forest hill avenue widening f&r project no. 60k-0679r1...road widening project consists of...
TRANSCRIPT
Report of Subsurface Exploration, Laboratory Testing,
and Geotechnical Engineering Evaluation Forest Hill Avenue Widening
Richmond, Virginia
F&R Project No. 60K-0679r1
Prepared for:
Stantec Consulting Services, Inc. 2810 North Parham Road, Suite 242
Richmond, Virginia 23294
Attention: David L. Bowers, P.E.
Prepared by:
Froehling & Robertson, Inc. 3015 Dumbarton Road
Richmond, Virginia 23228
February 2010
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 i Richmond, Virginia February 12, 2010
TABLE OF CONTENTS
SECTION PAGE 1.0 INTRODUCTION ........................................................................................................... 1
1.1 PROJECT INFORMATION .................................................................................................. 1
1.2 SCOPE OF SERVICES ....................................................................................................... 1
2.0 SUBSURFACE EXPLORATION PROCEDURES................................................................... 2
3.0 SITE AND SUBSURFACE CONDITIONS ........................................................................... 4
3.1 SITE DESCRIPTION ......................................................................................................... 4
3.2 REGIONAL GEOLOGY ...................................................................................................... 5
3.3 SUBSURFACE CONDITIONS ............................................................................................... 5
3.3.1 General ............................................................................................................. 5
3.3.2 Surficial Soils ..................................................................................................... 6
3.3.3 Pavement Sections ............................................................................................ 6
3.3.4 Fill/Possible Fill Soils ......................................................................................... 7
3.3.5 Residual Soils .................................................................................................... 8
3.3.6 Subsurface Water.............................................................................................. 8
4.0 SOIL CHARACTERISTICS ................................................................................................ 9
4.1 LABORATORY TESTING ................................................................................................... 9
5.0 DESIGN RECOMMENDATIONS ................................................................................... 11
5.1 GENERAL .................................................................................................................. 11
5.2 PAVEMENTS .............................................................................................................. 11
5.2.1 New Pavements .............................................................................................. 12
5.2.2 Pavement Overlays ......................................................................................... 12
5.3 ASPHALT REINFORCEMENTS ........................................................................................... 13
5.4 CONCRETE SIDEWALKS ................................................................................................. 14
5.5 RETAINING WALLS ...................................................................................................... 14
5.5.1 Foundations .................................................................................................... 14
5.5.2 Settlement ...................................................................................................... 15
5.5.3 Lateral Earth Pressures .................................................................................... 15
5.6 BMP ...................................................................................................................... 17
5.7 DRAINAGE ................................................................................................................ 17
6.0 CONSTRUCTION RECOMMENDATIONS ...................................................................... 19
6.1 SITE PREPARATION ...................................................................................................... 19
6.2 PAVEMENT CONSTRUCTION ........................................................................................... 20
6.3 CONSTRUCTION MATERIALS TESTING (CMT) CONSIDERATIONS .............................................. 21
6.4 CONTROLLED STRUCTURAL FILL ...................................................................................... 21
6.5 CONSTRUCTION DRAINAGE............................................................................................ 22
7.0 CONTINUATION OF SERVICES .................................................................................... 22
8.0 LIMITATIONS ............................................................................................................. 23
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 ii Richmond, Virginia February 12, 2010
APPENDICES
APPENDIX A
ASFE Information about Geotechnical Reports
Site Vicinity Map (Drawing No. 1)
APPENDIX B
Boring Location Plan (Drawing No. 2, Drawing No. 3, and Drawing No. 4)
Soil Classification Chart (1 page)
Key to Boring Log Soil Classification (1 page)
B – Roadway Boring Logs, B-1 through B-18 (18 pages)
R – Retaining Wall Boring Logs, R-1 through R-16 (16 pages)
BMP – Storm Water Detention Pond Boring Logs, BMP-1 and BMP-2 (2 pages)
C – Pavement Coring Logs, C-1 through C-9, B-8, B-13, B-14, B-16, & B-17 (3 pages)
APPENDIX C
Moisture-Density Relationship Curves (5 pages)
California Bearing Ratio Test (5 pages)
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 1 Richmond, Virginia February 12, 2010
1.0 INTRODUCTION
1.1 Project Information
Project information was provided by the Donald D. Logan, P.E. and Mr. Archie J. Drudge of
Stantec Consulting Services (Stantec). The proposed project consists of improvements to Forest
Hill Avenue consisting primarily of road widening with the additions of sidewalks, bicycle lanes,
and retaining walls on both sides of the road. This phase of the project is expected to extend
from Hathaway Road to the Powhite Parkway, an approximate length of one mile. The
approximate project location is shown on the attached Site Vicinity Map (Drawing No. 1,
Appendix A).
We understand that portions of the existing road will be re-graded, demolished, and/or milled
and re-surfaced with new asphalt. Due to proposed grading, some retaining walls are proposed
intermittently along the north and south sides of the widened road. The land acquired for the
road widening project consists of road-shoulders, private property including lawns and
driveways, embankments, ditches, and drainage channels. In this regard, subgrade preparation
for the widening of Forest Hill Avenue will vary from simple surficial soils stripping and
regrading to over-excavation and/or demolition of driveways and drainage systems to cutting
and filling of up to 10 feet of a vegetated and sometimes wooded shoulder area with Controlled
Structural Fill.
At the time of this report, preliminary traffic loading information was provided as
approximately 45,000 vehicles per day (VPD). For design purposes, we assumed a maximum of
5% of this number will be comprised of Heavy Commercial Vehicles (HCV). Structural loading
for the retaining walls was not provided to us. For our analysis, we assumed that the retaining
walls will not exert more than 1,500 psf on the subgrades.
1.2 Scope of Services
The purposes of our involvement on this project were as follows: 1) provide general
descriptions of the subsurface soil conditions encountered at the boring locations, 2) provide
various feasible pavement design recommendations, 3) provide retaining wall design
recommendations, and 4) comment on geotechnical aspects of the proposed development. To
accomplish the above objectives, we undertook the following scope of services:
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 2 Richmond, Virginia February 12, 2010
1) Visited the site to observe existing surface conditions and features;
2) Coordinated with Miss Utility services for utility clearance;
3) Reviewed readily available geologic and subsurface information relative to the
project site;
4) Executed a geotechnical subsurface exploration program consisting of thirty-six (36)
Standard Penetration Test (SPT) borings drilled to depths ranging from 4.5 to 20 feet
below existing site grades;
5) Performed twelve (12) pavement cores to ascertain existing pavement section
thicknesses in select locations;
6) Performed laboratory testing on select recovered soil samples to ascertain
characteristic soil properties;
7) Prepared this written report summarizing our geotechnical engineering work on the
project, providing descriptions of the subsurface conditions encountered, providing
pavement and foundation design criteria, and discussing geotechnical related
aspects of the proposed construction.
Our geotechnical scope of services did not include a survey of boring locations and elevations,
quantity estimates, preparation of plans or specifications, or the identification and evaluation
of wetland.
2.0 SUBSURFACE EXPLORATION PROCEDURES
Our geotechnical subsurface exploration program consisted of thirty-six (36) soil test borings;
eighteen were bored to a minimum depth of 4.5 feet for pavement design considerations. The
remaining eighteen borings were bored to a termination depth of 20 feet (except for two which
were terminated early due to auger refusal) in areas intended for retaining walls and for a
storm water detention pond along the road. In addition to the soil borings, we performed
twelve (12) pavement cores to ascertain existing pavement thicknesses.
The exploration was performed between December 4, 2009 and January 18, 2010, at the
approximate locations shown on the attached Boring Location Plans (Drawing No. 2, Drawing
No. 3, and Drawing No. 4, Appendix B). F&R personnel marked the boring locations in the field
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 3 Richmond, Virginia February 12, 2010
by approximating distances from existing features indicated on the provided site plan. No claim
is made as to the accuracy of the information contained in the provided documents. In
consideration of the methods used in their determination, the boring locations shown on the
attached Boring Location Plans should be considered approximate.
The test borings were performed in accordance with generally accepted practice using a CME-
55 rotary drill rig mounted on a tracked all-terrain vehicle equipped with an automatic hammer.
Hollow-stem augers were advanced to pre-selected depths, the center plug was removed, and
representative soil samples were recovered with a standard split-spoon sampler (1 3/8 in. ID, 2
in. OD) in general accordance with ASTM D 1586, the Standard Penetration Test. The split-
spoon sampler was driven into the soil by freely dropping a weight of 140 pounds from a height
of 30 inches. The number of blows required to drive the split-spoon sampler three or four
consecutive 6-inch increments was recorded, and the blows of the second and third increments
were summed to obtain the Standard Penetration Resistance (N-value). The N-value provides a
general indication of in-situ soil conditions and has been correlated with certain engineering
properties of soils.
The test borings were advanced through the asphalt or soil overburden to depths ranging from
4.5 to 20 feet below the existing site grades. Subsurface water level readings were taken in
each of the test borings during and immediately upon completion of the drilling process. Upon
completion of drilling, the boreholes were backfilled with auger cuttings (soil) and if the boring
was performed in an existing paved area, patched with asphaltic concrete. Periodic observation
and maintenance of the boreholes should be performed to monitor for subsidence at the
ground surface, as the borehole backfill could settle over time.
Representative soil samples recovered in the field were placed in glass jars and transported to
our laboratory for classification and further testing. A member of our geotechnical staff visually
classified each split-spoon soil sample on the basis of texture and plasticity in general
accordance with the Unified Soil Classification System (USCS) (ASTM D2487) and/or the Visual-
Manual Procedure (ASTM D 2488). The group symbol for each soil type, based on the USCS, is
indicated in the parentheses following the soil description on the boring logs. The geotechnical
engineer grouped the various soil types into zones noted on the boring log. The stratification
lines designating the interfaces between earth materials on the boring log are approximate; in
situ, the transitions may be gradual. Copies of our boring logs (soil profiles) and classification
procedures are provided in Appendix B.
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 4 Richmond, Virginia February 12, 2010
Boring annotations prefaced with the letter “B” indicate the boring was performed for the
roadway (i.e. B-1). The letter “R” indicates the boring was performed for the retaining walls
(i.e. R-1), BMP indicates the boring was performed for the storm water detention pond (i.e.
BMP-1), and pavement cores are prefaced with the letter “C” (i.e. C-1).
Split-spoon soil samples recovered on this project will be stored at F&R’s office for a period of
sixty days. After sixty days, the samples will be discarded unless prior notification is provided to
us in writing.
3.0 SITE AND SUBSURFACE CONDITIONS
3.1 Site Description
The improvements to Forest Hill Avenue are projected between the cross street of Hathaway
Road and the Powhite Parkway overpass. Forest Hill Avenue passes from a commercial zone at
the western edge of the proposed widening, through a residential area with several tributary side
streets, and to the exit from Powhite Parkway. The Willow Oaks Country Club is located on the
north side of the east end of the proposed widening project. The surrounding topography is
generally flat with gradual elevation changes up to approximately 45 feet. The majority of this
elevation change occurs in a downward slope between the country club to the Powhite Parkway
overpass.
Overhead power lines are prevalent on the north side of Forest Hill Avenue with smaller lines
supplying power to individual homes on both the north and south sides. The overhead power
lines cross to the south side of the road near 6528 Forest Hill Avenue and continue from this site
into the commercial zone. The presence of many underground utilities is evident by utility
markings along/across Forest Hill Avenue. Also, there were a few drop inlets noted along the
south side of the road. A concrete sidewalk stretched along the north side of the western portion
of Forest Hill Avenue. We did not observe rock outcroppings, erosion, or evidence of shrink-swell
soils and most of the land on either side of Forest Hill Avenue was either a maintained lawn or a
thinly treed forest.
Current pavement conditions were generally good with isolated longitudinal cracks along the road
length. There were a few small areas of pavement that had been removed and patched likely due
to utility work in those areas. Reflective cracking was also observed intermittently along the road’s
length. Rutting and pavement failure was not observed within the proposed project site.
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 5 Richmond, Virginia February 12, 2010
3.2 Regional Geology
Available geologic references report that the project site lies within the very eastern edge of
the Piedmont Physiographic Province of Virginia. The Piedmont Province is the largest
physiographic province in Virginia. It is bounded on the east by the Coastal Plain Province and
on the west by the mountains of the Blue Ridge Province. The Piedmont Province is
characterized by gently rolling topography, deeply weathered bedrock, and a relative scarcity of
solid rock outcrop. Rocks are strongly weathered in the Piedmont's humid climate, and
bedrock is generally buried under a thick (5-65 feet) blanket of saprolite. Soils are residual in
nature.
