to their own air cooled plant while the time share units are using variable refrigerant system. The hotel is using R\O desalination plant with around 1500 m3/h capacity

Scope of work: preparation of Working Drawing, Tender Documents, Site Supervision and Participating in Construction Management responsibilities for HVAC systems as well as Infrastructure Network and District cooling plant.

32

Sonesta Hotel Extension, Cairo, Egypt:

A new 10 floor building, including 160 guest rooms attached to the existing hotel. The total connected power is 2 MVA with 600 T.R air cooled chiller plant.

Scope of work: working drawings. Tender documents and site supervision for all mechanical works.

General projects

Higher judge project: Sana’a, Yemen Republic:

The project is of 27000 m2 area consisting of High Court Building including 8 courts, criticism court, guard building, and investigation buildings.

Scope of work: Mechanical system , electrical motor control centers and Building management system for the project, including

Bahrain National Assembly Building, Manama, Bahrain:

The project consists of three separate but interconnected elements:Shura Building: can be considered as the administrative center of the Shura Council where the members have their offices, meet in committee, meet with members of the press and prepare papers and recommendations for considerations by others.

Parliament Building: which fulfils a similar function to the Shura Council but for the members of Bahrain Parliament. Auditorium: where the members of the Shura Council and the Parliament will meet for debate and discussion and also royal visitors and overseas dignitaries will be met and entertained. The total connected load is around the chiller plant with an air cooled system located in a central energy building outside the project zone. Scope of Work: Working Drawings, Tender Documents and Site Supervision for HVAC, Sanitary & Fire Fighting Networks. (E/M Budget is around 15 Million $).

General projects

air conditioning, fire fighting, water wells and treatment and plumbing systems. The total cost of the project is 40,000,000 U$D.

33

General projects

EL-Sheikh Isa Bin salman al khalifa conference hall & library, Manama, Bahrain:

The project consists of Two main blocks connected to each other through the ground floor, the first block accommodates the following:

Movie & Music Studios, A National Library, Children Cinema Theatre, Art Gallery, Meeting Halls & Book Stores.

While the second block accommodates the following:

Multipurpose Hall for 500 Seats, Main Conference Hall for 1000 seats, Offices, Administration area & Lecture Halls, Press Conference Hall, Majlis and Amir Collection Hall.

Scope of work: Drawings, Tender Documents and Periodical Site Supervision for Conference Systems, HVAC, Sanitary & Fire Fighting Networks. (E/M Budget is around 16 Million $).

Judge Academy City Project, October city, Cairo, Egypt:

The project is consisting of academy buildings. Hotel Building, administration, theater and lecture halls, library, judge institute and judge assistant institute. The project total area is 500,000 m2 and of 200,000,000 L.E cost.

Scope of work: includes the preparation of the Mechanical System Design (Air Conditioning, district cooling plant, electrical motor control centers, Building managementand and Fire Fighting system for the city buildings) .

34

FLOATING HOTELS

FLOATING HOTELS

Heating Ventilation and Air Conditioning, Mechanical Room System for the following Floating Hotels Restaurants:

Seagull Floating Restaurants, Egypt. San Giovanni 1 Floating Restaurants, Egypt. Oberoi Floating Hotel, Calcutta, India. Amaroco 1 Floating Hotel, Egypt. Amaroco 2 Floating Hotel, Egypt. Mont Carlo Floating Hotel, Egypt. Monaco Floating Hotel, Egypt. Miramar Floating /Fixed Hotel, Cairo, Egypt. Etab Novotel Floating Hotel, Cairo, Egypt. Nile Crown 2 Floating Hotel, Egypt. Nile Crown 3 Floating Hotel, Egypt. Cairo Floating Hotel, Egypt. Alsaraya Floating Restaurants, Egypt. Alkhan Floating Restaurants, Egypt. Solaris1 Floating Hotel, Egypt. Solaris2 Floating Hotel, Egypt. Orchestra Floating Hotel, Egypt. Sun Boat 1, Floating Hotel, Egypt. Sun Boat 2 Floating Hotel, Egypt. Amo Floating Hotel, Egypt. LIT Kira, Floating Hotel, Egypt. Seti III Floating Hotel, Egypt. King Mina Floating Hotel, Egypt. Elsalam Floating Hotel, Egypt. MR. GED Floating Hotel, Egypt. La Bella de tours Floating Hotel, Egypt. Song of Egypt Floating Hotel, Egypt. Aida II Floating Hotel, Egypt. Aida III Floating Hotel Egypt. Nile Dolphin Hotel, Luxor - Aswan, Egypt. Karma Floating Hotel Egypt. River mist Hotel, Egypt. Moon Dance Floating Hotel, Egypt. El Gamila Floating Hotel, Egypt. Rubi II Floating Hotel, Egypt. Al Sultana Floating Hotel, Egypt. Nile Paradise Floating Hotel, Egypt. Grand Sun, Aswan, Egypt. Grand Rose, Aswan, Egypt.

