a highlight on stability of road embankments ...the main section details the design of floating...

12
A HIGHLIGHT ON STABILITY OF ROAD EMBANKMENTS ON SOIL REINFORCED BY FLOATING STONE COLUMNS: A TUNISIAN CASE STUDY Mounir BOUASSIDA * 1 JM DEBATS 2 ABSTRACT Nowadays, the use of floating stone columns to reinforce soft/compressible soils is becoming more common. In fact the optimization of the length of the floating columns will make this improvement technique much more cost-effective. Adopting such reinforcement scheme relies on the verification of the residual settlements within the unreinforced soil layers which should remain within an admissible range. The financial harbor at Raoued (Ariana governorate) located north of Tunis City is a large project where the first step in progress is to build several kilometers of roads over 5000 Acres. The geotechnical profile of this area neighboring the Mediterranean Sea is essentially composed of soft soil layers up to 15 m depth overlying compressible clays horizons extending to30 m depth. Two options of soil improvement techniques were studied: preloading embankments associated to geodrains of 30 m length and reinforcement by floating stone columns of 14-17 m length. Due to the significant savings in time provided by the stone column reinforcement compared to the use of geodrains with preloading the suggested paper details the design of the stone columns, taking into account the requirement of an allowable residual differential settlement of 2 cm within the unreinforced compressible clays having good homogeneity and also an OCR of 1.3 as predicted from CPTu tests. The design of floating column reinforced foundation was carried out by using the methodology suggested by Bouassida and Carter (2014) and inherent verifications detailed by Bouassida and Hazzar (2015). 1. INTRODUCTION Presently a wide spectrum of improvement techniques is affordable for the treatment of weak and highly compressible soils like soft clays. Prefabricated vertical drains, vacuum consolidation, stone columns, sand compaction piles and deep soil mixing are among the most widely used techniques to enhance bearing capacity, to mitigate settlements and accelerate the consolidation of soft soils. Choosing the suitable solution among these techniques depends on several factors like the ground conditions to ensure suitable installation. This is often checked by performing ”trial zones” which also permit to quantify the expected benefits. In this context the Project of Financial Harbor at Raoued (PFHR) at Ariana (Tunisia) is addressed for the construction, in a first step, of roads on embankments with variable height up to 4m. The * 1 Université de Tunis El Manar, Ecole Nationale d'ingénieurs de Tunis. Ingénierie Géotechnique, LR14ES03, BP 37 Le Belvédère 1002 Tunis, Tunisia. [email protected] 2 Eguilles, Aix en Provence, France. 13 7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

Upload: others

Post on 14-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • A HIGHLIGHT ON STABILITY OF ROAD EMBANKMENTS

    ON SOIL REINFORCED BY FLOATING STONE COLUMNS: A

    TUNISIAN CASE STUDY

    Mounir BOUASSIDA *1 JM DEBATS

    2

    ABSTRACT

    Nowadays, the use of floating stone columns to reinforce soft/compressible soils is becoming

    more common. In fact the optimization of the length of the floating columns will make this

    improvement technique much more cost-effective. Adopting such reinforcement scheme

    relies on the verification of the residual settlements within the unreinforced soil layers which

    should remain within an admissible range. The financial harbor at Raoued (Ariana

    governorate) located north of Tunis City is a large project where the first step in progress is to

    build several kilometers of roads over 5000 Acres. The geotechnical profile of this area

    neighboring the Mediterranean Sea is essentially composed of soft soil layers up to 15 m

    depth overlying compressible clays horizons extending to30 m depth. Two options of soil

    improvement techniques were studied: preloading embankments associated to geodrains of 30

    m length and reinforcement by floating stone columns of 14-17 m length. Due to the

    significant savings in time provided by the stone column reinforcement compared to the use

    of geodrains with preloading the suggested paper details the design of the stone columns,

    taking into account the requirement of an allowable residual differential settlement of 2 cm

    within the unreinforced compressible clays having good homogeneity and also an OCR of 1.3

    as predicted from CPTu tests. The design of floating column reinforced foundation was

    carried out by using the methodology suggested by Bouassida and Carter (2014) and inherent

    verifications detailed by Bouassida and Hazzar (2015).

