a green & clean future - · pdf filea green & clean future research proposal for a...
TRANSCRIPT
A Green &
Clean Future Research proposal for a small-scale hydro-power plant in the Salzach
Authors: Stijn Kuipers, Job Last, Harald Mathä, Jordi Smit
Date: 09-04-2013
Supervisors: Dr. M. Bokhorst, Dr. ir. ES van Leeuwen, drs. J. Dekkers
Project topic: The optimal size and location for a hydro-power plant in the lower
Salzach catchment taken into account the characteristics of the
river.
2
Contents
1. Introduction Proposal 3
2. Approach and Methodology Proposal 5
3. Pilot 7
4. Introduction Pilot Study 7
5. Methodology Pilot Study 8
6. Investigated Subjects Pilot Study 10
a. Stakeholders Analysis 10
b. Sediment and Ecology 16
c. Discharge 20
d. Optimal Location 24
e. Optimal Capacity 26
7. Planning and critical success factors 29
8. Overall conclusions and recommendations 31
9. Literature References 32
3
Introduction
The global warming is one of the biggest issues in the world at this moment. There are worldwide
effects, a few examples are: the melting polar cap(s), expanding deserts, the extremes in weather
conditions are increasing, flooding risks and droughts are becoming almost everyday issues and the
ozone layer is being destroyed. This however is just the tip of the iceberg. The effects will most
likely intensify with higher rates every year if no actions are taken. Most of these effects are
negative but can be prevented, and with the intention to neutralize the effects of this global warming
and prevent irreversible processes from happening we take all kinds of measures. One of those
measures is the use of green energy like solar power, wind energy, geothermal energy and
hydropower. However, the main reason to use hydropower is because of the depleting fossil fuels.
But if we take a look in history we find that hydropower has been used for thousands of years now.
History experts guess that the Chinese have been using hydropower for 5000 years now. The oldest
hydropower machine is 3500 years old and was used to irrigate the fields. In the past the energy was
used directly and nothing of it was stored for the simple reason that there was no way to store it yet.
After the industrial revolution the use of hydropower increased a lot. Due to technical
improvements, hydropower plants were able to generate more and more energy and after a while
even store the energy with the help of generators which converted the energy in electrical power.
The recent hydropower installations which can store energy and use turbines are just 100 years old.
Hydropower can be generated at a lot of places, has the potential to generate a lot of energy, the
energy can be converted and stored and is therefore on of the better substitutes for fossil fuels. The
amount of energy that is generated mostly depends on the discharge, which is dependent on the
height difference, width of the river and the depth of the river.
Austria is therefore a good country to generate energy through hydropower. This, along with the
fossil fuel problem and the environmental problem, is one of the reasons that the use of hydropower
has a growing popularity in Austria. ‘Since the 1950s the use of hydro power in Austria has been
used for all kinds of purposes, whether they are small or very large.’[ERNEUERBARE ENERGIE
OSTERREICH. 2012] Lately a lot of big power plants were built in Austria and there are several
planned in the future. But the focus mainly lies on the smaller hydro power plants which still have
to get a green light to be built in the smaller rivers. ‘Most of these rivers are not yet analyzed for
hydro power plant potential’ [ERNEUERBARE ENERGIE OSTERREICH. 2012]
One of the already used river for hydro power in Austria is the Salzach river. The Salzach river is a
right tributary river of the Inn and is 225 km long. The Salzach river was very important for the
local economy. It was used to transport Salt down the river. The source of this river lies in the
Kitzbühl Alps near the town Krimml. The river runs through a lot of towns, has an average
discharge of 251 m3/s and has a basin area of 6700 km2.
This river already contains a few small scale hydro power plants and government has planned to
build a several more dams. Most of the dams are run-off river hydro power plants. The other type of
hydro power is a pressure hydro power installation. In this research plan the focus lies on planning
another small scale run-off river hydro power plant. The idea is to take the already planned plants
into account because they will most certainly be built. So the main question asked in this research
plan is:
‘What is the optimal location and size for a hydropower plant in the lower Salzach catchment taken
into account the characteristics of the Salzach River?’
4
The characteristics which have to be taken into account concerns the river discharge during normal
and extreme situations, the width of the river, height difference and the depth of the river. One
might also think about the sediment and living organisms. Other subjects which have to be taken
into account when building a hydro power plant are the optimal size of the plant in terms of power
production and area of coverage. Furthermore the inventory of the stakeholders and desirability
from both general and local are important factors. Even politics, laws and protected areas have to be
taken into account as well. The characteristics of the river like velocity and curvature of the river
are also important factors. Other factors like the presence of other power plants nearby and the
effect of these plants on the new plant are also important. This also counts for the residential areas,
which affect the location of the power plant.
All these subjects derived the following sub-questions:
Which are they key obstacles to building a new small-scale hydropower plant at the Salzach
when it comes to the interests of the individual stakeholders?
How to merge the interests of the individual stakeholders using a SSM (Soft Systems
Methodology) - based approach?
What actions have to be taken when minimizing the effect of the sediment on the hydro-
power plant?
Which parts of the river are not protected and what are the solutions for the change in
ecology due to the build of a small-scale hydro-power plant?
How does the natural discharge and design flow of the Salzach River and its hydropower
plants develop through the Lower Salzach catchment?
How does the rising water level due to the new hydropower plant and the design flow affect
the flood risk and what solutions are possible?
What is the optimal location taken into account the several factors?
What is the optimal capacity of the new run-of-river hydropower plant?
5
Approach and Methodology
Approach
The goal of this research is to find an optimal location and size for a hydropower plant in the Lower
Salzach River between the places Werfen and Salzburg. The potential size of the hydropower plant
depends on the chosen location, thus it is necessary to start with looking for a location. Before
starting to develop a method, it is needed to determine the factors that have to be taken into account
by searching for the optimal location.
The scheme on the right shows the factors that will be
taken into account during the project. These factors are
determined through literature study and interviews. It is
quite obvious that the most important factor is the
presence of other hydropower plants nearby. To generate
energy, the water of the river has to fall down by gravity
over a certain distance (gross head), created by building a
dam. Turbines will convert the kinetic energy into
electricity.
When two hydropower plants share a small distance
between them, at least one of them will have a small gross
head. Therefore the efficiency will be low. The distance
between the power plants is proportional to the gradient,
the slope, of the river. In this research we assume the
minimum distance is about 2,6 kilometers, because a
majority of the power plants in the study area share this
distance.
The next factor is the mean natural discharge, this is the
volume of water that flows down per time unit. It should
be the same across the whole river, unless tributaries are
joining the Salzach. For there are many (small) tributaries,
it is safe to say the natural discharge in our study area
increases. It does fluctuate a lot though, due to the melting
snow during spring and summer. The flow peaks can get
very high, much higher than the turbines can handle. If the
discharge exceeds the ‘design flow’, gates in the dam will
open and let the water pass through.
The fourth factor is the gradient, also called the slope of
the river. The steepness of the river affects the velocity of
the water. A higher velocity means more kinetic energy
and thus more electricity. However, a higher velocity
increases the discharge too, because more water will flow
in shorter time. If the discharge exceeds the maximum
plant discharge, possible energy will be lost.
A solution for this problem is to build hydropower plants
closer to each other in steep areas. On the other hand,
curves in the river lower the velocity of the water, so it is
preferred to build power plants in steep and straight areas.
6
The width and depth of the river affects the design flow. The parts where is river is wider, there is
more space to build a larger and more efficient power plant, because the amount and size of the
turbines could be increased.
Also, the presence of residential area affects the optimal location as well. Politically, there is
resistance against building hydropower plants in and nearby towns, so it is better to avoid these
areas when searching for an optimal location. Ecology is of interest as well, since a new
hydropower plant will distort the environment and ecological cycles. It will be necessary to look
into these consequences and decide if a new power plant should or should not be built.
