~9 counrp ~~~~`'' ''~~ san francisco ~o-~~'~ a planning ...sfmea.sfplanning.org/1144-1150 harrison...

39
~ 9couN rp ~ ~~~`'' ''~~ SAN FRANCISCO ~ o -~~'~ a PLANNING DEPARTMENT lba.,~~~ : ..o ~~, 3 S , ~ p7 Certificate of Determination C ommunity Plan Evaluation C ase No.: 2016-001738ENV P roject Address: 1144-1150 Harrison Street Z oning: Western SoMa Mixed Use -General (WMUG) District Western SoMa Special Use District 5 5/65-X Height and Bulk District Block/Lot: 3755/023 Lot Size: 75,625 square feet P lan Area: Western SoMa Community Plan Project Sponsor: Scott Youdall, 1140 Harrison Associates, LP, (925) 490-2990 Staff Contact: Alesia Hsiao, (415) 575-9044, [email protected] ~ :Z~~rx~~►~~~~~~~~~ T he project site is located midblock along the north side of Harrison Street, between 8th Street and Langton Street, in San Francisco's South of Market neighborhood. The project site consists of a roughly square-shaped parcel on the block bounded by Harrison Street to the south, 8~" Street to the west, Folsom Street to the north an d 7th Street to the east. There are several alleys in the immediate project vicinity. Berwick Place abuts the project site to the west. Hallam Street terminates at the northern boundary of the p roject site, and Heron Street terminates at the western boundary of the project site. The project site is within the Western SoMa Light Industrial and Residential Historic District (historic district). The 75,625 square foot site is currently occupied by a 25-foot tall, one-story plus mezzanine industrial building constructed in 1907 that is a contributor to the historic district. The existing building varies in building h eight at 26 feet and 6 inches along Harrison Street to 33 feet along Berwick Street an d the northeastern CEQA DETERMINATION (Continued on next page). T he project is eligible for streamlined environmental review per Section 15183 of the California E nvironmental Quality Act (CEQA) Guidelines and California Public Resources Code Section 21083.3. DETERMINATION Ido erebX certi hat the above determination has been made pursuant to State an d Local requirements. ~ ,,--- tif 19' ~ ! F~ L isa Gibson Date E nvironmental Review Officer cc: Scott Youdall, Project Sponsor Project Distribution Doug Vu, Current Planner Historic Distribution List S upervisor Jane Kim, District 6 1650 Mission St. Suite 400 San Francisco, CA 94103-2479 Reception: 415.558.6378 Fax: 415.558.6409 Planning I nformation: 415.558.6377

Upload: others

Post on 09-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • ~9 couNrp

    ~~~~`'' ''~~ SAN FRANCISCO~o-~~'~ a PLANNING DEPARTMENTlba.,~~~:..o ~~,

    3S , ~ p7

    Certificate of DeterminationCommunity Plan Evaluation

    Case No.: 2016-001738ENV

    Project Address: 1144-1150 Harrison Street

    Zoning: Western SoMa Mixed Use -General (WMUG) District

    Western SoMa Special Use District

    55/65-X Height and Bulk District

    Block/Lot: 3755/023

    Lot Size: 75,625 square feet

    Plan Area: Western SoMa Community Plan

    Project Sponsor: Scott Youdall, 1140 Harrison Associates, LP, (925) 490-2990

    Staff Contact: Alesia Hsiao, (415) 575-9044, [email protected]

    ~:Z~~rx~~►~~~~~~~~~

    The project site is located midblock along the north side of Harrison Street, between 8th Street andLangton Street, in San Francisco's South of Market neighborhood. The project site consists of a roughlysquare-shaped parcel on the block bounded by Harrison Street to the south, 8~" Street to the west, FolsomStreet to the north and 7th Street to the east. There are several alleys in the immediate project vicinity.Berwick Place abuts the project site to the west. Hallam Street terminates at the northern boundary of theproject site, and Heron Street terminates at the western boundary of the project site. The project site iswithin the Western SoMa Light Industrial and Residential Historic District (historic district). The 75,625square foot site is currently occupied by a 25-foot tall, one-story plus mezzanine industrial buildingconstructed in 1907 that is a contributor to the historic district. The existing building varies in buildingheight at 26 feet and 6 inches along Harrison Street to 33 feet along Berwick Street and the northeastern

    CEQA DETERMINATION(Continued on next page).

    The project is eligible for streamlined environmental review per Section 15183 of the CaliforniaEnvironmental Quality Act (CEQA) Guidelines and California Public Resources Code Section 21083.3.

    DETERMINATION

    I do erebX certi hat the above determination has been made pursuant to State and Local requirements.