    1. INTRODUCTION

    Presently a wide spectrum of improvement techniques is affordable for the treatment of weak

    and highly compressible soils like soft clays. Prefabricated vertical drains, vacuum

    consolidation, stone columns, sand compaction piles and deep soil mixing are among the most

    widely used techniques to enhance bearing capacity, to mitigate settlements and accelerate the

    consolidation of soft soils. Choosing the suitable solution among these techniques depends on

    several factors like the ground conditions to ensure suitable installation. This is often checked

    by performing ”trial zones” which also permit to quantify the expected benefits. In this

    context the Project of Financial Harbor at Raoued (PFHR) at Ariana (Tunisia) is addressed for

    the construction, in a first step, of roads on embankments with variable height up to 4m. The

    *1 Université de Tunis El Manar, Ecole Nationale d'ingénieurs de Tunis. Ingénierie Géotechnique, LR14ES03, BP 37 Le Belvédère 1002

    Tunis, Tunisia. [email protected] 2 Eguilles, Aix en Provence, France.

    13

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

    mailto:[email protected]

  • PFHR is located in a coastal area close to the Mediterranean sea. In such area recent

    sedimentary deposits, e.g. compressible soft soils, are often encountered.

    This paper, first, briefly introduces the consistency of the geotechnical surveys performed at

    site and the synthesis of the geotechnical data to be considered for the design. Especially the

    overconsolidation of the compressible clay layers encountered is investigated from oedometer

    and CPTu test results. The main section details the design of floating stone column

    reinforcement as a foundation of road embankments. This alternative raises the problem of

    long term settlement in the unreinforced clay layers: are those settlements admissible in

    magnitude and in time as a function of embankment height? The design of stone columns

    reinforcement is carried out by duly taking all those considerations into account.

    2. THE PROGRAMME OF GEOTECHNICAL SURVEYS

    As reported in [1] and [2], two main geotechnical surveys were carried out in 2014 and in

    2017 for the construction of road embankments the geotechnical surveys comprised:

    - Eighteen pressuremeter profiles performed to various depths (81 to 96 m);

    - Three boreholes performed up to 40 m depth below ground surface. From these boreholes

    sixteen intact soil specimens were extracted to be used for identification and mechanical

    laboratory tests. Laboratory tests included grain size distribution, Atterberg limits, unit

    weight and water content determination and essentially oedometer tests.

    - Seven SPT tests were performed.

    - Five profiles of CPTu tests were performed to refusal depths varying from 19 to 35 m

    depth (first survey).

    - Eight profiles of CPTu tests were performed to refusal depths varying from 24.9 to 30.3m

    depth (second survey).

    Detailed experimental results of in-situ and laboratory tests are given in the reports [1] and

    [2].

    3.SYNTHESIS OF GEOTECHNICAL INVESTIGATIONS

    From the existing geotechnical reports two soil profiles were considered for the design as

    summarized in Table 1.

    Table 1. Typical geotechnical profiles

    Profile n° 1 (unfavored data between I-2 &

    III-4)

    Profil n° 2 (unfavored data between I-1, III-1

    & III-2)

    Horizons Thickness

    (m)

    Em (MPa) Pl* (MPa) Horizons Thickness

    (m)

    Em (MPa) Pl* (MPa)

    I 6 0.9 0.21 II 4 3.5 0.68

    II 6 3.5 0.68 III 38 3 0.45

    III 18 3 0.45 IV 15 5.3 0.9

    IV 20 5.3 0.9 V 21 13 1.55

    V 34 13 1.55 - - - -

    14

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

  • Along the main direction 1-A of road embankments the soil profiles given in Table 1

    indicates homogeneous formations interrupted by some indurated layers or lenses. Herein,

    focus is given on clayey layers of horizon III, in particular the evaluation of their over-

    consolidation ratio (OCR), compression index and estimates of vertical and horizontal

    coefficient of consolidation. Those parameters significantly affect the estimation of primary

    consolidation (or long term) settlement and also its evolution in time.