Based on the Geologic Map of Virginia (1993), the project site is underlain by the Petersburg
Granite Formation. This formation consists of light- to dark-gray to pink, fine- to coarse-
grained, equigranular to porphyritic, foliated to nonfoliated, and ranges from granite to
granodiorite in composition; multiple intrusive phases are present. The granite contains
xenoliths of biotite gneiss and amphibolite. Its mineralogy includes quartz + sodic plagioclase +
potassium feldspar + biotite ± hornblende and accessory minerals include ilmenite, magnetite,
pyrite, zircon, apatite, titanite, muscovite, and fluorite (Goodwin, 1970; Daniels and Onuschak,
1974; Wright and others, 1975). Current mapping restricts the Petersburg Granite Formation to
a contiguous unit that crops out in the Cities of Richmond and Petersburg.
3.3 Subsurface Conditions
3.3.1 General
The subsurface conditions discussed in the following paragraphs and those shown on the
attached boring logs represent an estimate of the subsurface conditions based on
interpretation of the boring data using normally accepted geotechnical engineering judgments.
The transitions between different soil strata are usually less distinct than those shown on the
boring logs. Sometimes the relatively small sample obtained in the field is insufficient to
definitively describe the origin of the subsurface material. In these cases, we qualify our origin
descriptions with “possible” before the word describing the material’s origin (i.e. possible fill,
possible residuum, etc.). Although individual test borings are representative of the subsurface
conditions at the boring locations on the dates shown, they are not necessarily indicative of
subsurface conditions at other locations or at other times. Data from the specific test borings
are shown on the attached boring logs in Appendix B.
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 6 Richmond, Virginia February 12, 2010
3.3.2 Surficial Soils
Surficial Soil was encountered in several borings as noted on the individual boring logs and
ranged in depths from 0.1 to 0.5 feet below the existing ground surface. Surficial Soil is
typically a dark-colored soil material containing roots, fibrous matter, and/or other organic
components, and is generally unsuitable for engineering purposes. F&R has not performed any
laboratory testing to determine the organic content or other horticultural properties of the
observed Surficial Soil materials. Therefore, the term Surficial Soil is not intended to indicate a
suitability for landscaping and/or other purposes. The Surficial Soil depths provided in this
report are based on driller observations and should be considered approximate. We note that
the transition from Surficial Soil to underlying materials may be gradual, and therefore the
observation and measurement of Surficial Soil depths is subjective. Actual Surficial Soil depths
should be expected to vary across the site, especially in peripheral areas where trees and root
balls systems are located.
3.3.3 Pavement Sections
Asphalt and underlying aggregate was encountered in several of our borings. We performed
nine cores in locations with existing asphalt to obtain existing pavement thicknesses. The
asphalt pavement thickness ranged from 5.0 to 13.0 inches. Aggregate was reported under all
asphalt pavements and ranged in depth from 5.5 to 12.0 inches. Data from the pavement cores
are listed in the table below:
Core Location Thickness of Asphalt
(Inches) Thickness of Aggregate
(Inches) Total Pavement
Thickness
C – 1 6.0 9.0 15.0
C – 2 5.3 5.7 11.0
C – 3 8.5 5.5 14.0
C – 4 8.0 7.0 15.0
C – 5 6.0 8.0 14.0
C – 6 6.5 9.5 16.0
B – 8 5.0 10.0 15.0
B – 13 6.0 7.0 13.0
B – 14 6.5 7.5 14.0
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 7 Richmond, Virginia February 12, 2010
In addition to the above cores, six cores were examined for pavement layer information. In
general, the cores showed the pavement to be good condition with the exception of C-8 and B-
18. The middle of these two cores was broken into several pieces upon removed from the core
hole. The individual cores and their layers are listed in the table below:
Core Location
Thickness of Surface Layer
(Inches)
Thickness of Intermediate Layer (Inches)
Thickness of Base Layer
(Inches)
Thickness of Aggregate Layer
(Inches)
Total Pavement Thickness
C – 7 1.5 3.5 3.0 11.0 19.0
C – 8 1.5 Disintegrated 3.0 7.5 12.5
C – 9 2.0 11.0
Intermediate and Base Layers indistinguishable
12.0 25.0
B – 16 1.25 3.0 3.0 9.0 16.25
B – 17 1.5 2.5 3.0 10.0 17.0
B – 18 1.5 Disintegrated 3.0 12.0 19.0
3.3.4 Fill/Possible Fill Soils
Fill/Possible Fill may be any material that has been transported and deposited by man.
Materials described as fill/possible fill were encountered in all but two roadway borings and in
all but seven retaining wall borings. The fill materials encountered in the existing roadway
ranged in depths from about 1.0 to 5.0+ (the termination depth) feet below existing grades. In
boring B-5, fill material was encountered to a depth of 7.5 feet. The fill material encountered in
the proposed retaining wall areas ranged in depth from about 1.5 to 10.0 feet.
Fill in the proposed storm water detention pond was encountered to depths ranging from 8.0
to 14.2 feet below existing site grades. This coincides with information indicating this part of
the site was previously used as a detention pond and has since been filled. We understand
there could also be large boulders buried around these locations due to past activities. Based
on the non-uniformity of the N-values obtained during our exploration, the soils sampled in the
BMP borings appear to have been placed in an uncontrolled manner.
Sampled fill/possible fill materials were generally described as Sandy Lean and Fat CLAY (CL and
CH), Sandy SILT (ML), Clayey SAND (SC), and Silty SAND (SM). For soils samples obtained in the
proposed retaining wall and roadway areas, standard penetration resistances (N-values) within
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 8 Richmond, Virginia February 12, 2010
the sampled coarse-grained fill materials (SANDs) ranged from 3 to 43 blows per foot (bpf)
indicating these soils are very loose to dense in relative density. The N-values obtained within
the sampled fine-grained fill material (CLAYs and SILTs) ranged from 0 to 15 bpf indicating these
soils are very soft to stiff in consistency. In general, the very soft to soft soils were encountered
in borings B-5 and R-1.
3.3.5 Residual Soils
Natural residual soils were encountered below the Surficial Soils, Asphalt, and Fill/Possible Fill
material in most borings and extended to the borings’ termination depths. Sampled natural
residual soils consisted of Sandy Lean and Fat CLAY (CL and CH), Sandy SILT (ML), Elastic SILT
(MH), Clayey SAND (SC), and Silty SAND (SM). The N-values in the sample natural residual fine-
grained soils (CLAYs and SILTs) ranged from 3 to 19 bpf indicating the fine-grained soils are soft
to very stiff in consistency. Standard penetration resistances in the sampled natural residual
coarse-grained soils (SANDs) ranged from 4 to 100+ bpf. These N-values indicate the granular
soils (SANDs) are very loose to very dense in relative density. In a few of the retaining wall
borings and both the storm water detention pond borings, weathered rock was encountered at
the boring’s termination depth.
3.3.6 Subsurface Water
The test borings were monitored during and upon completion of drilling operations to obtain
short-term subsurface water information. Subsurface water was identified in seven of the
thirty-six borings. The subsurface water data, obtained during our subsurface exploration, have
been summarized in the following table. The borings from which subsurface water was neither
encountered nor observed have been omitted from the table for simplicity. Specific subsurface
water data may be found on individual boring logs.
Boring Location
Depth of Boring (Feet)
Subsurface Water Depth While Drilling (Feet)
Subsurface Water Depth After
Drilling (Feet)
Cave-in Depth at End of Day (Feet)
B – 5 10.0 6.0 6.0 7.5
R – 2 20.0 18.0 Not Observed 17.5
R – 3 20.0 14.0 14.9 16.0
R – 4 20.0 18.5 Not Observed 19.0
R – 9 20.0 16.0 13.0 18.0
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 9 Richmond, Virginia February 12, 2010
Boring Location
Depth of Boring (Feet)
Subsurface Water Depth While Drilling (Feet)
Subsurface Water Depth After
Drilling (Feet)
Cave-in Depth at End of Day (Feet)
R – 10 20.0 Not Encountered 15.0 15.5
R – 15 20.0 18.5 18.0 19.0
It should be noted that the location of the subsurface water levels could vary by several feet
because of seasonal fluctuations in precipitation, evaporation, surface water runoff, local
topography, and other factors not immediately apparent at the time of this exploration.
Normally, the highest subsurface water levels occur in the late winter and spring and lowest
levels occur in the late summer and fall. It should be noted that borehole cave-in often
indicates wet and unstable conditions.
4.0 SOIL CHARACTERISTICS
4.1 Laboratory Testing
Representative soil samples were subjected to Natural Water Content, #200 Sieve Wash, and
Atterberg Limits testing to substantiate the visual classifications and assist with the estimation
of the soils’ pertinent engineering properties. The results of our laboratory testing are included
in the following tables:
Boring No.
Sample Depth (Feet)
Liquid Limit/ Plasticity Index
Natural Water Content (%)
#200 Sieve Wash
USCS Class.
B – 1 2.0 – 3.5 27/19 17.4 50.6 CL
B – 2 1.0 – 5.0 39/20 18.1 45.5 SC
B – 5 3.5 – 5.0 38/20 18.6 43.6 SC
B – 6 3.5 – 5.0 NA/NA 30.5 NA CL – CH
B – 7 1.5 – 3.0 NA/NA 12.3 NA SM
B – 8 1.0 – 5.0 49/27 19.0 43.0 SC
B – 10 1.5 – 3.0 31/15 11.9 46.0 SC
B – 11 1.0 – 5.0 43/17 20.2 34.6 SC
B – 12 1.5 – 3.0 NA/NA 23.7 NA SC
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 10 Richmond, Virginia February 12, 2010
Boring No.
Sample Depth (Feet)
Liquid Limit/ Plasticity Index
Natural Water Content (%)
#200 Sieve Wash
USCS Class.
B – 13 0.0 – 1.5 35/13 9.8 25.7 SC
B – 15 1.0 – 5.0 25/9 13.4 25.5 SC
R – 1 1.5 – 3.0 46/17 22.4 42.1 SM
R – 2 8.5 – 10.0 NA/NA 20.5 NA SM
R – 5 6.0 – 7.5 NA/NA 20.3 NA SM
R – 5 3.5 – 5.0 46/15 23.1 40.0 SM
R – 9 6.0 – 7.5 NA/NA 20.7 NA SM
R – 10 3.5 – 5.0 NA/NA 27.8 NA CL
R – 11 6.0 – 7.5 NA/NA 20.3 NA SM
R – 13 1.5 – 3.0 52/21 27.2 50.0 MH
R – 15 6.0 – 7.5 NA/NA 41.8 NA CH
R – 16 3.5 – 5.0 NA/NA 4.9 NA SM
Classification procedures are further explained in Appendix B.
In addition to the above testing, moisture-density relationship testing using the Standard
Proctor method (AASHTO T 99) and California Bearing Ratio (CBR) testing was performed on
five (5) bulk samples for use in pavement design recommendations. The results of these
laboratory tests are included in the following table:
Boring No.
Sample Depth (Feet)
LL/PI Passing
#200 Sieve, %
Maximum Dry Density/Optimum
Moisture
CBR @ 98% Compaction
USCS Class.
Bulk 1 0.5 – 2.0 27/7 27.4 120.5/10.2 16.7 SC
Bulk 2 0.5 – 2.0 36/14 38.6 112.3/13.4 9.1 SC
Bulk 3 0.5 – 2.0 38/17 58.3 109.7/15.1 9.0 CL
Bulk 4 0.5 – 2.0 31/13 43.8 113.6/13.0 12.2 SC
Bulk 5 0.5 – 2.0 31/12 45.1 114.9/12.5 12.9 SC
The charts and graphs documenting our tests are included in Appendix C.
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 11 Richmond, Virginia February 12, 2010
5.0 DESIGN RECOMMENDATIONS
5.1 General
The following evaluations and recommendations are based on our observations at the site,
interpretation of the field data obtained during this exploration, and our experience with
similar subsurface conditions and projects. Soil penetration and laboratory testing data have
been used to calculate recommended pavement sections and assist with the estimation of
favorable engineering characteristics of the soil. Subsurface conditions in unexplored locations
may vary from those encountered. If the proposed road, retaining walls, and/or sidewalks
change locations or if vehicle and/or structural loading is different from that stated in Section
1.1, we request that we be advised so that we may re-evaluate our recommendations.
