  • 7/31/2019 A7670 ESE Installation Manual

    1/42

    Evolium UTRAN

    A7670 ESE Installation Manual

    RNC Transport Node Document

    Installation Manual

    Release R5

    3BK 17429 3155 RJZZA Ed.02

    Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    2/42

    Status RELEASED

    Short title a7670ins

    All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Evolium.

    BLANK PAGE BREAK

    2 / 423BK 17429 3155 RJZZA Ed.02

    Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    3/42

    Contents

    Contents

    Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

    1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

    1.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.1 Hardware Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.2 System State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.3 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.4 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.5 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.6 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

    1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.2.2 Site-Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.2.3 External Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

    1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.4 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

    1.4.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.4.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141.4.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

    2 Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

    2.1 Before Going Onsite . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162.2 Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

    2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

    2.3 Position Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.4 Drill Holes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

    2.4.1 Concrete Floor (C1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.4.2 Raised Floor (C2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

    2.5 Install Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.5.1 Concrete Floor (C1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.5.2 Raised Floor (C2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.5.3 Assemble Earthquake Frame (O1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

    2.6 Cable Power Supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.6.1 Route Power Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.6.2 Protective Earth Cable Connection (GND) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.6.3 Connect DC 48-Volt Power Supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 262.6.4 Connect to Test Power Jacks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28

    2.7 Perform E1 Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.7.1 Install E1 Cable Between A7670 ESE and DDF . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.7.2 Wiring Table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

    2.8 Install RNC Ev Optical Fiber Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362.8.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362.8.2 Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362.8.3 Connection Table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38

    2.9 Shelf Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 392.9.1 STM1 E1 Conversion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 392.9.2 STM1 VC4STM1 VC12 Conversion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40

    2.10 Before You Leave . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.10.1 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.10.2 Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 3 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    4/42

    Contents

    4 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    5/42

    Preface

    Preface

    Purpose This document describes how to install and cable an A7670 ESE subrackbefore commissioning.

    This method is applicable only to the A7670 ESE in R2.2 .

    Note: The A7670 ESE is also called the A9140 RNC Transport Node.

    Whats New In Edition 02

    First official release of document for R5 MR1.

    In Edition 01

    First official release of the document for HSDPA Field Trial

    Audience This scenario is intended for:

    Installers

    Field service technicians

    Site administrators

    Project managers

    Occasional users.

    Assumed Knowledge You must have a basic understanding of the following:

    Basic knowledge of Evolium UTRAN equipment

    Experience in electrical mounting cabling.

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 5 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    6/42

    Preface

    6 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    7/42

    1 Overview

    1 Overview

    This overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 7 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    8/42

    1 Overview

    1.1 Presentation

    This method describes how to install an A7670 ESE.

    The A7670 ESE performs STM1E1 and STM-1 VC4STM1-VC12conversions for the Iub link.

    IMA configurations are supported.

    1.1.1 Hardware Description

    The figure below shows the front view of the A7670 ESE.

    1.1.2 System State

    1.1.2.1 Initial State

    To the start of this method, the following materials are delivered and packedonsite:

    The A7670 ESE rack with the A7670 ESE shelfThe installation kits.

    1.1.2.2 Final State

    At the end of this method:

    The rack is ready for commissioning (refer to A7670 ESE commissioning

    Manual)

    The rack is powered Off.

    8 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    9/42

    1 Overview

    1.1.3 Cases

    The following cases apply to this method:

    C1: The rack is installed on a concrete floor (cable routing above the rack)

    C2: The rack is installed on a raised floor (cable routing below the raised

    floor).

    Cable entry

    STM1

    Optical cable

    Power supply

    E1

    Cable way

    Floor

    7670 ESERack

    Figure 1: Rack installation on Concrete Floor

    STM1Optical cable

    Cable routing

    Raised floorCable entry

    Power supply

    7670 ESERack E1

    Figure 2: Rack installation on Raised Floor

    1.1.4 Options

    The following option applies to this method:

    O1: Earthquake frame installation

    1.1.5 Restrictions

    None.