    ~,,--- ti f 19' ~ ! F~Lisa Gibson DateEnvironmental Review Officer

    cc: Scott Youdall, Project Sponsor Project DistributionDoug Vu, Current Planner Historic Distribution ListSupervisor Jane Kim, District 6

    1650 Mission St.Suite 400San Francisco,CA 94103-2479

    Reception:415.558.6378

    Fax:415.558.6409

    PlanningInformation:415.558.6377

  • Certificate  

    PROJECTside  of  thbusiness buildings inventory The propoto seven‐scontainingamenity asize from units,  146private opwidened Hallam St The projeBerwick Pfloor and and six staccessiblealley wouFolsom St The projespaces,  anlevel gara3,766 sf obicycle  lomidblock along Hadrivewaywould reqon‐street the  drivewcommercito four aloHarrison Place at Hcurb  ramincludes a

                     1 Exceptionsfor measurethose section

    of Determinatio

    T DESCRIPThe  building. until Augustin San Franc

    y storage.  

    osed project wstory, 65‐foot g 341,780 squand  leasing spapproximate6  two‐bedroopen  space woHarrison  Strtreet, and two

    ct site has a gPlace, allowinthe basementories within te north‐southuld  enhance treet, while al

    ct would prond two servicage.  The projef bicycle storounge  space. passage, wit

    arrison  Street. at the southequest that thecommercial lway  and  theial loading zoong HarrisonStreet  betweHarrison Streps  at  the  intadditional  tra

                           s from the provisement of height ins. A minor devi

    on

    ION (continuThe  existingt  2017.  The  acisco, althoug

    would demoltall1, approxi

    uare feet (sf) opace, and 69,ely 425 sf to apom  units,  andould be provreet  sidewalko common roo

    grade change ng a  courtyart level garagethe perimeterh midblock papedestrian  anlso providing

    ovide 172 on‐sce vehicle spaect would prorage on  the gPrimary  pedth pedestrian.   Vehicular east corner of e San Franciscoading zone e midblock  pone. The propn Street betweeen  Langton et, reconstructersection  of ansportation 

                       sions of the Planin Sections 260 aiation in the mea

    ued) g  building  coauto  repair  bgh it continue

    lish the majorimately 430,0of residential ,547 sf of garpproximatelyd  four  three‐vided with prk,  a  30‐foot wof decks on th

    of 7.5 feet frord  level at  the, resulting inr of the projecassage directnd  bicycle  co a visual brea

    site vehicle paces), as well ovide 372 Claground  floor. destrian  accesn  access  for  taccess  to  thethe site with 

    co Municipal Talong the nor

    passageway,  aposed project een 7th Street aStreet  and  Bct  the existingBerwick  Placdemand man

    nning Code with nd 261 of this Coasurement of buil

    overs  the  entbusiness  has s to use the p

    rity of the exi000 gross squauses (371 unirage space. Thy 1,328 sf and ‐bedroom  unirivate balconiwide  public he sixth floor.

    om Harrison he  interior of n the buildingct site. The prtly  connectingonnections  beak in the mass

    arking spacesas utility, trasass 1 and 41 CThe project wss  for  the  rethe  commercie  basement  lean 18‐foot‐wTransportatiorth side of Haand  a  66‐footwould reducand 8th Streeterwick  Placeg sidewalks ace  and Heronnagement me

    respect to heighode, and no suchlding height is al

    tire  parcel  ansince  relocatproject proper

    isting masonrare foot (gsf),its), 6,600  sf ohe proposed would includ

    nits. Approximies and deckmidblock  pa.  

    Street upwarthe  site  to beg containing sroject would pg Hallam  Stretween Harrsing of the pr

    s (167 vehiclesh, and electrClass 2 bicyclewould also psidential  useial uses provevel  garage w

    wide curb cut oon Agency (SFarrison Streett  long  passence the numbet, widen the se,  install  a  raalong both sin  Street.  In easures such 

    ht are confined toh deviation shalllowed under Pla

    1144-Case N

    nd  operated ted  to  other rty for limited

    ry building a, mixed‐use aof commerciadwelling unide 131 studiomately  29,724ks,  three  commassage  from H

    rd to its northe  inserted beseven stories provide a 30‐reet with Harrison  Street, Hoject.  

    e spaces, threrical rooms we parking spacprovide approe would  be  pvided  along Bwould  be  thon Harrison SFMTA) desigt west of the nger  loadinger of travel lansidewalk fromaised  crosswaides of Berwiaddition,  theas providing

    o minor deviatiol depart from thanning Code Sec

    1150 Harrison No. 2016-00173

    as  an  auto  rexisting  indud overflow v

    and construct apartment buial uses, 12,250its would ranos, 90 one‐bed4  sf  of  publimon  courtyaHarrison  Stre

    hwest corner etween  the grwithin the in‐foot wide purrison  Street.Hallam  Stree

    ee car share vwithin the baseces, approximoximately 650provided  fromBerwick Placrough  a  propStreet. The spgnate a 52‐foodriveway betg  zone west  ones from fivem 8 to 15 feet alk  across  Beick Place, ande  proposed  pg car‐share pa

    ons from the prohe purposes or inction 304(d)(6).  