The presence of nature reserves is important, as well the consequences for the environment of the
rising of the water level upstream and the lowering downstream.
Alpine rivers usually carry a lot of sediment, which fills up the river, increasing flood risk. Thereby,
the sediment is able to block the turbines of hydropower plants, causing massive damage. In the
project the volume of sediment will be calculated and there will be looked into the possibilities to
solve this problem. On the basis of Meyer-Peter and Mullers formula [WHIPPLE, K. 2004, P. 5], the
sediment load could be calculated and measures can be taken.
The rising of the water level not only affects the environment, the flood risk will increase too. The
hydropower plant will cause higher water levels and function as an obstacle in the river. The project
will show the consequences of these higher water levels and offer solutions to reduce the flood risk.
Last but not least, the area of coverage and transport of energy will be taken into account. The
energy generated, will serve households in the area. The demand will have to meet the supply, to
minimize the loss of energy due to transport.
Upon these factors the methodology for finding the optimal location is based. When this location
has been found, it is possible to calculate the optimal size of the hydropower plant. The capacity
and size of the plant and turbines depends on the width, depth and shape of the river. It is needless
to say the natural discharge is the most important factor. Using the Basso and Botter equation
[BASSO, S. AND G. BOTTER. 2012] the optimal capacity and size of the plant will be calculated.
Methodology
All the factors have to be analyzed and weighed to find the optimal location. For this, detailed data
is necessary, a big part of the project will contain the creating of a complete dataset. Since most of
the data is not available, fieldwork is necessary to collect it. Using GIS (Geographic Information
Systems), it is possible to compare and analyze the spatial data. A MCA (Multi Criteria Analysis)
should weigh all of the several factors to find an optimal location. When this location is found, the
optimal capacity and size of the turbines and plant will be calculated.
The pilot study will show a shortened version of the approach, and explain the methodology used
for the pilot study further.
List of products
The products of this project will show the potential of hydropower plants in the Lower Salzach Area.
With the help of suitability maps, the project will recommend an optimal location. Other possible
locations will be described as well, to show the potential of the area. Furthermore the capacity and
the possible generated energy will be showed, explaining the area of coverage of possibilities for
transport.
7
Pilot
Introduction Pilot Study
The amount of hydro-power that is generated in Austria is rising quickly. The government promotes
this way of generating energy because of the fact that is a clean and renewable form of energy. The
Salzach is one of the rivers that contains a several power plants which generate a respectable
amount of renewable energy. But the river has the capacity to contain more plants and so it can
generate even more energy and supply more households. The amount of households that can be
supplied by a new hydro-power plant depends on the size, efficiency and other characteristics of the
plant which on their turn are dependable on the discharge, sediment load and other characteristics.
These considerations derive the following question:
''What is the optimal location and size for a hydropower plant in the lower Salzach catchment taken
into account the characteristics of the Salzach River?''
However there are a few characteristics which can't be investigated on short terms because they
have to be monitored over a longer period. For example the sediment load of the river has to be
measured for at least a year to get a good idea of the bed load of the river. This also counts for the
impact of the ecology due to the building and construction of a hydro-power plant. Furthermore for
the efficiency of the plant, the fluctuation in discharge, depth of the river and many more factors as
well, these are characteristics that have to be monitored for a longer period. Unfortunately this is
just a small part of the factors that have to be accounted for, one should also think about the
influence of objectors of this plant and whether their opinion is valid and strong enough or not.
So based on the fact that some characteristics take a longer time to take into account we now mainly
focus on the optimal location based on the mean natural discharge, curvature of the river, whether it
is or is not in a city, gradient of the river, protected areas, presence hydropower plants nearby and
the width of the river.
8
Methodology Pilot study
The pilot study will be done by using ArcGIS, a software program used for finding and analyzing
differences in spatial data. The first thing needed to start looking for an optimal location is the data.
All of the factors have to have data available to find differences between different parts of the river
in the study area. For there is not much complete data available, it is necessary to create a dataset.
Therefore, existing and future hydropower plants have been put in a file as points.
Next thing is to find as much data as possible concerning all of the factors, then analyzing it using
ArcGIS and several tools, so that it is possible to point an optimal location. A critical step is
splitting the river into segments with the help of ArcGIS. The program calculated the length of the
river as approximately 330 kilometers, so it was cut in 166 segments.
Every segment should be approximately two kilometers, but ArcGIS miscalculated. The actual
length is circa 1.3 kilometers. For further analyzing the length of the segments does not matter
though.
The dataset consists of the following columns (noted as rows below):
Segment number
Height start segment in m
Height end segment in m
Height difference in m
Average Width River in m
Natural Discharge
Maximum Plant Discharge
Presence Plant
Presence Measure Station
Suitability Presence Other Plants
Suitability City
Suitability Shape River The first column mentions the segment number, since just the study area is going to be analyzed,
only segments near and in the area are investigated. These are numbers 1, upstream, until 53,
downstream. The next three are necessary to calculate the gradient using a digital elevation model
(DEM). The model, a raster tiff-file, has a ten meter resolution and has been developed in an
unknown year.
The width of the river has been calculated with the measure tool from Google Labs in Google Maps.
This is a up to date way to measure, but hard to be precise, since this is manually done. The natural
discharge is known for the years 2012 en 2013 at three points in the study area, thanks to measure
stations in Werfen (in the south), Golling (in the middle) and Salzburg (in the north) [Land Salzburg
2013a].
Create dataset with existing and future plants
Add data of factors
Compare data by analyzing
using GIS
Find optimal location by taking all
factors into account
9
For every existing and future plant the maximum plant discharge can be found by looking on the
sites of the two owners of the plants, Verbund and Salzburg AG [Verbund Österreich.
2013c][ SALZBURG AG 2013c]. Presence Plant en Presence Measure Station shows the names of the
plants en stations, if they are present in a certain segment.
Finally, the suitability per segment concerning the presence of other plants, residential areas and the
shape of the river are converted into zero and one. A zero states a negative suitability, a one a
positive suitability. Between hydropower plants, as said, a distance of at least four segments is
necessary, based on the present pattern. Suitability city is negative when at the sides of the river
where the plant is going to be, houses are build. The suitability for the shape of the river will be
judged when a few final locations are known. The ‘straightness’ of the river will weigh when the
final location will be chosen. The final three criteria are judged using ESRI’s World Imaginary Map,
last updated March 2013.
10
Stakeholders
In countries where many powerful rivers are present, waterpower is most of the time one of the
preferred energy sources. It’s seen as a sustainable source of energy, since there is no exhaustion of
any fossil fuels or any other signs of environmental pollution, at least not a first glance. It appears to
be clearly superior since it’s green, renewable energy, which gets broad acceptance from the public
and helps in fulfilling international goals in climate protection. [KLEINWASSERKRAFT ÖSTERREICH
2008. P.1] In the following research questions on stakeholders in hydropower, the focus is on
identifying key stakeholders as well having a look at their interests and arguments in favor of or
contra the subject.
“Which are they key obstacles to building a new small-scale hydropower plant at the Salzach, when
it comes to the interests of the individual stakeholders?”
Possible Stakeholders in Hydropower
In order to have a look at possible obstacles in building a new hydropower plant in the Salzburg
region, you first have to look at key stakeholders and their interests. Since the harvesting of
waterpower isn’t only an issue in Austria, general groups of stakeholders can be identified, mostly
indifferent of the region or country. Heller et al. identify the following possible stakeholders for a
project study very similar to the situation in Austria:
Figure 1: Possible relevant stakeholders in hydropower [Heller et al. 2010. P. 298]
In a less complex manner, we also can distinguish two main groups. There are those organizations
which are pro water power and on the other hand we’ve got the opponents, which support the
opinion that the beauty and biological functionality of nature falls short in the struggle for energy.