Determination of an appropriate pavement design and foundation system is dependent on the
proposed loads, soil conditions and characteristics, and construction constraints such as
proximity to other structures, pavements, etc. The subsurface exploration aids the
geotechnical engineer in determining the soil stratum appropriate for the design needs or the
determining the appropriate measures needed to facilitate a suitable working surface. In
addition, since the method of construction greatly affects the soils intended for structural
support, consideration must be given to the implementation of suitable methods of site
preparation, fill compaction, and other aspects of construction.
In general, the existing fill/possible fill materials may remain in place provided they perform
satisfactorily under proofrolling as described in Section 6.1.
5.2 Pavements
The thickness of the recommended pavement sections is directly related to the service life, the
initial cost of placement, the preparation of the soil subgrade, and the method by which the
granular base and the pavements are placed. The following pavement sections are designed and
evaluated using the AASHTO Guide for Design of Pavement Structures 1993 with the 2009 VDOT’s
“Guidelines for Use of the 1993 AASHTO Pavement Design Procedure” for the design and analysis
of pavement structures based on a performance period of 20 years and a Design CBR (DCBR) value
of 8.0 based on results from our laboratory testing. The DCBR value is calculated by taking 2/3 of
the average CBR value. For our design purposes, we used the maximum assumed vehicle count as
stated in Section 1.1 of this report. Traffic volumes are not expected to exceed 45,000 VPD with
5% of that traffic being heavy commercial vehicles. We understand that there is an approximate
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 12 Richmond, Virginia February 12, 2010
50% directional split. Accounting for this, we have designed our pavement sections for the
eastbound and westbound lanes using 90% of 23,000 VPD (due to two lanes) in each direction. If
the traffic loads differ from the numbers used for our design, F&R should be notified so that we
can adjust our pavement design recommendations as necessary.
5.2.1 New Pavements
Before placement, the subgrades intended to support new pavements should be prepared in
accordance with Section 6.1 of this report. Based on the boring data, we anticipate that the upper
4 to 6 feet of soft soils will need to be removed in the proposed pavement areas in the vicinity of
boring B-5.
The following flexible pavement section is recommended in travel and turn lanes.
Flexible Pavement – Standard Duty
Layer VDOT Specification Recommended Minimum
Thickness (Inches)
Surface Course Asphalt Concrete (SM-9.5) 1.5
Intermediate Course Asphalt Concrete (IM-19.0) 2.0
Base Course Asphalt Concrete (BM-25.0) 4.0
Sub-Base Untreated Dense-graded
Aggregate Material No. 21B 10.0
We recommend that a drainage layer be used under all new pavement areas in accordance
with the drainage guidelines in Section 5.7. The drainage layer should consist of a minimum of
6 inches of free draining VDOT No. 57 Stone. For hydraulic continuity, wherever possible the
bottom of the Aggregate Base Material (ABM) layer, 21 B, of any widened lanes should match
or extend deeper than the bottom of the existing ABM layer. This will prevent the creation of a
“pool effect” or entrapment of water within the existing ABM layer. If water is trapped
beneath the pavement, the ensuing weakening of the subgrades may cause premature cracking
or failure in the new pavements.
5.2.2 Pavement Overlays
If the existing asphalt pavement sections are to be left in place and an overlay is to be used in
these areas, we recommend milling a maximum of 2 inches of existing pavement followed by
overlaying with a minimum of 2.0 inches of SM-19.0 and 1.5 inches of new SM-9.5. Deeper cuts
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 13 Richmond, Virginia February 12, 2010
may be required depending on the condition of the existing asphalt pavement and final design
grades. It is our opinion that any existing cracks will probably reflect through an overlay within
a 1-year of the placement of new pavement. We also believe that the existing pavements will
likely crack away from the new pavements in visible joint cracks within the 1-year time frame.
5.3 Asphalt Reinforcements
There are several pavement enhancing products (i.e. HaTelit) available that can prolong the life
of and reduce crack transfers of new pavement sections or of pavement overlays. According to
Greg Kiggins with Huesker Inc., HaTelit, their pavement reinforcement, can also reduce new
pavement sections by approximately 1.5 inches. If HaTelit is used in the pavement design,
calculations show the following section can be used.
Alternate Flexible Pavement – Standard Duty
Layer VDOT Specification Recommended Minimum
Thickness (Inches)
Surface Course Asphalt Concrete (SM-9.5) 2.0
HaTelit or equivalent
Base Course Asphalt Concrete (BM-25.0) 4.0
Sub-Base Untreated Dense-graded
Aggregate Material No. 21B 10.0
If existing pavements are to be milled and an overlay is used in concurrence with a geotextile,
the following section can be used.
Overlay Over Existing Flexible Pavement – Standard Duty
Layer VDOT Specification Recommended Minimum
Thickness (Inches)
Surface Course Asphalt Concrete (SM-9.5) 2.0
HaTelit or equivalent
Existing Pavement Section after Milling a maximum of 2.0 inches
In addition to reducing the design pavement thickness, products such as HaTelit are designed to
reduce longitudinal cracking between old and new pavement sections, reduce reflective
cracking, reduce the potential for rutting, extend maintenance intervals, simple to install, etc.
We recommend that the client explore the options available and consider incorporating such
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 14 Richmond, Virginia February 12, 2010
products into new pavement sections and any overlays. Not all products perform equally and
appropriate calculations should be made for individual products. At a minimum, prior to
placing an overlay, we recommend implementing a surface treatment (chip seal) in order to
reduce the reflective cracking potential.
5.4 Concrete Sidewalks
A properly constructed slab-on-grade sidewalk is expected to perform adequately on approved
existing fill materials or natural soils. The design should incorporate a minimum four-inch-
thickness of positively drained, free-draining stone.
If possible, limit utility trenches underneath sidewalks. Where unavoidable, utility trench
backfill beneath sidewalks should be compacted to a minimum of 95 percent of the maximum
dry density as determined by ASTM D 698 (Standard Proctor), or equivalent.
Proper jointing of the sidewalks is essential to minimize cracking. For sidewalks, joint spacing
loosely depends on sidewalk geometry and aesthetics as well as guidance by appropriate ACI
design criteria.
Rigid – Sidewalks
Layer VDOT Specification Recommended Minimum
Thickness (Inches)
Concrete 4,000 psi 28-day compressive
strength air-entrained concrete 4
Base Untreated Dense-graded
Aggregate Material No. 21B 4
5.5 Retaining Walls
5.5.1 Foundations
Based on the results of our exploration, we recommend that the retaining walls be supported
on continuous strip footings. Footings should be founded on suitable undisturbed natural soils,
approved existing fills, or on compacted structural fill (Engineered Fill). Existing soft soils
encountered (specifically those identified in boring R-1) are generally considered not suitable
for support of retaining wall foundations and should be removed from all proposed footing
locations.
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 15 Richmond, Virginia February 12, 2010
The footings may be designed for a net allowable bearing pressure of 2,000 psf. A minimum
footing width of 24 inches should be maintained for continuous (wall type) strip footings with a
minimum embedment depth of 30 inches below final grades for shrink-swell and bearing
capacity considerations.
During construction of the retaining walls, an experienced geotechnical engineer or his/her
representative should be on site to confirm that the in-situ bearing capacity at the bottom of
each footing excavation is adequate for the design loads recommended in this report.
Over-excavation of footing areas may be required to remove unsuitable material that may
underlie the proposed retaining walls (such as those encountered in boring R-1). Any such
buried utility services must be removed from the footprint of the retaining walls, unless proper
utility abandonment is feasible (i.e. cleaning out utility pipe and backfilling with concrete,
flowable fill, or stone).
5.5.2 Settlement
Based on the boring data and assumed structural information, we estimate that foundation
settlements will be less than 1 inch with differential settlement of up to one-half the estimated
total settlement. The magnitude of differential settlements will be influenced by the variation
in excavation requirements across the along the retaining walls’ footprints, the distribution of
loads, and the variability of underlying soils.
Our settlement analysis was performed on the basis of assumed structural loading and
excavation requirements discussed in the project information section of this report. Actual
settlements experienced by the structure and the time required for these soils to settle will be
influenced by undetected variations in subsurface conditions, final grading plans, and the
quality of fill placement and foundation construction.
5.5.3 Lateral Earth Pressures
The following information is provided to aid in analysis of soil loads on the below-
grade/retaining walls constructed along the road widening. Earth pressures on walls below
grade are influenced by the structural design of the walls, conditions of wall restraint, methods
of construction and/or compaction, and the strength of the materials being restrained. The
most common condition assumed for earth retaining wall design is the active condition. Active
conditions apply to relatively flexible earth retention structures, such as freestanding walls,
where some movement and rotation may occur to mobilize soil shear strength.
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 16 Richmond, Virginia February 12, 2010
Based on our experience with similar soils and conditions, we recommend the following lateral
earth pressure coefficients and equivalent fluid pressure (equivalent fluid unit weight)
parameters for design of retaining or below-grade walls:
DESIGN PARAMETERS TYPICAL ON-SITE GRANULAR SOILS
VDOT NO. 57 STONE
Moist unit weight of backfill 115 pcf 105 pcf
Angle of Internal Friction (ø) 28o 36o
Equivalent Fluid Unit Weight (pcf), Active 40 30
Equivalent Fluid Unit Weight (pcf), At Rest 60 45
Coefficient of Earth Pressure at Rest (Ko) 0.53 0.41
Coefficient of Passive Earth Pressure (Kp) 2.01 3.01
Coefficient of Active Earth Pressure (Ka) 0.36 0.26
Coefficient of Friction [Concrete on Soil]() 0.30 0.50 ¹The given coefficient of Passive Earth Pressure (Kp) is lower than the theoretical values. This is done since the movement of the wall, necessary to develop the full extent of Kp, is excessive. The on-site parameters are considered typical for most on site borrow soils (typically Clayey SAND), which would be encountered in excavations and/or cut areas.
To reduce lateral earth pressure, drainage of the backfill behind the walls must be provided.
This drainage system may consist of drain lines located around the perimeter of the wall
foundations that discharge to a suitable outlet. These drain lines should be surrounded by a
minimum of 6 inches of free-draining granular filter or by No. 57 Stone wrapped in filter fabric.
The space between the back face of the walls and the excavation should be backfilled with an
18-inch-thick, free draining granular fill. Suitable man-made drainage materials may be used in
lieu of the granular backfill adjacent to the below grade walls. Examples of suitable materials
include Enka Mat, Mira Drain, or Geotec Drains, or equivalent. The material should be placed in
accordance with manufacturer’s recommendations and hydraulically connected to the
foundation drainage system, which in turn should be properly drained. Where exposed to
weather, the top 2 feet of backfill should consist of a clayey material to minimize water
infiltration into the granular material and thus reduce the excess water to be handled by the
drainage system. The ground surface adjacent to the below-grade walls should be kept
properly graded to prevent ponding of water adjacent to the below-grade walls.
Heavy equipment should not operate within 5 feet of below-grade walls to prevent lateral
pressures in excess of those cited. If other surcharge loads are located a short distance outside
below-grade walls they may also exert appreciable additional lateral pressures. Surcharge
loads should be evaluated using the appropriate active coefficients provided above. The effect
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 17 Richmond, Virginia February 12, 2010
of surcharge loads should be added to the recommended earth pressures to determine total
lateral stresses.
5.6 BMP
Based on information provided by the client and the soil samples obtained during our
exploration, we believe the proposed BMP site is currently situated on an old fill site. BMP
construction may be hindered by the presence of boulders or other uncontrolled debris. Our
borings showed approximately 8.0 to 14.2 feet of fill across the site. Beneath the fill were
residual soils and weathered rock. We recommend that all BMPs be designed in accordance
with state and local design regulations.
5.7 Drainage
An important consideration with the design and construction of pavements and foundations is
surface and subsurface drainage. Where standing water develops, softening of the subgrade and
other problems related to the deterioration of the pavement or retaining wall settlements or
failures can be expected. Furthermore, good drainage should minimize the possibility of the
subgrade materials becoming saturated over a long time. Based upon the results of the soil test
borings, we do not expect the subsurface water levels to affect the performance of pavements,
sidewalks, or retaining walls. The use of underdrains or a drainage layer along the edges of the
pavement, beneath sidewalks, and behind retaining walls, and/or the use of soils stabilization
techniques, such as those described above, will assist in decreasing the deteriorating effect of
water on the subgrades. Surface runoff water that is trapped during construction on the exposed
subgrade soils could create additional deterioration of the soil's bearing capacity. Standing water
that may develop on the surface of the pavement may be minimized by:
adequate design (surface graded to control runoff to desired locations - catch
basins, drain inlets, gutters, etc.);
adequate compaction of each lift of pavement section component material (to
minimize localized settlements that result in ponding);
accurate grading of each lift of pavement section component material (to achieve
the desired design grades);
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 18 Richmond, Virginia February 12, 2010
installing temporary weep holes in drainage structures, construction of drainage swales
and diversion ditches and proper backfill and grading behind curbs to minimize water
intrusion from behind the curbs.