    Street 38ENV

    2

    repair ustrial vehicle 

    a six‐ ilding 0 sf of nge  in droom c  and rds, a eet  to 

    along round nterior ublicly .   The et  and 

    ehicle ement mately 0 sf of m  the e  and posed ponsor ot long tween of  the  lanes along erwick d add project arking 

    ovisions ntent of 

  • Certificate  

    and memtime  trancosts, and Constructcommencexcavationbasementto resist hhammers  PROJECTThe propo San Franci

    C82ex

    Departmen

    Departmen

    R R R

     Bay Area ASan FranciSan Franci

    RH

    San Franci

    R

    San Franci

    RloB

    Aco  

    of Determinatio

    mberships, pronsportation  ind providing le

    tion of  the prce in Novembn of approximlevel. The pr

    hydrostatic upis not propos

    T APPROVALosed project w

    isco Planning 

    Conditional U23(c)(11) for axception abov

    nt of Building I

    Review and ap

    nt of Public He

    Review for comReview for comReview and ap

    Air Quality Misco Fire Deparisco Departme

    Review  and  aHarrison Stree

    isco Board of S

    Review and ap

    isco Municipal

    Review  and  aoading  zone erwick Place.

    Approval  of  consistency wi

    on

    oviding delivenformation  dess accessory p

    roposed projeber 2018 and bmately 52,947roposed buildplift pressuresed. 

    LS would require

    Commission 

    Use  (CUA) Aua major develve the base he

    Inspection  

    pproval of dem

    ealth 

    mpliance withmpliance withpproval of a D

    Management Dirtment nt of Public W

    pproval  of pet sidewalk. 

    Supervisors  

    pproval of sid

    l Transportatio

    approval  of along  the  n construction ith the Better 

    ery package ldisplays  and parking than 

    ect would ocbe completed7 cubic yards ding would bees with  the  in

    e the followin

    uthorization plopment in theight limit of 5

    molition and 

    h the Maher Oh article 38 of Demolition an

    strict 

    Works 

    permits  for  re

    dewalk legisla

    on Agency 

    an  on‐street orth  side  of 

    within  the  pStreets Plan 

    lockers, provinformation the neighbor

    ccur  for  apprd by May 2021of soil to a dee supported bnstallation of 

    ng approvals: 

    pursuant  to Phe Western So55‐X to the m

    building perm

    Ordinance, arthe Health C

    nd Constructio

    emoval  of Un

    ation to widen

    commercial Harrison  St

    public  right‐o

    viding multimabout  travelrhood parking

    roximately 301. Project conepth of 20 feeby a structurapre‐drilled s

    Planning CodoMA Special Umaximum heig

    mits. 

    rticle 22A of thCode for enhanon Dust Cont

    nderground  S

    n the sidewalk

    loading  zontreet  between

    of‐way  (e.g., 

    1144-Case N

    modal wayfinl  options,  ung rate.   

    0 months,  andnstruction is eet below gradal mat foundaoldier piles; u

    de Sections 26Use District rght limit of 65

    he Health Conced ventilattrol Plan. 

    Storage Tank

    k on Harrison

    ne  and  an  onn  the  propos

    sidewalk wi

    1150 Harrison No. 2016-00173

    ding signagenbundling  pa

    d  is anticipatexpected to rede for the propation, thick enuse of pile dr

    63.29, 303, 30requesting a h5‐X.  

    de. tion. 

    ks  identified  i

    n Street. 

    n‐street  passsed  driveway

    idening)  to  e

    Street 38ENV

    3

    , real‐arking 

    ted  to equire posed nough riving 

    04 and height 

    in  the 

    senger y  and 

    ensure 

  • Certificate  

    San Franci

    Agu

    The condiof the 30‐San Franc

    COMMUNCaliforniaprojects thor  generasubject  toproject‐spexaminatiparcel on the zoningsignificanpreviouslyat  the  timdiscussedto  the proimpact. 

    This  deteHarrison ProgrammProject  (Wdeterminethe Weste

    The Westpopulatiovibration;and servihazardou

    As a  resuIndustrialfrom 50‐Xneighborh

                     2 San FranciFinal Enviro2009082031, 26, 2018. 

    of Determinatio

    isco Public Uti

    Approval  of  auidelines. 

    Review and ap

    itional use au‐day appeal pcisco Adminis

    NITY PLAN EVa  Public  Resohat are consisal  plan  policio additional epecific significion of environwhich the prg action, genent  off‐site  andy identified in

    me  that  the EId in the underoposed proje

    ermination  eStreet  projec

    matic EIR for Western  SoMe if the projecern SoMa PEIR

    tern SoMa PEon and housin; air quality; gce systems; bs materials; m

    ult of  the Wesl/Residential)X to 55/65‐X. Thood  serving

                           sco Planning Deonmental  Impactcertified Decem

    on

    ilities Commis

    a  stormwater 

    pproval of a d

    uthorization isperiod for thisstrative Code

    VALUATION ources  Code stent with theies  for whichenvironmentacant effects wnmental effecroject would beral plan or cd  cumulativen the EIR, butIR was  certifirlying EIR. Seect,  then  an E

    valuates  thect  described the Western S

    Ma  PEIR).2  Prct would resuR. 

