a study of the cooling facility in preparation for the...

1
A Study of the Cooling Facility in A Study of the Cooling Facility in Preparation Preparation for the for the ATLAS Inner Detector Testing ATLAS Inner Detector Testing V. Vacek, V. Vacek, [email protected] CTU, Faculty of Mechanical Engineering, Department of Applied Physics Technická 4, 16607 Praha 6 ©2003 V. Vacek Underground Underground facilities facilities Surface facilities Surface facilities SR building on the ATLAS site at CERN SR building on the ATLAS site at CERN Cooling circuit layout: Cooling circuit layout: Rack @ Test Area between Test Area between 6 th and 7 th pillar in the middle of two air ducts; Pixel manifold Pixel manifold close to the 11 th pillar [to minimize interference with TRT system test area; SCT manifold SCT manifold between 14 th and 15 th pillar An evaporative cooling plant is designed to cover cooling power needs at three locations inside the SR Building – Main test Area, Pixel assembly area and SCT assembly area. The use of the C 3 F 8 refrigerant is required for final „cold test mode“ and the use of theC 4 F 10 is foreseen for the first step tests so called „warm test mode“ Tray with reserved place - tubes for “warm” testing Estimation of the Compressor size Estimation of the Compressor size „cold test mode“ Evap. @ T sat = -25°C; P sat =1.74 bar a • Full available latent heat l =101.5 [kJ/kg] • If no sub-cooling then [throttling @ 20-25 °C] reduced latent heat l reduced = 52 [kJ/kg] To evacuate 25 kW requires to evaporate approx. 0.48 kg/s of C 3 F 8 Compressor size is very dependant on pressure condition at its inlet due to the density change [ρ ρ ρ(P,T) very sensitive to P but less to T]; assuming P inlet = 1.4 bar a and T(16-22°C) then ρ≅ 11 kg/m 3 and we may need compressor with pumping capacity around 155 m 3 /h of C 3 F 8 vapor This value can handle 1 compressor, type This value can handle 1 compressor, type HAUG QTOG 180/100 LR HAUG QTOG 180/100 LR An option An option - with “standard ATLAS cooling Rack”: Utilization of the distribution rack prototype for a final system is proposed. It has 96 inlet lines with pressure regulators and 48 outlet lines with back pressure regulators (assuming that we still require them for all inlet lines and common return lines) – It might serve as the rack for SR Test AREA purposes (It could be a useful verification test a useful verification test for final ATLAS ID cooling system ). Test Area Test Area [only SCT needs] [only SCT needs] Estimated cooling power to be available at Pixel Assembly Area: requirements for partial tests [up to 15% of needed cooling power, i.e. approx. 7 loops] – two single two single inlet/outlet units to be installed, i.e. eight eight Loops available Single Single Inlet/outlet unit Assembly Area Assembly Area - - Pixel Pixel ~ 3 kW ~ 3 kW Recalculation of the C.S. parameters with different fluid, C 4 F 10 shows: 1) desired evaporation temperature can be achieved at reasonable pressure around 1.9 bar a 2) high condensing temperature at the pressure around 9 bar a enables to sub- cool liquid in condenser sufficiently even with tap water 3) due to the sufficient sub- cooling we could use nearly all latent heat of evaporation [83 kJ/kg, compared to 52 kJ/kg for C 3 F 8 in a “cold” circuit], resulting in significant reduction of the flow from 0.30 kg/s compared to 0.48 kg/s for C 3 F 8 in a “cold” circuit Calculation performed for SR1 C.S.installation ONLY !!! ONLY !!! (~ 25 kW of cooling power) (~ 25 kW of cooling power) 4) Pressure drops were recalculated for the first pipe line scheme prepared for C 3 F 8 [for the meeting on 13/11/2002]; as expected slightly lower due to flow reduction see - 3) Potential problems and difficulties main difficulty consists in maintaining a proper conditions during the compression of the C 4 F 10 vapor has to stay in superheated state [buffer helps, but the intake tube has to heated and compressor itself probably as well]. Temperature after the compression [at 9 or 10 bar] has to be well above 80 ºC. [We might also face problem with a “cold compressor” start up]. minor problems: • heat transfer coefficient of the C 4 F 10 – is lower than for C 3 F 8 – this will not slightly affect Warm testing process (typical temperature differences observed between “silicon” and C 3 F 8 fluid were ranging between 10 and 12ºC). So for C 4 F 10 we expect them ranging between 14 and 16ºC. It would bring the surface “silicon” temperature up 30 ºC during Warm testing • capillaries – no major problems foreseen, needs some analysis Typical Average values of the HTC Typical compression curves Other Parts needed to be available and Other Parts needed to be available and installed: installed: Tube system (some parts insulated – before capillaries), manifolding