We note that the following guidelines are found in the Guidelines For 1993 AASHTO Pavement
Design:
1) Standard UD-2 underdrains and outlets are required on all raised medians to prevent
water infiltration through or under the pavement structure. Refer to the current VDOT
Road and Bridge Standards for installation details.
2) When Aggregate Base Material, Type I, Size #21-B is used as an untreated base or
subbase, it should be connect to a longitudinal pavement drain (UD-4) with outlets or
daylighted (to the face of the ditch) to provide for positive lateral drainage on all
roadways with a design ADT of 1,000 vehicles per day or greater. (Refer to the current
VDOT Road and Bridge Standards for installation details.) Other drainage layers can also
be used. When the design ADT is less than 1,000 vehicles per day, the Engineer must
assess the potential for the presence of water and determine if sub-surface drainage
provisions should be make.
3) Undercutting, transverse drains, stabilization, and special design surface and subsurface
drainage installations, should be considered whenever necessary to minimize the
adverse impacts of subsurface water on the stability and strength of the pavement
structure.
4) Standard CD-1 and CD-2 should be considered for use with all types of unstabilzed
aggregates, independent of the traffic levels.
5) For roadways with a design ADT of 20,000 vehicles per day or greater, a drainage layer
should be used, placed on not less than 6 inches of stabilized material and connected to
a UD-4 edge drain.
We recommend that pavement underdrains be designed and installed beneath new pavements
and sidewalks in accordance with guidelines contained in VDOT’s Road and Bridge Standards
and Drainage Manual. However, construction during wet seasonal conditions (typically
November through May) with heavy precipitation may result in a perched groundwater table or
softening of the soils at the surface. Additional underdrains may be required based on
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 19 Richmond, Virginia February 12, 2010
prevailing conditions during construction that were not evident during our subsurface
exploration.
6.0 CONSTRUCTION RECOMMENDATIONS
6.1 Site Preparation
General site work, including clearing, stripping, and grubbing, should be performed in
accordance with the VDOT’s Road and Bridge Specifications.
Before proceeding with construction, surficial soils and deleterious non-soil materials should be
stripped and removed from the proposed construction area. During the clearing, stripping, and
grubbing operations, positive surface drainage should be maintained to prevent the
accumulation of water. Underground utilities should be re-routed to locations outside of the
proposed placement of new pavements and footprints of the retaining walls. Where
unavoidable, utility trench backfill should be compacted to a minimum of 95 percent of the
maximum dry density as determined by the Standard Proctor test.
Shallow ditches line the sides of the existing road throughout the majority of the project. To
accomplish the proposed roadway widening, it is our assumption that all existing ditches will be
filled with approximately 1 to 3 feet of controlled structural fill (once surficial soil and all
deleterious materials and unsuitable fill are removed).
After clearing, stripping, and grubbing, areas intended to support pavements, sidewalks,
retaining walls, and new fill should be carefully evaluated by a geotechnical engineer. At that
time, proofrolling of the subgrade with a 20- to 30-ton loaded truck or other pneumatic-tired
vehicle of similar size and weight should be performed under the observation of the
geotechnical engineer to aid in identifying any localized soft or unsuitable materials.
Proofrolling should be performed during a time of good weather and not while the site is wet,
frozen, or severely desiccated. The proofrolling observation is an opportunity for the
geotechnical engineer to locate inconsistencies intermediate of our boring locations in the
existing subgrade. Construction during periods of wet weather will exacerbate unsuitable
conditions.
Where encountered, soils deemed soft and/or unsuitable for pavement support by the
geotechnical engineer should removed from below the proposed pavement. In the event that
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 20 Richmond, Virginia February 12, 2010
large areas of unstable and unsuitable subgrade are encountered, scarifying with drying and
recompaction, moderate undercutting with replacement using stable engineering fill, or a
combination of these remedial type measures could be considered under the advisement of the
geotechnical engineer. Construction during periods of wet weather will exacerbate unsuitable
conditions.
If large areas of the subgrade are identified as unsuitable for placement of the new pavement
section and the above methods do not remediate the soils, we recommend the use of a soil
stabilization geogrid (Tensar BX 1100 or equivalent) or stabilization geofabric (Amoco 2000 or
equivalent) be placed over the subgrade soils beneath the gravel base to assist in the remediation
process. An alternative to the use of geosynthetics is the use of a lime additive mixed with the
soft, wet soils. Lime stabilization has proven to be an effective way of stabilizing unsuitable soils.
Very dense soils (soils with N-values of 50 bpf or higher) were encountered in seven (7) of our
borings. Excavations above apparent rock depths can generally be accomplished by
conventional earthmoving equipment. Referencing the soil test boring logs, N-values up to
about 50 bpf indicate soils that can usually be excavated by conventional means. N-values of
50 blows for 6-inches or less penetration of the split-spoon sampler typically require heavy
equipment or rippers to efficiently excavate. Material below “Auger Refusal” depths, such as
those encountered in borings R-14 and BMP-1, may require hoe ramming or blasting. We do
not anticipate that rock will be encountered during general grading activities. It should be
understood, however, that the rock surface is variable and could be encountered at other
locations than those explored by our borings, especially at the east end of the project, although
this occurrence would most likely be isolated and somewhat limited in area.
The Fill identified in our borings was relatively “clean” or did not contain deleterious material
which would render it unusable for engineering purposes. Nonetheless, all existing fill
materials should be thoroughly evaluated in the field during construction and its suitability for
engineering use should be determined at that time.
6.2 Pavement Construction
Proper compaction of all elements of the pavement section is necessary. In accordance with
VDOT, we recommend that the upper 12 inches of all subgrades be compacted to 100% of the
Standard Proctor maximum dry density test prior to placement of new pavements. Field
compaction testing should be performed by a trained technician at a minimum of every 1000
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 21 Richmond, Virginia February 12, 2010
feet with a sand cone, nuclear densiometer, or other appropriate method. The aggregate base
course should be compacted in accordance with VDOT standards, which usually range from
95% to 100% of Standard Proctor maximum dry density. The specific compaction requirement
is a function of the stone’s gradation. We recommend that asphalt compaction be monitored
at the time of placement by nuclear gauges and that acceptable compaction be defined as a
test section density of at least 98% of the maximum density determined on a density control
strip constructed by an approved roller at the start of paving operations. The size of test
sections should be determined based on field observations made by experienced testing
personnel. A minimum of 5 density tests should be performed in each test section and the
results averaged. In addition to the average required compaction recommended above, no
individual test should be below 95% compaction.
6.3 Construction Materials Testing (CMT) Considerations
We recommend that all construction activities, including pavement placement, trenching,
construction of retaining walls, and placement of backfill, be observed, and compacted backfill
be tested, by a qualified engineering technician working under the supervision of a professional
geotechnical engineer to verify that the recommendations presented herein are followed.
6.4 Controlled Structural Fill
Controlled structural fill may be constructed using the non-organic on-site soils or an off-site
borrow having a classification of CL, ML, SC, SM, or better as defined by the Unified Soil
Classification System. Other materials may be suitable for use as general controlled structural
fill materials and should be individually evaluated by the geotechnical engineer. Controlled
structural fill should be free of boulders, organic matter, debris, or other deleterious materials
and should have a maximum particle size no greater than 3 inches. Soils classified as CH or MH
should not be used as structural fill in fill depths 3 feet or shallower. These soils are difficult to
moisture condition and pose expansive (heaving, shrink-swell) risk to pavements, sidewalks,
and retaining walls.
Fill materials should be placed in horizontal lifts with maximum height of 8 inches loose
measure. New fill should be adequately keyed into stripped and scarified subgrade soils.
During fill operations, positive surface drainage should be maintained to prevent the
accumulation of water. We recommend that structural fill be compacted to at least 95 percent
of the Standard Proctor maximum dry density. In confined areas such as utility trenches,
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 22 Richmond, Virginia February 12, 2010
portable compaction equipment and thin lifts of 3 to 4 inches may be required to achieve
specified degrees of compaction.
In general, we recommend that the moisture content of fill soils be maintained within three
percentage points of the optimum moisture content as determined from the Standard Proctor
density test. Generally, we do not anticipate significant problems controlling moistures within
fill during periods of dry weather, but moisture control may be difficult during winter months or
extended periods of rain. We recommend that the contractor have equipment on site during
earthwork for both drying and wetting of fill soils. Attempts to work the soils when wet can be
expected to result in deterioration of otherwise suitable soil conditions or of previously placed
and properly compacted fill.
Where construction traffic or weather has disturbed the subgrade, the upper 8 inches of soils
intended for structural support should be scarified and re-compacted. Each lift of fill should be
tested in order to confirm that the recommended degree of compaction is attained. Field
density tests should be performed for every 10,000 square feet (approximately 100 feet square)
of fill area, with a minimum of two tests per lift, to verify fill compaction. In confined areas, a
greater frequency may be required.
6.5 Construction Drainage
Subsurface water for the purposes of this report is defined as water encountered below the
existing ground surface. Based on the subsurface water data obtained during our exploration
program, we do not anticipate that subsurface water will be have a negative impact on
construction during anticipated earthwork for the proposed pavements, sidewalks, and
retaining walls at the site. However, the contractor should be prepared to dewater work areas
with appropriate grading, drainage ditches, swales, etc. Fluctuations in subsurface water levels
and soil moisture can be anticipated with changes in precipitation, runoff, and season.
7.0 CONTINUATION OF SERVICES
We recommend that we be given the opportunity to review pavement, sidewalk, and retaining
wall details, grading plan, and project specifications when construction documents approach
completion. This review evaluates whether the recommendations and comments provided
herein have been understood and properly implemented. We also recommend that Froehling
& Robertson, Inc. be retained for professional and construction materials testing services
Stantec Consulting Services, Inc. Forest Hill Avenue Widening F&R Project No. 60K-0679r1 23 Richmond, Virginia February 12, 2010
during construction of the project. Our continued involvement on the project helps provide
continuity for proper implementation of the recommendations discussed herein. These
services are not part of the currently authorized scope of services.
8.0 LIMITATIONS
This report has been prepared for the exclusive use of Stantec or their agent, for specific
application to the proposed Forest Hill Avenue Widening project in Richmond, Virginia, in
accordance with generally accepted geotechnical engineering practices. No other warranty,
express or implied, is made. Our conclusions and recommendations are based on design
information furnished to us; the data obtained from the previously described subsurface
exploration program, and generally accepted geotechnical engineering practice. The
conclusions and recommendations do not reflect variations in subsurface conditions which
could exist intermediate of the boring locations or in unexplored areas of the site. Should such
variations become apparent during construction, it will be necessary to re-evaluate our
conclusions and recommendations based upon on-site observations of the conditions.
Regardless of the thoroughness of a subsurface exploration, there is the possibility that
conditions between borings will differ from those at the boring locations, that conditions are
not as anticipated by the designers, or that the construction process has altered the soil
conditions. Therefore, experienced geotechnical engineers should evaluate earthwork and
pavement construction to verify that the conditions anticipated in design actually exist.
Otherwise, we assume no responsibility for construction compliance with the design concepts,
specifications, or recommendations.
In the event that changes are made in the design or location of the proposed roadways, parking
lots and walkways, the recommendations presented in the report shall not be considered valid
unless the changes are reviewed by our firm and conclusions of this report modified and/or
verified in writing. If this report is copied or transmitted to a third party, it must be copied or
transmitted in its entirety, including text, attachments, and enclosures. Interpretations based
on only a part of this report may not be valid. This report contains 23 pages of text and the
attached appendices.
APPENDIX A
Geotechnical Services Are Performed forSpecific Purposes, Persons, and ProjectsGeotechnical engineers structure their services to meet the specific needs oftheir clients. A geotechnical engineering study conducted for a civil engi-neer may not fulfill the needs of a construction contractor or even anothercivil engineer. Because each geotechnical engineering study is unique, eachgeotechnical engineering report is unique, prepared solely for the client. Noone except you should rely on your geotechnical engineering report withoutfirst conferring with the geotechnical engineer who prepared it. And no one— not even you — should apply the report for any purpose or projectexcept the one originally contemplated.
Read the Full ReportSerious problems have occurred because those relying on a geotechnicalengineering report did not read it all. Do not rely on an executive summary.Do not read selected elements only.
