lsc - 28 february 2014 - m. pezzetti – cryogenics 1 28 february 2014 m. pezzetti edms id: 1346282...
TRANSCRIPT
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 1
R2E mitigation for LHC cold compressor equipment progress.
28 February 2014
M. Pezzetti
EDMS Id: 1346282 v.1
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 2
R2E LHC cold compressors
• Project Overview• Actual status• Next Steps
A special THANKS to all the people concerned:ICL, R2E, RWG, EN/STI, EN/EL, EN/CV, TE/CRG…..
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 3
Last 09 April 2013 TE/TM meeting :
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 4
QURC R2E project overview:
P4 high priority, to be done during LS1.
• ICL positioning validation• P4 equipment inventory, very short time! (https://edms.cern.ch/comment/1323557)
• ECR (edms1346280) driven by cryogenic but all group involved
• R2E/P4 Planning (w.r.t LS1 planning)• EN/EL (DIC : 350 cables)• Special cable magnet bearing assembly (https://edms.cern.ch/comment/1342848)
• Magnet Bearing electronics MBC170(prototype validated, ordered, production delivery March 2014)
• RadWG (new w.r.t TETM of april’13) valve positioner & I/O cards (https://edms.cern.ch/document/1340848/1)
(ordered, in production delivery beginning April 2014)• Cryo RF relocation (development, construction & installation May/June)
AMB special cable FINAL length = 45 meters
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 5
Cryo cabinet relocation (Cable length 45m)[UX45 – level 2] QURC [8 cabinet QURC (AMB, Drive, local PLC & 45 SIPART positioner ][US45 - level 1] QUI [1 cabinet (PROFIBUS & 20 SIPART positioner)][UX45 – level 1] QURC a-b [2 cabinet (PLC, PROFIBUS)][UX45 – level 0] Cryo RF [4 cabinet (PROFIBUS & 20 SIPART positioner)]
TOTAL 15 cabinets to be redesign and relocated in UL44/46.
R2E P4 relocation to be done in LS1
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 6
2013 2014
Preparation (cables & cabinets)
ECR document, Integration activities
EN/EL QURC QUI RF
01 02 03 04 05 06
S34 CoolDown
07
S45 CoolDown
08 09
CRYO maintenance CRYO OP Re-commissioning
New MECOS AMB@P4AMB final validation20K Stand alone50-60% torque
R2E/P4 work PLANNING
Intense co-activities period!!!
Main tasks to be done:• Preparation (cables & cabinets) until end of February• EN/EL cabling campaign 01 March – 30 June• Installation new magnetic bearing electronic mid-April final validation in May/June
R2E project Schedule for LS1 7
EN Point 4
Maria Barberan courtesy
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 8
Project organization (main tasks)Project coordination
M. Pezzetti (TE-CRG)Dep.: B. Ivens (TE-CRG)
R2E Project and coordination / planning
M. Brugger (EN/STI) / AL Perrot (EN-MEF)
LS1 scheduling
M. Barberan Marin (EN-MEF)
Technical coordinator
B. Ivens (TE-CRG)
EN/EL cabling
JC. Guillame (EN-EL)
Cabinet Design & Construction
B. Ivens (TE-CRG)
AMB Technical contact
M. Pezzetti (TE-CRG)
Cryo Operation
L. Herblin (TE-CRG)
Electronics experts
J. Casas (TE-CRG) / F.Formenti (TE)
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 9
Main personnel resources
Electrical work TE-CRG-CE: 1 staff (B. Ivens) + 4 FSU
EN-EL CABLING: CEGELEC + 1 staff / 1 FSU
Magnetic bearing elect.: being defined, estimated 1 engineer + 1 technician.
Approx. 10 persons involved for the main tasks (during 3-4 months).
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 10
R2E P4 budget status (budget code 99547)
TE/CRG cabling manufacturing 75 kCHF (old figures 50 kCHF) new!
New AMB MECOS electronics (R&D + prod.)
150 kCHF (30 kCHF 2013 / 120 kCHF 2014)
EN/EL cabling 250 kCHF, 2014 budget (to be validated by EN/EL) new!
new SIPART 250 (Ph1 cabling (20 kCHF 2014)- Ph2 installation (230 kCHF 2015 or later) new!
AMB Commissioning 20 kCHF/ 2014 budget new!
RF + Others 100 kCHF (HW + FSU manpower) new!
TOTAL ~800 kCHF
To be compared R2E/P8 budget was 700 KCHF (without RF relocation).