35

Mosques

Qurayat Mosque, Qurayat Saudi Arabia:

The project is a Masjid with a central chiller plant used for the air conditioning of the covered area, in addition to a desert cooler system to condition the open court of the mosque. The additional zones use Direct expansion system for the air conditioning.

The project is using heat pump to pre-cool and heat the domestic water - Electrical system includes power supply station, low current system and emergency power supply with total cooling load of 7000T.R and 6 MVA. Scope of work: Deign of MEP Mosque services Design of HVAC, lightening, power supply including all MEP work.

Hail Mosque, Saudi Arabia:

The project is a Masjid with a central chiller plant used for the air conditioning of the covered area, in addition to a desert cooler system to condition the open court of the mosque. The additional zones used Direct expansion system for the air conditioning.

The project is using heat pump to pre-cool and heat the domestic water - Electrical system includes power supply station, low current system and emergency power supply with total cooling load of 7000T.R and 6 MVA.

Scope of work: Deign of MEP Mosque services Design of HVAC, lightening, power supply including all MEP work.

Mosques

36

Mosques

Sakaka Mosque, Saudi Arabia:

The project is a Masjid with a central chiller plant used for the air conditioning of the covered area in addition to a desert cooler system to condition the open court of the mosque. The additional zones used Direct expansion system for the air conditioning. The project is using heat pump to pre-cool and heat the domestic water - Electrical system includes power supply station,

low current system and emergency power supply with total cooling load of 7000T.R and 6 MVA.

Scope of work: Deign of MEP Mosque services Design of HVAC, lightening, power supply including all MEP work.

El-Aref Be Allah Sidi Abo Al Hassan Mosque Aswan Egypt:

The project is a Masjid with a desert cooler air conditioning system to condition the open court of the mosque, while the additional zones use a direct expansion system for the air conditioning. Electrical system includes power supply station, low current system and emergency power supply with total cooling load of 700T.R and 1 MVA.

Scope of work: Deign of MEP services like of HVAC, lightening, power supply including all MEP work.

37

BANKS

Housing & Development Bank Mohandessieen - Giza - Egypt:

Office building and administration sectors. Design of the ventilation and the air conditioning system, plumbing system and fire fighting system. The project covers a 1000 Tons refrigeration capacity.

Scope of work: working drawings and tender documents for all Mechanical works.

HSBC Cairo regional processing center:

Six floors intelligent, LEED certified office building, HSBC bank branch, call center, training center& all high tech facilities

Scope of work: working drawings, tender documents and site supervision for all Mechanical works.

Abu Dhabi Bank - Egypt:

Consists of HVAC Technical Evaluation for Mechanical items for three branches:-

New Cairo Branch.Talat Harb Branch.Assuit Branch.El Shoefat Branch.Fifth complex branch.

BANKS

38

BANKS

BNP Paribas-Bank, EL Zamalek Branch:Design of the ventilation and the air conditioning system. Scope of work: working drawings, tender documents and site supervision for all Mechanical works.

BNP Paribas-Bank, EL Maadi Branch:Design of the ventilation and the air conditioning system. Scope of work: working drawings, tender documents and site supervision for all Mechanical works.

City-Bank, Garden City, Cairo, Egypt:Design of the ventilation and the air conditioning system for the new City branch office at Cairo and Proposals for the improvement for the existing air conditioning systems.

HSBC-Bank, El Shams Club Branch: Design of the ventilation and the air conditioning system, plumbing system and fire fighting system.

Housing & Development Bank Fifth Complex Administration Building, Area Number 28, Egypt: Office building and administration sectors. Design of the ventilation and the air conditioning system, plumbing system and fire fighting system. The project is of 500 Tons refrigeration capacity.

Scope of work: working drawings and tender documents for all Mechanical works.

Barclays Bank, Port-Said Branch:Design of the ventilation and the air conditioning system.

Scope of work: working drawings, tender documents and site supervision for all Mechanical works.

39

Crédit Agricole Bank:Design of the ventilation and the air conditioning system.

Scope of work: working drawings, tender documents and site supervision for all Mechanical works.

Alexandria Bank-Egypt:

Consist of the HVAC Technical evalution for all Mechanical work in the following branches:

• El Haram Branch. • San Stephano Branch. • Battrawy Branch. • Horreya Branch • Glym Branch. • Saad Zaghlool Branch. • Sharm Branch.

Arab Aferican Bank.

BANKS

40

MED GULF:Dubai, United Arab EmiratesTel: 971042829533PO. Box: 7099E-mai: [email protected]

MEDA B D

E L H A M I D B A K R Y

26 Syria St. Al - Mohandessin, Giza EgyptTel & Fax: (+202) 33386292 - 37489121Mob: 0106651551P.O. Box: 668 Orman GizaE-Mail: [email protected]

MED Saudi Arabia:Saudi Arabia.Tel: + 966552082273E-mail: [email protected]

MED GULF:Sharjah, United Arab EmiratesTel: 971065742775Fax: 971065742776PO. Box: 28530E-mai: [email protected]