    EIR  included ng; cultural angreenhouse gbiological resomineral and en

    stern SoMa Coto Western  The WMUG dg,  commercia

                       partment, Westet Report  (PEIR), 

    mber 6, 2012. Ava

    sion 

    managemen

    dewatering pe

    s the Approvs CEQA exem. 

    OVERVIEW Section  2108 developmenh  an  Environal review excewhich are pecucts shall be limbe located; b)community ple  impacts  that which, as a ried, are deterction 15183(cEIR need  not

      potential  pabove,  and  iSoMa Commuroject‐specificult in any sign

    analyses of  tnd paleontologas emissionsources; geolonergy resourc

    ommunity PlaSoMa Mixeddistrict permil,  institutiona

    ern SoMa CommPlanning Deparailable online at:

    nt plan  that  c

    ermit.  

    val Action. Thmption determ

    83.3  and  CEQnt density estanmental  Impaept as might uliar to the pmited to those were not analan with whicat were  not  dresult of subsrmined  to ha) specifies that  be prepared

    project‐specifiincorporates nity Plan, Rezc  studies  wenificant enviro

    the  followingogical resourcs; wind and sogy and soils;ces; and agric

    an,  the projec‐Use ‐ Generaits residentialal,  and  indu

    munity Plan, Rezortment Case Nos: http://www.sf‐p

    complies with

    he Approval Amination pur

    QA  Guidelinablished by exact  Report  (Ebe necessary

    project or its se effects that:alyzed as signch the projectdiscussed  in stantial new inave a more  seat if an impacd  for  the pro

    ic  environmeby  referencezoning of Adjaere  preparedonmental imp

    g environmences; transportshadow; recre; hydrology acultural and fo

    ct  site was  rezal (WMUG) al uses and suustrial/PDR  u

    oning of Adjacens. 2008.0877E anplanning.org/ind

    1144-Case N

    h  the City’s  s

    Action date ersuant to Sect

    nes  Section  1xisting zoningEIR) was  certy  to examine site. Section 1 a) are peculinificant effectt is consistentthe  underlyinformation thevere adversect is not peculoject  solely  on

    ental  effects e  informationacent Parcels, ad  for  the  propacts that wer

    ntal  issues:  latation and circeation; publicand water quorest resource

    zoned  from Sand the heighupports a flexiuses,  such  as 

    nt Parcels, and 3nd 2007.1035E, Stdex.aspx?page=1

    1150 Harrison No. 2016-00173

    stormwater d

    establishes thetion 31.04(h) 

    5183  provideg, communitytified,  shall  nwhether  ther

    15183 specifieiar to the projts in a prior Et; c) are potening  EIR;  or  dhat was not ke  impact  thanliar to the parn  the  basis  o

    of  the  1144n  contained  iand 350 Eight oposed  projere not identif

    and use; aesthculation; noisc services, utiuality; hazardes. 

    SLR  (Service/ht and bulk dible mix of smbars,  restau

    50 Eighth Street tate Clearinghou1893, accessed Fe

    Street 38ENV

    4

    design 

    e start of the 

    e  that y plan not  be re are es that ject or EIR on ntially d)  are known n  that rcel or of  that 

    4‐1150 in  the Street ect  to fied in 

    hetics; se and ilities, ds and 

    /Light district maller urants, 

    Project use No. ebruary 

  • Certificate  

    retail,  burequiring developm

    Individuaproject‐levdevelopmenvironm1144‐1150SoMa  PEdescribedmeasures the  provievaluationCertificatecomplete 

    PROJECTThe  squarLangton Sone‐story immediatthat frontsstory warfronts on 1900).  Thinterior alinto  two swest of thincludinglight  inducommerci Harrison on both  sExpressesclosest buMuni lineinclude  thMission E

                     3  San FranciHarrison StrDepartment4  San FranciHarrison Str

    of Determinatio

    siness  serviceCU authoriz

    ment (R&D) fa

    al projects thavel environm

    ment  proposamental  review0 Harrison StrIR.  This  dete

    d  the  impacts applicable toisions  of  then for the 1144e  of  DetermiCEQA evalua

    T SETTING re‐shaped prStreet in the Splus mezzan

    tely adjacent ts on Harrisonrehouse withHarrison Stre

    here  is  a  proplterations to thstories of offihe project siteg  commercial,ustrial buildinial buildings. 

