A. Perin, TE-CRG, YETS meeting 15.09.2015
CRG activities for YETS 2015
September 15th 2015
Year End Technical Stop (YETS) Meeting
A. Perin, TE-CRGm with contributions from M. Pezzetti, N. Vauthier, G. Ferlin, U. Wagner.
A. Perin, TE-CRG, YETS meeting 15.09.2015
CRG preparation of YETS2015
• Preliminary preparation phase: not all defined.
• An additional round is necessary in about 4 weeks
• Activities classified in two categories:
A) Affecting other non-CRG systems (no CS/CM): this is the main subject for coordination
B) CRG internal «transparent» for other systems
N.B.: activities are also planned on experiments (mainly CMS)
A. Perin, TE-CRG, YETS meeting 15.09.2015
S. Claudet, T
E-CRG
06.08.2015
A. Perin, TE-CRG, YETS meeting 15.09.2015
LHC YETS overview
Strategy
• Cryostart / cryomaintain until week 46.
• Baseline: keep the helium in the magnet cryostats at 4.5 K. Exception if a warmup od S81 is required to fix the 15R8 problem.
Main issues to be corrected
• Leak in IP8 A cold box: will require warmup of the cold box. Cryoplant B still operational.
G. Ferlin
, TE-CRG-O
A
A. Perin, TE-CRG, YETS meeting 15.09.2015
InstrumentationCatégorie A
• Mise en service des capteurs Basse Pression nécessitant les supports CRG-OA pour installation + support EN-ICE/BE-CO/CRG-CE pour Layout/FEC/PVSS
• Installation capteur de pression ATLAS UX15 nécessitant les supports CRG-ME pour installation + support EN-ICE/BE-CO/CRG-CE pour Layout/FEC/PVSS
• La consolidation des EH 500W/100W dans les triplets nécessitant les CRG-OA pour installation + support EN-ICE/BE-CO/CRG-CE pour Layout/FEC/PVSS
Catégorie B
• Les events concernant l’intrumentation cryogénique listés sur le logbook*: > 100 corrective actions foreseen
Essentially in the shadow of other activities and when access is possible.
N. Vauthier, T
E-CRG-CI
A. Perin, TE-CRG, YETS meeting 15.09.2015
YETS Main activities • Cat A
• P18/P2 QURC consolidation for VFD, equipotential (for ECM issues not yet solved);
• P18 QSCB equipotential cabling for motor-compressor consolidations;
• P6 QSCB equipotential cabling for motor-compressor consolidations;
• P8 QSC surface 24 VDC redundant;
• P8 QSCB equipotential cabling for motor-compressor consolidations;
• Cat B• LHC sector redeployment for EH consolidations (see CI section) ( need 1/2 day
control stop per sector)
Control & electricity
M. Pezzetti ,
TE-CRG-OA
Essentially in the shadow of other activities with short and localized interruptions of cryo.