rack, plate HEX (heat exchangers ; liquid-vapor), heaters (HEX for outlet tubes), dummy heater for all installed power of the Compressor-Condenser Unit SCT structures come placed in the transport box. Insulation (and sealing) for the transport boxes has to be considered. To proceed with a “Cold” testing mode, flushing system will be necessary: Power supplies •for the heaters after the HEX •for dummy heater of the Compressor-Condenser Unit DAQ system for monitoring of the structural parameters (at the test area and assembly areas) and cooling circuit control parameters => communication with PLC control possible Extras Extras (but necessary): •working table&cabinet with basic tools and bits (connectors, tubes, wires, multimeter, etc.) •vacuum pump, leak tester •container with spare fluid of the C 3 F 8 •filling manifold for refrigerant, spare sensors – temperature, pressure, humidity ones; flow meter •N 2 flasks at all three cooling places/stations for flashing the structures Summary: Study of the Cooling facilities for SR Building was completed Main parts of the C.S. were designed and overall layout with three main cooling outlets was determined The use of the same hardware for „warm testing mode“ was evaluated Summary: Summary: Study of the Cooling facilities for SR Study of the Cooling facilities for SR Building was completed Building was completed Main parts of the C.S. were designed and Main parts of the C.S. were designed and overall layout with three main cooling outlets overall layout with three main cooling outlets was determined was determined The use of the same hardware for The use of the same hardware for „ warm warm testing mode testing mode“ was evaluated was evaluated ~ 43 m ABSTRACT: ABSTRACT: The Department of Applied Physics has been participating and cooperating in cooling systems development for the Atlas Inner Detector since 1995. The ATLAS Inner Detector combines high- resolution detectors at the inner radii with continuous tracking elements at the outer radii, all contained in the Central Solenoid, which provides a nominal field of 2 T. The highest granularity is achieved around the vertex region using semiconductor pixel detectors (PIXEL part) followed by a silicon micro strip detector (SCT). At larger radii typically 36 tracking points are provided by the straw tube tracker (TRT). The Inner Detector will be assembled and tested on the surface prior to its installation in the underground experimental area. The work is expected to be carried out in the SR building on the ATLAS site at CERN. An adequate evaporative cooling plant is required to be built and available, namely for the SCT and Pixel parts of the Inner detector. We present a pilot study of the cooling plant that should cover requirements for overall testing procedures of the whole SCT detector (approx. 22 kW of cooling power needed) and also the partial cooling requirements at the individual assembly sites for PIXEL (approx. 3 kW of cooling power needed) and SCT structures (approx. 1.8 kW of cooling power need). The main compressor-condenser unit was sized for the plant and three main distribution places for a refrigerant delivery were allocated. Manifolding modularities were designed and tube lines layout was prepared including the tubes sizing and pressure drop calculations. There are two testing modes under the consideration. The first “Warm testing mode“ is being prepared for the initial tests during a final assembly at SR building. The use of the C 4 F 10 refrigerant is foreseen for this application. Evaporation temperature in the supporting structures sticking together detector modules is foreseen around 16 ºC or slightly above this value (depending on the dew point temperature in the assembly hall), While temperatures on the silicon surfaces may reach values around 30 ºC when the expected heat loads are evacuated. A separate individual cooling unit is planned to be employed. The second, so called “Cold testing mode” is meant as the final testing process prior to placement of the completed inner detector in the underground experimental area. The cooling system working with C 3 F 8 refrigerant has been chosen for the final application. This type of the system has been under the development and testing since 2000 . A possibility of the multiple use of the same mechanical hardware for the both testing modes was also studied and evaluated . The last part of the project deals with an assessment of the supporting equipment and facilities needed to operate the cooling plant, i.e. heaters and relevant power supplies, insulation and sealing means, flushing gas system, base parts of the DAQ system and various mechanical spares. This research has been supported by Gr. No. MPO ČR , RP– 4210/69 (2296303), and partly also by VZ-MSM - J04/98: 212200008.