    3.1. Evaluation of OCR of clayey layers (horizon III)

    From results obtained from oedometer tests carried out on several intact soil specimens it was

    recommended by [3] to consider that clay layers of horizon III are, at least, normally

    consolidated. Such recommendation was checked by analyzing the profiles of CPTu tests in

    layer III which look quite homogenous, but sometimes are interrupted by thin hard layers or

    lenses. The recorded results from CPTu tests are helpful to learn much better about the OCR

    of layers in horizon III. First, the advantage of CPTu test is to record in a direct manner the

    the tip resistance without any disturbance of the in-situ soil. Whilst from oedometer tests the

    results can be seriously affected by the disturbance of specimens during their extraction from

    sampling tubes, transportation and preparation steps before performing the oedometer test

    itself. Second, since the seventies in Sweden, several correlations were proposed for

    estimating the preconsolidation pressure 'p of clays from the tip resistance qc or from the

    corrected tip resistance qt recorded during the cone penetration test. Due to this the correlation

    expressed by Eq (1) and shown in Fig. 1 was agreed because its correlation coefficient is quite

    good as R2 = 0.884 (Bowles, 1982):

    'p = 0.5439 qt0.8635 (1)

    Figure 1. Correlated pre-consolidation pressure vs corrected tip resistance from CPT-u tests

    (Bowles, 1982)

    The evaluation of OCR

    From CPTu test results given in [1] the profiles PZ EX2 et PZ EX6 were compiled from

    which the tip resistance qc was considered as a safe alternative since qc is lower than qt and

    15

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

  • therefore, the estimated pre-consolidation pressure from correlation (1) will not be

    overestimated. Detailed discussion on the method of determination of the OCR of clay layers

    in horizon III is available in [4]. It was agreed that the minimum and safe OCR value is 1.3

    for clay layers encountered between 17 and 28 m depth. This over-consolidation was

    confirmed from identification laboratory tests, in particular by a consistency index of 0.75,

    and by the geological era (10,000 years) of the Raoued area that served as the basin of

    Meliane river.

    Overconsolidation of clay layers from -14 m to -28 m depth is essentially attributed to the

    overlaid formation composed by silt sand horizons having low consistency. For such

    condition the following explanation might prevail.

    Step 1: the deposit of sub clay layers on the prior river bed (e.g. from -30 to -13 m depth for

    instance) the sea level was zero. At this stage the effective stress at elevation -21 equals (21-

    13)m x 17 kN/m3 -21x10 kN/m

    3 = -74 kPa (under-consolidated stage, obviously).

    Step 2: Deposit of alternated sand/clay formation over the sub-clay layer, e.g. from -13 up to

    zero level, the sea level is always located at zero level. At this stage the effective stress at

    elevation -21 becomes: (21-0)x 17 kN/m3 - 21x10 kN/m

    3 = 147 kPa. Hence, the sub clay

    layers, after consolidation over some thousands years, might be over-consolidated

    approximately in a ratio as (147+74)/147 = 1.5 which would confirm the magnitude of

    expected over consolidation.

    For those arguments, from CPTu data available in reports [1] and [2], an over-consolidation

    ratio OCR = 1.3 can be adopted. This value is rather conservative for clay layers located from

    14 m to 28 m depth in view of estimating their long term settlement.

    3.2. Evaluation of vertical and horizontal coefficients of consolidation and compression

    index of clay layers

    Figure 2. Withman and Lambe's (1969) chart

    16

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

  • 4. DESİGN OF EMBANKMENT FOUNDATION ON REINFORCED

    SOİL BY FLOATİNG COLUMNS

    The adopted methodology, as detailed in Bouassida & Carter (2014) and Bouassida (2016),

    relies on two verifications: the bearing capacity and settlement. Implementation of this

    methodology in Columns 1.01 software (Bouassida & Hazzar, 2012) enables the prediction of

    optimized area ratio on the basis of given short term settlement (end of construction). This

    settlement is estimated using the linear elastic behavior by adopting Young modulus of

    column material equals 10 times that of the initial soil after the French recommendation

    revised in (2011). The first design step aims at the estimation of Young modulus of all

    crossed layers from the surface up to 30 m depth where the effect of surcharge load due to

    embankments vanishes and, in addition, a stratum level appears (horizon IV in Table 1).

