7/31/2019 A7670 ESE Installation Manual
1/42
Evolium UTRAN
A7670 ESE Installation Manual
RNC Transport Node Document
Installation Manual
Release R5
3BK 17429 3155 RJZZA Ed.02
Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
2/42
Status RELEASED
Short title a7670ins
All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Evolium.
BLANK PAGE BREAK
2 / 423BK 17429 3155 RJZZA Ed.02
Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
3/42
Contents
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
1.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.1 Hardware Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.2 System State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.3 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.4 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.5 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.6 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.2.2 Site-Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.2.3 External Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.4 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
1.4.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.4.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141.4.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
2 Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.1 Before Going Onsite . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162.2 Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.3 Position Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.4 Drill Holes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
2.4.1 Concrete Floor (C1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.4.2 Raised Floor (C2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
2.5 Install Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.5.1 Concrete Floor (C1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.5.2 Raised Floor (C2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.5.3 Assemble Earthquake Frame (O1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
2.6 Cable Power Supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.6.1 Route Power Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.6.2 Protective Earth Cable Connection (GND) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.6.3 Connect DC 48-Volt Power Supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 262.6.4 Connect to Test Power Jacks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
2.7 Perform E1 Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.7.1 Install E1 Cable Between A7670 ESE and DDF . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.7.2 Wiring Table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
2.8 Install RNC Ev Optical Fiber Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362.8.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362.8.2 Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362.8.3 Connection Table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
2.9 Shelf Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 392.9.1 STM1 E1 Conversion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 392.9.2 STM1 VC4STM1 VC12 Conversion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
2.10 Before You Leave . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.10.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.10.2 Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 3 / 42
-
7/31/2019 A7670 ESE Installation Manual
4/42
Contents
4 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
5/42
Preface
Preface
Purpose This document describes how to install and cable an A7670 ESE subrackbefore commissioning.
This method is applicable only to the A7670 ESE in R2.2 .
Note: The A7670 ESE is also called the A9140 RNC Transport Node.
Whats New In Edition 02
First official release of document for R5 MR1.
In Edition 01
First official release of the document for HSDPA Field Trial
Audience This scenario is intended for:
Installers
Field service technicians
Site administrators
Project managers
Occasional users.
Assumed Knowledge You must have a basic understanding of the following:
Basic knowledge of Evolium UTRAN equipment
Experience in electrical mounting cabling.
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 5 / 42
-
7/31/2019 A7670 ESE Installation Manual
6/42
Preface
6 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
7/42
1 Overview
1 Overview
This overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 7 / 42
-
7/31/2019 A7670 ESE Installation Manual
8/42
1 Overview
1.1 Presentation
This method describes how to install an A7670 ESE.
The A7670 ESE performs STM1E1 and STM-1 VC4STM1-VC12conversions for the Iub link.
IMA configurations are supported.
1.1.1 Hardware Description
The figure below shows the front view of the A7670 ESE.
1.1.2 System State
1.1.2.1 Initial State
To the start of this method, the following materials are delivered and packedonsite:
The A7670 ESE rack with the A7670 ESE shelfThe installation kits.
1.1.2.2 Final State
At the end of this method:
The rack is ready for commissioning (refer to A7670 ESE commissioning
Manual)
The rack is powered Off.
8 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
9/42
1 Overview
1.1.3 Cases
The following cases apply to this method:
C1: The rack is installed on a concrete floor (cable routing above the rack)
C2: The rack is installed on a raised floor (cable routing below the raised
floor).
Cable entry
STM1
Optical cable
Power supply
E1
Cable way
Floor
7670 ESERack
Figure 1: Rack installation on Concrete Floor
STM1Optical cable
Cable routing
Raised floorCable entry
Power supply
7670 ESERack E1
Figure 2: Rack installation on Raised Floor
1.1.4 Options
The following option applies to this method:
O1: Earthquake frame installation
1.1.5 Restrictions
None.
