a report of training ongc
TRANSCRIPT
-
8/4/2019 A Report of Training ONGC
1/33
A
REPORT ON TRAINING
IN
OIL AND NATURAL GAS CORPORATIONLIMITED
SURFACE TEAM
AHMEDABAD ASSET
SUBMMITTEDBY: -
-
8/4/2019 A Report of Training ONGC
2/33
ACKNOWLEDMENT
Fi r s t ly , we would l ike thanks Mr . N. Khandur i fo r h i s g rea t e f fo r t s ina r r an gi ng ou r training at Ahmadabad asset under surface team. We would like to express our
sincere thanks to installation managers of GGS motera KALOL,C.T.F, G.C.S ,G.C.P, KALOL
G.G.S VII , E.T.P, C.W.I .P, Nawagam C.T.F, Desalte r plant, Artificial lift & security dept.O.N.G.C AHMEDABAD. We express our deepest thanks to Mr. M.G Desai (Head of
Chemical Engg Dept .) for providing us the moral support and encouragement, without which it
would have been difficult to complete this training.
Preface
Theory o f any sub jec t i s impor tan t bu t wi thou t i t s p rac t i ca l knowledge i t
becomes use less , pa r t i cu la r ly fo r t echn ica l s tuden ts . A techn ica l s tuden t
cannot become a perfect engineer or technologist without practical understandingof their branch, hence training provides a golden opportunity for all technical students to
interact with the working environment. The principal necessity of in-plant training is to get details
about unit operation and unit process which are carried out in chemical industries and toknow more about the equipments used in these industries. The in-plant training pr ogram is
very advantageous for the technical students who have a vivid idea about the industries.
Th is t r a in ing he lps to unders tand the bas ic concep t o f the indus t ry . Dur ing
th is pe ri od th e students becomes aware of the problems faced in the plant and are alsoaware of the industrial atmosphere and also with the industrial people.
CONTENT
- 3
TOPIC PAGE NO
1. GGS Moter 1
2. KALOL GCS (GAS COLLECTION STATION) 6
3. GAS COMPRESSION PLANT (GCP)-KALOL 11
4. CENTRAL FARM TANK (CTF)-KALOL 15
5. GGS VII-KALOL 20
6. EFFLUENT TREATMENT PLANT (ETP)-II (KALOL) 26
7. CENTRAL WATER INJECTION PLANT (CWIP) 30
8. CENTAL TANK FARM (CTF)NAWAGAM 339. DESALTER PLANT: NAWAGAM 35
10. WWTP-WASTE WATER TREATMENT PLANT 39
11. ARTIFICIAL LIFT (Ahmedabad) 43
GGS-MOTERA
INSTALLATION MANAGER - Mrs. Purvi Dutta choudhary
- 4 -
-
8/4/2019 A Report of Training ONGC
3/33
DATE OF COMMISION:29.03.1992
AREA OF INSTALLATION: WELL PRODUCTION STATUS: TOTAL WELLS CONNECTED-
33TOTAL FLOWING WELLS-28TOTAL LIQUID PRODUCTION-40 m3/day. WATER
INJECTION WELLS- nil GAS INJECTED-20000 m3/dayVESSELS: LOW PRESSURE SEPARATOR- (vol- 6 m3) GROUP SEPARATOR- (vol-6 m3) TEST
SEPARATOR- (vol- 6m3) VERTICAL SCRUBBER-(capacity-1.7 lacks m3/day)HORIZONTAL
SCRUBBER-(capacity- 50000 m3/day)BATH HEATER- 1 NO.S TANKS OIL STORAGE TANKS-3 NO.S (45 m3)
FUNCTION:At group gathering system (GGS) fluid from various wells is collected in header from various wells
through pipeline network. Then the low pressure fluid (1- 2 kg/cm2) goes to the low pressure
separator, and then in the output we get separated oil and gas. Oil goes directly to storage tanks and
gas goes to common sucker separator. On the other hand fluid of 4-5 kg/cm2 pressure goes to groupseparator. Then from the outlet of this separator gas goes to common suction separator and oil goes
directly to storage tanks. Then in common suction separator all the gases from the outlet of group
separator and low pressure separator is further separated, thus if any amount of oil is still present ingas can be separated. So after separation gas is directly sent to GAIL and oil goes to storage tankThe gas which was present in above withdrawn oil is low pressure gas, but some high pressure gas
also comes out of reservoir. So that gas is sent to gas scrubber where whatever amount of gas is
present in gas is separated and the gas what we get after separation is not suitable for consumers so itis sent back to reservoir for artificial lifting.
GGS FACILITIES
1. PIPELINES
For oil- 4inches in diameterHighly resistant against corrosive action of fluid
For gas- 2inches in diameter
2. SCRUBBERS
Horizontal scrubber
Function- extract oil from gas Pressure- 40 Kg/cm2
Vertical scrubber
Function- same as above Pressure- 70 Kg/cm2
3. SEPARATOR:
To flash the well fluid to separate into liquids and gas at a controlled pressure.