    4.1 Estimation of modulus of deformation

    From the performed CPTu and SPT tests executed in clay layers and sand layers, respectively

    the Young modulus is deduced for each layer from the following correlations suggested by

    Bowles (1996) and Das (2014):

    clayey formation: E = (3 to6)* qc (2)

    Silt-saturated fine sand E = 300 * (N+6) (3)

    Or:

    E = 320 * (N+15) (4)

    N denotes the SPT number measured from the SPT test.

    From correlations given by Eqs (2), (3) and (4) and considering safe estimations the adopted

    modulus of deformation are the following:

    For clays: E = 4 * Qc (5)

    For sands the correlation given by Eq (3) was agreed. Hence, the adopted modulus of

    deformations are summarized in Tables 2 and 3.

    Table 2. Modulus of deformation of sand layers

    Depth (m) SPT E (kPa)

    1 to 5 N = 8 4200

    5 to 12 N = 15 6300

    Table 3. Modulus of deformation of clay layers.

    Depth (m) CPT E (MPa)

    12 to 23 qc = 1.25 MPa 5

    23 to 27 qc = 1.6 MPa 6.4

    27 to 30 qc = 2.5 MPa 10

    ≥ 30 m qc = 10 MPa 40

    17

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

  • 4.2 Road embankments: geometry and associated networks

    Those embankments have a variable height from 0.5 to 4 m and different cross section with a

    slope 2 on vertical over 3 on horizontal directions. Over their length profile these

    embankments have progressive slopes each 80 m to 100 m distance. At 0.5 m depth below the

    basis of those embankments gravity hydraulic networks will be installed with very low slope

    of 0.2 percent. For such networks the requirement is to not exceed a long term residual

    settlement of 2 cm. The biggest cross section of embankment has by 4 m height, 62 m of

    width base and 52 m at width crest with 80 kPa uniformly distributed load. Due the

    compressibility of clay layers in horizon III and transmitted excess of vertical stress within

    those layers long term settlements are expected so that functioning of the hydraulic gravity

    networks will be affected.

    4.3 Why was the reinforcement by stone columns contemplated?

    It is noted that the verification of bearing capacity for the embankments' foundation is

    warranted so that the 80 kPa surcharge load is admissible. In fact, based on the safe

    determination of undrained cohesion equal to 35 kPa of superficial layer there is no risk in

    regard to the admissible bearing capacity. In turn, the settlement verification requires a

    comprehensive analysis as explained above.

    As a first option, it was judged that the long term settlement of embankments can be

    accelerated, prior to their construction by a preloading associated to vertical drains of length

    extending up to 28 to 30 m. Although this option offers a safe solution to avoid any surprise

    for the functioning of hydraulic networks it will take a long time for the preloading over an

    approximated area of 5000 Acres. Also the installation of prefabricated vertical drains (PVD),

    however already experienced in Tunisia for infrastructure projects, but with length less than

    18 m, presents the risk on inclined installation of the PVD from which the full depth of

    treatment will not be covered also needs to be checked.

    Therefore, the second suitable solution consists in both reducing and accelerating the

    consolidation settlement essentially over the first 14 m depth of sand silt formation. Such

    solution obviously offers the benefit in saving the preloading time. This alternative is feasible

    when floating stone column reinforcement is targeted. Whilst the length of the stone columns

    should be optimized taking into account the over-consolidation of clay layers (horizon III) and

    the decrease of induced excess vertical stress due to the surcharge embankment.

    For the purpose of suitable and easy execution the optimized length of stone columns was

    decided as 14m. Beyond 14 m depth the treatment by stone columns in the clay layer will be

    time consuming but it remains effective.

    4.4 Design using floating stone columns -Settlement reduction - Long term settlement.

    4.4.1 Short term settlement

    Consider a total short term settlement of 16 cm which is quite admissible for 4 m

    embankment height, on the basis of soil layers and column material properties the optimized

    improvement area ratio as determined by the software Columns 1.01 is found by 16%. The

    settlement of reinforced soil layers over 14m depth equals 8.1 cm. Since stone columns

    behave like vertical drains the settlement of reinforced soil will occur at the end of

    embankment construction. It is proposed that stone columns of diameter 1m are installed in

    triangular pattern with an axis to axis spacing equals 2.46 m. Assuming that the consolidation

    18

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

  • of reinforced soil only occurs horizontally the use of Barron's chart leads that 90% of

    consolidation is expected in three months approximately. This duration coincides almost with

    one stage construction of 4m embankment height. The primary consolidation settlement of

    unreinforced layers over 14 m in such duration can be neglected so that the residual settlement

    of unreinforced clay layers corresponds to the residual settlement to be induced under the road

    embankments.