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 9 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    10/42

    1 Overview

    1.1.6 Grouped Task Sequence

    The following figure shows the grouped task sequence for installing the A7670ESE:

    Before You Start

    Position Rack

    Install RNC Ev

    Optical fiber Cable

    Before You Leave

    Drill Holes

    Install Rack

    Cable Power Supply

    Perform E1 Cabling

    Assemble

    Hearthquake Frame (O1)

    Figure 3: A7670 ESE Installation Scenario

    10 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    11/42

    1 Overview

    1.2 Preparation

    1.2.1 Prerequisites

    The following prerequisites apply:

    The A7670 subrack is available

    The following installation kits are available

    Power cables

    STM-1 cables

    E1 cables.

    1.2.2 Site-Specific Information

    The following site-specific information is required:

    Address and access to the site (key holder)

    Grounding plate location

    Customer power supply cabinet location

    Fuse breaker location in customer power supply cabinet

    Precise rack location.

    1.2.3 External Tasks

    None.

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 11 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    12/42

    1 Overview

    1.3 Scheduling

    Time based on technical constraintsThe amount of resources in the following table do not take into accountindividual customer or safety requirements.

    Grouped Task Site Time/Task

    Before You Start (Section 2.2) A7670 ESE 15 min.

    Position Rack (Section 2.3) A7670 ESE 30 min.

    Drill Holes (Section 2.4) (C1 or C2) A7670 ESE 10 min.

    Install Rack (Section 2.5) (C1 or C2) A7670 ESE 10 min.

    Assemble Earthquake Frame (O1) (Section2.5.3) (C1 or C2) A7670 ESE 10 min.

    Cable Power Supply (Section 2.6) A7670 ESE 60 min.

    Perform E1 Cabling (Section 2.7) A7670 ESE 60 min.

    Install RNC Ev Optical Fiber Cable (Section2.8)

    A7670 ESE 60 min.

    Before You Leave (Section 2.10) A7670 ESE 15 min.

    TOTAL TIME: 4h 20 min. Total Time

    O1: 10 min.

    C1: 10 min. (included)

    C2: 10 min. (included)

    12 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    13/42

    1 Overview

    1.4 Resources

    1.4.1 Tools

    1.4.1.1 Hardware Tools

    Refer to the Tools Catalog to check the content of the required tools.

    Name Reference Calibration

    Basic tools OUT 001 No

    1.4.1.2 Installation Kits

    The following table is used to check, onsite, the mandatory or optional deliveryitem kits.

    The symbols used are: = mandatory kit

    # = technical choice kit

    XXX = customer option kit.

    Mandatory kits Mnemonic Reference Qty

    Basic kit BKIT7670 3BK 26733 AA 1

    # DC power cable 1x10mm2

    100 m roll (black)

    PC10B1D 3BK 08937 BAAA 1

    # DC power cable 1x10mm2black in 250 m roll

    PC10B1D 3BK 08957 BBAA 1

    # DC power cable 1x10mm2blue in 100 m roll

    PC10BL1 3BK 26923 AAAA 1

    # DC power cable 1x10mm2blue in 250 m roll

    PC10BL1 3BK 26923 ABAA 1

    Protective Earth (GND)cable (yellow / green)

    PC16YG1D 3BK 08957 BAAA reel

    # Up to 4 optical fiber cable20 m (C2)

    Up to 7 optical fiber cables20 m (C1)

    ULOPT6 3BK 25999 HAAA 1

    XXX 36U rack INCA7670 3BK 26659 AAAA 1

    1.4.1.3 Software Tools

    None.

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 13 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    14/42

    1 Overview

    1.4.1.4 Forms

    Item Part Number Site

    Completion CheckList

    3BK 17429 0006 RJZZA(Z2EV00007-0031)

    RNC Ev

    Evolium A9140 RNCService ReferenceSheet

    3BK 17429 5007 RJZZA(Z2EV00007-0036)

    RNC Ev

    1.4.2 Supplies

    The installer must supply a set of rubber sleeves.