    Street is an easides of  the  ss  (8‐Bayshoreus stops are apes near the prhe  9‐San  BruExpress, 83X‐M

                           isco Planning Dereet, April 3, 201t, 1650 Mission Stisco  Planning  Dreet, August 21, 2

    on

    es,  and  lightzation. Large‐acilities are no

    at could occumental evaluatal,  the  site, w would  be  rreet  is consisermination  aof  the propo

    o the project. e  Planning  C4‐1150 Harrisination  and ation necessa

    roject  site  is  lSouth of Marknine  industriato the east of tn Street. The ph mezzanine eet and a oneposed  projecthe existing buice space wit. The surroun,  residential, ngs, while Ha 

    ast‐west roadtreet. The proe, 8AX‐Bayshopproximatelyroject site incuno,  9R‐San Mid‐Market E

                       epartment, Comm18. This documetreet, Suite 400 a

    Department,  Com2017. 

    t manufactur‐scale commeot be permitte

    r in the futurtion to determand  the  timequired.  Thistent with, anlso  finds  thaosed 1144‐115The propose

    Code  applicabon Street proaccompanyinry for the pro

    located  on  thket neighborhal building  (1the project sitproperties acrindustrial  bu‐story art gallt  at  1170 Hauilding to tranth no expansinding area aroand  light  indallam Street 

    dway with fouoject  site  is  sore “A” Expry 280 feet awalude the 12‐FBruno  RapiExpress, 30‐S

    munity Plan Evaent, and other cits part of Case Filmmunity  Plan  Ev

    ring.  All  typeercial uses,  loed within this

    re under the mine if they wme  of  develos  determinatind was encomat  the Wester50 Harrison Sed project is able  to  the  pject is requireng  project‐spoposed projec

    he  north  sidehood. The 75,1126 Harrisonte is a two‐stoross Berwick Puilding  (1170lery space wiarrison  Street nsform the exion of  the buound the produstrial uses. and Langton

    ur lanes traveserved by  theress, and 8BXay near the inFolsom–Pacifid,  10‐TownsStockton, and 

    aluation Eligibilitted documents, le No. 2016‐0017aluation  Eligibilit

    es  of  residenoft‐style  live/ws district. 

    Western SoMawould result inopment  and ion  concludempassed withrn  SoMa  PEIStreet projectalso consistenproject  site.3,4 ed. In sum, thpecific  initial ct. 

    e  of Harrison,625‐square‐fon Street  consory residentiaPlace to the w0 Harrison  Stith mezzanine(Case No.  2

    xisting one‐stuilding envelooject site is cha Harrison Strn Street consis

    elling west, twe 27‐Bryant, 4X‐Bayshore  “ntersection ofic and 19‐Polsend,  14‐Miss 45‐Union–St

    ty Determination,are available  for

    738ENV. ty  Determination

    1144-Case N

    ntial  uses  arework spaces,

    a Community n further impto  assess  w

    es  that  the  prhin,  the analyIR  adequatelt, and  identifnt with the zo4  Therefore, he Western Sostudy  comp

    n  Street,  betwoot project sitstructed  in 19al building (cowest of the protreet  construe (7 Heron St2015‐016239Etory warehouope.  It  is apparacterized byreet and Berwst of  integrat

    wo parking lan47‐Van Ness, “B” Express) f 8th and Harrk. Routes sligsion,  14R‐Mitockton. Ther

    , Citywide Plannr review at  the S

    n,  Current  Planni

    1150 Harrison No. 2016-00173

    e  permitted, , and  research

    Plan will unpacts specific whether  addiroposed  projysis  in  the Wely  anticipatedfied  the mitigoning controlno  further  CoMa PEIR anprise  the  ful

    ween  8th  Streete is occupied907). The proonstructed in oject site are aucted  in  1900treet construcNV)  that  inv

    use with mezzproximately 2y a variety ofwick Place  coted  residentia

    nes, and sideand  the Baybus  lines, anrison streets. ghtly further ssion  Rapid,re are bicycle 

    ing Analysis,  114San Francisco Pl

    ing  Analysis,  114

    Street 38ENV

    5

    some h and 

    dergo to the itional ect  at estern d  and gation ls and CEQA nd this ll  and 

    et  and d by a operty  1901) a one‐)  that cted in volves zanine 20  feet f uses, ontain al and 

    walks yshore nd  the Other away   14X‐lanes 

    44‐1150 lanning 

    44‐1150 

  • Certificate  

    on HowarEnclave), within a o POTENTIThe WestPopulatioand VibraUtilities, aHazards aThe proposite  descrforecast  fconsidereproposed in the We

    Significanhistoric renot  indiviLight Indua contribuloss of  thwould noto  other  owould enthe vicinitsuch damresource transit  imgeneratinmechanicgenerate econstructicomply wAQ‐7  woMinimizadetermineareas. Thethe projec