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 9 / 42
-
7/31/2019 A7670 ESE Installation Manual
10/42
1 Overview
1.1.6 Grouped Task Sequence
The following figure shows the grouped task sequence for installing the A7670ESE:
Before You Start
Position Rack
Install RNC Ev
Optical fiber Cable
Before You Leave
Drill Holes
Install Rack
Cable Power Supply
Perform E1 Cabling
Assemble
Hearthquake Frame (O1)
Figure 3: A7670 ESE Installation Scenario
10 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
11/42
1 Overview
1.2 Preparation
1.2.1 Prerequisites
The following prerequisites apply:
The A7670 subrack is available
The following installation kits are available
Power cables
STM-1 cables
E1 cables.
1.2.2 Site-Specific Information
The following site-specific information is required:
Address and access to the site (key holder)
Grounding plate location
Customer power supply cabinet location
Fuse breaker location in customer power supply cabinet
Precise rack location.
1.2.3 External Tasks
None.
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 11 / 42
-
7/31/2019 A7670 ESE Installation Manual
12/42
1 Overview
1.3 Scheduling
Time based on technical constraintsThe amount of resources in the following table do not take into accountindividual customer or safety requirements.
Grouped Task Site Time/Task
Before You Start (Section 2.2) A7670 ESE 15 min.
Position Rack (Section 2.3) A7670 ESE 30 min.
Drill Holes (Section 2.4) (C1 or C2) A7670 ESE 10 min.
Install Rack (Section 2.5) (C1 or C2) A7670 ESE 10 min.
Assemble Earthquake Frame (O1) (Section2.5.3) (C1 or C2) A7670 ESE 10 min.
Cable Power Supply (Section 2.6) A7670 ESE 60 min.
Perform E1 Cabling (Section 2.7) A7670 ESE 60 min.
Install RNC Ev Optical Fiber Cable (Section2.8)
A7670 ESE 60 min.
Before You Leave (Section 2.10) A7670 ESE 15 min.
TOTAL TIME: 4h 20 min. Total Time
O1: 10 min.
C1: 10 min. (included)
C2: 10 min. (included)
12 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
13/42
1 Overview
1.4 Resources
1.4.1 Tools
1.4.1.1 Hardware Tools
Refer to the Tools Catalog to check the content of the required tools.
Name Reference Calibration
Basic tools OUT 001 No
1.4.1.2 Installation Kits
The following table is used to check, onsite, the mandatory or optional deliveryitem kits.
The symbols used are: = mandatory kit
# = technical choice kit
XXX = customer option kit.
Mandatory kits Mnemonic Reference Qty
Basic kit BKIT7670 3BK 26733 AA 1
# DC power cable 1x10mm2
100 m roll (black)
PC10B1D 3BK 08937 BAAA 1
# DC power cable 1x10mm2black in 250 m roll
PC10B1D 3BK 08957 BBAA 1
# DC power cable 1x10mm2blue in 100 m roll
PC10BL1 3BK 26923 AAAA 1
# DC power cable 1x10mm2blue in 250 m roll
PC10BL1 3BK 26923 ABAA 1
Protective Earth (GND)cable (yellow / green)
PC16YG1D 3BK 08957 BAAA reel
# Up to 4 optical fiber cable20 m (C2)
Up to 7 optical fiber cables20 m (C1)
ULOPT6 3BK 25999 HAAA 1
XXX 36U rack INCA7670 3BK 26659 AAAA 1
1.4.1.3 Software Tools
None.
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 13 / 42
-
7/31/2019 A7670 ESE Installation Manual
14/42
1 Overview
1.4.1.4 Forms
Item Part Number Site
Completion CheckList
3BK 17429 0006 RJZZA(Z2EV00007-0031)
RNC Ev
Evolium A9140 RNCService ReferenceSheet
3BK 17429 5007 RJZZA(Z2EV00007-0036)
RNC Ev
1.4.2 Supplies
The installer must supply a set of rubber sleeves.