Flow lines from various wells open into the pipelines of GGS. Various provisions for varioussupplies to 3 types of separator:
TEST SEPARATOR
-
8/4/2019 A Report of Training ONGC
4/33
Fluid enters tangentially and due to the sudden pressure drop to the set level , the fluid gets separatedinto separated into liquid and gases. Baffles are fitted inside the separator to help in better separation.
It is used for testing the fluid obtained from a source. It can withstand pressure of 9 kg/cm2.
GROUP SEPARATOR
It is also a two phase vertical cylindrical vessel just the same as the previous one but here fluid from
all the well comes whose pressure is up to 4-5 kg/cm2. Separated gas is sent to flare lines.
LOW PRESSURE SEPARATOR
When the fluids coming out of the wells have pressure of about 1-2 kg/cm2 then fluid goes tothisseparator. All these separators have same capacity.
4. VALVESGate valves: used to minimize the pressure drop in the open position and stop the flow rather than
controlling it
Check valves: it is one-way valve which normally allow fluid to flow through it in only one
direction. This prevents the back flow of fluid into wells.
5. STORAGE SYSTEM
Purpose:To store oil before transporting
To measure oil produced Process:
Oil from bath heater and separator is taken into overhead cylindrical tanks for measurement.
6. OIL DISPATCH SYSTEM
Purpose:To dispatch oil from GGS to CTF. Process:
Oil stored in the storage tanks is sent to CTF by road tanker as there is no pumping system
available in the installation.
7. BATH HEATER
Used to reduce the viscosity of oil coming from reservoir by heating that oil in bath heater.
8. FIRE FIGHTING SYSTEM
Large water tank- (capacity- 350 m3)
Small water tank- (capacity- 100m3)
-
8/4/2019 A Report of Training ONGC
5/33
KALOL GCS (GAS COLLECTION STATION)INSTALLATION MANAGER : Mr.B.B.Patel
ESTABLISHED IN : 1973
-
8/4/2019 A Report of Training ONGC
6/33
RECEIVING STATUS :Total Wells Connected-32Total Working Wells- 13Receiving pressure-4kg/cm2
OBJECTIVES:
To collect natural gas from wells
To collect associated gas from GGS
To send gas to GCP.To send compressed gas (CG) to GGS for artificial lifting
To send CG to IFFCO, RIL, etc.
FUNCTIONS:
Its main function is gas collection and distribution. GCS receives associated gas from GGS andnatural gas directly from the wells. They both are mixed in scrubber, treated and they are transferred
to GCP for further compression. Now the compressed gas is again received back by GCS and then the
compressed gas is sent to various destinations.
GCS FACILITIES
1. MANIFOLDS
Gas grid manifold (to provide high pressure compressed gas through 4 & 6 pipeline to northand south Kalol gas system)
2. BEAN HOUSING
To control the flow of gas from the reservoir
3. SCRUBBER
Purpose
It is a purifier that removes impurities from gas. Scrubber systems are a diverse group of air
pollution control devices that can be used to remove particulates and/or gases from industrial exhaust
streams. Traditionally, the term scrubber has referred to pollution control devices that use liquid to
scrub unwanted pollutants from a gas stream. Recently, the term is also used to describe systems
that inject a dry reagent or slurry into a dirty exhaust stream to scrub out acid gases. Scrubbers are
one of the primary devices that control gaseous emissions, especially acid gases. Process it involves
the addition of an alkaline material (usually hydrated lime and soda ash) into the gas stream to reactwith the acid gases. The acid gases react with the alkaline sorbents to form solid salts which are
removed in the particulate control devices. These systems can achieve acid gas (SO2 and HCl)
removal efficiencies.
4. SEPARATOR
Functions at 4kg/cm2In this only natural gas is separated to remove any condensed liquids if present. The gas firstly
goes to separator then to scrubber.
5. STORAGE TANK
-
8/4/2019 A Report of Training ONGC
7/33
-
8/4/2019 A Report of Training ONGC
8/33
GAS COMPRESSION PLANT (GCP)-KALOLINSTALLATION MANAGER: Mr. Rajesh KumarDATE OF COMMISION: GCP-I: 26.02.1990GCP-II: 15.03.1994
TOTAL CAPACITY: 5 lack m3/day
-
8/4/2019 A Report of Training ONGC
9/33
TOTAL COMPRESSORS: 106 in old plant and 4 in new plant Capacity (old) =3 lacks m3/dayCapacity (new) = 2 lacks m
3/day
REVERSE-OSMOSIS PLANT (R-O): twoDISCHARGE PRESSURE: 40 kg/cm2
PROCESS DESCRIPTION: In this plant, gas from GCS (gas collecting system) at 4kg/cm2 pressure
comes through pipe lines to GCP. Firstly it goes to common inlet separator, where the primary
separation is done, usually the content of oil in gas is negligible but if its there it gets separated. Nowthe gas goes to 1st stage suction separator, there further separation is done. Till now the pressure is
4kg/cm2, now this gas goes for first stage compression goes into compressor. After compression the
gas we get is of 12-14 kg/cm2 and because of compression temperature rises to 1250C so to lowdown
the temperature to 40-450C, compressed gas is sent to inter gas cooler. Now the cooled gas of 12-14
kg/cm2
pressure goes to 2nd
stage suction separator where further separation occurs. Then it goes to
2nd
stage gas compressor there compression is done and in the output we get gas of 40 kg/cm2pressure but temperature has again gone up to 1450C because of compression so it again goes to
cooler which is also known as after cooler . Now as cooling has occur so condensation will be done
so again whatever amount of oil will be there will be drained out from discharge separator. Then
finally gas from the discharge separator at 40 kg/cm2 pressure is sent back to GCS.