    The Westcultural  a                 5 Page & Tur6 San Francis

    of Determinatio

    rd, Folsom, 7tSALI  (Servicone‐block rad

    AL ENVIRONtern  SoMa  PEon and Housination; Air Quand Service Sand Hazardouosed 1144‐115ribed  in  the Wor  the Westerd  the  incremproject woulstern SoMa P

    nt and unavoiesources, tranidually eligibustrial and Reutor to the hihe  existing  strot convey its soffsite  historinsure that proty during dem

    mage  is documimpact.  Tran

    mpacts  identifg uses, Mitigal equipmentexcessive conion activities with  the Consould  reduce  cation  Plan  fored  that  the  pe proposed prct vicinity, but

    ern SoMa PEand paleontol                       rnbull, 1140‐1150sco Planning Dep

    on

    th and 8th strece/Arts/Light ius include 30

    NMENTAL EFEIR  includedng; Cultural auality; GreenhSystems; Biolus Material; M50 Harrison SWestern  SoMrn SoMa Com

    mental  impactld not result iPEIR. 

    idable impactnsportation anble  for  listingesidential Hisstoric districtructure was dsignificance.  Iic  resources oject contractomolition and mented  and  rnsit  ridership fied  in  the Wgation Measurt meets the renstruction noisis minimizedstruction Dusconstruction‐r  health  riskproposed  buiroject would t at levels com

    IR identified logical  resour                   0 Harrison Street Hpartment, Histori

    ets. The surroIndustrial, an0‐X, 40‐X, 55‐

    FFECTS d  analyses  of and Paleontohouse Gas Emlogical ResouMineral and EStreet project iMa  PEIR  andmmunity Plan.ts of  the propin any new o

    ts were identnd circulationg  in  the Califostoric Districtt, the proposedetermined nIn addition, tin  the  projecors use all feaconstruction,repaired. Thegenerated  b

    Western  SoMre M‐NO‐1c equirements ose, Mitigationd to the maximst Control Orrelated  air  qks  and  hazarilding would shade nearbymmonly expe

    feasible mitigrces,  transpo

    Historic Resource ic Resource Evalua

    ounding parcnd P  (Public)‐X, and 55/65‐

    environmenological Resoumissions; Winurces; GeologyEnergy Resouis in conform would  repre Thus,  the pposed 1144‐11or substantiall

    tified in the Wn, noise, air qornia Registet.5,6 Although ed project is cnot  to materihe proposed ct  vicinity. Masible means t, and undertaerefore,  the pby  the  projecta  PEIR. As  twould ensurof the Noise On Measure M‐mum extent frdinance, andquality  impacds.  The  shadnot  shade  o

    y streets, sidected in urban

    gation measurtation  and  c

    Evaluation‐ Partsation Response for

    cels are within) zoning dist‐X.  

    ntal  issues  incurces; Transpnd and Shadoy and Soils; Hurces; and Agance with theesent  a  smal

    project  analyz150 Harrisonly more sever

    Western SoMaquality, and ser but  is a  conthe proposedcompatible wially  impair  tproject woul

    Mitigation Meto avoid damake a monitorproject wouldt would  not the  proposedre  that projecOrdinance. Si‐NO‐2a wouldfeasible. The d  implementacts  by  requirdow  fan  anaoutdoor  recreewalks, and pn areas. 

    ures to addrescirculation, n

    s One and Two, Mr 1144‐1150 Harri

    1144-Case N

    n the WMUGtricts. Height 

    cluding:  Lanportation and ow; RecreatioHydrology agriculture ande height, use all  part  of  thezed  in  the Wn Street projecre impacts th

    a PEIR for thshadow. The ntributor  to  td project invowith the histothe historic dd not cause aeasures M‐CPmage to the hiring program d not  contribuconsiderably

    d  project wouct generated nince the propd ensure thatproposed proation of Mitigring  a  Constalysis  for  theeation  facilitiprivate prope

    ss significant noise  and vib

    March 2, 2017. ison Street, Febru

    1150 Harrison No. 2016-00173

    G, RED (Residand bulk dis

    nd Use; AesthCirculation; 

    on; Public Serand Water Qud Forest Resouand density fe  growth  tha

    Western  SoMa ct. As a  resulhan were iden

    he following tproject buildthe Western olves demolitric district andistrict  such  ta significant imP‐7a  and M‐Cistoric buildinto ensure thaute  to any hiy  contribute  tuld  involve  nnoise  from  roposed project t project noiseoject is requirgation Measutruction  Emise  proposed  pes  or  other  prty at times w

    impacts relaration,  air qu

    uary 28, 2018. 