1.4.3 Applicable Documents
You need the following documents to complete this scenario:
Applicable Notification List
(3DF 00462 0004 AAAGA)
Applicable Operation Instructions(3DF 00300 0004 UAZZA)
General Wiring Handbook for UMTS(3BK 17429 8099 RJZZA)
Tools Catalogue(3BK 17429 0007 RJZZA)
SPP-57 / Specification For RNC Evolution Site Preparation(8BL 00704 0062 DRBRA)
A7670 Commissioning Manual(3BK 17429 4141 RJZZA)
Evolium A9140 RNC Evolution Installation Manual(3BK 17429 8015 RJZZA).
14 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
15/42
2 Scenario
2 Scenario
This section presents all checks needed before beginning the scenario, and alldetailed tasks to be performed on each site.
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 15 / 42
-
7/31/2019 A7670 ESE Installation Manual
16/42
2 Scenario
2.1 Before Going Onsite
Before going onsite, ensure that:
All Prerequisites (Section 1.2.1) are fulfilled
The Site-Specific Information (Section 1.2.2)is available and ready for
operation
The Applicable Documents (Section 1.4.3) are available
Tools (Section 1.4.1) are available and ready for operation
Personnel are available and ready for operation (refer to Scheduling
(Section 1.3))
Supplies (Section 1.4.2) are available and ready for operation
The header field of the CCL is filled in
The customer has been informed of the:
Date
Time
Site name
Site address
Purpose of the operation.
2.2 Before You Start
2.2.1 Checks
Perform the following operations:
Check that the A7670 ESE is powered off.
Check that all Prerequisites (Section 1.2.1) are fulfilled.
Check the availability of all necessary Tools (Section 1.4.1) and Supplies
(Section 1.4.2).
Inform the operator.
2.2.2 Required Knowledge
You must be familiar with the following:
Safety rules and precautions
Grouped task sequence
Operator hints
How to document faults and anomalies.
16 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
17/42
2 Scenario
2.3 Position Rack
If the A7670 ESE is installed at same site as an RNC Ev, the rack must beinstalled close to the corresponding RNC Ev, just to the right or left of the RNCEv (due to cable length).
2.4 Drill Holes
To be compliant with EN 60950 rules, the rack must be secured to the floor.
There are two installation cases:
Installation on concrete floor
Installation on raised floor
2.4.1 Concrete Floor (C1)To drill the concrete floor:
1. Mark the concrete foundation using the drilling diagram described in Figure 5.
2. Drill the holes in the concrete foundation (diameter 12 mm, h = 70 mm).
Drilling Point
Rear
Front
Figure 4: Drilling Diagram
2.4.2 Raised Floor (C2)
1
2
Figure 5: Drilling on a Raised Floor
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 17 / 42
-
7/31/2019 A7670 ESE Installation Manual
18/42
2 Scenario
To drill the raised floor:
1. Cut a rectangular hole in the tile to insert the cables using the drillingdiagram described in the previous section.
2. Drill the holes in the tile (diameter 12 mm).
3. Drill the floor (diameter 12 mm, h = 60 mm +/- 3 mm).
18 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
19/42
2 Scenario
2.5 Install Rack
2.5.1 Concrete Floor (C1)
2.5.1.1 Materials
Item Qty Designation Reference Kit
1 4 Expanding plug 1AD 01666 0001
2 4 Screw HM8x65 1AD 00215 0042
3 4 Washer 8 1AD 00087 0149
RKIT36U 3BK 27026AAAA
2.5.1.2 Procedure
5 mmLevelling foot
Figure 6: Rack Installation on Concrete Floor
To secure the rack to the concrete floor:
1. Level the rack.
2. Secure the rack to the concrete floor.
2.5.2 Raised Floor (C2)
2.5.2.1 Materials
Item Qty Designation Reference Kit
1 4 Cylinder splicing sleeveM8x30mm 1AD 01655 0001
2 4 Screw HM 8x80 1AD 00215 0092
3 4 Threaded bar M8x1000mm 1AD 01660 0003
4 8 Washer 8 1AD 00087 0149
5 8 Hex. nut M8 1AD 00197 0006
6 1 Metallic sheath, length 4.5m 1AB 06084 0030
JDTCFF 3BK 25341 AAAA
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 19 / 42
-
7/31/2019 A7670 ESE Installation Manual
20/42
2 Scenario
2.5.2.2 Procedure
4
5
2
1
4
3
Figure 7: Rack Installation on Raised Floor
To secure the rack to the raised floor:
1. Insert the expanding plug in the concrete floor.
2. Screw the threaded rod (3), then the washer (4) and nut (5).
3. Screw the coupling nut (1).
4. Screw the screw (2) with the washer (4).
Note: In this case, do not level the rack.
2.5.3 Assemble Earthquake Frame (O1)
This option can be installed with a raised floor exactly 34 cm high from theconcrete ground only.
20 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
21/42
2 Scenario
2.5.3.1 Materials
Item Qty Designation Reference Kit
1 2 Pedestal 3BK 25339 AAXX
2 2 Bracket 3BK 25340 AAXX
3 4 Screw HM16x40 1AD 00204 0059
4 4 Washer 16.4x32x2.8 1AD 00254 0006
5 4 Screw HM8x35 1AD 00204 0038
6 4 Washer 8.2x16x1.4 1AD 00254 0003
7 4 Hex. nut M8x6.8 1AD 00197 0006
8 4Expanding plug M10x60 1AD 02655 0001
9 4 Washer lock 10.2x20x1.6 1AD 00453 0005
10 4 Screw HM10x65 1AD 00050 0010
JDSISM 3BK25284 AAAA
2.5.3.2 Procedure
5
7
6
1 4 3 2
10
9
8
Figure 8: Mechanical Assembly of Earthquake Frame
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 21 / 42
-
7/31/2019 A7670 ESE Installation Manual
22/42
2 Scenario
7670 Rack
5
6
340 mm
Tile
7
10
9
8
Earthquakeframe
Figure 9: Earthquake Frame Assembly (Raised Floor at Same Level asEarthquake Frame)
To secure the earthquake frame:
1. Assemble the earthquake frame using the screw (3) and washer (4) (referto Figure 9).
2. Using the earthquake frame, mark the concrete ground.
3. Drill the ground and insert the wall plug (8) (refer to Figure 10).
4. Secure the earthquake frame using washer (9) and screw (10).
5. Secure the rack to the frame using (5), (6) and (7).
6. Cut and fit the tiles around the earthquake frame.
22 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
23/42
-
7/31/2019 A7670 ESE Installation Manual
24/42
2 Scenario
2.6.1.2 Procedure
A7670 ESE
48 Volts
Power Supply
48 0
Power cable1 x 10 mm
Jumper cables
GND ProtectiveEarth (16 mm
Figure 10: Power Supply Distribution.
1. For a raised floor, drill a 5 cm diameter hole in the tile to insert the cables.
For a concrete foundation, secure the metallic sheath to the top of the rack.