    1.4.3 Applicable Documents

    You need the following documents to complete this scenario:

    Applicable Notification List

    (3DF 00462 0004 AAAGA)

    Applicable Operation Instructions(3DF 00300 0004 UAZZA)

    General Wiring Handbook for UMTS(3BK 17429 8099 RJZZA)

    Tools Catalogue(3BK 17429 0007 RJZZA)

    SPP-57 / Specification For RNC Evolution Site Preparation(8BL 00704 0062 DRBRA)

    A7670 Commissioning Manual(3BK 17429 4141 RJZZA)

    Evolium A9140 RNC Evolution Installation Manual(3BK 17429 8015 RJZZA).

    14 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    15/42

    2 Scenario

    2 Scenario

    This section presents all checks needed before beginning the scenario, and alldetailed tasks to be performed on each site.

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 15 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    16/42

    2 Scenario

    2.1 Before Going Onsite

    Before going onsite, ensure that:

    All Prerequisites (Section 1.2.1) are fulfilled

    The Site-Specific Information (Section 1.2.2)is available and ready for

    operation

    The Applicable Documents (Section 1.4.3) are available

    Tools (Section 1.4.1) are available and ready for operation

    Personnel are available and ready for operation (refer to Scheduling

    (Section 1.3))

    Supplies (Section 1.4.2) are available and ready for operation

    The header field of the CCL is filled in

    The customer has been informed of the:

    Date

    Time

    Site name

    Site address

    Purpose of the operation.

    2.2 Before You Start

    2.2.1 Checks

    Perform the following operations:

    Check that the A7670 ESE is powered off.

    Check that all Prerequisites (Section 1.2.1) are fulfilled.

    Check the availability of all necessary Tools (Section 1.4.1) and Supplies

    (Section 1.4.2).

    Inform the operator.

    2.2.2 Required Knowledge

    You must be familiar with the following:

    Safety rules and precautions

    Grouped task sequence

    Operator hints

    How to document faults and anomalies.

    16 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    17/42

    2 Scenario

    2.3 Position Rack

    If the A7670 ESE is installed at same site as an RNC Ev, the rack must beinstalled close to the corresponding RNC Ev, just to the right or left of the RNCEv (due to cable length).

    2.4 Drill Holes

    To be compliant with EN 60950 rules, the rack must be secured to the floor.

    There are two installation cases:

    Installation on concrete floor

    Installation on raised floor

    2.4.1 Concrete Floor (C1)To drill the concrete floor:

    1. Mark the concrete foundation using the drilling diagram described in Figure 5.

    2. Drill the holes in the concrete foundation (diameter 12 mm, h = 70 mm).

    Drilling Point

    Rear

    Front

    Figure 4: Drilling Diagram

    2.4.2 Raised Floor (C2)

    1

    2

    Figure 5: Drilling on a Raised Floor

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 17 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    18/42

    2 Scenario

    To drill the raised floor:

    1. Cut a rectangular hole in the tile to insert the cables using the drillingdiagram described in the previous section.

    2. Drill the holes in the tile (diameter 12 mm).

    3. Drill the floor (diameter 12 mm, h = 60 mm +/- 3 mm).

    18 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    19/42

    2 Scenario

    2.5 Install Rack

    2.5.1 Concrete Floor (C1)

    2.5.1.1 Materials

    Item Qty Designation Reference Kit

    1 4 Expanding plug 1AD 01666 0001

    2 4 Screw HM8x65 1AD 00215 0042

    3 4 Washer 8 1AD 00087 0149

    RKIT36U 3BK 27026AAAA

    2.5.1.2 Procedure

    5 mmLevelling foot

    Figure 6: Rack Installation on Concrete Floor

    To secure the rack to the concrete floor:

    1. Level the rack.

    2. Secure the rack to the concrete floor.

    2.5.2 Raised Floor (C2)

    2.5.2.1 Materials

    Item Qty Designation Reference Kit

    1 4 Cylinder splicing sleeveM8x30mm 1AD 01655 0001

    2 4 Screw HM 8x80 1AD 00215 0092

    3 4 Threaded bar M8x1000mm 1AD 01660 0003

    4 8 Washer 8 1AD 00087 0149

    5 8 Hex. nut M8 1AD 00197 0006

    6 1 Metallic sheath, length 4.5m 1AB 06084 0030

    JDTCFF 3BK 25341 AAAA

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 19 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    20/42

    2 Scenario

    2.5.2.2 Procedure

    4

    5

    2

    1

    4

    3

    Figure 7: Rack Installation on Raised Floor

    To secure the rack to the raised floor:

    1. Insert the expanding plug in the concrete floor.

    2. Screw the threaded rod (3), then the washer (4) and nut (5).

    3. Screw the coupling nut (1).

    4. Screw the screw (2) with the washer (4).

    Note: In this case, do not level the rack.