GCP FACILITIES
1. GAS COMPRESSION SYSTEM
PURPOSE
To compress gas at high pressure
PROCESS
It has two stage gas compression systems. First stage compressors takes gas from first suction
separator and other stage takes gas from second suction separator as shown in the flow diagram.
RPM= 990 Capacity-2100m3/hr
Model- 14 X 8 X 5 2 RDH-2
Make-Ingersoll sand
Type- double-acting reciprocating horizontal
Number of stages- Two
2. RAW WATER TREATMENT SYSTEM (R-O Plant)
Purpose:
to remove true deposit solids from water
Process
Firstly the raw water from the storage tank flows into pipelines and come into desired location. To
this raw water we add sodium hypo chloride which destroys the bacteria present in water. Then the
water is treated with sodium bi sulfate to reduce the chlorine content which would have increasedbecause of sodium hypo chloride addition. Then this treated water with sodium hexa meta phosphate
so that scaling can be minimized which will occur in tubing having membranes. Then this water goes
to multi grade filter where various types of gravel, sand are filtered. Then thefiltered water is treated
-
8/4/2019 A Report of Training ONGC
10/33
with 98% H2SO4 so that pH of water is maintained. Then again this water goes to cartridge filter, sothat if any filtration is left can be completed. Now this filtered water is pumped into tubing system
having membranes with the help of high pressure pump. Then there high- quality demineralised wateris produced which is then sent to storage tanks.
3. AIR COMPRESSION SYSTEM:
Make- Ingersoll RandModel- 8 X 5 E&1-NL2
Discharge Pressure- 110 PSI
Capacity- 200 CFM(each)
4. COOLING SYSTEM:
Purpose:
There are two types of gas coolers inter gas coolers and after gas coolers. Its a type ofheat
exchanger. Running water through it helps in cooling of gas and they are sent finally to dischargeseparator. Inter gas cooler takes the gas of first stage compression and gas cooler takes second stage
compression.
Process:
Its a type of heat exchanger, it contains baffles and one shell and two tubes pass exchanger system.
Cooled treated water enters from one side and gas enters from the other side. There occurs a counter
current flow. This results in exchange of heat between two liquids and hence the fluid is cooled.
5. GAS DETECTION &MONITORING SYSTEM
Used to detect the leakage of gas in the plant
6. FIRE FIGHTING SYSTEM
6 fire fighting pump
4 diesel pump and 2 motor driven pump
7. ELECTRICAL SYSTEM
Two 11 KV sub-station8 step down transformers
-
8/4/2019 A Report of Training ONGC
11/33
CENTRAL FARM TANK (CTF)-KALOLINSTALLATION MANAGER : Mr. T. C. TiwariCOMMISSIONED IN: August, 1971
-
8/4/2019 A Report of Training ONGC
12/33
OBJECTIVES:
Collection of oil from Kalol, Sanand, Jhalore, South Kadi ,Viraj , Paliyad, LimbodraTreatment of crude oil
Chemical analysis
Pumping oil to desalter Nawagam plant
Pumping effluent to ETP (effluent treatment plant)
RECEIVING SYSTEM
Crude oil received at CTF Kalol through.
8 diameter line from Sanand and Jhalore field at 1000m3/day.
12 and 8 lines from Kalol field at 170m3/day.
12 lines from south Kadi and Viraj field at 43m3/day.
COLLECTION
6000 m3/day
FUNCTIONS
Crude oil is received from various GGS. The oil which is having higher water cut is sent to
heater treater while oil having low water is directly dispatched to desalter.
TESTS PERFORMED
Test for specific gravity-
A hydrometer is an instrument used to measure the specific gravity (or relative density) of liquids;
that is, the ratio of the density of the liquid to the density of water.
A hydrometer is usually made of glass and consists of a cylindrical stem and a bulb weighted with
mercury or lead shot to make it float upright. The liquid to be tested is poured into a tall jar, and the
hydrometer is gently lowered into the liquid until it floats freely. The point at which the surface of theliquid touches the stem of the hydrometer is noted. Hydrometers usually contain a paper scale inside
the stem, so that the specific gravity can be read directly.
Test for water content (DEAN STARK METHOD) This method is used for determining water-in-oil. The method involves the direct co distillation of the oil sample. As the oil is heated, any water
present vaporizes. The water vapors are then condensed and collected in a graduated collection tube,
such that the volume of water produced by distillation can be measured as a function of the total
volume of oil used.
CTF FACILITIES
1. DISPATCH SYSTEM
Dispatch is done through 12diameter line, 51Km long pipeline to desalter Nawagamthrough topumps at 130 m3/hr rate.
6 effluent dispatch pump each of 50 m3/hr capacity.