    Street 38ENV

    6

    dential stricts 

    hetics, Noise rvices, uality; urces. for the at was PEIR lt,  the ntified 

    topics: ding is SoMa tion of nd the that  it mpact CP‐7b ngs in at any istoric to  the noise‐ooftop could e from red to ure M‐ssions project public within 

    ted to uality, 

  • Certificate  

    wind,  biomeasures to the pro

    Mi

    D.  CulturResources

    M‐CP‐1a: Historical 

    M‐CP‐1b: 

    M‐CP‐1c: I

    M‐CP‐4a: PPreliminarAssessmen

    M‐CP‐4b: AccidentaArcheolog

    M‐CP‐7a: PResourcesConstructi

    M‐CP‐7b: MonitorinResources

    of Determinatio

    ological  resouidentified in

    oposed project

    itigation Meas

    ral  and  Paleos 

    DocumentatResource 

    Oral Histories

    Interpretive P

    Project‐Specifry Archeologicnt (PAR) 

    Procedures fol Discovery ofgical Resources

    Protect Historfrom Adjacenion Activities 

    Construction ng Program for 

    on

    urces,  and  han the Westernt. 

    Table 1 –

    sure 

    ontological 

    tion  of  a 

    rogram 

    ic cal 

    or f s 

    rical nt 

    r Historical 

    azards  and  hn SoMa PEIR 

    – Western SoM

    A

     

    Not Applicabbuilding is a nhistoric resou

    Not Applicabbuilding is a nhistoric resou

    Not Applicabbuilding is a nhistoric resou

    Applicable: Trequire more grade excavat

    Not Applicabby implementarcheological 

    Applicable: Aresources are 

    Applicable: Hpresent in pro

     

    hazardous maand states w

    Ma PEIR Mit

    Applicability 

    ble: The existinnot an individurce. 

    ble: The existinnot an individurce. 

    ble: The existinnot an individurce. 

    The project wothan five feet tion. 

    ble: This is suptation of M‐CPtesting. 

    Adjacent historpresent. 

    Historic resouroject vicinity. 

    aterials.  Tablwhether the m

    tigation Meas

     

    ng dual 

    N

    ng dual 

    N

    ng dual 

    N

    ould of below 

    PPaPM(P

    perseded P‐4a, 

    N

    ric  Ttadr(1

    rces are  TtmrpadM

    1144-Case N

    le  1  below  limitigation mea

    sures 

    Com

    Not Applicabl

    Not Applicabl

    Not Applicabl

    Pursuant to thPAR, the projeagreed to impPlanning DepMitigation Me(ArcheologicaProject Mitiga

    Not Applicabl

    The project spto implement adjacent histodamage causerelated constru(see Project M1). 

    The project spto implement monitor adjacresources for dproject‐relatedactivities and damage (see PMeasure 2). 

    1150 Harrison No. 2016-00173

    ists  the mitigasure would 

    mpliance 

    le 

    le 

    le 

    he results of thect sponsor haplement the artment’s Staneasure #3 al Testing), as ation Measure 

    le  

    ponsor has agrpractices to prric resources fed by project‐uction activiti

    Mitigation Meas

    ponsor has agra program to ent historic damage caused constructionto repair suchProject Mitigat

    Street 38ENV

    7

    gation apply 

    he as 

    ndard 

    3. 

    reed rotect from 

    es sure 

    reed 

    ed by n h tion 

  • Certificate  

    Mi

    E. Transpo

    M‐TR‐1c: TOptimizatWB off‐ram

    M‐TR‐4: Loading S

    M‐C‐TR‐2Impact  FImpacts 

    F. Noise a

    M‐NO‐1a:Residentia

    M‐NO‐1b:Sensitive U

    M‐NO‐1c: Generating

    M‐NO‐1d:Environm

    M‐NO‐2a:Noise Con

    of Determinatio

    itigation Meas

    ortation and C

    Traffic Signal tion (8th/Harrismp) 

    Provision paces on Folso

    :  Impose  DeFees  to  Offs

    nd Vibration 

     Interior Noiseal Uses 

     Siting of NoisUses 

    Siting of Noisg Uses 

    :  Open  Spaceents 

      General  Cntrol Measures

    on

    sure 

    Circulation 

    son/I‐80 

    of  New om Street 

    evelopment set  Transit 

    e Levels for 

    se‐

    se‐

    e  in  Noisy 

    onstruction s 

    A

     

    Not applicablremoved from

    Not Applicabnot involve anFolsom Streetgenerate neglfreight loadinactivities alon

    Not Applicabsuperseded bSection 423, EImpact Fees aFund. 

    Not applicablenvironment longer a CEQ

    Not applicablenvironment longer a CEQ

    Applicable: Tnoise‐generat

    Not applicablenvironment longer a CEQ

    Applicable: Tnew construc

    Applicability 

    le: Automobilem CEQA analy

    ble: The projecny physical cht and is expectligible demandng/service vehing Folsom Stre

    ble: This measuy Planning CoEastern Neighband Public Ben

     

    le: Impacts of on the project

    QA topic. 

    le: Impacts of on the project

    QA topic. 

    The project proting uses. 

    le: Impacts of on the project

    QA topic. 

    The project proction that could

     

    e delay is ysis.  