    2.5.3 Assemble Earthquake Frame (O1)

    This option can be installed with a raised floor exactly 34 cm high from theconcrete ground only.

    20 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    21/42

    2 Scenario

    2.5.3.1 Materials

    Item Qty Designation Reference Kit

    1 2 Pedestal 3BK 25339 AAXX

    2 2 Bracket 3BK 25340 AAXX

    3 4 Screw HM16x40 1AD 00204 0059

    4 4 Washer 16.4x32x2.8 1AD 00254 0006

    5 4 Screw HM8x35 1AD 00204 0038

    6 4 Washer 8.2x16x1.4 1AD 00254 0003

    7 4 Hex. nut M8x6.8 1AD 00197 0006

    8 4Expanding plug M10x60 1AD 02655 0001

    9 4 Washer lock 10.2x20x1.6 1AD 00453 0005

    10 4 Screw HM10x65 1AD 00050 0010

    JDSISM 3BK25284 AAAA

    2.5.3.2 Procedure

    5

    7

    6

    1 4 3 2

    10

    9

    8

    Figure 8: Mechanical Assembly of Earthquake Frame

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 21 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    22/42

    2 Scenario

    7670 Rack

    5

    6

    340 mm

    Tile

    7

    10

    9

    8

    Earthquakeframe

    Figure 9: Earthquake Frame Assembly (Raised Floor at Same Level asEarthquake Frame)

    To secure the earthquake frame:

    1. Assemble the earthquake frame using the screw (3) and washer (4) (referto Figure 9).

    2. Using the earthquake frame, mark the concrete ground.

    3. Drill the ground and insert the wall plug (8) (refer to Figure 10).

    4. Secure the earthquake frame using washer (9) and screw (10).

    5. Secure the rack to the frame using (5), (6) and (7).

    6. Cut and fit the tiles around the earthquake frame.

    22 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    23/42

  • 7/31/2019 A7670 ESE Installation Manual

    24/42

    2 Scenario

    2.6.1.2 Procedure

    A7670 ESE

    48 Volts

    Power Supply

    48 0

    Power cable1 x 10 mm

    Jumper cables

    GND ProtectiveEarth (16 mm

    Figure 10: Power Supply Distribution.

    1. For a raised floor, drill a 5 cm diameter hole in the tile to insert the cables.

    For a concrete foundation, secure the metallic sheath to the top of the rack.

    2. Insert the cables in the hole or in the metallic sheath.

    3. Insert the cables in the cable passage.

    4. Secure the cables to the cable passage.

    24 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    25/42

    2 Scenario

    2.6.2 Protective Earth Cable Connection (GND)

    2.6.2.1 Materials

    Description Reference Kit

    GND Protective Earth cable (yellow / green) 3BK 08957 BAAA Installation kit

    Lug hole 10 mm for 16 mm2 1AB 03205 0048 Installation kit

    2.6.2.2 Procedure

    1. Prepare the head of cable at the site side.

    2. Crimp an adapted 2-hole lug to the head of cable.

    3. Connect the GND cable to the site GND.

    4. Remove 1 cm of skin at the head of the cable (rack side).

    5. Insert the cable in GND connector at the rear top of the subrack (seeFigure 12).

    6. Screw the GND cable to the subrack.

    Groundingcable

    To groundingpoint

    1032 KEPS

    2holelug

    Studs

    Figure 11: Connecting to Chassis Ground

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 25 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    26/42

