a critical review of our community project introduction...profile in order to provide information...
TRANSCRIPT
Community Development and Education ES6006
Page 1 of 47
A critical review of our Community Project
Introduction
This assignment aims to provide a critical review of our community project. Throughout this
assignment the other two members of the team will be called W and X, to maintain
anonymity. Firstly, an overview of the project will be described, I will then go on to reflect
and critically evaluate the process we went through, the way we worked as a team, the
approach we took in relation to theory and the overall project itself as an example of
community development. Dewey (1933, cited in Smith, 1999 & Twelvetrees 2008) explained
how reflective practice is an active process which allows us to learn from exploring an
experience and developing our ideas to problem solve and improve our future practice.
Overview of the project
As part of the community project, we discovered that my school, a Special Educational Needs
and Disabilities (SEND) school, was in need of work experience (WE) placements for the
Key Stage 4 (KS4) pupils. This community we focussed on was a homogenous, KS4
community within the school, whom had ‘bonding’ social capital due to their strong relations
within the community (Woolcock, 1998, cited in Smith, 2009). They are classed as
homogenous due to their similar status. This community was believed to be marginalised as
they did not receive many business establishments accepting the pupils for WE opportunities.
This was suggested to be due to their SEND title. Thompson (2002) explained that
marginalisation is when a community is actively excluded, which includes physical and social
isolation. To overcome this marginalisation W and X’s mainstream schools were the venues
for action. They offered two pilot WE sessions to two pupils from the SEND school. These
WE links were aiming to gain ‘bridging’ and ‘linking’ social capital between the SEND
Community Development and Education ES6006
Page 2 of 47
school and different communities (Woolcock, 1998, cited in Smith, 2009). These two types of
social capital can generate broader identities and more resources for the community (Smith,
2009).
The pilot sessions were aimed to provide a meaningful WE opportunity in order to improve
each pupil’s self-esteem, confidence and independence, and to give them an insight into
working in a professional setting.
The process we went through
The most integral part of the community project was to conduct a needs analysis to identify
what the community needed. This should have been carried out in the form of a community
profile in order to provide information that could have helped us understand how they needed
support (Twelvetrees, 2008). Due to time constraints, a formal community profile was not
carried out, but I was classed as a ‘personal contact’ from the particular community, therefore
was able to conduct an ‘issue profile’ (Twelvetrees, 2008). An ‘issue profile’ is where some
of the issues the community had were discussed. This allowed us to fully understand what the
community needed and provided us with an analysis as a basis for action. The limitations of
this ‘issue profile’ was that we had not collected first person evidence from the community
themselves.
The pre-planning for the projects initial design was conducted over two meetings (Appendices
1 & 2). Twelvetrees (2008) claimed that the most important part of a project is pre-planning
as it allows all project members to understand the process and the desired outcomes. A logical
framework approach for planning was conducted using the ‘plan down’ approach because the
broad goal had already been decided. However, due to time constraints it was not completed,
Community Development and Education ES6006
Page 3 of 47
instead the basic planning cycle was conducted. Bakewell and Garbutt (2005) acknowledged
that logical frameworks stimulate people to carefully think about the project plan and
objective. Therefore, if we had completed it we may have understood that the project was
aimed more at the personal development of the individuals within the community.
A Gantt chart was produced halfway through the project in order to provide a visual schedule
of when the project started and the aimed completion date, it also included the dates of the
main tasks. The Gantt chart was good for establishing the timeframes however, due to it not
being completed at the beginning of the project, we did not benefit from using it. We found
the dates difficult to read on the chart and it was acknowledged by Jefferies (2009) that the
chart needed updating when any dates were changed. The Gantt chart (Figure 1) showed
evidence that on-going planning was conducted due to the constant monitoring of the project.
The monitoring allowed us to review the project to ensure it was progressing as planned
(Eldred, 2002).
(Figure 1)
29-Jan 18-Feb 09-Mar 29-Mar 18-Apr 08-May 28-May
Planning
Meeting 1 at School A (Emily's School)
Meeting 2 at School A (Emily's School)
Implementation of Work Experience
Evaluation Meeting
Write up reflection
Gantt Chart for the Community Project
Community Development and Education ES6006
Page 4 of 47
Once the overall basis was planned we requested permission for the project via email to our
project tutor (Appendix 3). The feedback expressed concerns about it not being a valid
community project although, it was decided as long as we focused on my school as the main
‘community’ and the other two schools as venues for action to overcome the marginalisation,
then it should be a beneficial community project. This feedback should have alerted us to
think about the overall project outcomes in more depth, which it failed to do. When the
permission was granted, we conducted the project inception event by obtaining permission
from the non-participatory stakeholders (Head Teachers and parents) and the primary
stakeholders (class teachers). Even though the Head Teachers and parents were non-
participatory they held a high importance in this project (Shuman, 2010). Turcotte (2012)
acknowledged that good relations with community stakeholders increase the chance of the
project leaving a legacy.
When working as a group it was important to hold regular meetings. This was to discuss any
business about the project. It was essential to keep records of the meetings as Delephant
(2007) pointed out that they serve as an important communication function. The actions
decided from the meetings were added to our group action plan (Appendix 4) which
emphasised the time various tasks needed to be completed by and who was assigned
responsibility for them (Levi, 2011 & Eldred, 2002). Two of our group members always
completed the action points before the assigned deadline, however one member needed
reminders. The reminders were carried out in a humorous way to avoid conflict. The action
plan was supposed to be shared with the community members, however we did not conduct
this due to their level of needs. I found our meeting minutes and action plan highly useful to
continuously check what we had recently discussed and what action was needed. We shared
out the role of taking the meeting minutes as we discovered that the person who was
Community Development and Education ES6006
Page 5 of 47
completing the minutes was unable to say as much during that meeting. In a formal meeting
the role of taking the minutes is usually carried out by someone who is not involved, therefore
their input is not needed (Holder, 2005), this would have been more beneficial. For each
meeting, formal agendas should have been devised, but we decided against them as we found
them time consuming. We each attended the meetings with our own informal list of topics
and this enabled us to be actively engaged in the meetings. We conducted one formal agenda
throughout the project, this was used for the evaluation meeting so the community members
understood the timetable of the meeting (Appendix 5).
The way we worked as a team
Tuckman (Tuckman & Jenson, 1977, cited in Beck & Purcell, 2010) developed a basic model
of group development, he suggested groups inevitably go through these four distinctive
stages. Tuckman and Jenson (1977) discussed how the group stages may not be representable
for small groups, but large groups usually notice the stages. Initially, groups should be in the
forming phase, this phase appeared to happen during our first two group meetings where we
were discussing ideas for the project. This was difficult due to W being absent for the first
meeting, therefore we could not discuss many ideas (Appendix 1). After the second meeting
we had decided a hypothetical idea, so we set up a private community project discussion on
social media to enhance our group interaction (Schuman, 2010).