A Geotechnical Engineering Report Is Based on A Unique Set of Project-Specific FactorsGeotechnical engineers consider a number of unique, project-specific fac-tors when establishing the scope of a study. Typical factors include: theclient's goals, objectives, and risk management preferences; the generalnature of the structure involved, its size, and configuration; the location ofthe structure on the site; and other planned or existing site improvements,such as access roads, parking lots, and underground utilities. Unless thegeotechnical engineer who conducted the study specifically indicates oth-erwise, do not rely on a geotechnical engineering report that was:• not prepared for you,• not prepared for your project,• not prepared for the specific site explored, or• completed before important project changes were made.
Typical changes that can erode the reliability of an existing geotechnicalengineering report include those that affect: • the function of the proposed structure, as when it's changed from a
parking garage to an office building, or from a light industrial plant to a refrigerated warehouse,
• elevation, configuration, location, orientation, or weight of the proposed structure,
• composition of the design team, or• project ownership.
As a general rule, always inform your geotechnical engineer of projectchanges—even minor ones—and request an assessment of their impact.Geotechnical engineers cannot accept responsibility or liability for problemsthat occur because their reports do not consider developments of whichthey were not informed.
Subsurface Conditions Can ChangeA geotechnical engineering report is based on conditions that existed atthe time the study was performed. Do not rely on a geotechnical engineer-ing report whose adequacy may have been affected by: the passage oftime; by man-made events, such as construction on or adjacent to the site;or by natural events, such as floods, earthquakes, or groundwater fluctua-tions. Always contact the geotechnical engineer before applying the reportto determine if it is still reliable. A minor amount of additional testing oranalysis could prevent major problems.
Most Geotechnical Findings Are ProfessionalOpinionsSite exploration identifies subsurface conditions only at those points wheresubsurface tests are conducted or samples are taken. Geotechnical engi-neers review field and laboratory data and then apply their professionaljudgment to render an opinion about subsurface conditions throughout thesite. Actual subsurface conditions may differ—sometimes significantly—from those indicated in your report. Retaining the geotechnical engineerwho developed your report to provide construction observation is the most effective method of managing the risks associated with unanticipatedconditions.
A Report's Recommendations Are Not FinalDo not overrely on the construction recommendations included in yourreport. Those recommendations are not final, because geotechnical engi-neers develop them principally from judgment and opinion. Geotechnicalengineers can finalize their recommendations only by observing actual
Important Information About Your
Subsurface problems are a principal cause of construction delays, cost overruns, claims, and disputes.
Geotechnical Engineering ReportThe following information is provided to help you manage your risks.
subsurface conditions revealed during construction. The geotechnicalengineer who developed your report cannot assume responsibility or liability for the report's recommendations if that engineer does not performconstruction observation.
A Geotechnical Engineering Report Is Subject toMisinterpretationOther design team members' misinterpretation of geotechnical engineeringreports has resulted in costly problems. Lower that risk by having your geo-technical engineer confer with appropriate members of the design team aftersubmitting the report. Also retain your geotechnical engineer to review perti-nent elements of the design team's plans and specifications. Contractors canalso misinterpret a geotechnical engineering report. Reduce that risk byhaving your geotechnical engineer participate in prebid and preconstructionconferences, and by providing construction observation.
Do Not Redraw the Engineer's LogsGeotechnical engineers prepare final boring and testing logs based upontheir interpretation of field logs and laboratory data. To prevent errors oromissions, the logs included in a geotechnical engineering report shouldnever be redrawn for inclusion in architectural or other design drawings.Only photographic or electronic reproduction is acceptable, but recognizethat separating logs from the report can elevate risk.
Give Contractors a Complete Report andGuidanceSome owners and design professionals mistakenly believe they can makecontractors liable for unanticipated subsurface conditions by limiting whatthey provide for bid preparation. To help prevent costly problems, give con-tractors the complete geotechnical engineering report, but preface it with aclearly written letter of transmittal. In that letter, advise contractors that thereport was not prepared for purposes of bid development and that thereport's accuracy is limited; encourage them to confer with the geotechnicalengineer who prepared the report (a modest fee may be required) and/or toconduct additional study to obtain the specific types of information theyneed or prefer. A prebid conference can also be valuable. Be sure contrac-tors have sufficient time to perform additional study. Only then might yoube in a position to give contractors the best information available to you,while requiring them to at least share some of the financial responsibilitiesstemming from unanticipated conditions.
Read Responsibility Provisions CloselySome clients, design professionals, and contractors do not recognize thatgeotechnical engineering is far less exact than other engineering disci-plines. This lack of understanding has created unrealistic expectations that
have led to disappointments, claims, and disputes. To help reduce the riskof such outcomes, geotechnical engineers commonly include a variety ofexplanatory provisions in their reports. Sometimes labeled "limitations"many of these provisions indicate where geotechnical engineers’ responsi-bilities begin and end, to help others recognize their own responsibilitiesand risks. Read these provisions closely. Ask questions. Your geotechnicalengineer should respond fully and frankly.
Geoenvironmental Concerns Are Not Covered The equipment, techniques, and personnel used to perform a geoenviron-mental study differ significantly from those used to perform a geotechnicalstudy. For that reason, a geotechnical engineering report does not usuallyrelate any geoenvironmental findings, conclusions, or recommendations;e.g., about the likelihood of encountering underground storage tanks orregulated contaminants. Unanticipated environmental problems have ledto numerous project failures. If you have not yet obtained your own geoen-vironmental information, ask your geotechnical consultant for risk man-agement guidance. Do not rely on an environmental report prepared forsomeone else.
Obtain Professional Assistance To Deal with MoldDiverse strategies can be applied during building design, construction,operation, and maintenance to prevent significant amounts of mold fromgrowing on indoor surfaces. To be effective, all such strategies should bedevised for the express purpose of mold prevention, integrated into a com-prehensive plan, and executed with diligent oversight by a professionalmold prevention consultant. Because just a small amount of water ormoisture can lead to the development of severe mold infestations, a num-ber of mold prevention strategies focus on keeping building surfaces dry.While groundwater, water infiltration, and similar issues may have beenaddressed as part of the geotechnical engineering study whose findingsare conveyed in this report, the geotechnical engineer in charge of thisproject is not a mold prevention consultant; none of the services per-formed in connection with the geotechnical engineer’s studywere designed or conducted for the purpose of mold preven-tion. Proper implementation of the recommendations conveyedin this report will not of itself be sufficient to prevent moldfrom growing in or on the structure involved.
Rely, on Your ASFE-Member GeotechncialEngineer for Additional AssistanceMembership in ASFE/The Best People on Earth exposes geotechnicalengineers to a wide array of risk management techniques that can be ofgenuine benefit for everyone involved with a construction project. Conferwith you ASFE-member geotechnical engineer for more information.
8811 Colesville Road/Suite G106, Silver Spring, MD 20910Telephone: 301/565-2733 Facsimile: 301/589-2017
e-mail: [email protected] www.asfe.org
Copyright 2004 by ASFE, Inc. Duplication, reproduction, or copying of this document, in whole or in part, by any means whatsoever, is strictly prohibited, except with ASFE’s specific written permission. Excerpting, quoting, or otherwise extracting wording from this document is permitted only with the express written permission of ASFE, and only for
purposes of scholarly research or book review. Only members of ASFE may use this document as a complement to or as an element of a geotechnical engineering report. Any otherfirm, individual, or other entity that so uses this document without being an ASFE member could be commiting negligent or intentional (fraudulent) misrepresentation.
IIGER06045.0M
DATE: January 2010
SOURCE: DeLORME
DRAWN: N/A F&R# 60K-0679
Site Vicinity Map Forest Hill Avenue Widening
Richmond, Virginia
Drawing No.
1
FROEHLING & ROBERTSON, INC ENGINEERING ● ENVIRONMENTAL ● GEOTECHNICAL
Approximate Site Location
APPENDIX B
KEY TO BORING LOG SOIL CLASSIFICATIONS Particle Size and Proportion Verbal descriptions are assigned to each soil sample or stratum based on estimates of the particle size of each component of the soil and the percentage of each component of the soil.
Particle Size Proportion/
Descriptive Terms Descriptive Terms
Soil Component Particle Size Component Term Percentage
Boulder Cobble
Gravel-Coarse -Fine
Sand-Coarse -Medium
-Fine Silt (non-cohesive)
Clay (cohesive)
> 12 inch 3 - 12 inch 3/4 - 3 inch #4 - 3/4 inch #10 - #4 #40 - #10 #200 - #40 < #200 < #200
Major
Secondary
Minor
Uppercase Letters (e.g., SAND, CLAY)
Adjective
(e.g., sandy, clayey)
Some Little Trace
> 50% 20%-50% 15%-25% 5%-15% 0%-5%
Notes: 1. Particle size is designated by U.S. Standard Sieve Sizes. 2. Because of the small size of the split-spoon sampler relative to the size of gravel, the true percentage
of gravel may not be accurately estimated.
Density or Consistency The standard penetration resistance values (N-values) are used to describe the density of coarse-grained soils (GRAVEL, SAND) or the consistency of fine-grained soils (SILT, CLAY). Sandy silts of very low plasticity may be assigned a density instead of a consistency.
DENSITY CONSISTENCY
Term N-Value Term N-Value
Very Loose Loose
Medium-Dense Dense
Very Dense
0 - 4 5 - 10 11 - 30 31 - 50 > 50
Very Soft Soft
Firm Stiff
Very Stiff Hard
0 - 1 2 - 4 5 - 8 9 - 15 16 - 30 > 30
Notes: 1. The N-value is the number of blows of a 140 lb. hammer freely falling 30 inches required to drive a standard split spoon sampler (2.0 in. O.D., 1 3/8 in I.D.) 12 inches into the soil after properly seating the sampler six inches.
2. When encountered, gravel may increase the N-value of the standard penetration test and may not accurately represent the in-situ density or consistency of the soil sampled.