    2 Scenario

    2.6.3 Connect DC 48-Volt Power Supply

    2.6.3.1 Materials

    Description Reference Kit

    DC power cable 1x10mm2 black 3BK 08937 BAAA or BBAA Installation kit

    DC power cable 1x10mm2 blue 3BK 26923 AAAA or ABAA Installation kit

    Lug 2-holes 5 mm for 10 mm2 1AB 05153 0053 Installation kit

    Set of rubber sleeves none Consumable

    2.6.3.2 Procedure

    1. Make sure the A7670 ESE switches are Off (Refer to Figure 14).

    2. Make sure the site power supply breakers are Off.

    3. Run the wires from the power sources to the terminal block on the back ofthe shelf.

    4. Remove the protective cover from the input power terminal.

    5. Remove the two nuts and washers on the two studs labeled -VBATT.

    6. Fit a 2-hole lug of 5 mm for 10 mm2 to the end of wire.

    7. Fit a rubber sleeve to the head of the wire. Label the wire -VBATT.

    8. Place the 2-hole lug over the two studs. (Refer to Figure 13.)

    9. Repeat steps 5 to 8 for each wire (in this example, 4 wires). Label each

    wires according to the label on the stud to which it is attached.

    10. Fit a 2-hole lug to each end of the jumper cable.

    11. Place each 2-hole lug over the two studs on power feed A and power feed B.(Refer to Figure 15.)

    12. Insert the nuts and washers and tighten with a torque wrench.

    13. Put the protective cover back on the input power terminal.

    14. Fit the appropriate lugs at the site side.

    15. Fit the appropriate rubber sleeves.

    16. Connect the wire to the site power supply as follows:

    0V / A1 Black

    -48V / A1 Blue

    0V / A2 Black

    -48V / A2 Blue

    26 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    27/42

    2 Scenario

    1A

    2A

    From twopower feeds

    Powercable

    1032 KEPS

    2holelugStuds

    0VR

    VBATT

    0VR

    VBATT

    Figure 12: Power Cable Attachment

    Power module

    ON

    0V 48VZone 1

    Power status

    Test jacks

    Status LED

    Circuit breaker

    Figure 13: Circuit Breaker and Monitor Jacks

    Jumpercables (x4)

    Front twopower feeds

    Figure 14: Jumper Cable Attachment

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 27 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    28/42

    2 Scenario

    2.6.4 Connect to Test Power Jacks

    To connect to the test power jacks:

    1. Set the multimeter to the appropriate function and range.

    2. Insert the test probes in the jack labeled -48v and 0v for the appropriate

    power feed.

    3. Read the result (the acceptable input voltage range is from -40v to -70v).

    28 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    29/42

    2 Scenario

    2.7 Perform E1 Cabling

    This section provides the procedures for E1 120 Ohm only.

    2.7.1 Install E1 Cable Between A7670 ESE and DDF

    2.7.1.1 Connect E1 on A7670 ESE Side

    The table below lists the supplies needed to connect the E1 to the A7670 ESE.

    Description Reference Kit

    E1 cable with connector (20 or 40 m) shielded 3BK 26632 HA (20m)

    3BK 26632 JL (40m)

    List of kits

    Tie wraps 1AD 00414 0006 Basic kit

    To connect the E1 to the A7670 ESE:

    1. Insert both E1 cables with the connector into the cable passage.

    2. Using tie wraps, attach the cables to the cable passage (every meter).

    3. Remove the EMI covers, if installed, from the upper and lower connectors onthe back of A7670 ESE shelf where the board is installed. Store the covers.The upper connector corresponds to ports 1 to 16 on a 32-port board, andthe lower connector corresponds to ports 17 to 32. Refer to Figure 16.

    4. Align the first E1 cable with the connector with the upper connector for ports1 to 16 where the board is installed. Ensure that the connector and thecable are facing up. Push the connector into place. (Refer to Figure 17.)

    5. Label the first E1 cable with the labeling machine.

    6. Repeat steps 4 to 5 with the second E1 cable for the lower connector(ports 17 to 32).

    7. Attach E1 cables to the rear of the rack (tie wraps).

    8. Using the wiring table (refer to Table 1), connect the other end of the E1cable to the DDF (refer to E1 Connection on DDF Side(Section 2.7.1.2).