Upload: vananh

Post on 03-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

A Study of the Cooling Facility in A Study of the Cooling Facility in PreparationPreparation for the for the

ATLAS Inner Detector TestingATLAS Inner Detector TestingV. Vacek,V. Vacek,

[email protected]

CTU, Faculty of Mechanical Engineering, Department of Applied Physics

Technická 4, 16607 Praha 6

©2003 V. Vacek

Underground Underground

facilitiesfacilities

Surface facilitiesSurface facilities

SR building on the ATLAS site at CERNSR building on the ATLAS site at CERN

Cooling circuit layout:Cooling circuit layout:Rack @ Test Area betweenTest Area between 6th and 7th pillar in the middle of two air ducts; Pixel manifoldPixel manifold close to the 11th pillar [to minimize interference with TRT system test area; SCT manifoldSCT manifold between 14th and 15th pillar

An evaporative cooling plant

is designed to cover cooling

power needs at three

locations inside the SR

Building – Main test Area,

Pixel assembly area and SCT

assembly area.

The use of the C3F8refrigerant is required for

final „cold test mode“ and the

use of theC4F10 is foreseen

for the first step tests so called

„warm test mode“

Tray with reserved place -

tubes for “warm” testing

Estimation of the Compressor sizeEstimation of the Compressor size„cold test mode“

• Evap. @ T sat= -25°C; Psat=1.74 bara

• Full available latent heat l =101.5 [kJ/kg]

• If no sub-cooling then [throttling @ 20-25 °C] reduced latent heat

l reduced= 52 [kJ/kg]

To evacuate 25 kW requires to evaporate approx.

0.48 kg/s of C3F8

Compressor size is very dependant on pressure condition at its inlet due to the density change [ρρρρ(P,T) – very sensitive to P but less to T]; assuming Pinlet= 1.4 bara and T∈(16-22°C) then ρ ≅ 11 kg/m3

and we may need compressor with pumping capacity around

155 m3/h of C3F8 vapor

This value can handle 1 compressor, type This value can handle 1 compressor, type HAUG QTOG 180/100 LRHAUG QTOG 180/100 LR

•• An option An option -- with “standard ATLAS cooling Rack”:

Utilization of the distribution rack prototype for a final system is proposed. It has 96 inlet lines with pressure regulators and 48 outlet lines with back pressure regulators (assuming that we still require them for all inlet lines and common return lines) – It might serve as the rack for SR Test AREA purposes (It could be a useful verification testa useful verification test for final ATLAS ID cooling system).

Test Area Test Area [only SCT needs][only SCT needs]

Estimated cooling power to be available at

Pixel Assembly Area: requirements for partial tests

[up to 15% of needed cooling power, i.e.

approx. 7 loops] – two singletwo single inlet/outlet units to be installed, i.e. eighteight Loops available

SingleSingle Inlet/outlet unit

Assembly Area Assembly Area -- PixelPixel

~ 3 kW~ 3 kW

Recalculation of the C.S. parameters with different fluid, C4F10shows:

1) desired evaporation temperature can be achieved at reasonable pressure around 1.9 bara

2) high condensing temperature at the pressure around 9 bara enables to sub-cool liquid in condenser sufficiently even with tap water

3) due to the sufficient sub-cooling we could use nearly all latent heat of evaporation [83 kJ/kg, compared to 52 kJ/kg for C3F8 in a “cold”circuit], resulting in significant reduction of the flow from 0.30 kg/s compared to 0.48 kg/s for C3F8 in a “cold” circuit

Calculation performed for SR1 C.S.installation ONLY !!! ONLY !!! (~ 25 kW of cooling power)(~ 25 kW of cooling power)

4) Pressure drops were recalculated for the first pipe line scheme prepared for C3F8 [for the meeting on 13/11/2002]; as expected slightly lower due to flow reduction see - 3)

Potential problems and difficulties

• main difficulty consists in maintaining a proper conditions during the compression of the C4F10 –vapor has to stay in superheated state [buffer helps, but the intake tube has to heated and compressor itself probably as well]. Temperature after the compression [at 9 or 10 bar] has to be well above 80 ºC. [We might also face problem with a “cold compressor” start up].