They see the rivers and water bodies as ecologically highly endangered zones. [SCHÖNAUER S. 2007]
On the pro side we often find the government itself, which cares for gathering enough energy to
serve the demand in the country. Energy Producers do the energy harvesting and distribution to the
demanding areas, so the most of the time tend to see the positive sites over the possible
disadvantages of hydro power. “Verbund”, one of Austrias biggest distributers of hydropower sees it
as the “backbone of energy” and as an “investment into the future”. [VERBUND ÖSTERREICH. 2013a]
11
Furthermore there are construction companies and shareholders, so money is a big issue. That’s
why the economic view is dominant in most cases, although it has to be said that government and
the other stakeholders in favor of hydropower claim to pay great attention not to endanger or
damage the environment. It’s stated very clearly that waterpower needs clear guidelines, respecting
ecological issues. [KLEINWASSERKRAFT ÖSTERREICH 2008. P.2]
As the demand in energy is rising worldwide, nuclear power and thermal power is not really
accepted any more, not least because it isn't "sustainable". The sustainable forms of energy, like
solar- and hydropower get more acceptance among the people, at least in countries which are
willing to afford the higher price of sustainable energy. On the first glance it seems there is no
reason why anybody should be in opposition to hydropower, whether it is in large- or in small-scale
projects. Nevertheless there are many groups on the contra side of hydropower, especially in
Austria.
First thing that comes to mind are large scale projects, where huge dams are built up, creating huge
artificial lakes - the storage reservoirs for even bigger hydropower-plants. These huge water areas
make people, living in such areas before, homeless and the worldwide press has no merci with the
companies and governments responsible for this. But this is only one side of the game. In countries
like Germany and even more in Austria, where hydropower builds kind of a foundation of the
energy-resources available, there projects aren’t that big, but nevertheless the environmental and
ecological issues have to be considered. If no people are endangered and positive contributions to
meeting climate protection goals are made, most environmental groups and activists should be in
favor of hydropower - since it's "sustainable" - right?
But that’s most often not the case, ecological NGOs and other local environmental organizations
surely are in favor of meeting long time climate goals, but not at the cost of sacrificing local
environment and nature. One of the best quotes in the local news was: "Klimaschutz gegen
Naturschutz?", meaning that the protection and conservation in local nature falls short to the big
picture of harvesting more and more energy, while still trying to fulfill international climate
protection goals.
Environmental agencies complain about the fact that Energy providers responsible for destroying
nature don’t have to pay fees for doing so any longer. Those fees have been used to do good to the
local nature, like for example renaturating other areas in the region. Since the beginning of 2013
those fees aren’t mandatory any more, as long as the power plant helps in achieving long term
climate goals. [ORF. 2013]
The situation in the project-area
In the case of this project the Salzach-region is very similar in the other federal states of Austria.
The government and authorities have been aware of the countries power-potential, lying in the
streams and water bodies, and have used it over the last decades. Due to high energy demands those
trend isn't very likely to change. But just as in the international context, there are numerous
organizations on the other side, fighting against a further harvesting of hydro-power by building
further power plants. Their main argument against hydropower is that the preservation of untouched
river sections for further generations is much more important than getting comparatively little
power out of the small rivers in the region.
The following list of stakeholders is mainly focused on already planned hydropower projects in the
Salzach region (like for example the plant Sohlstufe Lehen), since those stakeholders will be
involved in the decision processes of further power stations too.
12
Main stakeholders in favor of new power-stations and pro hydropower
City of Salzburg & Province of Salzburg
From a logical point of view, the main interests of those local authorities has to be to getting out as
much energy as possible, at the least costs and especially whilst meeting international climate
protection goals. They basically see much potential in hydropower and although the protection of
nature and environment also is part of their responsibility, they are mainly in favor of new
hydropower projects. At the moment there are nearly 500 hydropower plants to be found in the
province of Salzburg. [LAND SALZBURG 2013]
Salzburg AG
A company seated in Salzburg City, for example responsible for the most recent plant at Sohlstufe
Lehen in Salzburg City and also operator of 28 hydropower stations in the state of Salzburg. 5 more
are already planned or currently built up. If there is another hydro-power-plant to be built, there’s a
good chance it will be operated by the Salzburg AG (or in cooperation with the “Verbund AG”). As
a stock company it’s owned by the city of Salzburg and the province of Salzburg for the most part.
[ SALZBURG AG. 2013a] [SALZBURG AG. 2013b]
Verbund AG
Austria’s biggest energy provider, who is serving about 40% of the national energy demand. It
gathers about 90% of its electricity by hydropower. Verbund is stock company and the Republic of
Austria owns 51% of it. [VERBUND ÖSTERREICH 2013b]
DOKA
A building company, who built the Plant at Sohlstufe Lehen. They could be interested in facilitating
the building of new power - plants. [DOKA. 2012]
Their biggest arguments in favor of hydropower are:
Austria has basically no fossil energy sources and even if there were any those would do
more climate damage than hydro- or solar power. Many decades the water power has served
well for Austria in harvesting energy and is sure to do so for the future.
The biggest argument is that although the power station cut the rivers and may impact nature,
they are thought of to be the best /most viable energy that Austria has to offer.
In most cases along the Salzach river, but especially at Sohlstufe Lehen Salzburg AG claims
that the riverbed needs structural reinforcement anyways.
There would have the alterative of just reinforcing the riverbed, without the power-plant, but
according to the company this would have cost more and would have had less positive effect
on the situation along the river.
13
Arguments especially for Sohlstufe Lehen
o Especially at Sohlstufe Lehen, by regulating the river, there will be less noise caused by
the river.
o At Sohlstufe Lehen the surroundings of the plants location also benefit, for example the
nearby "Glanspitz" park will be renewed
o There will be no further impact through power lines, since the will be built belowground.
They will connect the power plant t the city's energy network and to the electrical sub-
station in Hagenau.
o A big concern of opponents is, that fish are often not enabled to surpass the artificial bar-
riers build into the rivers properly. But according to the Salzburg AG this wasn't possible
at all before the building of the power station and will now be made possibly through a
small bypass-river.
[SALZBURG AG. 2013c][VERBUND ÖSTERREICH. 2012][LAND SALZBURG. 2013]
The main stakeholders against a further expansion of the hydro-power-network
In Austria and the near Bavarian regions the opponents are mostly local and national environmental
movements, ecological NGOs, as well as people living nearby the power stations. There are several
fishing clubs, wildlife clubs, canoeing clubs, animal rights movements and a whole lot of other
people, basically worried about possible damage to nature and wildlife by building new power
stations.
One of most important stakeholders against hydropower in Austria and especially along the river
Salzach would be the “Umweltdachverband”. Other organizations interested in protection of the
area are the “Plattform Lebendige Flüsse”, the "Kurratorium für Fischerei & Gewässerschutz" and
the "AG Lebensraum Salzach". All of those organizations are basically of the opinion that the price
of sacrificing nature is too high, just in order to gain a little bit more energy.
[HEINRICH BREIDENBACH. 2010][UMWELTDACHVERBAND. 2013] [LEBENDIGE FLÜSSE. 2013] [ÖKF:
2013]
Their arguments contra - hydropower are:
The basic and biggest factor is that the little energy, harvested by the small-scale power
plants, isn't worth the destruction of nature.
Their opinion of the larger - scale power plants at the river Danube is a little better, since
those are at least collecting the big part of all the hydro power.
On their websites they present the following numbers to reinforce their arguments:
14
o All the smale -scale hydro power plants deliver only 12.5% of all the hydropower
harvested in Austria, equalling only 7 % percent of the nations overall energy
consumption.
o For example ONE average larger-scale plant along the river Danube produces enough
energy to theoretically replace ALL of the smale sclae hydro powerplants in the province
Styria.
o Only 15% of all the river networks are (at least relatively) unobstructed, at least those
remaining parts of nature should be preserved
When it comes to a possible rise in energy consumption, they call attention to the studies of
"Statistik - Austria", which tend to show only very little increase in the annual energy-
consumption (at least when it comes to private households)
Another argument is that the caloric power stations can't really be replaced by hydropower,
since in times of highest energy consumption the hydro-power lacks high power outputs
(mainly due to fluctuation in the water levels)
The recommend other forms of green energy like solar- or wind power, and last but not least
saving energy in general.