    As with other installation cables, these E1 cables must be inserted in the same

    site cable passage (either at the top of rack or in a raised floor).

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 29 / 42

    http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-
  • 7/31/2019 A7670 ESE Installation Manual

    30/42

    2 Scenario

    The following figures show connections on the back side of the A7670 ESE:

    331

    64

    Port1

    Port16

    Top connector Botom connector

    32Port32

    Port17

    64

    33

    Figure 15: 64-pin Connectors on Back Side of A7670 ESE

    Cable tie

    Cable clamp

    Upper row

    Captive screw

    Cable clamp

    Notch

    Figure 16: E1 Cable Connection on Back Side of A7670 ESE

    30 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    31/42

    2 Scenario

    2.7.1.2 E1 Connection on DDF Side

    Cable Route for 120-ohm Terminal Block

    Rx Tx

    A7670 ESE

    RNC V1 Evol

    DDF

    Optical cable (STM1)in case of Conccrete FloorSTM1 for lub interface

    E1 cable

    (Note) One Terminal Block is used for one E1 cable.

    Figure 17: E1 Cabling with 120-Ohm Terminal Block

    1 2 3 4 5 6 07 8 9

    Link1

    Link2

    Link3 Link5

    Link4 Link6

    Link7

    Link8

    Not Use

    Figure 18: Front View of 120-ohm Terminal Block (JS10)

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 31 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    32/42

    2 Scenario

    Cable Route for 75/120-ohm Terminal Block

    RNC V1 Evol

    Figure 19: Cabling with 75/120-ohm Adapter Terminal Block

    4 3 2 1

    8 7 6 5

    12 11 10 9

    16 15 14 13

    20 19 18 17

    24 13 12 21

    34

    12

    78

    56

    1112

    910

    1516

    1314

    1920

    1718

    2324

    2122

    Circuit Number

    Pair CableConnect Point

    A B

    AB

    Figure 20: Rear View of 75/120-ohm Terminal Block Adapter

    1

    5 67 8

    910 11

    12

    13 1415 16

    1718 19

    20

    21

    22 2324

    42 3

    frame Earth

    Circuit Number

    Coaxial CableConnect Point

    (Note 1)Tx side connects the frameearth with DDF frame(Note 2)

    Adaptor is used separatelyfor Tx and Rx

    Figure 21: Front View of 75/120-ohm Terminal Block Adapter

    32 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    33/42

    2 Scenario

    2.7.2 Wiring Table

    The table below shows the wiring table for the E1 cables 3BK 26632 HAABand 3BK 26632 JLAB

    Cable Assignment Signal NameChamp

    pinUnit Pair Cond. Wire color 8xE1 board

    (Upper row)

    32xE1 board

    (Upper row)

    32xE1 board

    (Lower row)

    33 1 1 1 White P1 RT P1 TT P17 TT

    1 1 1 2 Blue P1 RR P1 TR P17 TR

    34 1 2 1 White P1 TT P1 RT P17 RT

    2 1 2 2 Yellow P1 TR P1 RR P17 RR

    35 1 3 1 White P2 TT P18 TT

    3 1 3 2 Brown P2 TR P18 TR

    36 1 4 1 White P2 RT P2 RT P18 RT

    4 1 4 2 Black P2 RR P2 RR P18 RR

    37 1 5 1 White P2 TT P3 TT P19 TT

    5 1 5 2 Green P2 TR P3 TR P19 TR

    38 1 6 1 White P3 RT P19 RT

    6 1 6 2 Orange P3 RR P19 RR

    39 1 7 1 White P3 RT P4 TT P20 TT

    7 1 7 2 Grey P3 RR P4 TR P20 TR

    40 1 8 1 White P3 TT P4 RT P20 RT

    8 1 8 2 Purple P3 TR P4 RR P20 RR

    41 2 1 1 White P5 TT P21 TT

    9 2 1 2 Blue P5 TR P21 TR

    42 2 2 1 White P4 RT P5 RT P21 RT

    10 2 2 2 Yellow P4 RR P5 RR P21 RR

    43 2 3 1 White P4 TT P6 TT P22 TT

    11 2 3 2 Brown P4 TR P6 TR P22 TR

    44 2 4 1 White P6 RT P22 RT

    12 2 4 2 Black P6 RR P22 RR

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 33 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    34/42