Secondly, Tuckman suggested is the storming phase; this meant groups should have some
conflict in order to resolve it together and develop into a stronger working team. Conflict is a
normal process of group work and West (2004) agreed by explaining how it adds creativity to
the project. We were aware that not having conflicts was acknowledged as a negative aspect
because the absence of conflict may have indicated that we had a dominant leader who did not
Community Development and Education ES6006
Page 6 of 47
allow conflict or that we all lacked desire to improve our project (Levi, 2011). This suggested
that Tuckman’s theory of group development was not necessarily how all groups develop and
transform. We did however have some frustration, this was when members took a long time
to message back on the technology discussion (Appendix 6) however, we all understood we
each had different commitments therefore we did not allow this to cause conflict. The impact
of the frustration caused anxiety levels to rise in certain project members who needed
organisation.
The third phase ‘norming’ was not recognised in our group as a specific development stage.
Although, the fourth phase ‘performing’, happened quickly for us due to our motivational
drive and organisational skills, this was demonstrated by attending the school based meetings
with the pupils early on in the project (Appendices 7 & 8). We each gained a clear
understanding of the objectives of our project and we hoped it would be implemented at a
high quality level. Due to this need for high quality achievement, we continuously monitored
the on-going project and when we noticed an issue we immediately resolved it (Appendices 9
& 10) (Schuman, 2010).
Throughout the project we did not assign individual roles for each member as we consciously
gained a distributed leadership. Bennett et al (2003, p. 3, cited in Bolden, 2011) defined a
distributed leadership as “a group activity that works through and within relationships, rather
than individual action”. We shared our ideas and concerns and worked together using our
individual areas of expertise to make a final decision (Schuman, 2010). This was best for our
group project because we all had different skills and ideas to work together at a high
performance level. This was classed as social facilitation because we enhanced each other’s
performance (Levi, 2011). This leadership style was opposed to a centralised leadership
Community Development and Education ES6006
Page 7 of 47
where the leader makes the decisions. Kokemuller (2016) acknowledged that a centralised
leadership reduces group conflict. This was not the case in our group where distributed
leadership worked well. Covertly however, it was acknowledged that I held a stronger
leadership role within the group due to being part of the particular community everyday as my
work role.
Belbin (1981-1993, cited in West, 2004) suggested that within any group there will be a
number of different types of individuals. Belbin’s team role theory was discussed and we
believed we were all ‘specialists’ due to having our own areas of specialism in this project.
We agreed with Belbin’s role descriptions that we were dedicated and committed, however
we did not agree that we lacked interest in each other’s subjects. We believed this project did
the opposite because it allowed us the opportunity to gain an insight and interest into each
other’s job roles. It was acknowledged that we had aspects of each team role, but not any
particular identifiable role as defined by Belbin, who insisted that a high performance team
will need a variety of all the roles (Aritzeta, Swailes & Senior, 2007).
The approach we took in relation to theory
Whilst planning the project we believed we were conducting a ‘bottom up’ approach as we
were designing the plan to meet a need. We imagined that the pupils attending the WE
sessions would have gained the ‘bridging’ link with other communities. However, when we
reflected back on the project it was understood that we conducted a ‘top down’ approach
instead (Gilchrist, 2003, cited in O’Connor et al., 2006, p. 120). This was proven by us not
communicating with the community members to find out what they needed. We as the
‘experts’ assumed their needs and asked them to be part of the project. We led the project plan
as dominating ‘experts’ and took ownership of the project (Chitty, 2013). However, it could
Community Development and Education ES6006
Page 8 of 47
be argued that we did address their needs as I hypothesised what the community needed by
being a ‘personal contact’. However, this should have been consolidated and communicated
with them before being carried out.
In relation to community education, the ‘top down’ approach we used was the opposite of
Freire’s (1921-1997) educational method (Smith, 2002). His educational method ‘problem-
posing’ re-formed pupils into critical learners through the use of dialogue with the teacher and
this enabled both pupils and teachers to be active learners (Major, 2014). Freire believed that
pupils could empower themselves by taking responsibility of their own learning and making
sure their education was useful and suited to them, rather than being taught from a curriculum
which was set by the elite (Dugan, 2003). This philosophy of ‘problem-posing’ education was
not carried out in our community project. We did not allow the pupils the responsibility to
experience the planning of the community project, and therefore we did not allow them to feel
a sense of empowerment. We as the elite dominated the plan. However, it could have been
suggested that the pupils in the community would not have had the ability, due to their SEND,
to understand a sensible idea of what they needed within education.
In terms of community development, Rogers (1902-1987) emphasised the importance of
having positive relationships between the teacher and learner in order to facilitate the learning
to the highest level (Smith, 2004). Rogers pointed out that the facilitator needed to be aware
of the learners’ feelings and opinions in order to gain the pupils’ trust and confidence. This
was not carried out, as we were not aware of their opinions about the project and we did not
allow their voices to be heard. Rogers also insisted that the facilitators needed to have an
empathetic understanding of the pupils in order for their learning to increase because they felt
valued and appreciated. Throughout our project, I believe we were empathetic to the
Community Development and Education ES6006
Page 9 of 47
individuals needs and we removed any barriers to their learning experience. The is
demonstrated in the qualitative evaluation data (Appendix 11) which shows they felt valued,
although it could be argued that if an outsider conducted the evaluation the answers may have
been different.
According to Arnstein’s Ladder of Participation (Arnstein, 1969), our community project was
in the ‘non-participatory’ level. This meant that our overall objective enabled us as the
powerholders to educate the participants, instead of allowing them to participate in the
planning of the project. If the legacy of the project continued in the future we would aim to
conduct the ‘tokenism’ level, where the participants would have the ability to express their
wishes. Ruesga and Knight (2013) explained that engagement from the community is
essential as they are the only people who understand what they really need in relation to
community development.
The evaluation of the project took place over a number of different stages. Evaluation is an
important part of a project as it measures the impact of the project and identifies the strengths
and weaknesses (Field, 2003). As part of the formative evaluation we conducted constant
monitoring, this allowed us to reflect, evaluate and improve all aspects of the project. As part
of the summative evaluation we conducted a meeting with the participants, this was
completed by asking them set questions to determine the overall standard of the project
(Appendix 11). After conducting the alternative model to evaluation (Rowlands, 1991, cited
in Smith, 2006), we realised we should have allowed the community participants to conduct
the evaluation themselves which would have allowed them have ownership of the overall
result. This would have also moderated the different perceptions therefore, reducing the bias
of the project evaluation.