Oil dispatch pump
-
8/4/2019 A Report of Training ONGC
13/33
(A-700) BPCL 3 in number each of 120 m3/hr capacity. (C-558)BPCL 4 in number each of 135 m3/hr.
2. MASS FLOW METER
Coriolis meter
3. STORAGE TANKS10 tanks of capacity 2000 m3 out of which 2 are used for effluent storage and rest for storage of
oil.
8 tanks of capacity 10000 m3 for storage of oil.
4. SCRAPPER SYSTEM
There are two scrappers receiving platforms from 12 pipeline for S.Kadi and 8pipeline for Sanand- Jhalore field also there is one scrapper launching platforms for 12 pipeline desalter plant
NGM.
5. HEATER TREATERIn all 6 heater treater are there in this plant.
4 of which are of capacity 300m3/day.
2 jumbo heater treater are also there, one of which is of capacity 800m3/day and second one is of1000m3/day
One jumbo heater treater is under construction.
5 heater treater feed pump are available which are centrifugal and there capacity is 45m3/hr.
It has three chambers namely
Heating chamber
Middle chamber
Electrical Chamber HEATING CHAMBER: The fire tube which extends up to this section is in
submerged condition in emulsion oil. The heating of oil emulsion decreases the viscosity of oil andwater and reduces the resistance of water movement. The heat further reduces the surface tension
of individual droplets by which when they collide form bigger droplets. This progressive action
results in separation of oil and free water. MIDDLE CHAMBER: The fluids from heating enter intothis chamber through fixed water .It doesnt allow gas to pass into electrical chamber. The gas whichenters heating chamber leaves from top through mist extractor. The oil in this chamber is controlled
by oil level controller. ELECTRICAL CHAMBER: In this section constant level of water ismaintained so that oil is washed and free water droplets of water are eliminated before fluid proceeds
towards electrode plates (electric grid). These plates are connected with high voltage supply of 10000
to 25000volts. When fluid passes through these electrodes the droplets polarizes and attracts each
other. This attraction causes the droplets to combine; they become large enough to settle into oil andwater layers by the action of gravity
6. FIRE FIGHTING SYSTEM
4 Motor driven pump of 410 m3/hr capacity work at 10kg/cm2 pressure.2 diesel engine driven pump of 410 m3/hr capacity work at 10 kg/cm2 pressure.
Jockey pumps are 2 in number which are motor driven and there capacity is 80 m3/hr.
Various potable fire extinguisher are present such as dry carbon, carbon dioxide.
-
8/4/2019 A Report of Training ONGC
14/33
HEATER TREATER
CTF (Central Tank Farm)
GGS VII-KALOLINSTALLATION MANAGER - Mr. Ajay Ratan
DATE OF COMMISION: July- 1976
-
8/4/2019 A Report of Training ONGC
15/33
-
8/4/2019 A Report of Training ONGC
16/33
PHYSICAL & CHEMICAL PROPERTIES
Ionic Nature- non-toxic
Viscosity at 300C- less than 100 poise
pH of 5% solution- 5.5 to 8.0
Solubility in H20- dispersible
Solubility in xylene & tolune- soluble
Flammability- inflammable
LABELLING, STORAGE & HANDLING
Storage conditions- store in cool, well- ventilated area
Disposal- incinerate in a furnace as per local state or national legislation
EMERGENCY MEASURES
Spillages- adsorb onto sand, earth or similar adsorbent material .Wash the spillage area.
FIRST AID
Skin contact- wash with water followed by soap & water
Eye contact- irrigate with clean water or an eye wash solution, obtain medical attention as
precaution. Inhalation- The affected person should be moved to fresh air & made to rest.
Ingestion- Give water or milk to drink.
3. TRIPLEX RECIPROCATING PUMP
Used for pumping oil from storage tank to discharge line to NAWAGAM
Maximum pressure- 64 Kg/cm2
Input- 86 KWPump RPM-260
Oil used for lubrication- 80L
Servo gear HP- 140It is motor driven pump
KW- 110
HP-150
RPM-1480
4. BOOSTER COMPRESSOR
Used to compress the gas which comes out from the separator vent at pressure 1.5 kg/cm2 to 4 5
kg/cm2 which is then send to GCS for further compression.
Make- Ingersoll rand
Model- 8.5 X 7 single stageCapacity- 10000m3/day
Suction pressure- 1.5 kg/cm2
Discharge pressure- 5 kg/cm2
5. POWER SUPPLY
Normal power is supplied from 11KV grid of the electric board
The overall normal requirement envisaged has been of the order of 100KVA
-
8/4/2019 A Report of Training ONGC
17/33
Emergency power plant is maintained by 320KVA diesel generator whose power factor is0.8 andpower of engine is 396 HP
6. FIRE WATER SYSTEM
2 reservoir of water having capacity 120 m3 and 350 m3
respectively are available.
2 pumps are also present one is motor driven and second one diesel engine driven. Second one is
used as stand by.