2. Insert the cables in the hole or in the metallic sheath.
3. Insert the cables in the cable passage.
4. Secure the cables to the cable passage.
24 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
25/42
2 Scenario
2.6.2 Protective Earth Cable Connection (GND)
2.6.2.1 Materials
Description Reference Kit
GND Protective Earth cable (yellow / green) 3BK 08957 BAAA Installation kit
Lug hole 10 mm for 16 mm2 1AB 03205 0048 Installation kit
2.6.2.2 Procedure
1. Prepare the head of cable at the site side.
2. Crimp an adapted 2-hole lug to the head of cable.
3. Connect the GND cable to the site GND.
4. Remove 1 cm of skin at the head of the cable (rack side).
5. Insert the cable in GND connector at the rear top of the subrack (seeFigure 12).
6. Screw the GND cable to the subrack.
Groundingcable
To groundingpoint
1032 KEPS
2holelug
Studs
Figure 11: Connecting to Chassis Ground
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 25 / 42
-
7/31/2019 A7670 ESE Installation Manual
26/42
2 Scenario
2.6.3 Connect DC 48-Volt Power Supply
2.6.3.1 Materials
Description Reference Kit
DC power cable 1x10mm2 black 3BK 08937 BAAA or BBAA Installation kit
DC power cable 1x10mm2 blue 3BK 26923 AAAA or ABAA Installation kit
Lug 2-holes 5 mm for 10 mm2 1AB 05153 0053 Installation kit
Set of rubber sleeves none Consumable
2.6.3.2 Procedure
1. Make sure the A7670 ESE switches are Off (Refer to Figure 14).
2. Make sure the site power supply breakers are Off.
3. Run the wires from the power sources to the terminal block on the back ofthe shelf.
4. Remove the protective cover from the input power terminal.
5. Remove the two nuts and washers on the two studs labeled -VBATT.
6. Fit a 2-hole lug of 5 mm for 10 mm2 to the end of wire.
7. Fit a rubber sleeve to the head of the wire. Label the wire -VBATT.
8. Place the 2-hole lug over the two studs. (Refer to Figure 13.)
9. Repeat steps 5 to 8 for each wire (in this example, 4 wires). Label each
wires according to the label on the stud to which it is attached.
10. Fit a 2-hole lug to each end of the jumper cable.
11. Place each 2-hole lug over the two studs on power feed A and power feed B.(Refer to Figure 15.)
12. Insert the nuts and washers and tighten with a torque wrench.
13. Put the protective cover back on the input power terminal.
14. Fit the appropriate lugs at the site side.
15. Fit the appropriate rubber sleeves.
16. Connect the wire to the site power supply as follows:
0V / A1 Black
-48V / A1 Blue
0V / A2 Black
-48V / A2 Blue
26 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
27/42
2 Scenario
1A
2A
From twopower feeds
Powercable
1032 KEPS
2holelugStuds
0VR
VBATT
0VR
VBATT
Figure 12: Power Cable Attachment
Power module
ON
0V 48VZone 1
Power status
Test jacks
Status LED
Circuit breaker
Figure 13: Circuit Breaker and Monitor Jacks
Jumpercables (x4)
Front twopower feeds
Figure 14: Jumper Cable Attachment
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 27 / 42
-
7/31/2019 A7670 ESE Installation Manual
28/42
2 Scenario
2.6.4 Connect to Test Power Jacks
To connect to the test power jacks:
1. Set the multimeter to the appropriate function and range.
2. Insert the test probes in the jack labeled -48v and 0v for the appropriate
power feed.
3. Read the result (the acceptable input voltage range is from -40v to -70v).
28 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
29/42
2 Scenario
2.7 Perform E1 Cabling
This section provides the procedures for E1 120 Ohm only.
2.7.1 Install E1 Cable Between A7670 ESE and DDF
2.7.1.1 Connect E1 on A7670 ESE Side
The table below lists the supplies needed to connect the E1 to the A7670 ESE.
Description Reference Kit
E1 cable with connector (20 or 40 m) shielded 3BK 26632 HA (20m)
3BK 26632 JL (40m)
List of kits
Tie wraps 1AD 00414 0006 Basic kit
To connect the E1 to the A7670 ESE:
1. Insert both E1 cables with the connector into the cable passage.
2. Using tie wraps, attach the cables to the cable passage (every meter).
3. Remove the EMI covers, if installed, from the upper and lower connectors onthe back of A7670 ESE shelf where the board is installed. Store the covers.The upper connector corresponds to ports 1 to 16 on a 32-port board, andthe lower connector corresponds to ports 17 to 32. Refer to Figure 16.
4. Align the first E1 cable with the connector with the upper connector for ports1 to 16 where the board is installed. Ensure that the connector and thecable are facing up. Push the connector into place. (Refer to Figure 17.)