Community Development and Education ES6006
Page 10 of 47
The project itself as an example of community development
After reflecting on the project itself I noticed we did not achieve many benefits that a
community project would normally, for example, all of the individuals within the community
should have gained new skills, the project should have enabled the community to have more
of an understanding of community work and all of the members should have also gained a
sense of empowerment and confidence. Due to all of the members in the community not
achieving these benefits it enabled us to question if this project was linked to community
development. At the beginning we envisioned this as a community project because if the
legacy of the project had continued, the WE sessions would have allowed each member of the
community to have benefited from a meaningful WE in the wider community. However, the
WE sessions would have aimed to benefit their individual needs therefore they would have
only gained personal skills. This further demonstrated that this project was more of a personal
development project for certain individuals within the community.
Although this was not an official community project, it was an effective project for a number
of different reasons. Firstly, an in-direct indicator proved that the pupils who completed the
WE had gained some independence and confidence by being able to carry out the role without
needing prompts. From this pilot project, we gained a link at other schools for more WE
sessions in the future. We have created a basic plan providing the suitable times to attend the
WE sessions, risk assessments (Appendix 12) and permission letters (Appendix 13) and any
problems or weaknesses with the WE have been identified and eliminated. The daily WE
feedback sheets (Appendix 14) have also made the professional community within the school
aware of the outcomes of the project for the particular individuals. This has empowered them
to think about carrying on the legacy of this project in the future, by making the WE sessions
Community Development and Education ES6006
Page 11 of 47
with these schools a permanent agreement. Empowerment is the core principle of community
development as it enhances people’s capacity and propensity to influence decisions that affect
them (Community Development Foundation, 2008). This demonstrated aspects of a
community project in the making, but involving the professional community within the
schools rather than the pupils. To improve the project in the future and make it an official
community project we would have to work alongside the community to allow their voices to
be heard, and with our support they would then have the power to decide the overall project
plan.
An unforeseen outcome was identified from the project which did not link to our objective
but, was still seen as a highly beneficial outcome for the professional community. We
facilitated a link between the professional community at my school and X’s school. We have
now prepared for some professionals to visit each school to discuss the different learning
happening. This will hopefully work towards both professional communities having ‘linking’
social capital.
Conclusion
To conclude, the project had many benefits for the individuals’ personal development within
the community. Even though it was not a community project it still had aspects of community
development and it allowed us as a team to work though many factors and roles. It also ended
with many positive unforeseen outcomes which will support the professional communities in
each school in the future. Positive links have been achieved and will hopefully continue in the
future, prior to more pilot work experience session, we hope a legacy of the project will
continue and benefit the individuals within the community.
Community Development and Education ES6006
Page 12 of 47
Word Count: 3262
Bibliography
Abudi, G. (2010). The five stages of team development: a case study. Retrieved April 9, 2016,
from https://www.projectsmart.co.uk/the-five-stages-of-team-development-a-case-study.php
Aritzeta, A., Swailes, S., & Senior, B. (2007). Belbin’s team role model: development,
validity and applications for team building. Journal of management study. 44 (1). P. 96 – 117.
Arnstein, S. (1969). A ladder of citizen participation. 35 (4). P. 216 – 224
Bakewell, O., & Garbutt, A. (2005). The use and abuse of the logical framework. Retrieved
April 17, 2016, from http://www.intrac.org/data/files/resources/518/The-Use-and-Abuse-of-
the-Logical-Framework-Approach.pdf
Beck, D., & Purcell, R, (2010). Popular education practice for youth and community
development work. Exeter: Learning Matters LTD.
Belbin Associates. (2015). Belbin’s Team Roles. Retrieved April 4, 2016, from
www.belbin.com/about/belbin-team-roles/
Bolden, R. (2011). Distributed leadership in organizations: A review of theory and research.
International journal of management reviews. 13(1). P. 251-269. DOI: 10.1111/j.1468-
2370.2011.003.06.x
Community Development and Education ES6006
Page 13 of 47
Chitty, M. (2013). Top down: Bottom up. Retrieved April 17, 2016, from
http://realisedevelopment.net/2013/01/top-down-bottom-up/
Community Development Foundation. (2008). Community developments role in
empowerment. Retrieved April 9, 2016, from http://www.cdf.org.uk/wp-
content/uploads/2011/12/CD-role-in-empowerment.pdf
Community Toolbox. (2015). Increasing participation and membership. Retrieved April 9,
2016, from http://ctb.ku.edu/en/increasing-participation-and-membership
Cupitt, S., & Ellis, J. (2007). Your project and its outcomes. Retrieved April 9, 2016, from
http://www.hcvs.org.uk/resources/yourprojectanditsoutcomes-139-146.pdf
Delephant, A. (2007). Making meetings work. London: Sage Publications LTD.
Dugan, M. (2003). Empowerment. Retrieved April 17, 2016, from
http://www.beyondintractability.org/essay/empowerment
Eldred, J. (2002). Managing community projects for change. Leicester: Adult Continuing
Education.
Field, J. (2003). Evaluating community projects. Leicester: Adult Continuing Education.
Community Development and Education ES6006
Page 14 of 47
Gilchrist, A. (2004). Community cohesion and community development – Bridges or
barricades? London: Community Development Foundation.
Holder, J. (2005). Aspect of minute taking as a profession: Who takes the minutes – where,
why and how? Retrieved April 17, 2016, from
http://org.intersteno.it/materiale/ConferencesVienna2005/DenHolder2005.htm
Jeffreys, J. (2009). Advantages and disadvantages of Gantt Charts. Retrieved April 6, 2016,
from http://www.pmhut.com/advantages-and-disadvantages-of-gantt-charts
Kokemuller, N. (2016). The Advantages of centralised organizational leadership. Retrieved
April 4, 2016, from www.smallbusiness.chron.com/advantages-centralized-organizational-
structure-21410.html
Levi, D. (2011). Group dynamics for teams. (3rd
Ed). London: Sage Publications Inc.
Major, T. (2014). Paulo Freire’s Education for Freedom: implications for teaching-learning
process in Botswana. National Teacher Educational Journal. 7 (1). P. 31 – 36.
O’Connor, I., Hughes, M., Turney, D., Wilson, J., & Setterlund, D. (2006). Social work and
Social care practice. London: SAGE Publications LTD.
Popple, K. (2015). Analysing community work – Theory and practice. (2nd
Ed). Berkshire:
Open University Press.
Community Development and Education ES6006
Page 15 of 47
Ruesga, G., & Knight, B. (2013). The view from the heights of Arnstein’s ladder. Resident
engagement by community foundations. National Civic Review. P. 13 – 16. DOI:
10.1002/ncr.21137
Schuman, S. (2010). The handbook for working with difficult groups. San Francisco: Jossey-
Bass
Smith, M. (2006). Evaluation for education, learning and change – theory and practice.