    2 Scenario

    Cable Assignment Signal NameChamppin

    Unit Pair Cond. Wire color 8xE1 board

    (Upper row)

    32xE1 board

    (Upper row)

    32xE1 board

    (Lower row)

    45 2 5 1 White P5 RT P7 TT P23 TT

    13 2 5 2 Green P5 RR P7 TR P23 TR

    46 2 6 1 White P5 TT P7 RT P23 RT

    14 2 6 2 Orange P5 TR P7 RR P23 RR

    47 2 7 1 White P8 TT P24 TT

    15 2 7 2 Grey P8 TR P24 TR

    48 2 8 1 White P6 RT P8 RT P24 RT

    16 2 8 2 Purple P6 RR P8 RR P24 RR

    49 3 1 1 White P6 TT P9 TT P25 TT

    17 3 1 2 Blue P6 TR P9 TR P25 TR

    50 3 2 1 White P9 RT P25 RT

    18 3 2 2 Yellow P9 RR P25 RR

    51 3 3 1 White P7 RT P10 TT P26 TT

    19 3 3 2 Brown P7 RR P10 TR P26 TR

    52 3 4 1 White P7 TT P10 RT P26 RT

    20 3 4 2 Black P7 TR P10 RR P26 RR

    53 3 5 1 White P11 TT P27 TT

    21 3 5 2 Green P11 TR P27 TR

    54 3 6 1 White P8 RT P11 RT P27 RT

    22 3 6 2 Orange P8 RR P11 RR P27 RR

    55 4 7 1 White P8 TT P12 TT P28 TT

    23 3 7 2 Grey P8 TR P12 TR P28 TR

    56 3 8 1 White P12 RT P28 RT

    24 3 8 2 Purple P12 RR P28 RR

    57 4 1 1 White P13 TT P29 TT

    25 4 1 2 Blue P13 TR P29 TR

    34 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    35/42

    2 Scenario

    Cable Assignment Signal NameChamppin

    Unit Pair Cond. Wire color 8xE1 board

    (Upper row)

    32xE1 board

    (Upper row)

    32xE1 board

    (Lower row)

    58 4 2 1 White P13 RT P29 RT

    26 4 2 2 Yellow P13 RR P29 RR

    59 4 3 1 White P14 TT P30 TT

    27 4 3 2 Brown P14 TR P30 TR

    60 4 4 1 White P14 RT P30 RT

    28 4 4 2 Black P14 RR P30 RR

    61 4 5 1 White P15 TT P31 TT

    29 4 5 2 Green P15 TR P31 TR

    62 4 6 1 White P15 RT P31 RT

    30 4 6 2 Orange P15 RR P31 RR

    63 4 7 1 White P16 TT P32 TT

    31 4 7 2 Grey P16 TR P32 TR

    64 4 8 1 White P16 RT P32 RT

    32 4 8 2 Purple P16 RR P32 RR

    Table 1: Wiring Table for E1 Cables 3BK 26632 xxAB

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 35 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    36/42

    2 Scenario

    2.8 Install RNC Ev Optical Fiber Cable

    2.8.1 Materials

    Description Reference Kit

    Optical fiber cable:

    Case 1: Up to 7 pairs of fibers

    Case 2: Up to 4 pairs of fibers

    3BK 25999 HAAA List of kits

    2.8.2 Procedure

    1. Insert the multifiber cable in the cable passage.

    2. Insert the multifiber cable in the cable gland of the RNC Ev (refer to the RNCEv Installation Manual).

    3. Attach the multifiber cable to the cable passage and to the equipment.

    4. Connect the optical fibers to the A7670 ESE, to the ODF and to the RNCEv ( refer to Figure 23).

    5. Label the fibers.

    As with other installation cables, these cables must be inserted in the same sitecable passage (either at the top of the rack or in the raised floor).The single optical fibers must not be tied to the rack; the multifiber cablecan, however, be tied to the rack.