5. Label the first E1 cable with the labeling machine.
6. Repeat steps 4 to 5 with the second E1 cable for the lower connector(ports 17 to 32).
7. Attach E1 cables to the rear of the rack (tie wraps).
8. Using the wiring table (refer to Table 1), connect the other end of the E1cable to the DDF (refer to E1 Connection on DDF Side(Section 2.7.1.2).
As with other installation cables, these E1 cables must be inserted in the same
site cable passage (either at the top of rack or in a raised floor).
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 29 / 42
http://-/?-http://-/?-http://-/?-http://-/?-http://-/?- -
7/31/2019 A7670 ESE Installation Manual
30/42
2 Scenario
The following figures show connections on the back side of the A7670 ESE:
331
64
Port1
Port16
Top connector Botom connector
32Port32
Port17
64
33
Figure 15: 64-pin Connectors on Back Side of A7670 ESE
Cable tie
Cable clamp
Upper row
Captive screw
Cable clamp
Notch
Figure 16: E1 Cable Connection on Back Side of A7670 ESE
30 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
31/42
2 Scenario
2.7.1.2 E1 Connection on DDF Side
Cable Route for 120-ohm Terminal Block
Rx Tx
A7670 ESE
RNC V1 Evol
DDF
Optical cable (STM1)in case of Conccrete FloorSTM1 for lub interface
E1 cable
(Note) One Terminal Block is used for one E1 cable.
Figure 17: E1 Cabling with 120-Ohm Terminal Block
1 2 3 4 5 6 07 8 9
Link1
Link2
Link3 Link5
Link4 Link6
Link7
Link8
Not Use
Figure 18: Front View of 120-ohm Terminal Block (JS10)
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 31 / 42
-
7/31/2019 A7670 ESE Installation Manual
32/42
2 Scenario
Cable Route for 75/120-ohm Terminal Block
RNC V1 Evol
Figure 19: Cabling with 75/120-ohm Adapter Terminal Block
4 3 2 1
8 7 6 5
12 11 10 9
16 15 14 13
20 19 18 17
24 13 12 21
34
12
78
56
1112
910
1516
1314
1920
1718
2324
2122
Circuit Number
Pair CableConnect Point
A B
AB
Figure 20: Rear View of 75/120-ohm Terminal Block Adapter
1
5 67 8
910 11
12
13 1415 16
1718 19
20
21
22 2324
42 3
frame Earth
Circuit Number
Coaxial CableConnect Point
(Note 1)Tx side connects the frameearth with DDF frame(Note 2)
Adaptor is used separatelyfor Tx and Rx
Figure 21: Front View of 75/120-ohm Terminal Block Adapter
32 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
33/42
2 Scenario
2.7.2 Wiring Table
The table below shows the wiring table for the E1 cables 3BK 26632 HAABand 3BK 26632 JLAB
Cable Assignment Signal NameChamp
pinUnit Pair Cond. Wire color 8xE1 board
(Upper row)
32xE1 board
(Upper row)
32xE1 board
(Lower row)
33 1 1 1 White P1 RT P1 TT P17 TT
1 1 1 2 Blue P1 RR P1 TR P17 TR
34 1 2 1 White P1 TT P1 RT P17 RT
2 1 2 2 Yellow P1 TR P1 RR P17 RR
35 1 3 1 White P2 TT P18 TT
3 1 3 2 Brown P2 TR P18 TR
36 1 4 1 White P2 RT P2 RT P18 RT
4 1 4 2 Black P2 RR P2 RR P18 RR
37 1 5 1 White P2 TT P3 TT P19 TT
5 1 5 2 Green P2 TR P3 TR P19 TR
38 1 6 1 White P3 RT P19 RT
6 1 6 2 Orange P3 RR P19 RR
39 1 7 1 White P3 RT P4 TT P20 TT
7 1 7 2 Grey P3 RR P4 TR P20 TR
40 1 8 1 White P3 TT P4 RT P20 RT