    4.4.2 Estimation of long term settlement

    The oedometer and CPTu methods are both considered for estimating the consolidation

    settlement of unreinforced clay layers. Comparison between the predictions of these methods

    is then discussed.

    Estimation of long term settlement using the oedometer method

    The prediction of long term settlement over 14 m thickness of clay layers by the oedometer

    method is 18.5 cm for a surcharge load of 80 kPa. This prediction is obtained by an Excel

    sheet calculation by subdividing the 14 m in sub-layers of thickness 3 m. Excess of vertical

    stress due to embankment load, vertical effective stress and preconsolidation stresses were

    calculated at mid thickness of each sub layer. The averaged long term settlement per meter of

    embankment height and per meter of compressible layer is sketched in Figure 3.

    Figure 3. Variation of normalized long term settlement per meter of compressible clay later

    and per meter of embankment height.

    Estimation of long term settlement using the CPTu test results.

    The long term settlement can be estimated from the correlation between oedometer modulus

    Eoedand the tip resistance qc:

    Eoed = 5 qc (6)

    19

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

  • Considering each CPT profile (in total there are eight profiles), by adopting the correlation in

    Eq (5) for each 50 mm thickness the oedometer modulus is calculated and the long term

    settlement is predicted. The averaged settlement per one kPa and per meter of clay layer is

    0.185 mm/kPa/m as detailed from the Excel sheet calculation given in Table 4.

    Table 4. Estimation of long term settlement from CPTu data

    It is noted that the estimation of long term settlement from the CPTu data exceeds by 10%

    that estimated from the oedometer method. Hence, this confirms that adopted OCR = 1.3 for

    the compressible clay layers is secured for the prediction of long term settlement. The

    duration of long term settlement, calculated for consolidation ratio = 50%, by assuming one

    drainage path (from the tip of stone columns) of the unreinforced layers over 14 m thickness,

    is about 16 years. Therefore, the variation of primary consolidation settlement evolves slowly.

    Verification of residual differential settlement

    Predicted long term settlement shown in Figure 3 corresponds to uniform settlement induced

    by uniform surcharge load which is not the case of embankment having variable height.

    Along a given section of road embankment of typical length equals 100 m the height is

    variable and so is the induced settlement. Figure 4 clearly shows quite variable absolute

    settlement along the main section 1-A of the PFHR of total length approximating 1,180 m. In

    this figure the variation of differential settlement is also shown. Thus, it is the differential

    settlement: s = si -si-1 between two successive points "i-1" and "i" almost distanced by 100 m within a section of road embankment, rather that the absolute settlement, that will affect the

    functioning of hydraulic networks which will be installed with a quite low slope of 0.2 %.

    Such analysis can be highlighted from Figure 5 that shows the evolution of residual

    differential settlement along the first sub-section (0 to 180 m) of main axis 1-A compared to

    the allowable residual long settlement of "+" or "-" 2 cm.

    20

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

  • Figure 4. Variation of absolute and differential long term settlement along axis 1-A

    Figure 5. Variation of differential long term settlement along the first section of axis 1-A

    From Figure 5 the most unfavorable situation corresponds to the sub-section between points

    0 and 1 where the differential settlement equals 8.1 cm. The admissible differential

    21

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

  • settlement equals 2 cm that corresponds to a vertical degree of consolidation calculated from

    one-dimensional Terzaghi's theory:

    U(Tv) = 2 cm/6.1 cm = 0.32786.

    From the equation of time factor: Tv = cv*t/H2 one can determine from which time the

    differential settlement will exceed the admissible limit of 2 cm, it is: t = 14 years. It is the

    soonest time from which the residual differential settlement might affect the functioning of

    hydraulic gravity networks.