Retrieved April 18, 2016, from http://infed.org/mobi/evaluation-theory-and-practice/
Smith, M. (2009). Social Capital – the encyclopaedia of informal education. Retrieved April
6, 2016, from http://infed.org/mobi/social-capital/
Smith, M. (2002). Paulo Freire and informal education. Retrieved April 17, 2016, from
http://infed.org/mobi/paulo-freire-dialogue-praxis-and-education/
Smith, M. (2004). Carl Rogers and informal education. Retrieved April 17, 2016, from
http://infed.org.mobi/carl-rogers-core-conditions-and-education/
Smith, M. (1999). Reflection, Learning and Education. Retrieved April 9, 2016, from
http://infed.org/mobi/reflection-learning-and-education/
The Global Fund for Forgotten People. (2016). The issue with marginalisation. Retrieved
April 6, 2016, from http://www.forgottenpeople.org/how-we-help/marginalised-communities/
Community Development and Education ES6006
Page 16 of 47
Thompson, J. (2002). Community education and neighbourhood renewal. Leicester: Adult
Continuing Education.
Turcotte, M. (2012). Engage your community stakeholders. Retrieved April 6, 2016, from
http://nbs.net/wp-content/uploads/Community-Engagement-Guide.pdf
Tuckman, B., & Jenson, M. (1977). Stages of small group development revisited. Group and
organisation management. 2 (4). P. 43 - 48
Twelvetrees, A. (2008). Community work. (4th
Ed). Hampshire: Macmillan Publishers LTD.
West, M. (2004). Effective Teamwork. Oxford: Blackwell.
Community Development and Education ES6006
Page 17 of 47
Appendices
Key
Emily’s school – school A
W’s school – school B
X’s school – school C
Community Development and Education ES6006
Page 18 of 47
Appendix 1 - Meeting Minutes 1 – Community project
Date and Time: 29.01.16 – 12.35pm
Location: University of Gloucestershire Lecture Room
Members Present: X & Emily Morse
Discussion:
Throughout the first session of community development and education practice groups were
given time to meet and discuss ideas for our projects with their group members.
Emily shared ideas about setting up an afterschool club which integrated mainstream children
with Special Educational Needs (SEN) children or a Saturday club to give parents respite and
children time to have fun and be included with mainstream and SEN children. After the
members discussed the logistics of staffing and time constrains of these ideas it was decided
that these would not be suitable.
It was then discussed about doing fundraising events for a local charity ‘The James Hopkins
Trust’. Richard was present and spoke to the members about making a connection with this
charity, enabling trust to be gained and then finding out what they needed may be difficult and
time consuming. So this was decided against too.
After thinking about what community’s may need, Emily explained how her SEN school
needed more work experience provisions for her KS4 pupils, X then said her school may be
able to accept a work experience student as a teaching assistant in her class.
Emily added that she would be there to support the pupil and that the pupil would gain
confidence and a new opportunity and X explained how her school staff and children will gain
more of an insight into SEN.
Emily and X were also thinking W’s school would also be willing to make this link with an
Community Development and Education ES6006
Page 19 of 47
SEN school which would make two provisions for SEN pupils.
As W was absent, Emily said she would contact him with the idea and then arrange to talk
more about this next week when we are altogether.
Action Plan:
Emily to contact W (via a private social media group just for the project members).
X to keep track of the conversation and minute any information/ conversations which took
place during the week via the social media group.
Emily to type up the minutes of the discussion and send it to the members.
Community Development and Education ES6006
Page 20 of 47
Appendix 2 - Meeting Minutes 2 – Community project
Date and Time: 5/2/16 12.30pm
Location: University of Gloucestershire – Lecture room.
Members Present: Emily Morse, X and W
Discussion:
Recapped ideas for project to give W a clearer understanding of proposal so far. W
agreed that the project for linking schools seems a good idea. We all agreed that initial
plans are feasible.
Emily outlined her involvement regarding supporting her pupils in each mainstream
school and the expectation she would have for them. She suggested that a different
pupil visits each school with a different role in each. W suggested a pupil could benefit
from the role of midday supervisor and supporting in his forest school lesson. X
suggested that supporting reading and phonics input in YR/1 class and supervising
continual outdoor provision could be suitable roles. All agreed.
Discussion was then held regarding reciprocal visits. X suggested a visit to each
school would be beneficial to all. W suggested 2-3 work placement visits per pupil
supported by Emily. W and X have set provisional dates to visit School A (Emily’s
School). X suggested to W that a visit to School C (X’s School) could incorporate
Outdoor Learning.
Emily noted that she has a risk assessment for her pupil which can be taken to each
placement.
Rick requested that before groups start work on their project, we send an outline to our
project tutor and obtain contact details of stakeholders for tutor to contact as a courtesy
measure.
All decided to share responsibility for recording minutes of meetings.
Community Development and Education ES6006
Page 21 of 47
Action Plan:
Emily to forward minutes of last week’s meeting to X and W.
X to type and forward minutes for this week.
W and X to obtain permission for project involvement from Head Teachers.
X, W and Emily to obtain schools’ contact details for the project tutor.
X to request permission to visit each school during school hours – 2 afternoons
required.
X and W to find out if risk assessments are required by their schools for workplace
visits.
Emily to arrange consent letter for her pupils.
W to visit School A (Emily’s School) 10/02/16 in own time.
Community Development and Education ES6006
Page 22 of 47
Appendix 3 - Emailed Project Proposal to the project tutor
7/2/16
Dear *****,
Myself, Emily and X have been deep in discussion and have come up with the following
proposal.
Emily works in a special school and has identified a need within that community for
meaningful work experience for her learners.
We are suggesting that the schools in which X and I work would be suitable places for that
experience to take place, thus creating links between the three schools.
In my school I will suggest to my Head teacher that the work experience takes place during
the lunch hour (Midday Supervisor role) and then for the two hours following lunch as a
helper on my Forest School sessions. Both of these activities would be accessible for Emily's
learner and something that they could make a meaningful and experiential contribution to.
X's practice works with younger children and she has suggested voluntary TA work hearing
children read as an activity suitable for Emily's student.
We will all visit each other's schools prior to the work experience itself to establish links and
to ascertain any additional needs/requirements that may be necessary.
If this is acceptable as a proposal we feel that it could have the potential to continue after our
involvement ceases, would form positive links between the three schools and, for the learners
at my and X's school help to normalise the different. Additionally, my Forest School groups
have children with an SEN within them (one with behavioural issues and one with a learning
difficulty) and it may be helpful for them to see and older student with an SEN in a role of
responsibility.
Community Development and Education ES6006
Page 23 of 47
If you have any questions regarding this proposal, please let us know.
W
8/2/16
Hi W, ...and X
Thanks for the introduction to your project. I’ve had a word with Rick as I was concerned that
this may not be a community project at all. That said, I can see the way that it has been crafted
means a win-win all round and Rick had seen this one evolve.
You will need to take care to focus on Emily’s school as ‘the community’ and the other
schools as venues for action that will help to overcome the marginalisation of the community
members. In this way it should stand as a community project rather than an inter-school
activity.
And thanks X for the invitation to join your online group – I look forward to watching the
project evolve on there and through our meetings.