rev. Dec 2001
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3 feet
Driller used automatichammer to perform SPT
2.0
3.5
5.0
6-4-2
3-3-5
3-4-6
Driller Reported "Asphalt"Driller Reported "Crushed Stone"
POSSIBLE FILL: Firm, Olive Brown, Sandy LeanCLAY - Moist
(CL-Possible FILL)RESIDIUUM: Stiff, Yellowish-Brown and Gray,Sandy Fat CLAY - Moist
(CH)Boring terminated at 5 feet
Boring backfilled upon completion
0.20.6
3.5
5.0
0.5
2.0
3.5
6
8
10
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/10/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B - 1
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/10/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 2.5 feet
Driller used automatichammer to perform SPT
2.0
3.5
5.0
2-3-3
2-2-3
2-3-3
5.25 inches Asphalt5.75 inches Crushed Stone
FILL: Loose, Yellowish-Brown, Clayey Fine toCoarse SAND, Micaceous - Moist
(SM-FILL)RESIDIUUM: Firm, Yellowish-Brown, SandyLean CLAY, Micaceous - Moist
(CL)Boring terminated at 5 feet
Boring backfilled upon completion
0.51.02.0
5.0
0.5
2.0
3.5
6
5
6
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/16/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B - 2
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/16/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3 feet
Driller used automatichammer to perform SPT
2.0
3.5
5.0
2-2-3
2-5-6
4-6-7
Driller Reported "Surficial Soil"POSSIBLE FILL: Firm, Olive Brown, Sandy LeanCLAY - Moist
(CL-Possible FILL)Stiff, Reddish-Brown, Sandy Fat CLAY - Moist
(CH-Possible FILL)
Boring terminated at 5 feetBoring backfilled upon completion
0.3
1.5
5.0
0.5
2.0
3.5
5
11
13
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/10/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B - 3
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/10/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3.5 feet
Driller used automatichammer to perform SPT
2.0
3.5
5.0
6-3-3
5-7-8
5-5-6
Driller Reported "Crushed Stone"FILL: Firm to Stiff, Strong Brown toYellowish-Brown and Grayish-Brown, Sandy FatCLAY, with little Silt, Micaceous - Moist
(CH-FILL)
Boring terminated at 5 feetBoring backfilled upon completion
0.6
5.0
0.5
2.0
3.5
6
15
11
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/15/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B - 4
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/15/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater wasencountered at 6 feetduring drilling
Groundwater wasobserved at 6 feet uponremoval of auger
Cave-in depth at 7.5 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
1-2-1
1-2-1
WOH
1-3-5
3-4-6
Driller Reported "Surficial Soil"FILL: Very Loose, Black, Silty Fine to MediumSAND, with little Organic Material - Moist
(SM-FILL)Very Loose, Yellowish-Brown, Clayey Fine toMedium SAND, with trace Organic Material,Micaceous - Moist
(SC-FILL)Firm, Yellowish-Brown, Sandy Lean CLAY, withtrace Crushed Stone - Moist
(CL-FILL)RESIDIUUM: Loose, Yellowish-Brown, Silty Fineto Coarse SAND, Micaceous - Moist
(SM)[Relict Rock Structure Apparent]
Boring terminated at 10 feetBoring backfilled upon completion
0.6
1.8
6.0
7.5
10.0
0.0
1.5
3.5
6.0
8.5
3
3
0
8
10
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/10/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B - 5
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/10/09
60K-0679
10.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 4 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
2-4-2
WOH-2-2
2-2-4
Driller Reported "Surficial Soil"FILL: Firm, Brown, Sandy Lean CLAY, with traceOrganic Material and Silt, Micaceous - Moist
(CL-FILL)RESIDUUM: Soft to Firm, Olive Brown toYellowish-Brown, Sandy Lean and Fat CLAY, traceRoots - Moist
(CL-CH)
Boring terminated at 5 feetBoring backfilled upon completion
0.3
1.5
5.0
0.0
1.5
3.5
6
4
6
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
11/30/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B - 6
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis11/30/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 4 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
10.0
4-4-5
5-4-5
3-4-4
2-3-3
Driller Reported "Surficial Soil"FILL: Loose, Dark Brown, Silty Fine to MediumSAND, with trace Gravel and Organic Material -Moist
(SM-FILL)Loose, Yellowish-Brown, Clayey Fine to MediumSAND, with trace Gravel and Organic Material -Moist
(SC-FILL)RESIDUUM: Loose, Olive Brown, Silty Fine toCoarse SAND, Micaceous - Moist
(SM)[Relict Rock Structure Apparent]
Boring terminated at 10 feetBoring backfilled upon completion
0.8
3.5
5.0
10.0
0.0
1.5
3.5
8.5
9
9
8
6
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
11/30/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B - 7
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis11/30/09
60K-0679
10.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3 feet
Driller used automatichammer to perform SPT
2.0
3.5
5.0
2-3-5
3-4-6
4-6-6
5 inches of Asphalt10 inches of Crushed Stone
FILL: Loose, Yellowish-Brown, Clayey Fine toMedium SAND, with trace Gravel - Moist
(SC-FILL)RESIDIUUM: Medium Dense, Yellowish-Red,Clayey Fine to Medium SAND, Micaceous - Moist
(SC)Boring terminated at 5 feet
Boring backfilled upon completion
0.51.3
3.5
5.0
0.5
2.0
3.5
8
10
12
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/16/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B - 8
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/16/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
5-6-4
5-6-8
4-5-6
Driller Reported "Gravel"FILL: Loose, Yellowish-Brown, Clayey Fine toMedium SAND - Moist
(SC-FILL)RESIDIUUM: Medium Dense, Yellowish-Brownand Yellowish-Red, Clayey Fine to Coarse SAND -Moist
(SC)Boring terminated at 5 feet
Boring backfilled upon completion
0.2
2.0
5.0
0.0
1.5
3.5
10
14
11
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/11/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B - 9
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/11/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
5-5-4
3-3-3
2-3-2
Driller Reported "Surficial Soil"POSSIBLE FILL: Loose, Olive Brown, Clayey Fineto Medium SAND, with trace Roots, Micaceous -Moist
(SC-Possible FILL)
Boring terminated at 5 feetBoring backfilled upon completion
0.1
5.0
0.0
1.5
3.5
9
6
5
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/11/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B -10
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/11/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
4-5-2
3-4-5
4-3-3
Driller Reported "Crushed Stone"FILL: Firm, Yellowish-Brown, Sandy SILT, withtrace Asphalt and Gravel, Micaceous - Moist
(ML-FILL)RESIDIUUM: Loose, Pink, Clayey Fine to CoarseSAND, Micaceous - Moist
(SC)[Relict Rock Structure Apparent]
Boring terminated at 5 feetBoring backfilled upon completion
0.51.0
5.0
0.0
1.5
3.5
7
9
6
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/14/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B -11
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/14/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
2-3-3
4-5-8
2-3-3
Driller Reported "Surficial Soil"RESIDIUUM: Loose to Medium Dense, OliveBrown to Reddish-Yellow, Clayey Fine to CoarseSAND, with little Silt, Micaceous - Moist
(SC)
Boring terminated at 5 feetBoring backfilled upon completion
0.3
5.0
0.0
1.5
3.5
6
13
6
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/14/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B -12
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/14/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3 feet
Driller used automatichammer to perform SPT
2.0
3.5
5.0
2-4-3
5-7-12
8-6-6
6 inches of Asphalt7 inches of Crushed Stone
RESIDIUUM: Loose to Medium Dense,Yellowish-Brown, Clayey Fine to Medium SAND,with little Silt, Micaceous - Moist
(SC)
Boring terminated at 5 feetBoring backfilled upon completion
0.51.0
5.0
0.5
2.0
3.5
7
19
12
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/15/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B -13
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/15/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 3 feet
Driller used automatichammer to perform SPT
2.0
3.5
5.0
6-2-3
6-8-15
4-8-15
6.5 inches of Asphalt7.5 inches of Crushed Stone
FILL: Firm, Reddish-Brown, Sandy Lean CLAY,with trace Gravel and Organic Material - Moist
(CL-FILL)Medium Dense, Yellowish-Brown, Clayey Fine toCoarse SAND, with trace Gravel and OrganicMaterial - Moist
(SC-FILL)Boring terminated at 5 feet
Boring backfilled upon completion
0.51.12.0
5.0
0.5
2.0
3.5
5
23
23
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/16/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B -14
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/16/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 4 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
2-5-3
4-5-8
1-2-1
Driller Reported "Surficial Soil"FILL: Loose to Medium Dense, Brown, ClayeyFine to Medium SAND, with trace OrganicMaterial and Silt - Moist
(SC-FILL)Soft, Brown, Sandy Lean CLAY, with trace RockFragments - Moist
(CL-FILL)Boring terminated at 5 feet
Boring backfilled upon completion
0.6
3.5
5.0
0.0
1.5
3.5
8
13
3
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/15/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B -15
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/15/09
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 4.6 feet
Driller used automatichammer to perform SPT
2.5
4.5
14-10-5-4
5-7-8-7
7 inches of Asphalt
9 inches of Crushed Stone
RESIDIUUM: Medium Dense, Yellowish-Brown,Clayey Fine to Medium SAND, Micaceous - Moist
(SC)
[Relict Rock Structure Apparent]
Boring terminated at 4.5 feetBoring backfilled upon completion
0.5
1.2
4.5
0.5
2.5
15
15
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
1/15/10
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B -16
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis1/15/10
60K-0679
4.5'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/1
2/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 5 feet
Driller used automatichammer to perform SPT
3.0
5.0
12-8-7-9
6-6-5-6
7.25 inches of Asphalt
9.75 inches of Crushed Stone
FILL: Medium Dense, Brown, Silty Fine toMedium SAND - Moist
(SM-FILL)
RESIDIUUM: Stiff, Yellowish-Brown, Sandy LeanCLAY - Moist
(CL)
Boring terminated at 5 feetBoring backfilled upon completion
0.5
1.0
3.0
5.0
1.0
3.0
15
11
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
1/15/10
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B -17
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis1/15/10
60K-0679
5.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 4.6 feet
Driller used automatichammer to perform SPT
2.5
4.5
15-9-7-5
9-5-4-5
7 inches of Asphalt
12 inches of Crushed Stone
FILL: Medium Dense, Brownish-Gray, ClayeyFine to Medium SAND - Moist
(SC-FILL)
RESIDIUUM: Stiff, Gray, Sandy SILT, Micaceous -Moist
(ML)
[Relict Rock Structure Apparent]
Boring terminated at 4.5 feetBoring backfilled upon completion
0.5
1.5
2.5
4.5
0.5
2.5
16
9
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
1/15/10
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
B -18
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis1/15/10
60K-0679
4.5'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 14 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
1-1-2
1-1-1
WOH-1-1
WOH-1-1
WOH-1-1
1-2-2
2-3-2
Driller Reported "Surficial Soil"FILL: Very Loose, Yellowish-Brown, Silty Fine toMedium SAND, trace Roots, Micaceous - Moist
(SM-FILL)
Soft, Dark Brown, Sandy Lean CLAY, trace Roots,Micaceous - Moist
(CL-FILL)
POSSIBLE FILL: Soft, Yellowish-Brown, SandyLean CLAY, with trace Organic Material andRoots, Micaceous - Moist
(CL-Possible FILL)RESIDIUUM: Very Loose to Loose, LightBrownish-Gray and White, Silty Fine to CoarseSAND, Micaceous - Moist
(SM)
Boring terminated at 20 feetBoring backfilled upon completion
0.4
3.5
7.5
10.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
3
2
2
2
2
4
5
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/10/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R - 1
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/10/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater wasencountered at 18 feetduring drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 17.5 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
3-4-3
5-5-8
4-8-7
5-7-8
4-3-3
2-3-2
1-2-3
Driller Reported "Gravel"POSSIBLE FILL: Firm, Strong Brown, Sandy FatCLAY, Micaceous - Moist
(CH-Possible FILL)Stiff, Reddish-Brown, Sandy Lean CLAY - Moist
(CL-Possible FILL)Medium Dense, Brown, Clayey Fine to MediumSAND - Moist
(SC-Possible FILL)RESIDIUUM: Medium Dense to Loose,Yellowish-Brown to Brown, Silty Fine to CoarseSAND, Micaceous - Moist
(SM)
Boring terminated at 20 feetBoring backfilled upon completion
0.2
1.7
3.5
5.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
7
13
15
15
6
5
5
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/11/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R - 2
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/11/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater wasencountered at 14 feetduring drilling
Groundwater wasobserved at 14.9 feet uponremoval of auger
Cave-in depth at 16 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
1-1-2
5-7-8
3-5-6
2-2-3
3-3-3
2-2-2
3-5-6
Driller Reported "Surficial Soil"RESIDIUUM: Soft, Olive Brown, Sandy LeanCLAY - Moist
(CL)Stiff, Yellowish-Brown, Sandy Fat CLAY,Micaceous - Moist
(CH)Very Loose to Medium Dense, Yellowish-Brownto Grayish-Brown, Silty Fine to Coarse SAND,Micaceous - Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.41.5
3.5
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
3
15
11
5
6
4
11
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/10/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R - 3
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/10/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater wasencountered at 18.5 feetduring drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 19 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
6-4-4
5-7-7
5-4-5
5-9-14
8-11-12
3-4-4
3-4-5
Driller Reported "Surficial Soil"FILL: Firm to Stiff, Yellowish-Brown toReddish-Brown, Sandy Fat CLAY, with traceOrganic Material - Moist