[HEINRICH BREIDENBACH. 2010][UMWELTDACHVERBAND. 2013] [LEBENDIGE FLÜSSE. 2013] [ÖKF:
2013]
Interview
In order to get some details about the opinions of the opposing stakeholders an interview with
"Naturschutzbund Salzburg" was done during our pilot study (on Tuesday, 02.04.2013), which is
one of the most active groups, when it comes to hydro power along the Salzach.
Basically the Naturschutzbund has a clear opinion on hydropower: No more hydro-power-stations,
there has been enough damage to nature and rivers. They are against building any new stations,
neither near the "Natura 2000" - protected areas of the lower-part - Salzach, nor in the middle part
of the river where the new Stegenwald - project is planned. The new location doesn’t really matter,
since the plant would to damage everywhere. They argue in favor of a re-natured Salzach which
should be preserved. It doesn't matter how fancy you build, color or sell the power-plants to the
public, they cut the river and have already done too much damage to nature.
On the statement that other forms of green energy (like solar or wind power) also do damage to
nature our interview partner agreed. But he especially mentioned the potential of photovoltaic-grids
which could be optimized. Apparently there are many places to put solar panels, like industrial-
buildings-roofs and so on. He mentioned that for example in the region of Traunstein in Bavaria 26%
of all energy produced would be harvested by photovoltaic grids. In most regions of Austria under 1%
of photovoltaic input is estimated (he wasn't quite sure about the percentage in detail).
As another factor he mentioned that often the waste heat of industry and caloric -power stations
isn't used as effectively as it could be. Especially in Salzburg the district heating had huge potential.
15
We also told him that it's often stated that the Salzach riverbed needs to be supported and power
stations would come in handy there. He stated that initially the power-stations along the Salzach did
a big part to causing such problems at first. "Curing" the river by building more power stations
doesn't do any good - it'll just make problems worse in the long run.
The better solution is to re-nature the river. If anything should be done about hydropower-stations in
Austria at all, the existing ones should be optimized, for example by using more efficient turbines.
“How to merge the interests of the individual stakeholders using a SSM (Soft Systems Methodology)
- based approach?”
In order to apply the SSM – Method to the situation at the Salzach River one has to understand first
what this SSM actually means. ‘Soft systems methodology (SSM) represents an approach to
investigate a problem situation, as it is perceived to exist in the ‘‘real world.’’ [CHECKLAND P.,
Scholes J. 1990]. Since the definition via usage in the “real world” is pretty open, it finds
application in various fields. Therefor exists is no exact definition, on how the soft Systems Method
should be applied in subject, it’s really depending on the individual case.
According to Checkland the solving of a problem consists of “defining the desired state and the
present state and selecting the best solution to reduce the difference between them.” [CHECKLAND
P., 1999] The special thing about SSM is although that it isn’t focusing on finding a solution at once.
The biggest emphasis is on identifying the problem situation itself. Often this isn’t easy, since many
stakeholders tend to be involved in complex real world situations, like for example building a
hydropower plant.
In basic the method is an iterative process based on the point of views of the individual stakeholders
in a specific problem case. In a first step everyone should have the possibility of bringing in their
opinion and then discuss it with the other parties. By doing so one gets to know the point of view of
other stakeholders and the own view of the situation is affected. The ultimate goal is, so to say, to
understand the others. By combining all those variations in worldviews, it becomes clear what
everyone views as desirable, and furthermore what everyone sees as “most plausible solution” to
the problem. [HARWOOD ET AL. 2012]
Due to the adaptation of the Soft Skill Method towards usage for environmental issues, two main
directions on how to follow it exactly have been found. [CHECKLAND P., Scholes J. 1990] While
Mode 1 relies more on following the method in a sequent and methodology driven way, the second
Mode inquires for a less theory driven and strict application, taking more of the actual real life
problem situation into account. When trying to solve the conflict around the Gordleton Mill in
Hampshire, where multiple stakeholders are involved in building a new hydro turbine into an old
mill, the second mode is used to gain better insight into the situation. [HARWOOD ET AL. 2012. P
1211]
When thinking of the Situation at the Salzach River, the second mode of application seems to be the
best way of applying SSM too. When thinking of the key stakeholders in both, the pro and the
contra parties it seems to present decent solution to get to a common point. Nevertheless it has to be
considered that all stakeholders have to be willing to discuss on their point of view, otherwise the
method can’t work out its potential to the fullest. It could become a problem in the project area, if
for example, the environmental organizations aren’t willing to think of a new hydropower plant at
all, rather than giving their opinion on, for example, how it should be built to do the least damage to
nature. Given some willingness to compromise SSM surely poses a potent instrument of getting to
know the “real problem situation” and finding the best solution on location, size and other details of
a hydropower project.
16
Sediment and ecology
Planning, designing and constructing a hydropower plant are tasks which come with many factors
that have to be taken into account. Not only to satisfy the supporters, who will say that hydropower
serves clean energy which is favourable under the current global warming caused due the burning
of fossil fuels to derive energy, but also to satisfy the objectors who are against building anything in
the river because of the fragile natural environment. The supporters reply to this point that clean
energy will be good for the environment of many other rivers and ecosystems in the long term.
Another challenge of planning and designing of a hydropower plant is one that concerns the bed
load transport processes because the sediment can damage the plant if the bed load problem is not
taken into account. This especially counts for the Salzach River, because the Salzach has a
relatively turbulent flow and the water level fluctuates a lot. This is caused by the main supply of
rainwater and partly melting snow. This means that the river is eroding a lot and deposits a lot of
sediment at the moment the water level is low and the velocity low. This leads to the following sub
question:
“What actions have to be taken when minimizing the effect of the sediment on the hydropower
plant?”'
According to Dr. Strobl from the University of Salzburg, the Salzach River has too much sediment
to be taken into account in the decision-making process. There are no particular places in the river
where there is less bed load and sedimentation. The sediment is an engineering problem, not a
problem that can be solved by location planners. This brings us to another question, namely:
“How can the design of the hydropower plant minimize the damage of bed load to the structure?”
Firstly, erosion of the river banks has to be diminished. This is done by placing block ramps in the
river for stabilisation. These ramps have to cover a fluctuation of the river of approximately three
meters. These ramps however are just local measures. Other than stabilizing the bed, the block
ramps also have two universal openings which are designed for the fish and sediment to pass. The
openings also have the function to let the water out in case of flooding. The power plant consists of
two of three turbines with sluices for the bed load in between the turbines. The main priority of the
plant overall is to optimize inflow of water and minimize the bed load into the intake. Fish are being
protected from entering the turbines by a special screen.
Figure 2: Cross section through a river flow power plant looking downstream [Brinkmeier & Aufleger 2010]
17
Figure 3: View of the plant with block ramps (right) and overflowed power plant (left) [Binkmeier & Aufleger 2010]
Furthermore, in the intention to avoid bed load input, a bed load barrier is situated across the intake,
leading towards the universal opening. The crest of the barrier is 0.5 m above the river bed
upstream of it, and right above the turbine inflow. By situating the intake of a plant in the outer
bend of a river, the input of the sediment into the intake can be reduced significantly [Brinkmeier &
Aufleger 2010].
Unfortunately, not all sediment can be kept out by the barrier, especially in case of a flood event.
The solution to this is that the construction has the ability to flush the sediment out of the
construction. It can also be removed externally. To increase the effect of the flush effect and avoid
input of sediment in the turbines an additional sluice is installed replacing the middle turbine of the
innermost block.
