abb offshore wind connection
TRANSCRIPT
© ABB
| Slide 1
ABB Power SystemsOffshore wind connection
Peter Lundberg, Global Product Manager, November 2016
November, 2016
© ABB
| Slide 2
Integrity, Health, Safety and EnvironmentAlways most important – our core values
Integrity
Code of conduct
Regular trainings
Personal responsibility
Leadership and culture
Health, Safety and Environment (HSE)
Hard work, never relax
Leadership and culture
Personal responsibility
Focus on full value chain
Risk assessments and mitigation
Regular trainings
24/7 – right balance
Resource efficiency
November, 2016
© ABB
| Slide 3
Installed offshore wind mainly in Europe, China offers highest growth
ChinaJapan
S. Korea
Source: MAKE, Global Offshore Wind Power Market march 2016
Europe
Current activity mainly in UK, DE, and DK
FR, NL and BL emerging - projects in development, large grid
connections expected 2018/19
1.1
8.6
2020
GW
2015
GW
11.2
0.4
0.3
Taiwan
Installed & grid connected
Expected grid connection
24.4
Asia
Current activity concentrated mainly to CN, fast growth
expected starting in 2018
KR, TW, JP emerging (albeit slowly)
North America
Limited to small demonstration projects, no
significant projects until 2020 or later
0.3
Offshore Wind Markets - Global
China 2025:
46 GW
2025
GW Expected grid connection
Offshore Wind Market
Europe 2025:
42 GW
1.2
GW
November, 2016
© ABB
| Slide 4
Installed base and outlook12 GW installed. 20 GW to be installed in next 5 years. Additional 60 GW expected between 2020 and 2025
Installed capacity by countries.
YE 2015 (Source: Make)
Installed capacity by countries.
YE 2020 (Source: Make)Installed capacity by countries.
YE 2025 (Source: Make)
12 GW 33 GW 95 GW
November, 2016
© ABB
| Slide 5
Offshore Wind ConnectionsABB offering
Offshore and onshore AC and DC stations including buildings
Reactive power control systems (FACTS)
HV-Cables including land and subsea cable laying
Training and advise on operation
System studies including grid code compliance solutions and advise on connection to onshore main grid
Maintenance contracts
November, 2016
© ABB
| Slide 6
ABB Offshore Wind ConnectionsGrid code compliance
AC faults are not propagated
through the HVDC system
Grid code compliance done
by HVDC
Relaxed requirements on
wind turbines
November, 2016
© ABB
| Slide 7
ABB Offshore Wind ConnectionsFault ride-through
Fault in the main AC grid
No shut-down of the wind park
Reduce stress on the turbines
Increase energy yield
November, 2016
© ABB
| Slide 8
ABB Offshore Wind ConnectionsVSC technology
Voltage sourced converters
Self-commutated IGBT valves
Multi-level topology
ensures low losses < 1 %
Requires no reactive power
compensation
November, 2016
© ABB
| Slide 9
ABB Offshore Wind ConnectionsTransmission distance
< 50 km AC cables
< 100 km DC or AC cables
> 100 km DC cables
November, 2016
© ABB
| Slide 10
ABB Offshore Wind ConnectionsOffshore HVDC wind power connections
Offshore
AC substation
Wind farms
Offshore HVDC
converter station
DC cable
transmission
Onshore HVDC
converter station
November, 2016
© ABB
| Slide 11
ABB Offshore Wind ConnectionsEliminating the need of AC substations
Offshore
AC substation
Wind farms
Offshore HVDC
converter station
DC cable
transmission
Onshore HVDC
converter station
November, 2016
© ABB
| Slide 12
ABB Offshore Wind ConnectionsEliminating the need of AC substations
Offshore
AC substation
Offshore HVDC
converter station
DC cable
transmission
Onshore HVDC
converter station
Wind farms
Offshore HVDC
converter station
November, 2016
© ABB
| Slide 13
An HVDC offhore wind solution conceptObjective and customer benefits
Objective
Reduced total cost and delivery time
Ensure predictable execution, based
on defined scope/concept including
well defined interfaces
Modular approach
A conceptual platform design,
enhanced flexibility with regards to
different requirements, site
conditions and general business
models
Minimize offshore hook-up work and
offshore commissioning
Direct connection of Wind Turbine
Generators
Customer benefits
Significantly (50-60%) reduce the
topside weight as compared to the
platform used in DolWin 2 (award
date 2011)
Increased number and smaller lifting
vessels offshore can be utilized
Increased number of yards for
manufacturing
Minimized interface work
Pre-approved technical systems,
smooth handling authority approvals
No need for AC collector platforms
November, 2016
© ABB
| Slide 14
Modularized platform – 2 concepts
Model 3A
2 valve hall modules
1 ABB/YARD General Module
1 Jacket
Minimize number of systems onboard.
Planned to be built modular onshore, tested
as far as possible
Assembly of modules can be completed
onshore or offshore, as best fits the project.
HVDC functionality similar for 3A & 4A.
One module common among yard and ABB
Model 4A
2 valve hall modules
1 ABB General Module
1 YARD Module
1 Jacket
Planned for client options and more systems is
therefore added in the base case.
Planned to be built modular, integrated onshore
and tested, lifted offshore as a single lift.
HVDC functionality similar for 3A & 4A.
ABB scope in dedicated ”ABB Modules”
and YARD scope in separate module
REF DWA
3A4A
November, 2016
© ABB
| Slide 15
Evaluation of HVDC Platform Structures
MODULAR
TOPSIDE
& JACKET
REDUCED
WEIGHT AND
VOLUME
November, 2016
© ABB
| Slide 16
Modular Approach
The key benefits with a modular approach
Parallel Engineering and manufacturing,
Many potential yards/workshops and lifting vessels
Equipment on ground level, separate testing.