8 1 8 2 Purple P3 TR P4 RR P20 RR
41 2 1 1 White P5 TT P21 TT
9 2 1 2 Blue P5 TR P21 TR
42 2 2 1 White P4 RT P5 RT P21 RT
10 2 2 2 Yellow P4 RR P5 RR P21 RR
43 2 3 1 White P4 TT P6 TT P22 TT
11 2 3 2 Brown P4 TR P6 TR P22 TR
44 2 4 1 White P6 RT P22 RT
12 2 4 2 Black P6 RR P22 RR
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 33 / 42
-
7/31/2019 A7670 ESE Installation Manual
34/42
2 Scenario
Cable Assignment Signal NameChamppin
Unit Pair Cond. Wire color 8xE1 board
(Upper row)
32xE1 board
(Upper row)
32xE1 board
(Lower row)
45 2 5 1 White P5 RT P7 TT P23 TT
13 2 5 2 Green P5 RR P7 TR P23 TR
46 2 6 1 White P5 TT P7 RT P23 RT
14 2 6 2 Orange P5 TR P7 RR P23 RR
47 2 7 1 White P8 TT P24 TT
15 2 7 2 Grey P8 TR P24 TR
48 2 8 1 White P6 RT P8 RT P24 RT
16 2 8 2 Purple P6 RR P8 RR P24 RR
49 3 1 1 White P6 TT P9 TT P25 TT
17 3 1 2 Blue P6 TR P9 TR P25 TR
50 3 2 1 White P9 RT P25 RT
18 3 2 2 Yellow P9 RR P25 RR
51 3 3 1 White P7 RT P10 TT P26 TT
19 3 3 2 Brown P7 RR P10 TR P26 TR
52 3 4 1 White P7 TT P10 RT P26 RT
20 3 4 2 Black P7 TR P10 RR P26 RR
53 3 5 1 White P11 TT P27 TT
21 3 5 2 Green P11 TR P27 TR
54 3 6 1 White P8 RT P11 RT P27 RT
22 3 6 2 Orange P8 RR P11 RR P27 RR
55 4 7 1 White P8 TT P12 TT P28 TT
23 3 7 2 Grey P8 TR P12 TR P28 TR
56 3 8 1 White P12 RT P28 RT
24 3 8 2 Purple P12 RR P28 RR
57 4 1 1 White P13 TT P29 TT
25 4 1 2 Blue P13 TR P29 TR
34 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
35/42
2 Scenario
Cable Assignment Signal NameChamppin
Unit Pair Cond. Wire color 8xE1 board
(Upper row)
32xE1 board
(Upper row)
32xE1 board
(Lower row)
58 4 2 1 White P13 RT P29 RT
26 4 2 2 Yellow P13 RR P29 RR
59 4 3 1 White P14 TT P30 TT
27 4 3 2 Brown P14 TR P30 TR
60 4 4 1 White P14 RT P30 RT
28 4 4 2 Black P14 RR P30 RR
61 4 5 1 White P15 TT P31 TT
29 4 5 2 Green P15 TR P31 TR
62 4 6 1 White P15 RT P31 RT
30 4 6 2 Orange P15 RR P31 RR
63 4 7 1 White P16 TT P32 TT
31 4 7 2 Grey P16 TR P32 TR
64 4 8 1 White P16 RT P32 RT
32 4 8 2 Purple P16 RR P32 RR
Table 1: Wiring Table for E1 Cables 3BK 26632 xxAB
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 35 / 42
-
7/31/2019 A7670 ESE Installation Manual
36/42
2 Scenario
2.8 Install RNC Ev Optical Fiber Cable
2.8.1 Materials
Description Reference Kit
Optical fiber cable:
Case 1: Up to 7 pairs of fibers
Case 2: Up to 4 pairs of fibers
3BK 25999 HAAA List of kits
2.8.2 Procedure
1. Insert the multifiber cable in the cable passage.
2. Insert the multifiber cable in the cable gland of the RNC Ev (refer to the RNCEv Installation Manual).
3. Attach the multifiber cable to the cable passage and to the equipment.
4. Connect the optical fibers to the A7670 ESE, to the ODF and to the RNCEv ( refer to Figure 23).
5. Label the fibers.
As with other installation cables, these cables must be inserted in the same sitecable passage (either at the top of the rack or in the raised floor).The single optical fibers must not be tied to the rack; the multifiber cablecan, however, be tied to the rack.