But whatever highly technological construction there is possible with respect to sediment and fish,
it comes to the Institute to decide whether a hydropower plant is constructed or not. It all depends
on the existing protection regimes. The overall concept of the in Institutes functioning in case of
ecology is based on conversation method of the biodiversity protection. This means that if a
hydropower plant is planned in a protected area it almost automatically means that it issues the
requirements for construction, thus making further development far more problematic.
So in the case of the Salzach River if a hydropower plant is planned, it has to deal with this institute.
This means that the project managers of the plant have to find a way to construct a power plant that
has the least negative effects on the ecology. In case of the Salzach River this will derive the
following question:
“Which parts of the river are not protected and what are the solutions for the change in ecology due
to the build of a small-scale hydropower plant?”
To this first part of the question there is an easy answer which is derived from the metadata. There
are a few protected areas along the Salzach, but the river itself is excluded from this area. This
means it is possible to build everywhere in the river.
18
Figure 4: Protected areas along the Salzach
[Done in ArcGIS]
The method to deal with a problem of protective laws and regimes is by analysing the legislation to
pertain the area with respect to new forms of renewable energy. Then analyse the current state of the
river ecosystem and project the state after the plant is built. And finally, analyse the impact on the
landscape. [Crncevic & Josimovic 2012]
When the biodiversity is high, the chance that a plant will disturb or alter the ecosystem is very high
and it will be difficult to build in that area. But when, for example, the area is very sensitive to
erosion this could also be a big problem.
Furthermore, a hydropower plant will slow down the flow but this does not necessarily have to
bring the regime or the species structure in danger. It can even attract organisms which prefer
slower or calmer streams and sandy and muddy sediments. Due to the water that is stocked, even
bigger organisms can develop. But then again, sensitive or protected species have to be accounted
for. It has to be determined how vulnerable they are to those changes.
If it seems necessary to take every organism of the ecological environment into account the
following changes should be monitored and analysed: Sediments, transparency, thermal
homogeneity, organic matter content, oxygen regime, nitrification, and depositional regime. This is
because a change in one of these factors has an effect on the biodiversity and therefore on the
ecology.
Unfortunately, the ecology is not all about the organisms and the biodiversity. The landscape has to
be taken into account as well. When constructing and using a hydropower plant, the slopes could
become unstable due to trucks or the rising water level when the plant is in use. One solution is to
put retaining walls on the slopes. But that is not just all.
19
The use and build of roads, pipelines and the plant itself could also destabilize the landscape in
many ways. Landslides could occur, intensive erosion could take place, cementation of the area
which can affect the rainwater infiltration and affect the overland flow and several other land
impacts could occur due to the build or operation of the plant.
If a landscape assessment has to take place as well, it should content at least the following aspects:
an evaluation of the sensitivity of the area and analyses of everything that has to be built.
Furthermore, a multiple criteria landscape impact assessment and definition of conflict resolution
measures. These analyses must contain the following aspects: natural factors (how to minimize
negative impact on the area), stakeholder analyses, visual sensitivity and the possibility of
mitigating the impact (undo the negative impacts).
So the best solution to the ecological conflicts is to study the impacts of the construction of the
plant on landscapes in which all possibilities and limitations for carrying out projects have been
analysed as well as the methods to overcome the conflicts. So in short defining the problem and
creating solutions in which all parties are satisfied is the best way to counter and minimize
ecological problems.
In case of the Salzach River hydropower plant the best way to preserve the fish is described above
as the universal opening in the block ramp [Brinkmeier & Aufleger 2010]
20
Discharge
“How does the natural discharge and design flow of the Salzach river and its hydropower plants
develop through the Lower Salzach catchment?”
The natural discharge is the volume of water that is passing though during a certain time unit. In
this pilot study, all discharges are measured in m3/s. To approach the development of the natural
discharge of the Salzach in the study area, it has been interpolated between three points:
Werfen upstream (segment number 11)
Golling in the middle (segment number 25)
Salzburg downstream (segment number 48)
Also, the natural discharges of two tributaries of the Salzach in the study area are known, Obergaeu
and Adnet, see Figure 5.
Figure 5: Locations Measure stations
[http://www.salzburg.gv.at/wasserwirtschaft/6-64-seen/hdweb/2.3.m.html]
In order to calculate the natural discharges of the segments between the known segments, it is
necessary to interpolate, while taking in account the discharges of the two tributaries. Since there
are many small tributaries, a constant increase of discharge of the Salzach river is plausible, except
for the two bigger tributaries where the measure station Obergaeu and Adnet are located. The
segments where those two joined the Salzach, their discharges were simply added.
Figure 6: Mean natural discharge Werfen 2012/2013
[http://www.salzburg.gv.at/wasserwirtschaft/6-64-seen/hdweb/stations/204032/station.html]
21
The measure station in Werfen, segment number 11, noted a mean natural discharge of 120 m3/s, see
Figure 6. Golling showed 150 m3/s and Salzburg 190 m
3/s. Since the tributaries have a mean natural
discharge of 18 m3/s (Obergaeu, segment 23) and 8 m
3/s (Adnet, segment 34), the results in Table 1
were calculated. The yellow numbers show the locations of the measure stations, the blue numbers
the segments where the tributaries join.
In this pilot study the assumption was made the design flow depends on the width of the river. The
depth is also important, but the depth data is unavailable. Since the width of the river is proportional
to the depth, the assumption should nevertheless be valid. The design flow of all the existing and
future plants in and near the study area is known, so the unknown segments were again interpolated,
taking into account the width of the river. First, the ratios between the design flow of the plants and
the width of the river at those points were calculated. To calculate the missing design flows, the
width of the river per segment was multiplied to the average ratio of five segments above the
missing segment, and five segments below. The results are also shown in Table 1, the yellow
numbers are the known design flows.
Table 1: Characteristics of the river segments [done with ArcGIS/Microsoft Excel]
Segment number Mean Natural Discharge Design flow Segment number Mean Natural Discharge Design flow
1 111,3 186,5 28 154,2 221,3
2 112,2 149,4 29 155,6 186,8
3 113,1 198,3 30 157,0 215,5
4 113,9 202,0 31 158,4 258,6
5 114,8 135,1 32 159,8 175,0
6 115,7 163,8 33 161,2 258,6
7 116,5 194,0 34 170,4 143,7
8 117,4 146,6 35 171,8 230,0
9 118,3 166,7 36 173,2 215,5
10 119,1 200,0 37 174,6 238,5
11 120,0 179,1 38 176,0 258,6
12 120,9 92,5 39 177,4 250,0
13 121,7 210,3 40 178,8 172,4
14 122,6 253,8 41 180,2 158,1
15 123,5 163,1 42 181,6 192,5
16 124,4 170,4 43 183,0 195,4
17 125,3 163,1 44 184,4 258,6
18 126,1 203,0 45 185,8 221,3
19 127,0 102,4 46 187,2 250,0
20 127,9 66,3 47 188,6 250,0
21 128,8 45,2 48 190,0 238,5
22 129,6 180,8 49 191,4 221,3
23 148,3 168,1 50 192,8 229,9
24 149,2 215,5 51 194,2 250,0
25 150,0 273,0 52 195,6 241,4
26 151,4 229,9 53 197,0 235,6
27 152,8 227,0
22
“How does the rising water level due to the new hydropower plant and the design flow affect the
flood risk and what solutions are possible?”
The plant will be constructed in a way that it serves the area for energy and, taking into account the
amount of hydropower plants, limits the gross head. Approximately, the plant will have a gross head
of five meters, so the water level will rise by only 2.5 meters.
During the fieldtrip the top three locations were visited and appeared to be properly able to handle
such a rise, even when taking into account the variations in water level through the year (see Figure
7).