Specifications of motor driven pump:
Capacity- 170 m3/hr
Discharge pressure- 6 Kg/cm2
Specifications of engine driven pump
Head- 100 m
Discharge rate- 171 m3/hr
Size- 100X 125 mm
Speed- 1800 RPM Pump input- 64.9 KW
-
8/4/2019 A Report of Training ONGC
18/33
EFFLUENT TREATMENT PLANT (ETP)-II (KALOL)
INSTALLATION MANAGER- Mr. Ajay Ratan
DATE OF COMMISION - 05.07.1993RECEIVING STATUS: Effluent from
GGS- I (Kalol),
GGS-VII (Kalol),GGS-II (Kalol),
CTF-(Kalol) and to CTF effluent of GGS- IV also comes.
PRODUCTION- 1000 m3/day and 50 m3/day (max.) of oil.
-
8/4/2019 A Report of Training ONGC
19/33
POWER CONSUMPTION - 19378 KW/day
OBJECTIVESThe main objective of this plant is to collect effluent from various GGS and CTF and treat that
water.
Finally the treated water is sent to water injection plant for final treatment.
PROCESS DESCRIPTION
Firstly effluent from various GGS (as mentioned above) comes into header of ETP and from thoseheaders it goes to hold up tank .Then it goes to equalization tank where effluent is allowed to stand
for some time. Thus because of this settling time water settles down and oil at the top. Then on
weekly basis oil from the top is sent to sludge separating tank as the content of oil in it isvery less.But water goes to receiving sump through centrifugal pump. Then from receiving sum pit goes to
flash mixer where alum and polyelectrolyte are added in 200 ppm and 10 ppm concentrations
respectively. Alum acts as coagulant & polyelectrolyte is added to separate further. Then from there
water goes to clariflocculator which has agitator inside the vessel. After agitation sludge settles downand after some time it is sent to sludge sump and then it is pumped to sludge
lagoons there sludge from sludge separating tank also comes and from there it is sent
for bioremediation. Now water which comes out of clariflocculator goes to clarified water tank andfrom there it is pumped into sand filters where the final filtration is done and then this water goes toconditioning tanks where again some settling time is given so that even if some amount of impurities
is there can settle down and finally the treated water goes to storing tank and from there it is pumped
into Cental Water Injection Plant (CWIP) through pipelines.
ETP FACILITIES
1. FLASH MIXERCapacity- 1.2 m3
Alum and poly electrolyte are added
2. CLARIFLOCCULATORCapacity-224 m3
Purpose- it helps in separation of water from oil.
It consists of huge cylindrical tank with a hollow cylinder inside. The solution of oil and water
enters through this hollow cylinder with oil on top. Oil separates at the top through V-notch providedat the sides (its periphery). Sludge settles down in a feet bottom and sludge is pumped through pump
to lagoon. Whereas water is transferred to storage tank-2 (SR-2) and from there water is sent to filter
for further purifications
3. PRESSURE FILTER
- 2.5 m3
Number- 2 Nos., but one filter is used at a time other is used as a standby.The filter consists of membrane made of sand and gravel (sizes ranges from 9mm-600mm).Water
is circulated here and all particles are filtered by them.
Back Wash Water arrangement is also made in order to clean the filter when its cleaning isrequired. This is done daily as two pressure filters are available, one is used at a time and other is
used as stand by.
-
8/4/2019 A Report of Training ONGC
20/33
4. PUMPING SYSTEM
7 centrifugal pump
Capacity- 40 m3/hr
Head- 50 m
Speed- 1470 RPM
Input- 13KW
Efficiency- 41%
3 screw pump
Head- 30 m
RPM- 1200
HP- 1.5
SAND FILTER
-
8/4/2019 A Report of Training ONGC
21/33
ETP (EFFLUENT TREATMENT PLANT) CENTRAL WATER INJECTION PLANT(CWIP)INSTALLATION MANAGER -Mr. Ajay Ratan
DATE OF COMMISION-04.04.1990
-
8/4/2019 A Report of Training ONGC
22/33
UNIT PRODUCTION - 1680 m3/day
POWER CONSUMPTION - 20000 KW/month
DISCHARGE RATE- 35 m3/hr
CHEMICALS USED Sodium sulfide- 40 ppm Scale inhibitor- 20 ppm Corrosion inhibitor- 20ppm
PROCESS DESCRIPTION -Water from ETP through pipelines comes to CWIP for further chemical
treatment before it is sent to GGS for water injection. Water at 35-37 m3/hr of flow rate and atpressure of 4 kg/cm2 is pumped into CWIP through pipelines from ETP. Effluent enters the treated
water tank (600 m3) where tube well water is also added in fixed proportion. This tube well water
(raw water) is passed to three micro filters of 25micron,10 micron and 3 micron one by one and thenfinally it is sent to raw water hold tank. At the outlet of the tank three chemicals are added, sodium
sulphite (40 ppm) which acts as oxygen scavenger, corrosion inhibitor (20 ppm) is added to prevent
corrosion and scale inhibitor (20ppm) is also added to decrease precipitation formation. Now this
effluent is sent to treated water tank where water from ETP is mixed with it by mean of agitator. Thiseffluent is then pumped with the help of water injection pump to headers. Now from headers the
water is injected at high pressure and at low pressure through four inch pipe line. Water is injected at
high pressure of 60-62 kg/cm2 to 13 wells used for artificial lifting which are connected to GGS VII.Low pressure water is injected at 40-42 kg/cm2 connected to 28 wells used for artificial lifting. Here4 wells are connected to GGS I, 4 wells to GGS XI, 10 wells to GGS II and 10 wells are connected to
GGS VII. So total wells connected to CWIP is 52 wells.