    From Figure 5 three critical sub-sections (e.g. where the residual differential settlement

    exceeds its admissible limit) are expected. For those sub-sections it recommended to proceed

    for a reinforcement with 17 m length of floating stone columns for reducing and accelerating

    the consolidation settlement of clay layers (horizon III). Nevertheless, the more likely,

    expected differential settlements would not affect the functioning of hydraulic gravity

    network because those settlements will only take place with a long passage of time.

    It is noted that all predictions on the basis of suggested design should be validated by

    scheduling a loading test with recorded load-settlement curves.

    4. CONCLUSIONS

    This paper addressed the design of floating stone column foundations for embankments road

    scheduled for the ongoing Tunisian project "Project Financial Harbour of Raoued". The

    geotechnical investigations conducted for this project have been synthesized with special

    focus on the over consolidation of clay layers overlaid by silt sand formation both having 14

    m thickness. In this regard the use of CPTu data revealed more suitable than data recorded

    during oedometer tests. Two ground improvement options were decided for this project: first

    option was a preloading associated with prefabricated vertical drains, and the second

    suggested to install floating stone columns of 14 m length crossing the homogenized silt sand

    formation.

    The study of behavior of road embankments having variable height is tributary of the residual

    differential settlement rather than the absolute consolidation settlement. From this analysis it

    is proposed to focus on the differential consolidation settlement to occur within the

    unreinforced clay layers starting from 14 m depth, below the ground surface, and should

    affect the functioning of the gravity hydraulic networks.

    The suggested design consists in stone columns of 14 m length crossing the sand silt

    formation installed by the vibrocompation method to improve the stiffness of treated silt sand

    layers. In turn, over limited sub-sections of the road embankments it was recommended to

    install stone columns of 17 m in length to fulfill the required residual settlement of 2 cm.

    For the road embankments foundation of the PFHR a technical-economical comparison will

    be carried out to state about the suitable improvement technique to be executed.

    REFERENCES

    [1] Hydrosol-Fondations. Campagne de reconnaissance géotechnique. Phase d'exécution du

    port financier à Raoued.

    [2] [1] Hydrosol-Fondations. Tunis Bay Project (Raoued-Tunis). Geotechnicalreport.

    [3]Terrasol-Tunisie. Rapport géotechnique de Raoued Port financier.

    22

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

  • [4]Africa Engineering (2017). Variante de renforcement par colonnes ballastées:

    Dimensionnement et modalités d'exécution, Mai.

    [5] Bouassida M., Hazzar L. (2008). Comparison between Stone Columns and Vertical

    Geodrains with Preloading Embankment Techniques. Proc. 6th Int. Conf. On Case

    Histories in Geotechnical Engineering. Arlington VA (USA), 11-18 August, Paper

    No. 7.18a.

    [6] Bouassida, M. and Carter, J. P. (2014). “Optimization of Design of Column-reinforced

    Foundations”. Int. J. Geomech., Volume 14, Issue 6 (December 2014),

    04014031-1-10.

    [7] Bouassida M. (2016); Design of Column-Reinforced Foundations. J. Ross Publishing

    (FL, USA), August. 224 pages. ISBN: 978-1-60427-072-3.

    [8]. M. Bouassida, and L. Hazzar (2012). Novel tool for optimised design of reinforced soils

    by columns. Ground Improvement: Proc. ICE, London 165, Issue 1, pp 31 –40.

    [9]. Document français (2011). Recommandations sur la conception, le calcul, l’exécution et

    le contrôle des colonnes ballastées sous bâtiments et sous ouvrage sensible au

    tassement (in French). Comité Français de Mécanique des Sols, Version n°2,

    March 16, 32 pages.

    [10]. Bowles, J. E. (1996). Foundation Analysis and Design, 5th. edition, McGraw-Hill, New

    York.

    [11]. Das M.B. (2014). Principles of Foundation Engineering. Cengage Learning. USA

    [12]. Lambe T.W. and Withman R.V. (1969). Soil mechanics. M.I.T.

    23

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul

    https://www.goodreads.com/book/show/204216.Principles_of_Foundation_Engineering

  • 24

    7. Geoteknik Sempozyumu 22-23-24 Kasım 2017, İstanbul