Figure 7: Possible location hydropower plant near Golling [own photograph]
During regular situations there should not occur problem concerning flood risks, but handling flood
peaks is another story. A study in 2005 [ASSANI ET AL. 2006] assessed the impact of dams on annual
maximum flow characteristics in three types of flow regimes. The regime that applied to this pilot
study is the natural type. This type is often associated with run-of-river hydropower plants.
Table 2: Changes to maximum discharges due to hydropower dams [ASSANI ET AL. 2006]
23
According to the table very little change has occurred to the maximum discharges. There is no
change in the timing, or in the magnitude. The frequency of the annual maximum discharges in
December and January were slightly increased. The coefficient of “skewness” (Pearson coefficient)
resembles the changes in the shape of the distribution curve of the rivers. For the natural type there
is a weak change, meaning the distribution gets a bit disturbed. [ASSANI ET AL. 2006]
Based on the table above, we can conclude a significant increase in flood risk is not realistic.
Massive flood peaks could however exceed the design flow and the hydropower plant could
function as an obstacle. A solution for this problem is to create gates in the hydropower plant, which
could open when there is a flood peak.
24
Optimal Location
“What is the optimal location taken into account the several factors?”
The first factor taken into account is the presence of the existing and future run of river hydropower
plants [Figure 8]. With this analysis it’s possible to decide which segments of our river are potential
locations for the new run of river hydropower plant. The minimum distance between two
hydropower plants will be two segments, because this is the smallest distance between two
hydropower plants obtained from the existing and future ones. The results of this analysis are three
parts of the river: 13 to 15 (1), 21 to 29 (2) and 42 to 44 (3). Those three parts are further analyzed
to get the optimal location for a new hydropower plant.
The second factor taken into account is the
design flow of each segment. When we sort
the remaining segments based upon the design
flow, the segments with the highest design
flow are 25, 44, and 14.
The third factor taken into account is the
political feasibility. These criteria won’t allow
it to build the new run of river hydropower
plant inside a city, because many people are
against it due the increase in flood risk. There
will be two segments remaining because of
this factor: 25 and 14.
With those two remaining segments, the fourth
factor taken into account is the shape of the
river. The shape of the river should be straight,
so speed can build up very easily. With these
criteria the optimal location will be 14 and last
will be 25.
Figure 8: Distance between power plants
[Done in ArcGIS]
The fifth factor is the highest natural discharge. This natural discharge is higher at segment 25 than
on segment 14. This means that a new hydropower plant in segment 25 will have a smaller dam to
create the same capacity as a new hydropower plant in segment 14. Because of this, segment 25 is
preferred due to the lower flood risk.
The sixth factor is the width of the river. This is important, because there should be enough space to
build the new hydropower plant with his turbines. The width at segment 25 is about 95 meters,
while the width at segment 14 is about 70 meters. So again, segment 25 is preferred.
Therefore, the optimal location for a new run of river hydropower plant will be segment 25. This
segment is about 1.3 kilometers long, so where exactly is the location of the new run of river
hydropower plant along segment 25?
1
2
3
25
The exact location of the new hydropower plant
will be just before the corner at the end of segment
25 [Figure 9]. Here it’s possible to build a new
hydropower plant and the speed of the water can
build up very easily, because the segments 23 and
24 are pretty straight. Beside this, a tributary is
joining the Salzach between segment 22 and 23. So
the discharge is increasing with 7.88 m3/s at that
point.
Figure 9: Optimal location [Done in ArcGIS]
The optimal location
26
Optimal Capacity
“What is the optimal capacity of the new run of river hydropower plant?”
To get the optimal capacity the formula that will be used is devised by BASSO, S. AND G. BOTTER
[BASSO, S. AND G. BOTTER. 2012]. The formula is as follows:
𝐸(𝑄) = 𝜌𝑔𝜂𝑝∫ 𝐻(𝑡)𝜂 (𝑞𝑤(𝑡)
𝑄) 𝑞𝑤(𝑡)𝑑𝑡
∆𝑇
0
The optimal capacity of the new run of river hydropower plant is dependent of the characteristics of
the Salzach river and some manmade characteristics. The first category will be called natural
characteristics and the second category human characteristics. The natural characteristics include
three variables and the human characteristics include four variables. The three natural
characteristics are fixed, so the only things we can change are the four human variables.
First, the natural characteristics of this formula will be explained. The ρ is the density of water. This
variable is constant along the river, namely 1000 kg/m3. The next variable is g, this is the gravity.
For this variable is 9,812 m/s2
used. The gravity is also constant along the river. The last natural
variable is qw(t). This is the natural discharge in m3/s. This natural discharge will increase if you go
downstream, because several streams are joining the Salzach along the river.
Beside this, the Salzach has gone through a bigger part of the catchment, so more water has joined
the river. This variable changes along the river, so we need to know the natural discharge on every
separate segment along the river. The numbers derived from the discharge section will be used in
the formula. Those natural characteristics can’t be changed by humans, so those variables will be
fixed in this analysis.
Second, the human characteristics of the formula will be explained. The variable ηp contains the
efficiency of the hydropower plant as a whole. This number shows how many energy is lost by the
conversion from kinetic energy to electrical energy. This value will be 66.17%. This number is
derived by VAZ, C., AND A. FERREIRA [2012], with looking at several run of river hydropower plants
and decide the bias corrected efficiency. This one is for every run of river hydropower plant
different, but it is fixed in this model as a simplification. The next human variable is H(t). This is
the hydraulic head at one moment in time. This is the difference in height between the height of the
dam on the top of the hydropower plant and the bottom of the hydropower plant just after the dam
of the hydropower plant. This variable is per existing and future hydropower plant different.
The lowest head is found at hydropower plant Gamp with a total head of 6.22 m. The highest head
is found at hydropower plant Urstein with a total head of 11.15 m. This variable will decide how
many water can be stored to put it through the turbines. The head is also dependent on the
environment of the location of the hydropower plant, because the head should be at the height,
where the risk of flooding for the environment is the lowest. This variable will be the only one
which can be changed in the model to make the capacity increase or decrease.
The third human variable is η. This is the efficiency of the turbine that is used inside the
hydropower plant. This one is derived to look at the actual annual energy production in MWh of the
existing and future hydropower plants. Then the mean of those efficiency rates is used to decide the
capacity of the new hydropower plants. This is 0.4727. This number isn’t the best number, but it’s a
good estimation according to the existing and future run of river hydropower plants. The final
human characteristic is Q. This is the design flow.
27
To get this variable for the segments without a hydropower plant the maximum plant discharge of
the segments with an hydropower plant and the width of the river are used to derive this variable.
The only variable left is T. This is the time in which the E(Q), optimal energy production, is being
produced. This variable is set to 1 second. The unit in which E(Q) is expressed is W/s. So to get the
annual production in MWh this number is multiplied with 60, 60, 24 and 365,25 and then divide by
a billion.
This model is used to get the optimal supply of the new run of river hydropower plant. This supply
is based upon how many people the new run of river hydropower plant will serve. To derive this
demand the annual energy production in MWh per person for the province Salzburg is used. This
number is available for the period from 2003 to 2010. The mean of those numbers is used to get the
yearly demand in MWh per person for the Salzburg area:
Values J by person MWh by person
2003/2004 8470000000 2,352777778
2005/2006 7980000000 2,216666667
2007/2008 8250000000 2,291666667
2009/2010 8110000000 2,252777778
Mean 8202500000 2,278472222
Table 3: Statistical values on energy consumption [Statistics Austria 2013]
This number is multiplied with the inhabitants per municipality to get the demand per municipality
for the Salzburg area. The optimal location taken into account the several factors that are explored
in the chapters above will be segment 25. This location is between Golling an der Salzach and
Kuchl. Therefore, the new run of river hydropower plant will serve the following municipalities:
Sankt Koloman, Kuchl, Scheffau and Golling an der Salzach.