CWIP FACILITIES
1. PUMPING SYSTEM
4 reciprocating pumps are available and out of which 2 are working and 2 are stand by.Specifications of pump are:
Capacity-35 m3/hr RPM-314
Maximum working pressure- 170 kg/cm2
BKW- 190.78
MOTOR
RPM-1455
HP/KW-322/240
Efficiency-95.5%
Volt-415
2. STORAGE SYSTEMBalancing tank- 200 m3Storage tank -600 m3
Treated water tank- 600 m3
-
8/4/2019 A Report of Training ONGC
23/33
CWIP (CENTRAL WATER INJECTION PLANT)
CENTAL TANK FARM (CTF)NAWAGAMINSTALLATION MANAGER - Mr.B.K.Shit
AREA OF INSTALLATION - 100 AcresRECEIVING STATUS
-
8/4/2019 A Report of Training ONGC
24/33
GGS- I, II, III500 m3/dayRamol, Nandej, Wasna fields- 800-900 m3/day
CTF Kalol- 8000 m3/dayMehsana fields- 8000 m3/day
STORAGE TANKS
8 tanks- 2000 m3
MAIN OBJECTIVE
As such in this installation no processing is done, they just pump desired crude oil to desalter plant
which has come from various CTF.
Every hour water content is checked in the samples of treated crude oil of desalter plantafterfulfilling the desired conditions of refineries dispatching is done from desalter to refineries .
They target to have water content of 0.5-1 % in oil before discharging.
PUMPING SYSTEMMake- BPCL
Type- Quintuplex plunger pump
Maximum discharge- 120 m3/hrMaximum operating pressure- 40 kg/cm2Rate BHP- 430 HP
MOTOR
HP- 545
KW-400
RPM-1450
Voltage-415
Frequency- 50 Hz
Current- 676 Amp
DESALTER PLANT: NAWAGAMINSTALLATION MANAGER : Mr. B.K. Shit
DATE OF COMMISION : 01.01.1995PLANT CAPACITY : 6.7 million metric tons per year
NUMBER OF TRAINS (UNIT) - 3 trains of 2.23 million metric tons per year (2 trains are operating
and 1 is stand by)
RECEIVING STATUS
Crude oil from
Mehsana Ahmedabad Assest
FEED STOCK CHARACTERSTICS
Chloride in oil feed water: 45oo ppmChlorides as Cl salt- 81 ptbSpecific gravity of oil-0.8948Totalsulphur, %wt- 0.007Wax content,%wt-6.8Total acidity, mg KOH/gm- 4.65
DESALTED CRUDE OIL CHARACTERSTICS
Salt content-10-15 ptb
PROCESS DESCRIPTION
Crude oil is received from the existing tank farm to new tanks through a 30 suction header. 4Nos.feed pumps are installed for pumping feed to desalter to three trains whereas the fourthpump is
common stand by for all the three trains. Demulsifier chemical is mixed with the feedcrude oil in the
suction line in the feed pump. Crude oil from the feed pump is further mixedwith wash water at a rate
-
8/4/2019 A Report of Training ONGC
25/33
of approximately 0.5 % of the crude before the crude is sent through heat exchanger. In this heatexchanger the feed is heated to about 63
0C by exchanging heat with the outgoing treated crude oil
from the desalter. Treated crude passes through the tube side of the heat exchangers. The crude fromthe exchangers will pass through the feed heater where in the temperature is raised to 100 0C before
entering the desalter vessel. In the desalter vessel feed crude is fed at lower portion of vessel where in
it travels and separates through electrostatic grid. The electrostatic grid aids the breaking of emulsion
and settlement of water at the bottom. The crude after losing water/salts will be let out through thecrude outlet line from the top of vessel. Desalter has bottom outlet connections at intervals for
removal of water and sediments settled atbottom of desalter. Part of the produced water is circulated
back into desalter vessel through desludging pump (rated at 50 m3/hr and 25 m head) to maintain thewater phase in the desalter in a fluidized conditions so that the sediments settle down at the bottom of
the vessel and form the thick mud.The desalter vessel is provided with sampling valves at various
elevations to collect and analyse the samples at various elevations on the desalter vessel. So byanalyzing these samples discharging is done.