Best wishes
*****
Community Development and Education ES6006
Page 24 of 47
Appendix 4 – Action Plan
Key – school A (Emily), school B (W) & school C (X)
Week / Ref
Objective Action Timescale Responsibility Outcome
1:A Contact W Inform of initial project proposal. Complete by 5.2.16
Emily Get view, opinions or alternative proposal
1:B Agree communication Set up agreed communication methods
Complete by 5.2.16
Emily X
Informal dialogue site Group email for sharing files and information
2:A Obtain Permission for school’s involvement
Individuals to arrange meetings with Head Teachers Discuss involvement and request times and dates for visits
ASAP X W
Permission to be involved in community based project. Agree dates and arrange cover with little or no disruption to hosting school.
2:B Complete risk assessments and check insurances
Clarify risk assessment and insurance requirements and details
12.2.16 X W
Risk assessments completed Insurance policies checked and photocopied for Emily
2:C Consent Letters Compile consent letters for parents of W/E students
12.2.16 Emily Clear and informative consent letter prepared
2: D Visit School A W to visit 10.2.16 W Emily
Meet Emily’s students and discuss suitable activities for W/E visit.
3:A Risk assessment check Complete risk assessments for individual students.
19.2.16 W X
Emily able to complete pre W/E visit administration
3:B Insurance check Check expiry date 19.2.16 W Emily able to complete pre W/E visit administration
4:A Risk assessment and Insurance check
As above Complete by 25.2.16
W Emily able to complete pre W/E visit administration
4:B Visit School A X to visit 24.2.16 X Meet Emily’s student and discuss suitable activities for W/E visit.
Community Development and Education ES6006
Page 25 of 47
Complete induction and risk assessment with student.
4:C Finalise W/E dates Confirm with schools 25.2.16 Emily Complete pre W/E visit checks
4:D Permission letters Send to parents/guardians 26.2.16 Emily Gain permission for W/E visit
5:A Filter induction pack Read through and highlight relevant points; raise any issues concerning student.
Complete by 26.2.16
Emily Clear information regarding safety and wellbeing of visitors to school C; clear understanding and expectations of student.
5:B Finalise visit dates Confirm with HT of school C; inform Emily.
25.2.16 X Administration finalised for visits to school C.
6:A Copy Insurance details Forward to Emily TODAY (26.2.16) W Emily completes pre visit admin.
6:B Visit 1 to School C Accompany student to W/E. 02.03.16 Emily W/E student visit completed. 3hours
6:C Report on visit and provide student feedback
Complete summary report; feedback report; upload to community group.
03.03.16 X Emily
Feedback available to inform student and teacher. Uploaded copy to group available.
6:D Finalise evaluation meeting Agree dates with schools; Arrange times and cover if required; Book room for meeting: Confirm with group members.
Complete by 04.03.16
Group Evaluation meeting date confirmed
7:A Visit 2 to school C Accompany student to W/E. 07.03.16 Emily W/E student visit completed. 3hours
7:B Report on visit and provide student feedback
Complete summary report; feedback report; upload to community group
07.03.16 X Emily
Feedback available to inform student and teacher. Uploaded copy to group available.
7:C Visit 1 to school B Accompany student to W/E. 10.03.16 Emily W/E student visit completed 2 hours.
7:D Report on visit and provide student feedback
Complete summary report; feedback report; upload to community group
10.03.16 W Emily
Feedback available to inform student and teacher. Uploaded copy to group available.
8:A Feedback report Complete feedback; upload to community group
Complete by 18.03.16
W Feedback available to inform student and teacher. Uploaded copy to group available.
Community Development and Education ES6006
Page 26 of 47
8:B Plan tasks for visit Plan W/E tasks for student to promote independent activity
Complete by 16.03.16
W Tasks completed successfully by student with little support required.
8:C Visit 2 to school B Accompany student to W/E. 17.03.16 Emily W/E student visit completed 2 hours.
8:D Gantt chart Complete chart as discussed at group meeting; upload to group email
Complete by 18.03.16
Emily Visual timetable of project available for use by group members.
8:E Action plan Update action plan; upload to group email
Complete by 18.03.16
X Clear record and working document for use by group members.
9:A Feedback report Complete feedback; upload to community group
Complete by 22.03.16
W Feedback available to inform student and teacher. Uploaded copy to group available.
9:B Evaluation meeting agenda Complete and upload to group files
Complete by 22.03.16
X Group members able to check details prior to meeting
9:C Student evaluation form Complete questionnaire for evaluation meeting and upload
Complete by 22.03.16
X Group members able to check details prior to meeting
9:D Meet at school A W/E evaluation 23.03.16 Emily W X
Obtain student feedback. Evaluation of project.
10:A Evaluation Write up final reports and upload 30.03.16 X W Emily
Project documentation finalised
Community Development and Education ES6006
Page 27 of 47
Appendix 5 – Evaluation agenda
Evaluation Meeting: 23rd March 2016 at 1pm: School A (Emily’s School)
AGENDA
1. Group members to discuss feedback reports-
2 per student
2. Welcome students individually and introduce unfamiliar adult
3. Student 1 to
comment on W/E
answer key questions
given feedback
4. Student 2
comment on W/E
answer key questions
given feedback
5. Thank students for their input
6. Group members discuss student feedback
7. Group discussion of project
8. Close meeting
9. AUB
Community Development and Education ES6006
Page 28 of 47
Appendix 6 - Members marking sheet for the community project engagement
Assignment Specific Focus 0-29 Fail 30-39 Resubmission 40-49 Third 50-59 2.2 60-69 2.1 >70 First*
Engagement Engagement in project as an active team member
Very poor attendance. Very weak team player. Disruptive and uncooperative. Weak or no communication No attempt at including others
Erratic attendance. Poor team member. Unreliable and inconsistent. Poor communication. Little attempt at including others
Adequate attendance. Some contribution to the team. Able to complete some simple tasks. Some attempts to communicate with team. Some attempts at including others.
Good attendance. Fair contribution to team activity with some useful ideas. Volunteered to take on some tasks and completed them to a good standard. Regular and effective communication with the team. Good awareness of others with efforts made to make sure they feel included.
Very good attendance. Very good contribution to the team with lots of ideas and motivation. Proactive about taking on tasks and working with others to complete to a high standard. Reliable. Very good communicator with team and others. Very good at making other members feel included.
Excellent attendance. Excellent team player with excellent motivation and the ability to motivate others. Creative and innovative and well aware of what needs doing – works to a consistently high standard. Excellent communication skills with team and other parties involved. Excellent at engaging and including others.
Me (Emily Morse) Very poor attendance. Very weak team player. Disruptive and uncooperative. Weak or no communication No attempt at including others
Erratic attendance. Poor team member. Unreliable and inconsistent. Poor communication. Little attempt at including others
Adequate attendance. Some contribution to the team. Able to complete some simple tasks. Some attempts to communicate with team. Some attempts at including others.