Those municipalities will be served, because these lay around the location of the new run of river
hydropower plant. There are living 13874 people in this area, so the total demand per year for this
area is 31610 MWh. But with a growing population the demand per year will eventually rise. To
solve this problem, the population in 2012 is compared to the population in 2001 to get the
population change during this period. This number is multiplied with 5 to get an estimation of the
population change in about 50 years. This number is multiplied with the mean of the annual energy
production in MWh during the period from 2003 until 2010. This number is the possible rise in
energy production in MWh in about 50 years. This is about 8225 Mwh. So when we add this
number to the actual demand, the demand over 50 years is derived. This is 39835 MWh per year.
The capacity of the new run of river hydropower plant will be based upon this capacity.
When the models to decide the supply and the demand are combined, the design of the new run of
river hydropower plant could be derived. Therefore, the model to decide the optimal supply will be
fill in to get at least the possible demand over 50 years. The only variable that will be adjusted to
get this number is the gross head (H). This will be set as low as possible to minimalize the risk of
flooding in the area around the new run of river hydropower plant, but the gross head will be that
28
high that the hydropower plant still is capable to serve the four municipalities over 50 years.
So when the gross head is set to 5.5 m, the optimal capacity will be 43903,1 MWh per year:
E(Q) ρ g ηp ∆T H η qw Q Wh MWh Mwh/year
1011785,217 1000 9,812 0,6617 1 4 0,4727 150,0 273,0 3642426781 3,6 31929,5
1264731,521 1000 9,812 0,6617 1 5 0,4727 150,0 273,0 4553033476 4,6 39911,9
1391204,673 1000 9,812 0,6617 1 5,5 0,4727 150,0 273,0 5008336824 5,0 43903,1
1517677,825 1000 9,812 0,6617 1 6 0,4727 150,0 273,0 5463640171 5,5 47894,3
With this capacity the new run of river hydropower plant can serve the four municipalities at least to
2063. The new hydropower plant will have than an overcapacity about 4000 MWh per year, but this
will be used to create a buffer for fluctuations in the demand, because the model to derive the
demand has several uncertainties.
One small part of the design of the new run of river hydropower plant is now known. But to derive
the total building costs many more parts should be known. For the total building costs the article by
Ogayar et al. [OGAYAR ET AL 2009] is used. This part of the study will be done in the actual research.
29
Planning and Critical success factors
Because of the lack of time it is important to expand the study and stretch it over at least a year. The
locations of the other plants are easy to locate and account for. But the effect of the other plants per
distance unit is yet to be investigated. The location has partly been chosen based on the largest
distance between the plants, but it is not perfectly clear which effect occur when the distance is too
small.
This brings us to the next factor, the curvature of the river. The effect of a curve in the river is very
important to measure. According to Dr. Strobl the plant needs the most free flow it can get. This
free flow is influenced by many factors from which three of them are the curvature and gradient of
the river and the effect of the other plants.
The effect of the gradient in the river is also important for the efficiency of the plant. We know that
the higher the gradient, the more efficient the plant is, but we don't know yet what the exact
influence is.
Furthermore, the effect of the discharge has a big influence on the generation of energy. This is the
main factor that is the most important factor. However, this discharge varies a lot over the year. The
plant has to account for these changes along with a maximum and minimum discharge. This has to
be measured at the exact location in segment 25 for at least a year.
The width of the river is easy to determine. The wider the river the more turbines will fit and the
bigger the plant can be. This means a higher energy generation and efficiency. It’s basically just a
matter of finding the widest part and then compensating other factors.
The biggest problem with the plant is the depth of the river, since it varies as much as the discharge
does. The depth of the river has an effect on the width and sediment load of the river. The depth
variation also has to be monitored over at least a year due to the seasonal difference in precipitation
and melting.
This brings us to the next factor which is the sediment load. The sediment does basically not have
an effect on the location itself, rather does it influence the design, efficiency and costs of the plant.
The bed load changes with the width, depth, velocity and discharge variances. The Meyer-
Peter/Muller formula could be helpful to derive the bed load, but the input data has to be monitored
over a period of a year at least as well.
When it comes to the presence of protected and residential areas it’s mainly an issue of checking
which areas are allowed to build in and which ones aren’t. Since the river-zone isn’t really part of
the surrounding protection zones, it appears not to be that much of an issue. Solving conflicts with
the opposing parties around the topic could take some time since most of the environmental groups
are strictly against new power stations.
The plant will also get the water level behind the dam to rise, which will result in higher flooding
risks. A map has to be made of the projected area that will possibly be flooded during extreme
situations in order to determine possible risks and solutions.
More information has to be gathered about the costs. For instance, the efficiency is depends on
sediment load. The more bed load, the higher the costs to prevent the sediment from entering the
turbines.
30
The bypass routes for the fish will also depend on the amount of fish in the river. We will need the
growth of the fish population as well as the current stock and migration patterns. This will take at
least a year as well, because of the seasonal habits of the fish.
And last but not least the energy supply has to meet the demand, this has to be done by making a
projection of the growth of the population and demand in the area. The plant has to be able to
supply all the inhabitants of the planned area for at least 50 years, which seems to be possible just
fine. Nevertheless the loss of energy due to transport has to be calculated, which can be done by
determining the efficiency of the particular power lines.
31
Overall Conclusions and Recommendations
Based on all the factors described in the methodology of this pilot study, the best location is in
segment 25. In this segment the following characteristics are optimal:
Distance to other hydropower plants,
Gradient,
Design flow,
Political feasibility,
Natural discharge
Width of the river
The plant could be built just before the curve, because in or beyond the curve the free flow would
lose velocity, so a straight flow is preferred. The natural discharge and the design flow are, as
mentioned above, optimal at the chosen location. Thanks to the high design flow and the width of
the river, it is unlikely the flood risk will rise due to the new power plant. Also, as stated in the pilot
study, changes in the annual maximum discharges are not likely to occur.
The solution for the problem with the bed load of the river and the avoidance of the discharge
disturbance lies mainly within the design of the plant. The sediment is kept out of the plant by
placing block ramps with openings through which sediment can safely be transported downstream
of the plant. There are also sluices in between the turbine intakes for the transport of sediment past
the structure.
Luckily the river is not part of a protected area so there will not be a conflict about that. In case the
fish want to pass the plant it can also use the opening in the block ramps or a small artificial bypass
river could be built. There are good examples on how to implement such a bypass, for example in
places like Sohlstufe Lehen. Other conflicts about sensitivity of the biodiversity or certain species
can be monitored, defined and tried to solve by taking the appropriate measures. These measures
depend on the conflicts that are observed, so nothing detailed can be stated about that now.
Although the building spot isn’t in a protected area, nevertheless there could be some negotiation
with environmental organizations necessary. Pretty much every group active in the Salzach area is
very strictly against building a new power station, no matter where. But since there are international
climate goals to fulfill and there is a strong direction pro hydro power, there will be new power
stations so the main discussion really needs to be on where the fit in best in terms of environmental
protection and nature conservation.
Furthermore, the optimal capacity is approximately 43900 MWH per year at a gross head of 5,5
meters. With this capacity the plant is able to serve the population (shown in the chapter on optimal
capacity) until 2063 under the current population growth. The plant even has a capacity-surplus of
about 4000 MWH per year, which serves as a buffer for fluctuations in demand and supply.
We suggest that a team of four members should further investigate this topic, one member should
specialize in the ecology of the river environment. One should be specialized in the design of the
structure, and another on focus on the hydrological characteristics of the river. Last but not least one
person is needed, which can deal with the opposing parties, whom are in favor or against the new
power plant. Of course it would be best, if there is proper knowledge in using GIS – Systems.