    36 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    37/42

    2 Scenario

    Optical cables used on the RNC Ev side:The optical cables used for Iub links use monomode fibers, with LC connectorsat the RNC Ev side, and SC connectors on the other side (connection to ODFor to A7670 ESE).

    MSIF

    0

    1

    2

    3

    lu / lur / O&M

    lub

    Figure 22: Optical Fiber Connection on RNC Ev Side

    The following connections are fixed:Slot # 0 Port #1Slot # 10 Port #2

    12

    Figure 23: Threading Fiber Cables in a Mid-mount Bracket

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 37 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    38/42

    2 Scenario

    2.8.3 Connection Table

    Type of Cable From To

    Optical fiber A7670 /STM1 board X #1/ RX RNC Evolution / M-SIF / #1 TX (Iub)

    Optical fiber A7670 /STM1 board X #1/ TX RNC Evolution / M-SIF / #1 RX(Iub)

    Optical fiber A7670 /STM1 board X #2/ RX RNC Evolution / M-SIF / #2 TX (Iub)

    Optical fiber A7670 /STM1 board X #2/ TX RNC Evolution / M-SIF / #2 RX(Iub)

    Optical fiber A7670 /STM1 board X #3/ RX RNC Evolution / M-SIF / #3 TX (Iub)

    Optical fiber A7670 /STM1 board X #3/ TX RNC Evolution / M-SIF / #3 RX(Iub)

    Table 2: Connection Table

    38 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    39/42

    2 Scenario

    2.9 Shelf Configurations

    Note: The configurations presented in the following tables illustrate maximumconfigurations.

    2.9.1 STM1 E1 Conversion

    Slot Front Board Adapter Board Function in UTRAN

    X ECC (Control) + Quad STM-1 IR RNC Ev 7670: Iub 1

    1 Filler plate

    2 Filler plate

    3 Filler plate

    4Filler plate

    5 Filler plate

    6 Filler plate

    7 E1 32 ports T1/E1 Iub (Node B 7670)

    8 E1 32 ports T1/E1 Iub (Node B 7670)

    9 E1 32 ports T1/E1 Iub (Node B 7670)

    10 E1 32 ports T1/E1 Iub (Node B 7670)

    11 E1 32 ports T1/E1 Iub (Node B 7670)

    12 E1 32 ports T1/E1 Iub (Node B 7670)

    Y ECC (Control)

    1 : 4 STM1 links are used for Iub.: Filling order: Start with boards 11,12, etc.

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 39 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    40/42

    2 Scenario

    2.9.2 STM1 VC4STM1 VC12 Conversion

    Slot Front Board Adapter Board Function in UTRAN

    X ECC (Control) + Quad STM-1 IR RNC Ev 76701

    1 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)

    2 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)

    3 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)

    4 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)

    5 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)

    6 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)

    7 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)

    8 STM-1/OC3 IR MS UCS (STM-1/OC3) Iub (Node B 7670)

    9 Filler plate

    10 Filler plate

    11 Filler plate

    12 Filler plate

    Y ECC (Control)

    1 : 4 STM1 links are used for Iub.: Filling order: Start with boards 2,3, etc. This allows mixed configurations (STM1 T1/E1 or VC12).

    40 / 42 3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02

  • 7/31/2019 A7670 ESE Installation Manual

    41/42

    2 Scenario

    2.10 Before You Leave

    2.10.1 Materials

    Description Reference Kit

    Earth braids None Supplied with rack

    2.10.2 Procedure

    1. If a metallic sheath was installed, stretch it for inspection.

    2. Secure the metallic sheath to the site cable passage (if applicable).

    3. Secure the earth braids to the side panels (delivered with the rack).

    4. Label the A7670 ESE rack to identify it.

    3BK 17429 3155 RJZZA Ed.02Z2EV00007-0018 Ed.02 41 / 42

  • 7/31/2019 A7670 ESE Installation Manual

    42/42

    2 Scenario

    BLANK PAGE BREAK