Good attendance. Fair contribution to team activity with some useful ideas. Volunteered to take on some tasks and completed them to a good standard. Regular and effective communication with the team. Good awareness of others with efforts made to make sure they feel included
Very good attendance. Very good contribution to the team with lots of ideas and motivation. Proactive about taking on tasks and working with others to complete to a high standard. Reliable. Very good communicator with team and others. Very good at making other members feel included.
Excellent attendance. Excellent team player with excellent motivation and the ability to motivate others. Creative and innovative and well aware of what needs doing – works to a consistently high standard. Excellent communication skills with team and other parties involved. Excellent at engaging and including others.
Anne McLaughlin Very poor attendance. Very weak team player. Disruptive and uncooperative. Weak or no communication No attempt at including others
Erratic attendance. Poor team member. Unreliable and inconsistent. Poor communication. Little attempt at including others
Adequate attendance. Some contribution to the team. Able to complete some simple tasks. Some attempts to communicate with team. Some attempts at including others.
Good attendance. Fair contribution to team activity with some useful ideas. Volunteered to take on some tasks and completed them to a good standard. Regular and effective communication with the team. Good awareness of others with efforts made to make sure they feel included
Very good attendance. Very good contribution to the team with lots of ideas and motivation. Proactive about taking on tasks and working with others to complete to a high standard. Reliable. Very good communicator with team and others. Very good at making other members feel included.
Excellent attendance. Excellent team player with excellent motivation and the ability to motivate others. Creative and innovative and well aware of what needs doing – works to a consistently high standard. Excellent communication skills with team and other parties involved. Excellent at engaging and
Community Development and Education ES6006
Page 29 of 47
including others.
Andrew Cox Very poor attendance. Very weak team player. Disruptive and uncooperative. Weak or no communication No attempt at including others
Erratic attendance. Poor team member. Unreliable and inconsistent. Poor communication. Little attempt at including others
Adequate attendance. Some contribution to the team. Able to complete some simple tasks. Some attempts to communicate with team. Some attempts at including others.
Good attendance. Fair contribution to team activity with some useful ideas. Volunteered to take on some tasks and completed them to a good standard. Regular and effective communication with the team. Good awareness of others with efforts made to make sure they feel included
Very good attendance. Very good contribution to the team with lots of ideas and motivation. Proactive about taking on tasks and working with others to complete to a high standard. Reliable. Very good communicator with team and others. Very good at making other members feel included.
Excellent attendance. Excellent team player with excellent motivation and the ability to motivate others. Creative and innovative and well aware of what needs doing – works to a consistently high standard. Excellent communication skills with team and other parties involved. Excellent at engaging and including others.
Community development and education – Practice ES6006
Page 30 of 47
Appendix 7- Meeting Minutes 3 – Community project
Date and Time: 10.2.16 1.15pm
Location: School A (Emily’s School)
Members Present: Emily Morse, W
Discussion:
The meeting was arranged to enable W to meet and introduce himself to Emily’s students in
advance of the work experience/community project.
Items discussed were:
additional risk assessments needed
details of host schools (School B and C) insurance policies
the nature of the work experience: Midday Supervisor and Forest School helper
Which students would benefit most from undertaking the work experience (to be
decided by Emily and the class teacher.
The meeting was constructive and allowed the students and W to become acquainted
Community development and education – Practice ES6006
Page 31 of 47
Action Plan:
W to type up the meeting minutes of this visit.
Emily to type up the permission forms for pupils parents.
Emily to discuss with the class teacher to decide what pupil is suitable.
W to find the expiry date of the school insurance policy.
Community development and education – Practice ES6006
Page 32 of 47
Appendix 8 - Meeting Minutes 6 – Community project
Date and Time: 24.02.16 12.45pm
Location: School A (Emily’s School)
Members Present: X & Emily Morse
Discussion:
Discussed the induction pack for pupil visiting School C (X’s School). Emily to read
through thoroughly and raise any issues at next meeting.
X was introduced to staff and students including work experience student.
X talked through W/E expectations with student.
X, Emily and student discussed and prepared a risk assessment for the visit and
preliminary section of induction. Most to be completed at time of first visit.
Provisional dates arranged for W/E visits.
Date of next meeting 26/02/16 at FCH room HC105. Time TBC.
Meeting closed.
Student offered to accompany X on unofficial school tour.
Action Plan:
Emily to filter induction pack ready for discussion at next meeting
X to confirm WE dates ASAP and email confirmation to Emily
X to type up Risk assessment and email to Emily ASAP
Community development and education – Practice ES6006
Page 33 of 47
Appendix 9 - Work experience session 1 – W’s school
The student from Emily’s school arrived promptly at W’s school at 12.30pm ready for his
first session of work experience. The student went straight into the playground where the
pupils were out for their lunch time break. W had a short conversation with the student about
the way the pupils were engaging in child-led play during this lunch break. The student stayed
next to Emily for the 15 minutes outside and did not engage in any of the pupils.
The pupils were asked to line up at the door in which Emily and the student followed them
into the classroom. The student sat next to Emily and W introduced them both to the pupils.
The student stayed sat next to Emily whilst the register was being taken and a discussion of
forest school was taking place. The pupils were asked to go to the hall to get changed for
forest school, the student and Emily sat outside the hall and waited until they were ready to
go.
W let us know that the pupils took a lot longer than usual to get ready for forest school
therefore the session was running late (which may cause a time issue as the student and Emily
had to leave earlier to allow time to get back to school). The class left the school at 1.45pm to
walk to the forest school site (10 minute walk away). The student was asked to carry the first
aid bag to the site and to walk at the back of the line to ensure all the pupils got to the site
safely. The student walked alongside Emily and did not support/ speak to the pupils. The
student found the walk difficult (due to asthma).
When arriving at the forest school site at 1.55pm and sat round to wait for instructions on
what the session would involve. The student was told by a teaching assistant that they she was
Community development and education – Practice ES6006
Page 34 of 47
going to carry out a safety sweep of the site to look for any dangerous items, Emily prompted
the student to go and help and he followed her around but did not find anything dangerous.
The pupils were told to make a model of the forest school site using natural resources. The
student was prompted to find natural resources by Emily in which he would not do alone,
Emily had to gather these resources alongside him. When he had a few resources, Emily
prompted him to go and take these to a group of pupils to see if they needed them for their
model. The student needed many prompts to take the resources to the group of pupils and
when he did he did not speak to them, he just held the resources out so the group could take
them.
The student and Emily had to leave at 2.05 in order to have time to walk back to the school
site and drive back to school before the end of the day, therefore there was not many
opportunities for the student to support the activities at forest school due to time constraints.
The student expressed how much he enjoyed the experience, however Emily was concerned
as to how much he benefitted from this session due to time issues and child-led activities
which the student did not feel confident to engage in.