NAWAGAM PLANT FACILITIES1. Storage system
Crude oil
No. of tanks: 4
Type: floating roof
Capacity:30,000 m3
Water
Raw water tank:2
Type: cone roof
Capacity: 700 m3 each
2. POWER SUPPLY SYSTEM
Distribution voltage:415 voltsNormal power: 240 volts, AC
Shut down: 110 volts, DC
Fire alarm system: 240 volts AC
3. FIRE FIGHTING SYSTEM
2 JOCKEY pump:
Working pressure: 8 kg/ cm2
Feed rate: 10 m3/hr
2 diesel engine driven pump
Feed rate: 410 m3/hr1 electrical driven pump
Feed rate: 410 m3/hr
2 water storing pond are there of capacity 3200 m3 each
4. PUMPING SYSTEM
Rotating pump Quantity Type Capacity(m3/hr) Head(m)
Desalter feed pump 4 Centrifugal 330 140
Service water pump 2 Centrifugal 40 50
Process water pump 2 Centrifugal 40 135
Desludging pump 2 Centrifugal 50 25
Drinking water pump 2 Centrifugal 5 25
-
8/4/2019 A Report of Training ONGC
26/33
Injectionpumps(reciprocating)
4 Centrifugal 700 lpm 29.7
5. COMPRESSORS
Air compressor
Quantity: 2
Capacity:350 Nm3/hr
Discharge pressure: 9kg/cm2
6. BURNERSNo. of burners: four reactor
Type of burner: forced draft
Type of fuel: natural gasHeat liberation(max) (mm BTU/hr): 8
7. MISCILLANEOUS
Instrumental Air Dryer:
Quantity: 2
Capacity: 150 m3/hr
Demulisifier mixer
Quantity: 2
-
8/4/2019 A Report of Training ONGC
27/33
WWTP-WASTE WATER TREATMENT PLANTThis plant is the part of DESALTER PLANT as the treated crude oil is sent to refineries buteffluent is
sent to WWTP for chemical treatment.
-
8/4/2019 A Report of Training ONGC
28/33
WWTP FACILITIES1. WASH TANKNumber of units- 2
Capacity- 1000 m3Storage temperature- 600C
Water from desalter plant is stored in these wash tanks, after filling of one wash tank tothe desired
level, valve of 2nd
wash tank is opened and 1st
tank is taken into consideration.
2. TPI (TILTED PLATE INTERCEPTOR) SEPARATOR
The effluent from wash tank is routed to TPI. The TPI consists of 3 bays each having one platespack.
It has one inclined plate at 450, depth of third bay is largest, the oily sludge is collected atthe hopper
is discharged into wet sump by gravity. So here the primary separation takes place.
3. FLASH MIXERNumber of unit- 1
Capacity-4.25 m3
Alum- 50 ppm
Waste water after removal of free oil in TPI flows by gravity into flash mixer where alumis addedas coagulant. A suitable agitator is provided to mix alum solution with the waste water. Suitable MS
ladder and MS rungs epoxy painted are provided in the system for approach and maintenance.
4. FLOCULATORType- paddle type
Chemical addedpolyelectrolyte
Volume of unit- 7 m3
DISSOLVED AIR FLOATATION UNIT (DAF)
The DAF unit is carbon steel epoxy painted construction fitted with flocculator. The effluentwaterafter getting dosed with alum in the flash mixer flows by gravity into the DAF unit. The already
coagulated effluent is added with deoiling type polyelectrolyte in the flocculation unit before DAF
chamber. Floatation of solids is accomplished by introduction of millions ofmicroscopic air bubble. As these bubbles rise they attach themselves to the particles in thesuspension
and carry them to the surface for removal. An important principle of DAF system is the introduction
of air in the recirculation effluent and blending the raw flow where the millions of microscopicbubbles are found to which the suspended particles get attached and lift to the surface removal. A
skimming arrangement is provided at the top to remove the floatation sludge blanket and this scum is
routed to oily sludge sump and from the bottom water goes to receiving sump and from there it is
discharged.
5. TREATED EFFLUENT SUMP
The treated effluent from DAF is routed by gravity to the treated effluent sump. Arrangements
should be made to pump the treated water to depleted pump.Number of unit- 1
Material of construction- RCC
Effective capacity- 50 m3Detention time- 0.25 hrs
6. OIL SLUDGE SUMP AND PUMP HOUSEThe oil sludge generated during treatment in TPI and DAF units flows by gravity to oilsludge from
there it is pumped to sludge thickener for thickening.
Number of unit- 1
-
8/4/2019 A Report of Training ONGC
29/33
Material of construction- RCCEffective capacity- 6.75 m3
Detention time- 1hrNumber of pumps provided- 2
Type- horizontal, centrifugal
Capacity- 10 m3/hr
Installed HP of drive- 3
7. THICKNER
Thickening is the unit process which is employed for thickening of the sludge to increase thesludgecontent in the sludge. The stream entering the thickener is sludge from oily sludge sump.Here
agitation is done and after that settling time is given so that sludge can settle at bottom andoil is sent
to wet slop from the top.Number of unit- 1
Material of construction- RCC
Effective capacity- 85 m3
Detention time- 1hr
PROCESS DESCRIPTION
Effluent from the desalter through pipelines is pumped into wash tanks and from there issent to TPIand then it is sent to flash mixer where alum is added. Then the effluent by gravityflows to DAF andoil to oil sludge. In DAF polyelectrolyte is added
And finally the effluent is sent to receiving sump and oil is sent to oil sludge and fromthere it is
sent to thickner and then sent back to desalter.