(CH-FILL)Loose, Dark Brown, Silty Fine to Medium SAND,with trace Organic Material - Moist
(SM-FILL-Surficial Soil)RESIDUUM: Medium Dense, Yellowish-Brownto White, Clayey Fine to Medium SAND - Moist
(SC)
Loose, Yellowish-Brown, Silty Fine to CoarseSAND, Micaceous - Moist
(SM)
Boring terminated at 20 feetBoring backfilled upon completion
0.3
3.5
5.0
10.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
8
14
9
23
23
8
9
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
11/30/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R - 4
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis11/30/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 16.5 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
4-3-3
5-5-7
2-4-4
2-4-4
5-6-5
3-3-6
2-4-5
Driller Reported "Gravel"RESIDIUUM: Firm, Yellowish-Brown, SandyLean CLAY, with trace Roots - Moist
(CL)Medium Dense, Yellowish-Brown, Clayey Fine toMedium SAND, with little Silt, Micaceous - Moist
(SC)Loose to Medium Dense, Pink toYellowish-Brown and Black, Silty Fine to CoarseSAND, Micaceous - Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.20.7
3.5
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
6
12
8
8
11
9
9
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/11/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R - 5
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/11/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notreported during drilling
Groundwater was notreported upon removal ofauger
Cave-in depth at 16.6 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
1-3-2
2-2-2
2-4-5
2-4-3
4-5-5
3-3-4
5-8-6
Driller Reported "Surficial Soil"POSSIBLE FILL: Firm to Soft, Olive Brown, SandyLean CLAY, with trace Organic Material - Moist
(CL-Possible FILL)RESIDIUUM: Stiff to Firm, Yellowish-Brown,Sandy Lean CLAY, with trace Roots, Micaceous -Moist
(CL)
Loose to Medium Dense, White, Brown, andPink, Silty Fine to Coarse SAND, Micaceous -Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.4
3.0
8.5
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
5
4
9
7
10
7
14
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/11/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R - 6
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/11/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 17 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
2-2-3
5-7-8
3-3-5
3-3-4
3-4-5
4-4-3
2-3-4
Driller Reported "Surficial Soil"RESIDUUM: Loose to Medium Dense,Yellowish-Brown, Clayey Fine to Medium SAND,with trace Organic Material and Silt - Moist
(SC)Loose, Pink, Silty Fine to Coarse SAND,Micaceous - Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.3
3.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
5
15
8
7
9
7
7
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
11/25/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R - 7
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis11/25/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 16 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
2-3-3
2-4-5
4-5-7
3-3-4
3-4-5
2-3-5
2-2-3
Driller Reported "Surficial Soil"RESIDUUM: Firm, Reddish-Brown, Sandy FatCLAY, trace Roots - Moist
(CH)Medium Dense to Loose, Yellowish-Brown, SiltyFine to Coarse SAND, with trace Clay, Micaceous- Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.3
1.5
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
6
9
12
7
9
8
5
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
11/25/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R - 8
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis11/25/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater wasencountered at 16 feetduring drilling
Groundwater wasobserved at 13 feet uponremoval of auger
Cave-in depth at 18 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
4-5-6
4-4-5
2-3-3
3-4-6
4-5-8
9-8-8
10-16-16
Driller Reported "Surficial Soil"RESIDIUUM: Stiff, Brown, Sandy Lean CLAY,with trace Organic Material - Moist
(CL)Firm, Yellowish-Brown, Sandy Fat CLAY,Micaceous - Moist
(CH)Loose to Dense, Pink, Silty Fine to Coarse SAND,Micaceous - Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.4
3.0
5.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
11
9
6
10
13
16
32
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/11/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R - 9
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanAbbott12/11/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater wasobserved at 15 feet uponremoval of auger
Cave-in depth at 15.5 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
2-3-3
2-4-4
2-2-3
3-3-4
3-4-5
7-11-14
24-45-46
Driller Reported "Surficial Soil"RESIDIUUM: Firm, Yellowish-Brown, SandyLean CLAY, with trace Roots, Micaceous - Moist
(CL)
Loose to Very Dense, Pinkish-White and Brown,Silty Fine to Coarse SAND, Micaceous - Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.4
6.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
6
8
5
7
9
25
91
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/14/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R -10
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/14/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 17 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
4-4-5
4-4-6
3-5-7
3-3-4
2-4-5
3-3-4
5-9-10
Driller Reported "Surficial Soil"Roots
FILL: Stiff, Yellowish-Brown, Sandy Fat CLAY,with trace Organic Material, Micaceous - Moist
(CH-FILL)RESIDUUM: Stiff, Yellowish-Brown, Sandy LeanCLAY, with little Gravel - Moist
(CL)Loose to Medium Dense, Yellowish-Brown, SiltyFine to Coarse SAND, Micaceous - Moist
(SM)
Boring terminated at 20 feetBoring backfilled upon completion
0.61.5
3.0
6.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
9
10
12
7
9
7
19
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
11/24/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R -11
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis11/24/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 17 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
2-3-3
3-5-6
2-4-5
3-3-5
3-4-5
2-2-2
5-9-18
Driller Reported "Surficial Soil"Roots
FILL: Stiff, Yellowish-Brown, Sandy Lean CLAY,with trace Organic Material - Moist
(CL-FILL)RESIDUUM: Very Loose to Medium Dense,Yellowish-Brown, Silty Fine to Coarse SAND,Micaceous - Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.41.5
3.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
6
11
9
8
9
4
27
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
11/24/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R -12
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis11/24/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 16 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
1-2-3
4-4-5
2-3-4
3-4-5
3-3-5
4-6-7
18-34-41
Driller Reported "Surficial Soil"RESIDIUUM: Firm to Stiff, Olive Brown toYellowish-Red, Sandy Elastic SILT, with little Silt,trace Organic Material, Micaceous - Moist
(MH)
Loose to Very Dense, Yellowish-Brown to Whiteand Brown, Silty Fine to Coarse SAND, Micaceous- Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.4
5.5
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
5
9
7
9
8
13
75
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/14/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R -13
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/14/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 10 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
1-4-3
4-5-6
2-3-4
3-5-7
5-5-10
50/1
Driller Reported "Surficial Soil"FILL: Firm to Stiff, Yellowish-Brown, Sandy LeanCLAY, with little Rock Fragments, trace OrganicMaterial - Moist
(CL-FILL)RESIDIUUM: Firm, Yellowish-Brown, SandyLean CLAY, Micaceous - Moist
(CL)Medium Dense, Yellowish-Brown to White, SiltyFine to Coarse SAND, Micaceous - Moist
(SM)
[Relict Rock Structure Apparent]
Weathered Rock sampled as Very Dense, White,Silty Fine to Corse SAND - Dry
(SM)
Boring terminated at 16 feet due to augerrefusal
Boring backfilled upon completion
0.6
3.0
6.0
13.5
16.0
0.0
1.5
3.5
6.0
8.5
13.5
7
11
7
12
15
100+
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
12/15/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R -14
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis12/15/09
60K-0679
16.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater wasencountered at 18.5 feetduring drilling
Groundwater wasobserved at 18 feet uponremoval of auger
Cave-in depth at 19 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
20.0
2-2-4
3-4-6
4-6-7
3-3-3
3-4-3
2-3-4
1-3-3
Driller Reported "Surficial Soil"FILL: Firm, Reddish-Brown and Brown, SandyFat CLAY, with trace Organic Material - Moist
(CH-FILL)RESIDUUM: Stiff, Reddish-Brown, Sandy FatCLAY - Moist
(CH)Medium Dense, Yellowish-Red, Silty Fine toMedium SAND - Moist
(SM)[Relict Rock Structure Apparent]
Firm, White and Yellowish-Red, Silty Fat CLAY,with trace Sand - Moist
(CH)Firm, Pink to Red, Sandy Elastic SILT - Moist
(MH)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.51.5
3.5
6.0
10.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
6
10
13
6
7
7
6
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
11/25/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R -15
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis11/25/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth at 16 feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
19.3
2-5-17
17-23-20
17-32-29
3-4-4
6-4-6
10-13-19
20-50/4
Driller Reported "Surficial Soil"POSSIBLE FILL: Medium Dense to Dense, OliveBrown, Silty Fine to Coarse SAND, with littleGravel - Moist
(SM-Possible FILL)RESIDUUM: Very Dense to Loose,Reddish-Brown, Silty Fine to Coarse SAND,Micaceous - Moist
(SM)[Relict Rock Structure Apparent]
Stiff, White to Red, Sandy SILT, Micaceous -Moist
(ML)[Relict Rock Structure Apparent]
Weathered Rock Sampled as Dense to VeryDense, Reddish-Brown, Silty Fine and MediumSAND - Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.3
3.0
8.5
10.0
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
22
43
61
8
10
32
100+
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
11/24/09
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
R -16
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis11/24/09
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth was at 13feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
15.0
3-9-16
8-7-4
5-10-16
4-4-5
10-8-5
9-7-10
50/1
Driller Reported "Surficial Soil"FILL: Dark, Brown, Clayey and Sandy Mixture,with little Gravel and Asphalt, trace OrganicMaterial - Moist
(SC-CL-FILL)
RESIDIUUM: Stiff to Very Stiff,Yellowish-Brown, Sandy Lean CLAY, with traceSilt - Moist
(CL)
Medium Dense, Yellowish-Brown, Silty Fine toCoarse SAND, Micaceous - Moist
(SM)[Rock]
Boring terminated at 15.4 feet due to augerrefusal
Boring backfilled upon completion
0.2
8.0
14.515.315.4
0.0
1.5
3.5
6.0
8.5
13.5
15.0
25
11
26
9
13
17
100+
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
1/8/10
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
BMP-1
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis1/8/10
60K-0679
15.4'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Groundwater was notencountered during drilling
Groundwater was notobserved upon removal ofauger
Cave-in depth was at 15feet
Driller used automatichammer to perform SPT
1.5
3.0
5.0
7.5
10.0
14.4
19.3
4-8-6
12-8-7
3-4-5
2-4-8
2-5-4
6-50/5
22-50/3
Driller Reported "Surficial Soil"FILL: Stiff, Dark Brown, Sandy Lean CLAY, withlittle Gravel and Asphalt - Moist
(CL-FILL)
RESIDIUUM: Weathered Rock Sampled as VeryDense, Yellowish-Brown, Silty Fine to CoarseSAND, Micaceous - Moist
(SM)
[Relict Rock Structure Apparent]
Boring terminated at 20 feetBoring backfilled upon completion
0.2
14.2
20.0
0.0
1.5
3.5
6.0
8.5
13.5
18.5
14
15
9
12
9
100+
100+
BORING LOG
Type of Boring:
ElevationDESCRIPTION OF MATERIALS
(Classification)N Value
(blows/ft)
(1 of 1) TotalDepth Elev:
Started: Completed:
Location:
Driller:
REMARKSSampleDepth(feet)
* SampleBlows
1/8/10
Stantec Consulting Services, Inc.Forest Hill Avenue Widening, Richmond, Virginia
BMP-2
*Number of blows required for a 140 lb hammer dropping 30" to drive 2" O.D., 1.375" I.D. sampler a total of 18 inches in three 6" increments.The sum of the second and third increments of penetration is termed the standard penetration resistance, N.
Report No.:
Client:
Project:
Boring No.:
Depth
January 2010
See Boring Location PlanEllis1/8/10
60K-0679
20.0'HSA 2-1/4" ID
Date:
BORI
NG
_LO
G 6
0K-0
679.
GPJ
F&
R.G
DT
2/3
/10
Forest Hill Avenue Widening Pavement Coring Logs
Depth (in) Pavement Core C-1
0.0 – 6.0 Asphalt
6.0 – 15.0 Crushed Stone
Depth (in) Pavement Core C-2
0.0 – 5.3 Asphalt
5.3 – 11.0 Crushed Stone
Depth (in) Pavement Core C-3
0.0 – 8.5 Asphalt
8.5 – 14.0 Crushed Stone
Depth (in) Pavement Core C-4
0.0 – 8.0 Asphalt
8.0 – 15.0 Crushed Stone
Depth (in) Pavement Core C-5
0.0 – 6.0 Asphalt
6.0 – 14.0 Crushed Stone
Depth (in) Pavement Core C-6
0.0 – 6.6 Asphalt
6.5 – 16.0 Crushed Stone
Depth (in) Pavement Core C-7
0.0 – 1.5 Surface Layer Asphalt
1.5 – 5.0 Intermediate Layer Asphalt
5.0 – 8.0 Base Layer Asphalt
8.0 – 19.0 Crushed Stone
Depth (in) Pavement Core C-8
0.0 – 1.5 Surface Layer Asphalt
1.5 – 2.0 Disintegrated Layer Asphalt
2.0 – 5.0 Base Layer Asphalt
5.0 – 12.5 Crushed Stone
Depth (in) Pavement Core C-9
0.0 – 2.0 Surface Layer Asphalt
2.0 – 13.0 Asphalt
13.0 – 25.0 Crushed Stone
Depth (in) Boring Location B-8
0.0 – 5.0 Asphalt
5.0 – 15.0 Crushed Stone
Depth (in) Boring Location B-13
0.0 – 6.0 Asphalt
6.0 – 13.0 Crushed Stone
Depth (in) Boring Location B-14
0.0 – 6.5 Asphalt
6.5 – 14.0 Crushed Stone
Depth (in) Boring Location B-16
0.0 – 1.25 Surface Layer Asphalt
1.25 – 4.25 Intermediate Layer Asphalt
4.25 – 7.25 Base Layer Asphalt
7.25 – 16.25 Crushed Stone
Depth (in) Boring Location B-17
0.0 – 1.5 Surface Layer Asphalt
1.5 – 4.0 Intermediate Layer Asphalt
4.0 – 7.0 Base Layer Asphalt
7.0 – 17.0 Crushed Stone
Depth (in) Boring Location B-18
0.0 – 1.5 Surface Layer Asphalt
1.5 – 4.0 Disintegrated Layer Asphalt
4.0 – 7.0 Base Layer Asphalt
7.0 – 19.0 Crushed Stone
APPENDIX C
Dry
density, pcf
70
80
90
100
110
120
130
140
Water content, %
0 5 10 15 20 25 30 35 40
100% SATURATION CURVESFOR SPEC. GRAV. EQUAL TO:
2.82.72.6
Test specification: ASTM D 698-07 Method A Standard
60K-0679 1-18-10
Forest Hill Avenue Widening
Stantec Consulting Services, Inc.