• minor problems:

• heat transfer coefficient of the C4F10 – is lower than for C3F8 – this will not slightly affect Warm testing process (typical temperature differences observed between “silicon” and C3F8 fluid were ranging between 10 and 12ºC). So for C4F10 we expect them ranging between 14 and 16ºC. It would bring the surface “silicon”temperature up 30 ºC during Warm testing

• capillaries – no major problems foreseen, needs some analysis

Typical Average values of the HTC

Typical compression curves

Other Parts needed to be available and Other Parts needed to be available and installed:installed:

Tube system (some parts insulated – before capillaries), manifolding rack, plate HEX (heat exchangers ; liquid-vapor), heaters (HEX for outlet tubes), dummy heater for all installed power of the Compressor-Condenser Unit

SCT structures come placed in the transport box. Insulation (and sealing) for the transport boxes has to be considered. To proceed with a “Cold” testing mode, flushing system will be necessary:

Power supplies

•for the heaters after the HEX

•for dummy heater of the Compressor-Condenser Unit

DAQ system – for monitoring of the structural parameters (at the test area and assembly areas) and cooling circuit control parameters => communication with PLC control possible

ExtrasExtras (but necessary):

•working table&cabinet with basic tools and bits (connectors, tubes, wires, multimeter, etc.)

•vacuum pump, leak tester

•container with spare fluid of the C3F8

•filling manifold for refrigerant, spare sensors – temperature, pressure, humidity ones; flow meter

•N2 flasks at all three cooling places/stations for flashing the structures

Summary:

• Study of the Cooling facilities for SR

Building was completed

• Main parts of the C.S. were designed and

overall layout with three main cooling outlets

was determined

• The use of the same hardware for „warm

testing mode“ was evaluated

Summary:Summary:

•• Study of the Cooling facilities for SR Study of the Cooling facilities for SR

Building was completedBuilding was completed

•• Main parts of the C.S. were designed and Main parts of the C.S. were designed and

overall layout with three main cooling outlets overall layout with three main cooling outlets

was determinedwas determined

•• The use of the same hardware for The use of the same hardware for „„warm warm

testing modetesting mode““ was evaluatedwas evaluated

~ 43 m

ABSTRACT:ABSTRACT:

The Department of Applied Physics has been participating and cooperating in cooling systems development for the Atlas Inner Detector since 1995. The ATLAS Inner Detector combines high-resolution detectors at the inner radii with continuous tracking elements at the outer radii, all contained in the Central Solenoid, which provides a nominal field of 2 T. The highest granularity is achieved around the vertex region using semiconductor pixel detectors (PIXEL part) followed by a silicon micro strip detector (SCT). At larger radii typically 36 tracking points are provided by the straw tube tracker (TRT).

The Inner Detector will be assembled and tested on the surface prior to its installation in the underground experimental area. The work is expected to be carried out in the SR building on the ATLAS site at CERN. An adequate evaporative cooling plant is required to be built and available, namely for the SCT and Pixel parts of the Inner detector.

We present a pilot study of the cooling plant that should cover requirements for overall testing procedures of the whole SCT detector (approx. 22 kW of cooling power needed) and also the partial cooling requirements at the individual assembly sites for PIXEL (approx. 3 kW of cooling power needed) and SCT structures (approx. 1.8 kW of cooling power need).

The main compressor-condenser unit was sized for the plant and three main distribution places for a refrigerant delivery were allocated. Manifolding modularities were designed and tube lines

layout was prepared including the tubes sizing and pressure drop calculations.

There are two testing modes under the consideration. The first “Warm testing mode“ is being prepared for the initial tests during a final assembly at SR building. The use of the C

4F10

refrigerant is foreseen for this application. Evaporation temperature in the supporting structures sticking together detector modules is foreseen around 16 ºC or slightly above this value (depending on the dew point temperature in the assembly hall), While temperatures on the silicon surfaces may reach values around 30 ºC when the expected heat loads are evacuated. A separate individual cooling unit is planned to be employed.

The second, so called “Cold testing mode” is meant as the final testing process prior to placement of the completed inner detector in the underground experimental area. The cooling system working with C

3F8refrigerant has been chosen for the final application. This type of the

system has been under the development and testing since 2000 .

A possibility of the multiple use of the same mechanical hardware for the both testing modes was also studied and evaluated .

The last part of the project deals with an assessment of the supporting equipment and facilities needed to operate the cooling plant, i.e. heaters and relevant power supplies, insulation and sealing means, flushing gas system, base parts of the DAQ system and various mechanical spares.

This research has been supported by Gr. No. MPO ČR , RP– 4210/69 (2296303), and partly also by VZ-MSM - J04/98: 212200008.