-
8/4/2019 A Report of Training ONGC
30/33
-
8/4/2019 A Report of Training ONGC
31/33
the well bore to cause the well to flow into the production facilities at the surface .In other wells,natural energy will not drive oil to the surface in sufficient volume. The reservoirs natural energy
must then be supplemented by some form of ARTIFICIALLIFT.Types of Artificial Lift Systems
There are four basic ways of producing an oil well by artificial lift. There are.(1) Gas Lift.(2) Sucker
Red Pumping.(3) Submersible Electrical Pumping.(4) Subsurface Hydraulic Pumping.(5) Screw
pump (pc pump).Choosing an Artificial Lift System
The choice of an artificial lift system in a given well depends upon a number of factors. Primary
among them, as far as gas lift is concerned is the availability of gas. Then gas lift is usually an idealselection of artificial lift.
The Process of Gas Lift
Gas Lift is the form of artificial lift that most closely resembles the natural flow process. It can beconsidered an extension of the natural flow process. In a natural flow well, as the fluid travels upward
towards the surface, the fluid column pressure is reduced and gas comes out of solution. The free gas
being lighter then the oil it displaces, reduce the weight of the fluid column above the formation. This
reduction in the fluid column weight produces the pressure differential between the well bore and thereservoir that causes the well to flow. When a well makes water and the amount of free gas in the
column is reduced the same pressure differential between the well bore and reservoir can be
maintained by supplementing the formation gas with injected gas.Types of Gas LiftThere are two basic types of gas lift systems used in the oil industry. These are:(1) Continuous
flow(2) Intermittent flow
Continuous Flow Gas Lift:In the continuous flow gas Lift process, relatively high pressure gas is injected down hole into the
fluid column. This injected gas joins the formation gas to lift the fluid to the surface by one or more
of the following processes.1. Reduction of the fluid density and the column weight so that the
pressure differential between the reservoir and the well bore will be increased.2. Expansion of theinjection gas so that it pushes ahead of it which further reduces the column weight thereby increasing
the differential between the reservoir and the well bore.3. Displacement of liquid slugs by large
bubbles of gas acting as pistons.Intermittent Flow Gas Lift:
If a well has a low reservoir pressure or every low producing rater it can be produced by a form of gas
lift called intermittent flow. As its name implies this system produces intermittently or irregularly andis designed to produce at the actual rate at which fluid enters the well bore from the formation. In the
intermittent flow system, fluid is allowed to accumulate and build up in the tubing at the bottom of
the well. Periodically, a large bubble of high pressure gas is injected into the tubing very quickly
underneath the column of liquid and liquid column is pushed rapidly up the tubing to the surface. Theaction is similar to firing a bullet from a rifle by the expansion of gas behind the rifle slug. The
frequently of gas injection in intermittent lift is determined by the amount of time required for a
liquid slug to enter the tubing. The length the gas injection period will depend upon the time required
push one slug of liquid to the surface.Advantages of Gas Lift
1) Initial cost of down hole equipment is usually low.2) Gas lift installations can be designed to lift
from one to many thousand of barrels.3) The producing rate can be controlled at the surface.4) Sandin the produced fluid does not affect gas lift equipment is most installation.5) Gas lift is suitable for
deviated well.6) Long service lift compared to other forms of artificial lift.7) Operating costs are
relatively low.8) Gas lift is ideally suited to supplement formation gas for the purpose of artificiallylifting wells where moderate amount of gas are present in the produced fluid.
9) The major items of equipment (the gas compressor) in a gas lift system are installed onthe surface
where it can be easily inspected, repaired and maintained.
-
8/4/2019 A Report of Training ONGC
32/33
Limitations1. Gas must be available. Natural gas is quite cheap as compared to air, exhaust gases
andnitrogen.2. Wide well spacing may limit the use of a centrally located source of highpercentage.3. Corrosive gas lift can increase the cost of gas lift operations if it is necessary to
treat or dry the gas before use.
-
8/4/2019 A Report of Training ONGC
33/33
SUCKER ROD PUMPING
80-90% of all artificial lift wells are being produced on sucker rod pumping; the most common is the
beam pumping system. Sucker Rod Pumping System is time tested technological marvel which has
retained its typical features for over a century. When oil well ceases to flow with own pressure, this
Artificial Lift system is installed for pumping out well fluid. In the well bore reciprocating pumpcalled Subsurface pump is lowered which is operated by surface system called SRP surface unit or
Pumping unit. Prototype of one such unit is in action here.
General considerations:Oil will pumping methods can be divided into two main groups: Rod System: Those in which the
motion of the subsurface pumping equipment, originates at the surface and is transmitted to the pump
by means of a rod string. Rod-less System: Those in which the pumping motion of the subsurfacepump is produce by means other than sucker rods. Of these two groups, the first is represented by the
beam pumping system and the second is represented by hydraulic and centrifugal pumping systems.
The beam pumping system consists essentially of five parts (1) The subsurface sucker rod driven
pump.(2) The sucker rod string which transmits the surface pumping motion and power to thesubsurface pump.(3) The surface pumping equipment which charges relating motion of the prime
motion of the prime mover into oscillating linear pumping motion.(4) The power transmission unit or
speed reducer (5) The prime mover which furnishes the necessary power to the system.