Community development and education – Practice ES6006
Page 35 of 47
Appendix 10 – Feedback from session 1 at W’s school
Feedback report on Work experience session 1. W’s school.
Context: Playground at lunchtime, whole school, Midday Supervisory role Time 12.30-13.00
Student arrived, with Emily, on time and suitably dressed.
Student joined W in playground
W briefed student about MSA role
Student was introduced to any child that asked who he was
No opportunity for the student to fully engage in role arose
Student stayed close to Emily due to low confidence
Student displayed interest in MSA role but not able to engage with children or activities due to short
time-frame (30mins) and low self-confidence
Context:
Preparing for Forest School session – 11 children, 2 FS assistants, one Learning Support, student
W took student and group of children to classroom
W explained ethos of ‘child-led learning through play’ to student and informed him of the
expectations of his role in the day’s session – to be on hand if needed but to allow the
children to ‘go their own way.’
W introduced student to children, explained why he was there (student stayed close to Emily
but engaged a little with children)
Took children to get changed, W told student he could stay outside of room if it made him
feel awkward to be there when children changing. Student chose to stay outside.
When children were ready, student asked to carry first aid back and to supervise end of line
on walk down to FS base camp
Student receptive to direction, showed enthusiasm for Forest School
Context:
Forest School base camp
Time 13.30-14.30
On arriving at site, W made student aware of safety issues (proximity to water, boundary of
site).
Student was aware safety issues.
Session activity began (make 3-d model of the base camp using natural resources)
Student seemed reluctant to move away from Emily, possibly anxious?
Emily asked student if he would like to collect sticks for the children to use in their models.
Student collected some wood but not confident in his interaction with children
At end of session W thanked student for coming – student expressed that he had enjoyed
the experience and was looking forward to coming again.
Emily and student left.
Community development and education – Practice ES6006
Page 36 of 47
General comments
Student was friendly and polite. He displayed a professional approach but, due to low self-
confidence, was not able to take a pro-active role with the experience. He was friendly towards the
children but did not actively seek to engage with them.
On reflection, W had not considered the structure of the work experience in relation to the student’s
social skills, only his physical ability. The student was reluctant to leave Emily but, due to this, he was
unable to access a meaningful experience. We have no doubt that he enjoyed the session. The time
considerations were significant in their limiting influence – the student had no opportunity to ease
himself into the work on offer, something that needs considering for future sessions.
For the follow-up session, W will have specific tasks ready for the student to complete.
Community development and education – Practice ES6006
Page 37 of 47
Appendix 11 - Evaluation of Work Experience Project questions for Students W’s school
What did you do at your work experience placement?
Helped with the children at Forest School, looked after them and helped W with tasks.
What skills did you use?
Listening skills and confidence building.
How did you feel about the first session?
I felt ok – I helped by carrying the First Aid bag and by collecting sticks to help the children
build their 3d model of Forest School.
How did you feel about the second session?
It was at a different place and I helped with the safety check, taking photographs and talking
with the other adult assistants.
What would you like to have done?
Just Forest School
What did you enjoy the most?
I enjoyed all of it and I felt comfortable being there.
What did you not enjoy?
Missing the hot chocolate!
Community development and education – Practice ES6006
Page 38 of 47
If it was possible, would you like to do more sessions?
I would like to continue doing the work experience.
What could be changed to make it better?
Making the sessions longer.
Is there anything else that you would like to say about your work experience?
[No response]
Evaluation of Work Experience Project Questions for Student (X’s School)
What did you do at your work experience placement?
Reading; 1-1 support in phonics; observing in PE.
What skills did you use?
Working with children.
How did you feel about the first session?
It was a bit rushed.
How did you feel about the second session?
More organised session; able to plan and revise a reading activity; Reading the book upside
down was difficult; liked to see children interested in the book and comfortable to ask me
questions.
Community development and education – Practice ES6006
Page 39 of 47
What would you like to have done?
Felt like I was involved with everything.
What did you enjoy the most?
Reading to the children.
What did you not enjoy?
Felt uncomfortable when the children were changing for PE.
If it was possible, would you like to do more sessions?
Yes. For anyone who wants to work with children, it’s an incredible experience.
What could be changed to make it better?
Like to have a longer day.
Is there anything else that you would like to say about your work experience?
No. It was good.
Community development and education – Practice ES6006
Page 40 of 47
Appendix 12 – Risk assessments
PLEASE ENSURE THAT THIS IS COMPLETED WITH THE CHILDREN
INVOLVED IN THE ACTIVITY (using photographs as stimuli)
Complete this form and return to EVO please
Date completed 24th February 2016 Class YR/1B
Staff member
present X
Activity with
date
Work experience.
TA role.
Number of
children 30
Ratio 4:30
What are the dangers? How can we stay safe?
Car Park – crossing to the entrance no
footpath
Equipment/Resources left on the
floor-trip hazard
Spillages- slip hazard
Use of class equipment/resources
Outdoor classroom-pollution in play
areas-particularly sand & gravel pit
Be aware of moving vehicles
Tidy away
Clean up
Student supervised at all times
Check before children use it – if
necessary call staff member and keep
children away.
Community development and education – Practice ES6006
Page 41 of 47
Signature of Teacher
HLTA X
Name of Teacher HLTA X
Date 24/02/16
Community development and education – Practice ES6006
Page 42 of 47
Appendix 13 – work experience permission letter
Dear Parents / Carers,
As part of our Work Related learning programme in Key Stage 4, we like to give our
students the opportunity to experience work in a real-life setting.
I recently have made contact with a local mainstream school to see if a student from
school can attend and complete a work experience as a teaching assistant/ classroom
support worker, the Head Teacher of the school is willing to pilot this with a 2 week
trial (1 morning a week) placement for work experience before deciding if this is
beneficial and appropriate for the students. If this work experience is beneficial we
hope to make a more permenant link with the school. I hope you will support this and
allow your child to attend a trial work experience at this school.
Please find below a placement description, risk assessment and block work placement
form for work experience at ****** School. If you wish your son / daughter to access
this work experience, please sign and return all forms as soon as possible, after reading
thoroughly. It is your responsibility to notify us of any task that you do not wish your
son / daughter to assist with.
Your son / daughter will access a two day placement at this setting.
Thank you for your support in this matter,
Emily Morse
_________________________________________________________________ __________
Placement Description
Contact name-
Student’s details- Name- Dates-
Placement details-
Placement contact-
Job- Teaching Assistant/ Classroom Support worker.
Aims and objectives- To support the school pupils in their activities and to act appropriately as a good role model.
Requirements- Flat and smart shoes and smart/ casual clothing. Working hours- 9.30-12.30 (3 hours)
The student will eat lunch with the pupils in the class or in the staff room at the school.