S. Claudet courtesy
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 11
QURC R2E project overview:
P8 low priority, LS2. stand by, Ph1 : ICL (already done!) and EN/EL DIC identification w.r.t technical solution as equal to P4. Cold compressor Special cables (already bought!) 75 kCHF.R2E condition don’t change until LS2.
P6 low-low priority, LS2. Stand by, preparation activities for Ph1 will start this years with ICL, P6 equipment inventory and DIC identification.R2E condition measurement in 2015/2016.
P6 no R2E mitigation need.
US85 level 0
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 12
ConclusionNo show stopper identified.
Integration P4-P8 approved, P4 equipment inventory done, ECR release (February), planning agreed with LS1 coordination, new magnetic bearing electronic prototype validated, special cables ready (10 March MECOS validation at CERN).
P4 DIC (Demande Installation Cables) approved/scheduled by EN/EL.
Next steps Cabling & installation (from March 2014 to end of June, no margin).Special cable fragile Close supervision during cabling campaign.
Tight timeline & intense co-activities between cabling, cryo technical and maintenance.
-> need a close technical supervision/coordination follow-up.
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 14
AMB key points
EMCCabling
Connectors
External & Redundant
48 VDCPower Supply
AMB Advance
technology(~10 years)
Special cables Technology @
CERN
Diagnostic knowledge improved
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 15
P4 Relocation UL positions
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 1616
R2E – QURC UX452
• Relocation QURC-EMC1/4 (VFD & AMB electronics)• SIPART positionners -> splitting positionner
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 1717
R2E – QURC UX451
QURCA/B-EM01• CPU deja dans UL44 QUPC armoire (CB 2011-12)• Cartes E/S schneider a extraire (blocks phoenix reste dans EM01) et creer une nouvelle armoire QURCA/B-EM02• PLC securite CCS a extraire et mettre dans la meme nouvelle armoire
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 1818
R2E – QUICA UX450
QUICA-EM01• CPU deja dans UL44 QUPC armoire (CB 2011-12)• Cartes E/S schneider a extraire (blocks phoenix reste dans EM01) et creer une nouvelle
armoire QUICA-EM02• Link/couplers a extraire et mettre dans la meme nouvelle armoire• SIPART positionneurs des vannes -> positionneurs deportee (tirroirs)
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 1919
R2E – QYC03/4 UX45½
• Deplacer les tirroirs, les platines et les alims labo (chauffages)• deplace de 2 racks actuelle vers 4 racks pour avoir plus de place disponible• Les equipements sont mellange on va les spliter dans 2 distinct ensembles, gauche et
droite.
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 20
Diagnostic Unit Project Overview
Internal Failures External-Internal/External
Failures
Power Amplifiers Failure Rotor deformation/bent rotor
Position Sensors Failure Rotor rub
Actuators Failure Rotor Impact
Controller
Failure
Loss of I/O board channel Rotor contact
Computer hardware failure Rotor mass loss
Computer software error
Tab.1
Component Faults
Power Amplifiers
power supply fault
input signal faults
bridge faults
Sensors
loose wire connection
power supply fault
Calibration fault
Sensor malfunctions
Actuators
Intermittent contact
Insulation deterioration
Power supply faults
Controller
Intermittent contact
Dielectric breakdown in capacitors
Dielectric breakdown in transistors
Connections insulation deterioration
External Faults
Motion of system base
Cracked rotor
Misalignment
Dynamic rotor loading
First STEP:Fault Detector Design and Implementation
Fault Models
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 21
P4 SEU Mitigation for valve positionner Controller
Cross Section estimation
LSC - 28 February 2014 - M. Pezzetti – Cryogenics 22
Cryo. equipment to be relocated
Current location/name
Future location/name
Remark(s) DIC/#cables/installation order
Cryo RF cavities UX45 level 0QYC03-04
UL44/46QYC01-02
Full relocation NOK/52priority: 4
QURC
cold compressors
UX45 level 2QURCA-EMC01-04QURCB-EMC01-04
UL44/46QURCA-EMC01-04QURCB-EMC01-04
Full relocation QURCA:OK/93Priority: 2QURCB:OK/93Priority: 3
cold box 1.8 K UX45 level 1QURCA-EM01QURCB-EM01
UL44/46QURCA-EM02QURCB-EM02
Part of eqpt to be relocated (DP/PA link coupler, power controllers for electrical heaters)
valves positioners SIPART
UL44QURC-QUI EM03
Included in QURC/QUI DIC
QUI (cryo. Distrib. Box 4.5 K)
UX45 level 0QUICA-EM01valves positioners
UL44QUICA EM02QURC-QUI EM03
Part of eqpt to be relocated (profibus link, coupler and I/O schneider card)
OK/76Priority: 1
3