Reduce complexity / Manage Interfaces
Dedicated ABB and yard module
Easy to adapt options
Drawbacks with a modular approach
To a certain extent Increased Weight
Some more engineering required.
November, 2016
© ABB
| Slide 17
Capabilities
Rated Power: 800-1,200 MW
Design lifetime: 25-30 Y
DC Voltage (outgoing): ±320 kV
AC Voltage (incoming): 72 kV
Reliability: 98.5%
Dimensions
Size: 40 x 60 x 26 m
Weight: 7,000 T
Volume: 45,000 m3
Location
North Sea conditions
Water Depth 20-50m
Ambient-T -3 to +30 deg.C
RH = 100% winter
and 51% in summer
Flexibility Parallel manufacturing, several
workshop can be utilized
Equipment lifted in on ground
level, separate testing
Divide the scope/interfaces into
modules
Separate lifting of individual
modules possible if needed
A modular approach is well suited
to offer various options
Wider range of lifting vessels
available on the market (cost
reduction and risk mitigation)
Size Reduced Volume
Reduced to ~40x60m,
compared with DolWin2
80x100m
Reduced Weight
More than 50% weight
reduction compared with
DolWin2
Structural
configuration Topside weight ~ 6,000-7,000T ;
can be divided into 3-5 modules
at lower weights
4-leg jacket is the best option for
the understructure
Living quarter, helideck, cranes,
etc. optional
An HVDC offshore solutionKey data Performance
November, 2016
© ABB
| Slide 18
ABB Offshore Wind ConnectionsFeatures of VSC technology
• Independent control of active
and reactive power flow
• Voltage and frequency control
• Connection to passive loads
• Enhancement of connected
AC networks
• No short-circuit power needed
• Black start capability
• Proven high reliability and availability
• Compact station design
• Multi-terminals
November, 2016
© ABB
| Slide 19
Our knowledge is based on a number of completedand ongoing offshore power projects
Princess Amalie
120 MW
AC-connection
Borwin 1
400 MW
HVDC-connection
Thornton Bank
325 MW
AC-connection
Dolwin 1
800 MW
HVDC-connection
Dolwin 2
900 MW
HVDC-connection
Valhall
80 MW HVDC
Power from shore
Troll 1 & 3
80+80 MW HVDC
Power from shore
November, 2016
© ABB
| Slide 20
Experience - Princess AmaliaHVAC-connection of 120 MW Windfarm
• Project
Owner: ENECO 50% and Q7
Holding (Econcern & EIH) 50%
In operation 2007
120 MW, 60 WTG:s
Located 28 km from shore , water
depth 19 - 24 m
• ABB Supply and Services
Electrical System design
Off-shore 150/36 kV substation
Project Utility SCADA
150 kV Export Cable
22 kV Array Cables
November, 2016
© ABB
| Slide 21
Experience - Thornton Bank phase 2 & 3HVAC-connection of 325 MW Windfarm
Customer: C-Power, Belgium
System responsibility for “Electrical balance of
plant”
325 MW Offshore AC Substation
Supply of 38 km of 150 kV Export sea cable
Supply of 55 km of 36 kV Array sea cables
Supply and installation of 6 km of 150 kV land
cable
Demolish temporary substation onshore
Completion July 2013
November, 2016
© ABB
| Slide 22
Experience - Germany, BorWin 1400 MW HVDC Offshore Wind Power Connection
Customer: TenneT, Germany/Netherlands
First HVDC Offshore Wind Power Connector
200 km cable connection (125 km sea, 75 km land)
Turnkey supply including buildings and platform
Contract Sep 2007
Completion Nov 2009
November, 2016
© ABB
| Slide 23
Experience - Germany, DolWin 1800 MW HVDC Offshore Wind Power Connection
Customer: TenneT, Germany/Netherlands
800 MW HVDC Offshore Wind Power
Connector
166 km cable connection
Turnkey supply including buildings and
platform
Contract 2010
Completion 2015
November, 2016
© ABB
| Slide 24
Experience - Germany, DolWin 2900 MW HVDC Offshore Wind Power Connection
Customer: TenneT, Germany/Netherlands
900 MW HVDC Light
135 km cable connection
Connects offshore North Sea wind farms to the
German grid
Turnkey supply including buildings and platform
Contract 2011
Delivery 2015
November, 2016
© ABB
| Slide 25
VSC based HVDCLet our experience work for you
23
1
19
2
8
10 11
125
65
14 1718
16
2021
1
VSC-HVDC projects by ABB
VSC-HVDC projects by others
1. Eagle Pass
2. Macinac
3. Cross Sound
4. Maritime
5. East West Interc.
6. CMS
7. NSL
8. Troll 1 & 2
8. Troll 3 & 4
9. DolWin 1
9. DolWin 2
9. BorWin 1
10. Valhall
10. Johan Svedrup
11. Skagerrak
12. Tjæ reborg
13. NordLink
13. Kriegers Flak
14. Hällsjön
15. NordBalt
16. Gotland
17. Ål-link
18. Estlink
19. Caprivi
20. Murraylink
21. Terranora
4
6
1. Trans Bay
2. INELFE
3. Italy-France
4. NEMO
5. SylWin
6. HelWin 1
6. HelWin 2
6. COBRAcable
7. Ultranet
8. South West Link
9. DolWin 3
9. BorWin 2
9. BorWin 3
1513
73
47
8
9
November, 2016
© ABB
| Slide 26
Offshore wind connectionsSummary
Offshore wind connections will increase
Transmission distance more than
~100 kilometers by HVDC
HVDC system enabled
for offshore DC grid
Fulfillment of Grid Codes
November, 2016