Community development and education – Practice ES6006
Page 43 of 47
All work experience will be supported on a 1:1 basis by a member of school staff. Students may assist with all or some of the following tasks depending on the individual’s needs and ability to access the task. This will be at the discretion of the supporting member of school staff, and fully supervised at all times. Key tasks:
To supervise the pupils during gymnastics.
To listen to pupils read.
To generally supervise and make sure the pupils are engaged with the lessons.
Transport-Student will be driven to and from placement by the accompanying member of school staff
Employer’s Health and Safety Risk Assessment.
This employer’s risk assessment reflects what the employer has identified as the significant risks and hazards
associated with this placement. It also records the Employer’s control measures, including any prohibited
activities, prohibited locations and personal protective equipment required to minimise these risks. It should be
used in conjunction with the learner’s job description associated with this placement, in preparation for and
during work experience.
The significant risks are:
Lack of knowledge, experience and awareness-Supporting school staff will have a full induction-including
Health and Safety, a tour of the work place and welfare facilities and an introduction to all colleagues. They will
then complete their own induction to the student so all information is accessible to them according to their
individual needs. In this way, training will be given on all tasks. The learner will be fully supervised by school
staff at all times when assisting with tasks.
Slips, trips and falls-Key task-General movement around the work place: Hazard: slips, trips and falls. Control
measure: Emphasis on good housekeeping-‘Tidy as you go’ policy and spills to be cleared up immediately.
Child protection.-Learner will be fully supervised at all times, by school staff.
Equipment and Machinery.-Key task: Use of equipment: Hazard: injury due to incorrect use. Control measures:
training in use of equipment by school staff as part of induction process outlined above. Learner will only use
equipment under full supervision of school staff, and subject to competence (at discretion of school staff).
Electricity.-Electrical items are visually inspected by school staff before use. Electrical items are only used
under full supervision of school staff. Annual PAT testing.
Chemicals. Only washing-up liquid and anti-bacterial sprays are to be used, under full supervision of school
staff. Parents must inform school of any known allergies.
Other possible hazards.-Key task: car park, student to be supervised when walking from the car park into the
school. If student sees a hazard in the setting they must report it to the staff member immediately.
Signature of placement supervisor_____________________ Date ___________________________
Parent / Guardian’s signature: ____________________________ Date _________________________________
Community development and education – Practice ES6006
Page 44 of 47
Appendix 14 – Two feedback sheets from the work experience sessions
Feedback report on Work experience session 2. X’s School 7/3/16.
Context: small group (9 pupils) year one, plus X (leading teaching) phonics session including reading and spelling small workroom Time 09.30
Student arrived, with Emily, on time and suitably dressed.
Children greeted student and .... X suggested student continue to support the same pupil
Student appeared more confident and happy to do this.
Student encouraged pupil to maintain appropriate attention by advising him to listen and to
talk when appropriate.
Student listened to pupil read and gave appropriate support.
Student cleared tables at the end of the session.
Student displayed a professional approach using initiative and appropriate support. He has
developed a rapport with this pupil who has benefitted from the support given. He asked where the
student was after lunch.
Context:
changing reading books
reading area
X took student to change pupils home reading books and did not remind him how to
complete this task
Student confidently collected books and replaced in correct folders.
Student displayed confidence in carrying out the task and supported X.
Context:
Reading Story
Whole class, Year one and reception mixed-29 children
Class teacher, X (TA role)
Time 10.45
Class teacher asked Student if he would like to read to the children.
He had practised the story that he had chosen and appeared keen and confident.
Read to the children, using expression and giving opinion, and showed the pictures to the
children. All children were focused and listened attentively.
When he had finished, X suggested he ask the children if they wanted to ask questions or
comment on the story.
Student listened and responded to the children showing sensitivity appropriate to their age.
Student read clearly and confidently. The children were engaged. Student spoke appropriately in the
question and answer session showing empathy and understanding of the children’s comments.
Community development and education – Practice ES6006
Page 45 of 47
Context: Reception class only – 15 children Painting-any picture based on The Gingerbread Man story.
Student sat with groups of 4 children to encourage them to stay on task
Reminded pupils to name their work and asked questions about what they were painting
Cleared the tables at the end of the task
Student worked independently, Emily observed.
Student supported and engaged pupils in the task. His questioning encouraged the children in
recalling the story.
General comments
As per previous visit, Student was friendly and polite towards the staff and pupils. He was
professional and showed maturity in his attitude to the tasks given.
He appeared more confident and relaxed on this visit. Both the class teacher and X felt that he
contributed well was valuable support in the classroom.
During break, X was able to introduce Student to The Forest School teacher who was working on
making a pulley system with a reception child. Student engaged with the teacher and pupil. We were
then able to briefly visit the Forest School area.
At lunch time, Student gave the lunch bands out. He completed this task independently.
Community development and education – Practice ES6006
Page 46 of 47
Feedback report on Work experience session 2. W’s school.
Context: Forest School site – Emily, student, two FS assistants, 15 Y3 children
Student arrived, with Emily, on time and suitably dressed.
Student met W at FS site
W welcomed student
Student asked to conduct safety sweep of FS area (checking for hazards, broken glass and
similar) in tandem with one of the other FS assistants
Student engaged in effective communication with other FS assistant and successfully
completed the safety sweep
Student had opportunity for independent action and took that opportunity
Student returned to W for further instruction
Emily was able to stand aside whilst student completing task
Student conducted themselves professionally and was not dependent on Emily’s reassurance. Was
able to engage with other assistant and completed task.
Context:
Second task – visiting each group of children and photographing them in FS context.
W asked student to take charge of camera and to walk round FS site and document children
engaging in the day’s activity (building dens)
Student effectively communicated his uncertainty regarding working the camera correctly. W
gave short tutorial, student then able to use camera
Student observed over 5-10 minute period walking around site, speaking to children and
taking photographs
Student returned to W and asked what he should do next.
Student successfully documented children engaging with the den-building activity
Student receptive to direction, showed enthusiasm for Forest School
Context:
Third task – collecting fuel
W needed fuel to be collected to use in Kelly Kettle
W asked student to collect a couple of bundles of twigs of a certain length and thickness
Student was a little concerned about ensuring the twigs were right size
W reassured student that a little variation was fine
Student collected good amount of twigs
At this point Emily pointed out that the time available to the student was coming to a close
W thanked Emily and student
Emily and student departed
General comments
Student was friendly and polite. Again, he displayed a professional approach and this time was able
to engage in tasks without being overly reliant on Emily’s presence.
Community development and education – Practice ES6006
Page 47 of 47
W had tasks ready and in place for the student to engage with and that led him away from the
‘sphere of safety’ that Emily represented to him. The student appeared to be more confident in the
second session and more willing to engage with the work aspect of work experience.
The experience was more meaningful as, although challenges were presented to him, the student
was able to challenge his own preconceptions regarding his ability.
There was a change noted by Emily and W inasmuch as, compared to the first session, the student
appeared to be more confident, relaxed and able to engage with the process.