32
Literature
ASSANI, A., E. STICHELBOUT, A. G. ROY AND F. PETIT [2006]: Comparison of impacts of dams on the annual
maximum flow characteristics in three regulated hydrologic regimes in Quebec (Canada). In: Hydrological
Processes, Issue 20. Page 3485 –3501.
BASSO, S. AND G. BOTTER [2012]: Streamflow variability and optimal capacity of run-of-river hydropower
plants. In: WATER RESOURCES RESEARCH, VOL. 48.
BOLLAERT E. F.R., P. HELLER AND A. J. SCHLEISS [2010]: Comprehensive system analysis of a multipurpose
run-of-river power plant with holistic qualitative assessment. In: International Journal of River Basin
Management, 8:3-4, Page 295-304.
BRINKMEIER B., AUFLEGER M. [2010]: Bed Load Transport Processes at River Flow Power Plants.
Hydraulic Model Test for the Lower Salzach River. In: River flow 2010. Bundesanstalt fur Wasserbau. Page
1253-1258.
CHECKLAND P., [1999]: Systems thinking, systems practice. Wiley. Chichester. In: HARWOOD I. A., P. S.
KEMP, L. J. WATKIN AND IAN D. WILLIAMS [2012]: Managing Sustainable Development Conflicts: The
Impact of Stakeholders in Small-Scale Hydropower Schemes.
CHECKLAND P., Scholes J [1990]: Soft systems methodology in action. Wiley. Chichester. In: HARWOOD I. A.,
P. S. KEMP, L. J. WATKIN AND IAN D. WILLIAMS [2012]: Managing Sustainable Development Conflicts: The
Impact of Stakeholders in Small-Scale Hydropower Schemes.
CRNCEVIC T., JOSIMOVIC B.,[2012]: The development of renewable energy capacities in Serbia: Case study
of three small hydropower plants in the “Golija” biosphere reserve with special reference to the landscape
heritage. In: Journal Renewable Energy 48 2012. Elsevier. Page 537-544.
DOKA [2012]: Schwanenhälse über der Salzach: Form und Funktion in Perfektion. See:
http://www.doka.com/web/newsroom/news/Kraftwerk_Lehen.de.php?&startPageLanguage=DEINT [Found
06.04.2013]
ERNEUERBARE ENERGIE OSTERREICH [2012]: Wasserkraft. See: http://www.erneuerbare-energie.at/wasser
[Found 06.04.2013]
HARWOOD I. A., P. S. KEMP, L. J. WATKIN AND IAN D. WILLIAMS [2012]: Managing Sustainable
Development Conflicts: The Impact of Stakeholders in Small-Scale Hydropower Schemes. In:
Environmental Management (2012), Band 49, Page 1208–1223. Publisher: Springer Science+Business
Media.
HEINRICH BREIDENBACH [2010]: Untere Salzach: Neue Kraftwerke im Schutzgebiet? Politischer Anlauf aus
Bayern für baldigen Baubeginn. See: http://breidenbach-texte-denken.at/reisen/2010_sf_34.html [Found
02.04.2013]
KLEINWASSERKRAFT ÖSTERREICH [2008]: MASTERPLAN Wasserkraft. Österreich ist ein Wasserkraftland
und es gibt noch ein beachtliches ungenutztes Potential. See:
http://www.kleinwasserkraft.at/sites/default/files/masterplan_wasserkraft_2.pdf [Found: 02.04.2013]
LAND SALZBURG [2013a]: HYDRIS ONLINE Messdatenbereitstellung. See:
http://www.salzburg.gv.at/wasserwirtschaft/6-64-seen/hdweb/2.3.html [Found 04.04.2013]
LAND SALZBURG [2013b]: Wasserkraft. See:
http://www.salzburg.gv.at/themen/nuw/wasser/wassernutzung/wasserkraft.htm [Found 06.04.2013]
33
LEBENDIGE FLÜSSE [2013]: Main Page. See: http://www.lebendigefluesse.at/ [Found 04.04.2013]
NATURSCHUTZBUND ÖSTERREICH [2013]: Landesgruppe Salzburg. Personal Interview with Hannes Augustin.
[Interview done on 08.04.2013]
NATURSCHUTZBUND ÖSTERREICH [2013]:Landesgruppe Salzburg. See:
http://naturschutzbund.at/landesgruppen/salzburg/news.html [Found 02.04.2013]
OGAYAR, B., P. VIDAL AND HERNANDEZ, J. [2009]: Analysis of the cost for the refurbishment of small
hydropower plants. Renewable Energy 34, Page 2501 - 2509.
ÖKF - ÖSTERREICHISCHES KURATORIUM FÜR FISCHEREI UND GEWÄSSERSCHUTZ [2013]:
Unsere Anliegen. Gewässerschutz. See: http://www.oekf.at/unsere-anliegen/gewaesserschutz/
[Found 02.04.2013]
ORF[2013]:Kraftwerk – Kein Ersatz mehr für die Natur. See: http://salzburg.orf.at/news/stories/2574319/
[Found: 02.04.2013]
SALZBURG AG [2013a]: Unsere Kraftwerke. See: http://www.salzburg-ag.at/herkunft/anlagen/ [Found
06.04.2013]
SALZBURG AG [2013b]: Unternehmen. See: http://www.salzburg-ag.at/unternehmen/ [Found 06.04.2013]
SALZBURG AG [2013c]: Neue Projekte. See: http://www.salzburg-ag.at/herkunft/neue-projekte [Found
02.04.2013]
SALZBURG AG [2013d]: Energie für 23.000 Haushalte. Kraftwerk Sohlstufe Lehen. http://www.salzburg-
ag.at/herkunft/neue-projekte/kraftwerk-sohlstufe-lehen/[Found 02.04.2013]
SCHÖNAUER S. [2007]: Wasserkraft – eine regenerative Energie? Bund Naturschutz in Bayern ev. See:
http://www.bund-naturschutz.de/uploads/media/Wasserkraft_keine_regenerative_Energie_02.pdf [Found:
03.04.2013]
STATISTICS AUSTRIA [2013]: STATcube — Statistical Database of Statistics Austria. See:
http://statcube.at/statistik.at/ext/superweb/login.do [Found 07.04.2013]
STROBL J. [2013]: Personal interview about the effect of bed load in the Salzach river on the decision-making
process for the location determination of a hydro-power plant. [Interview done on 05.04.2013]
UMWELTDACHVERBAND [2013]: Main Page. See: http://www.umweltdachverband.at/ [Found 02.04.2013]
VAZ, C., AND A. FERREIRA [2012]: Performance assessment of hydroelectric power plants. 4th Workshop on
Efficiency and Productivity Analysis Efficiency in the Health Sector. School of Technology and
Management, Polytechnic Institute of Bragança.
VERBUND ÖSTERREICH [2012]: Mit Wasserkraft aus Österreich zum Erfolg. See:
http://www.verbund.com/cc/de/ueber-uns/strom-aus-wasserkraft/mit-wasserkraft-zum-erfolg [Found
05.04.2013]
VERBUND ÖSTERREICH [2013a]: Das schafft Strom aus Wasserkraft. See:
http://www.verbund.com/cc/de/ueber-uns/strom-aus-wasserkraft [Found: 03.04.2013]
VERBUND ÖSTERREICH [2013c]: VERBUND in Salzburg. See:
http://www.verbund.com/pp/en/region/oesterreich/salzburg. [Found 04.04.2013]
VERBUND ÖSTERREICH[2013b]: Über Uns. See: http://www.verbund.com/cc/de/ueber-uns [Found
06.04.2013]
34
WHIPPLE, K. [2004]: Surface Processes and Landscape Evolution. See:
http://www.core.org.cn/NR/rdonlyres/Earth--Atmospheric--and-Planetary-Sciences/12-163Fall-
2004/AB399ECE-3A76-422B-B4B8-3A2E0C05D4D2/0/4_sediment_transport_edited.pdf
[Found 05.04.2013]