36 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
37/42
2 Scenario
Optical cables used on the RNC Ev side:The optical cables used for Iub links use monomode fibers, with LC connectorsat the RNC Ev side, and SC connectors on the other side (connection to ODFor to A7670 ESE).
MSIF
0
1
2
3
lu / lur / O&M
lub
Figure 22: Optical Fiber Connection on RNC Ev Side
The following connections are fixed:Slot # 0 Port #1Slot # 10 Port #2
12
Figure 23: Threading Fiber Cables in a Mid-mount Bracket
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 37 / 42
-
7/31/2019 A7670 ESE Installation Manual
38/42
2 Scenario
2.8.3 Connection Table
Type of Cable From To
Optical fiber A7670 /STM1 board X #1/ RX RNC Evolution / M-SIF / #1 TX (Iub)
Optical fiber A7670 /STM1 board X #1/ TX RNC Evolution / M-SIF / #1 RX(Iub)
Optical fiber A7670 /STM1 board X #2/ RX RNC Evolution / M-SIF / #2 TX (Iub)
Optical fiber A7670 /STM1 board X #2/ TX RNC Evolution / M-SIF / #2 RX(Iub)
Optical fiber A7670 /STM1 board X #3/ RX RNC Evolution / M-SIF / #3 TX (Iub)
Optical fiber A7670 /STM1 board X #3/ TX RNC Evolution / M-SIF / #3 RX(Iub)
Table 2: Connection Table
38 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
39/42
2 Scenario
2.9 Shelf Configurations
Note: The configurations presented in the following tables illustrate maximumconfigurations.
2.9.1 STM1 E1 Conversion
Slot Front Board Adapter Board Function in UTRAN
X ECC (Control) + Quad STM-1 IR RNC Ev 7670: Iub 1
1 Filler plate
2 Filler plate
3 Filler plate
4Filler plate
5 Filler plate
6 Filler plate
7 E1 32 ports T1/E1 Iub (Node B 7670)
8 E1 32 ports T1/E1 Iub (Node B 7670)
9 E1 32 ports T1/E1 Iub (Node B 7670)
10 E1 32 ports T1/E1 Iub (Node B 7670)
11 E1 32 ports T1/E1 Iub (Node B 7670)
12 E1 32 ports T1/E1 Iub (Node B 7670)
Y ECC (Control)
1 : 4 STM1 links are used for Iub.: Filling order: Start with boards 11,12, etc.
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 39 / 42
-
7/31/2019 A7670 ESE Installation Manual
40/42
2 Scenario
2.9.2 STM1 VC4STM1 VC12 Conversion
Slot Front Board Adapter Board Function in UTRAN
X ECC (Control) + Quad STM-1 IR RNC Ev 76701
1 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)
2 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)
3 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)
4 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)
5 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)
6 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)
7 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)
8 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)
9 Filler plate
10 Filler plate
11 Filler plate
12 Filler plate
Y ECC (Control)
1 : 4 STM1 links are used for Iub.: Filling order: Start with boards 2,3, etc. This allows mixed configurations (STM1 T1/E1 or VC12).
40 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02
-
7/31/2019 A7670 ESE Installation Manual
41/42
2 Scenario
2.10 Before You Leave
2.10.1 Materials
Description Reference Kit
Earth braids None Supplied with rack
2.10.2 Procedure
1. If a metallic sheath was installed, stretch it for inspection.
2. Secure the metallic sheath to the site cable passage (if applicable).
3. Secure the earth braids to the side panels (delivered with the rack).
4. Label the A7670 ESE rack to identify it.
3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 41 / 42
-
7/31/2019 A7670 ESE Installation Manual
42/42
2 Scenario