N/A
Brown Clayey Sand [Bulk Sample #1]
SC
13.5 %
27 7
27.4 %
Maximum dry density = 120.5 pcf
Optimum moisture = 10.2 %
Curve No.: 1
Project No.: Date:
Project:
Client:
Location: Richmond, VA
Sample Number: 1 [Control #111099]
Remarks:
MATERIAL DESCRIPTION
Description:
Classifications - USCS: AASHTO:
Nat. Moist. = Sp.G. =
Liquid Limit = Plasticity Index =
% < No.200 =
TEST RESULTS
FigureFROEHLING & ROBERTSON, INC.
COMPACTION TEST REPORT
Dry
density, pcf
70
80
90
100
110
120
130
140
Water content, %
0 5 10 15 20 25 30 35 40
100% SATURATION CURVESFOR SPEC. GRAV. EQUAL TO:
2.82.72.6
Test specification: ASTM D 698-07 Method A Standard
60K-0679 1-19-10
Forest Hill Avenue Widening
Stantec Consulting Services, Inc.
N/A
Brown Clayey Sand [Bulk Sample #2]
SC
18.5 %
36 14
Maximum dry density = 112.3 pcf
Optimum moisture = 13.4 %
Curve No.: 2
Project No.: Date:
Project:
Client:
Location: Richmond, VA
Sample Number: 2 [Control #111099]
Remarks:
MATERIAL DESCRIPTION
Description:
Classifications - USCS: AASHTO:
Nat. Moist. = Sp.G. =
Liquid Limit = Plasticity Index =
% < No.200 =
TEST RESULTS
FigureFROEHLING & ROBERTSON, INC.
COMPACTION TEST REPORT
Dry
density, pcf
70
80
90
100
110
120
130
140
Water content, %
0 5 10 15 20 25 30 35 40
100% SATURATION CURVESFOR SPEC. GRAV. EQUAL TO:
2.82.72.6
Test specification: ASTM D 698-07 Method A Standard
60K-0679 1-18-10
Forest Hill Avenue Widening
Stantec Consulting Services, Inc.
N/A
Brown Sandy Clay [Bulk Sample #3]
CL
20.9 %
38 17
58.3 %
Maximum dry density = 109.7 pcf
Optimum moisture = 15.1 %
Curve No.: 3
Project No.: Date:
Project:
Client:
Location: Richmond, VA
Sample Number: 3 [Control #111099]
Remarks:
MATERIAL DESCRIPTION
Description:
Classifications - USCS: AASHTO:
Nat. Moist. = Sp.G. =
Liquid Limit = Plasticity Index =
% < No.200 =
TEST RESULTS
FigureFROEHLING & ROBERTSON, INC.
COMPACTION TEST REPORT
Dry
density, pcf
70
80
90
100
110
120
130
140
Water content, %
0 5 10 15 20 25 30 35 40
100% SATURATION CURVESFOR SPEC. GRAV. EQUAL TO:
2.82.72.6
Test specification: ASTM D 698-07 Method A Standard
60K-0679 1-18-10
Forest Hill Avenue Widening
Stantec Consulting Services, Inc.
N/A
Brown Clayey Sand [Bulk Sample #4]
SC
18.4 %
31 13
43.8 %
Maximum dry density = 113.6 pcf
Optimum moisture = 13.0 %
Curve No.: 4
Project No.: Date:
Project:
Client:
Location: Richmond, VA
Sample Number: 4 [Control #111099]
Remarks:
MATERIAL DESCRIPTION
Description:
Classifications - USCS: AASHTO:
Nat. Moist. = Sp.G. =
Liquid Limit = Plasticity Index =
% < No.200 =
TEST RESULTS
FigureFROEHLING & ROBERTSON, INC.
COMPACTION TEST REPORT
Dry
density, pcf
70
80
90
100
110
120
130
140
Water content, %
0 5 10 15 20 25 30 35 40
100% SATURATION CURVESFOR SPEC. GRAV. EQUAL TO:
2.82.72.6
Test specification: ASTM D 698-07 Method A Standard
60K-0679 1-19-10
Forest Hill Avenue Widening
Stantec Consulting Services, Inc.
N/A
Brown Clayey Sand [Bulk Sample #5]
SC
19.4 %
31 12
45.1 %
Maximum dry density = 114.9 pcf
Optimum moisture = 12.5 %
Curve No.: 5
Project No.: Date:
Project:
Client:
Location: Richmond, VA
Sample Number: 5 [Control #111099]
Remarks:
MATERIAL DESCRIPTION
Description:
Classifications - USCS: AASHTO:
Nat. Moist. = Sp.G. =
Liquid Limit = Plasticity Index =
% < No.200 =
TEST RESULTS
FigureFROEHLING & ROBERTSON, INC.
COMPACTION TEST REPORT
California Bearing Ratio
Project No.: 60K-0679 Test Date: 1/25/2010
Client: Stantec Consulting Services Tested By: C.M.
Project: Forest Hill Avenue Widening Compaction method: AASHTO T 193
Location: Richmond, Virginia X Soaked CBR
X 65 BLOWS
Penetration(in)
0
0.025
0.05
0.075
0.1
0.15
0.2
0.25
0.3
0.4
0.5
Moisture Determination
CBR @ 0.1 in. penetration (dry): #N/A
CBR @ 0.1 in. penetration (wet): 16.7 Maximum Dry Density (pcf): 120.5
Swell (%): 0.0 Optimum Moisture Content (%): 10.2
Dry Density Before Soaking (pcf): 118.5
Dry Density After Soaking (pcf): 119.4 Visual Description:
Retained on 3/4 inch sieve (%): 0.0 Brown Clayey SAND
Surcharge Weight (pounds): 20.0
F&R Lab No.: 111099
Moisture Content Before Soaking (%): 9.1%
Moisture Content After Soak, Top in. (%): 4.6% Source: Bulk 1
Moisture Content After Soak, Ave. (%): 11.7%
0
100
200
300
400
500
0 0.1 0.2 0.3 0.4 0.5
Str
ess o
n P
isto
n (
psi)
Penetration (inches)
Soaked
Dry
FROEHLING & ROBERTSON, INC.
Engineering Environmental Geotechnical
3015 Dumbarton RoadRichmond, Virginia 23228-5831 I USA
T 804.264.2701 I F 804.264.7862
California Bearing Ratio
Project No.: 60K-0679 Test Date: 1/25/2010
Client: Stantec Consulting Services Tested By: C.M.
Project: Forest Hill Avenue Widening Compaction method: AASHTO T 193
Location: Richmond, Virginia X Soaked CBR
X 65 BLOWS
Penetration(in)
0
0.025
0.05
0.075
0.1
0.15
0.2
0.25
0.3
0.4
0.5
Moisture Determination
CBR @ 0.1 in. penetration (dry): #N/A
CBR @ 0.1 in. penetration (wet): 8.8 Maximum Dry Density (pcf): 112.3
Swell (%): 0.2 Optimum Moisture Content (%): 13.4
Dry Density Before Soaking (pcf): 110.8
Dry Density After Soaking (pcf): 111.9 Visual Description:
Retained on 3/4 inch sieve (%): 0.0 Brown Clayey SAND
Surcharge Weight (pounds): 20.0
F&R Lab No.: 111099
Moisture Content Before Soaking (%): 12.1%
Moisture Content After Soak, Top in. (%): 18.3% Source: Bulk 2
Moisture Content After Soak, Ave. (%): 14.6%
0
100
200
300
0 0.1 0.2 0.3 0.4 0.5
Str
ess o
n P
isto
n (
psi)
Penetration (inches)
Soaked
Dry
FROEHLING & ROBERTSON, INC.
Engineering Environmental Geotechnical
3015 Dumbarton RoadRichmond, Virginia 23228-5831 I USA
T 804.264.2701 I F 804.264.7862
California Bearing Ratio
Project No.: 60K-0679 Test Date: 1/25/2010
Client: Stantec Consulting Services Tested By: C.M.
Project: Forest Hill Avenue Widening Compaction method: AASHTO T 193
Location: Richmond, Virginia X Soaked CBR
X 65 BLOWS
Penetration(in)
0
0.025
0.05
0.075
0.1
0.15
0.2
0.25
0.3
0.4
0.5
Moisture Determination
CBR @ 0.1 in. penetration (dry): #N/A
CBR @ 0.1 in. penetration (wet): 8.1 Maximum Dry Density (pcf): 109.7
Swell (%): 0.2 Optimum Moisture Content (%): 15.1
Dry Density Before Soaking (pcf): 110.8
Dry Density After Soaking (pcf): 111.5 Visual Description:
Retained on 3/4 inch sieve (%): 0.0 Brown Sandy CLAY
Surcharge Weight (pounds): 20.0
F&R Lab No.: 111099
Moisture Content Before Soaking (%): 14.3%
Moisture Content After Soak, Top in. (%): 17.5% Source: Bulk 3
Moisture Content After Soak, Ave. (%): 15.0%
0
100
200
300
0 0.1 0.2 0.3 0.4 0.5
Str
ess o
n P
isto
n (
psi)
Penetration (inches)
Soaked
Dry
FROEHLING & ROBERTSON, INC.
Engineering Environmental Geotechnical
3015 Dumbarton RoadRichmond, Virginia 23228-5831 I USA
T 804.264.2701 I F 804.264.7862
California Bearing Ratio
Project No.: 60K-0679 Test Date: 1/25/2010
Client: Stantec Consulting Services Tested By: C.M.
Project: Forest Hill Avenue Widening Compaction method: AASHTO T 193
Location: Richmond, Virginia X Soaked CBR
X 65 BLOWS
Penetration(in)
0
0.025
0.05
0.075
0.1
0.15
0.2
0.25
0.3
0.4
0.5
Moisture Determination
CBR @ 0.1 in. penetration (dry): #N/A
CBR @ 0.1 in. penetration (wet): 12.0 Maximum Dry Density (pcf): 113.6
Swell (%): 0.1 Optimum Moisture Content (%): 13.0
Dry Density Before Soaking (pcf): 110.9
Dry Density After Soaking (pcf): 113.1 Visual Description:
Retained on 3/4 inch sieve (%): 0.0 Brown Clayey SAND
Surcharge Weight (pounds): 20.0
F&R Lab No.: 111099
Moisture Content Before Soaking (%): 12.8%
Moisture Content After Soak, Top in. (%): 16.5% Source: Bulk 4
Moisture Content After Soak, Ave. (%): 13.9%
0
100
200
300
400
0 0.1 0.2 0.3 0.4 0.5
Str
ess o
n P
isto
n (
psi)
Penetration (inches)
Soaked
Dry
FROEHLING & ROBERTSON, INC.
Engineering Environmental Geotechnical
3015 Dumbarton RoadRichmond, Virginia 23228-5831 I USA
T 804.264.2701 I F 804.264.7862
California Bearing Ratio
Project No.: 60K-0679 Test Date: 1/25/2010
Client: Stantec Consulting Services Tested By: C.M.
Project: Forest Hill Avenue Widening Compaction method: AASHTO T 193
Location: Richmond, Virginia X Soaked CBR
X 65 BLOWS
Penetration(in)
0
0.025
0.05
0.075
0.1
0.15
0.2
0.25
0.3
0.4
0.5
Moisture Determination
CBR @ 0.1 in. penetration (dry): #N/A
CBR @ 0.1 in. penetration (wet): 12.3 Maximum Dry Density (pcf): 114.9
Swell (%): 0.2 Optimum Moisture Content (%): 12.5
Dry Density Before Soaking (pcf): 113.1
Dry Density After Soaking (pcf): 114.3 Visual Description:
Retained on 3/4 inch sieve (%): 0.0 Brown Clayey SAND
Surcharge Weight (pounds): 20.0
F&R Lab No.: 111099
Moisture Content Before Soaking (%): 11.1%
Moisture Content After Soak, Top in. (%): 15.8% Source: Bulk 5
Moisture Content After Soak, Ave. (%): 13.4%
0
100
200
300
400
0 0.1 0.2 0.3 0.4 0.5
Str
ess o
n P
isto
n (
psi)
Penetration (inches)
Soaked
Dry
FROEHLING & ROBERTSON, INC.
Engineering Environmental Geotechnical
3015 Dumbarton RoadRichmond, Virginia 23228-5831 I USA
T 804.264.2701 I F 804.264.7862