    N

    ct would hanges to ted to d for icle eet. 

    N

    ure is ode borhoods nefits 

    TNai

     

    the t is no 

    N

    the t is no 

    N

    oposes  TacFSriapimnM

    the t is no 

    N

    oposes d generate 

    Tt

    1144-Case N

    Com

    Not Applicabl

    Not Applicabl

    The project is Neighborhooda portion of wimprovements

    Not Applicabl

    Not Applicabl

    The project spa noise study compliance wFrancisco GenSan Francisco requirements implementatioattenuation mproject sponsoimplement nomeasures durinoise‐generatiMitigation Me

    Not Applicabl

    The project spto develop and

    1150 Harrison No. 2016-00173

    mpliance 

    le 

    le 

    subject to Easds Tier 2 impawhich funds tras. 

    le 

    le 

    ponsor has prethat demonstr

    with the San neral Plan and Noise Ordinawith on of noise 

    measures. The or has agreed toise attenuationing siting of fuing uses (Projeeasure 4). 

    le 

    ponsor has agrd implement a

    Street 38ENV

    8

    tern act fee, ansit 

    epared rates 

    the ance 

    to n uture ect 

    reed a set 

  • Certificate  

    Mi

    M‐NO‐2b:During Pil

    G. Air Qu

    M‐AQ‐2: ManagemDevelopm

    M‐AQ‐3: RToxic  Air Sensitive R

    M‐AQ‐4:  SPM2.5  or TACs 

    M‐AQ‐6: MinimizatPollutants

    M‐AQ‐7: CMinimizatRisks and 

    I. Wind an

    M‐WS‐1: SAnalysis a

    L. Biologi

    M‐BI‐1a: PStatus Bird

     

    of Determinatio

    itigation Meas

     Noise Controle Driving 

    uality 

    Transportatioent Strategies

    ment Projects 

    Reduction in EContaminant

    Receptors 

    Siting  of Usesother  DPM 

    Construction tion Plan for C 

    Construction Etion Plan for HHazards 

    nd Shadow 

    Screening‐Levand Wind Test

    cal Resources

    Pre‐Constructid Surveys 

    on

    sure 

    ol Measures 

    on  Demand   for Future 

    Exposure to ts  for  New 

    s  that  Emit and  Other 

    Emissions Criteria Air 

    Emissions Health 

    el Wind ting 

    ion Special‐

    A

    excessive con

    Not Applicabinclude pile‐d

     

    Not Applicabnot generate mvehicle trips. 

    Not Applicabsuperseded bCode Article 3Exposure Zon

    Not Applicabconstruction anot result in s

    Not Applicabnot exceed thconstruction tsignificance. 

    Applicable: Tconstruction iquality. 

     

    Not Applicabnot exceed 80

     

    Applicable: Tbuilding dem

    Applicability 

    nstruction nois

    ble: The projecdriving activiti

    ble: The projecmore than 3,50

    ble: This measuy San Francisc38 (Air Pollutane). 

    ble: The projecand operationsubstantial em

    ble: The projece BAAQMD thresholds of 

    The project inclin an area of p

    ble: The projec0 feet in height

    The project inclmolition. 

    se.  odM

    ct does not ies. 

    N

     

    ct would 00 daily 

    NsDO

    ure is co Health ant 

    N

    ct‐related n would missions. 

    N

    ct would  N

    ludes poor air 

    TtEHM

     

    ct would t. 

    N

     

    ludes  TtsqJbt(

    1144-Case N

    Com

    of noise attenuduring construMitigation Me

    Not Applicabl

    Not applicablesubject to the TDemand ManOrdinance. 

    Not Applicabl

    Not Applicabl

    Not Applicabl

    The project spto implement Emissions MinHealth Risk anMitigation Me

    Not Applicabl

    The project spto conduct prespecial‐status qualified bioloJanuary 15 andbuilding demoto take place d(Project Mitiga

    1150 Harrison No. 2016-00173

    mpliance 

    uation measuruction (Projecteasure 5). 

    le 

    e, but project iTransportationagement 

    le 

    le 

    le 

    ponsor has agra Constructionimization Pland Hazards (Peasure 6). 

    le 

    ponsor has agre‐constructionbird surveys bogist between d August 15 ifolition is schedduring that peation Measure

    Street 38ENV

    9

    res t 

    is n 

    reed n an for Project 

    reed n by a 

    f duled riod e 7). 

  • Certificate  

    Mi

    M‐BI‐1b: PStatus Bat 

    O. HazardMaterials 

    M‐HZ‐2: Materials A

    M‐HZ‐3: SCorrective

     PUBLIC NA  “Notifioccupantsby  the  penvironm

    Six membpublic  intwould beInitial StuPaleontolosignificanthose iden

     

    of Determinatio

    itigation Meas

    Pre‐ConstructiSurveys 

    ds and Hazard

    Hazardous Abatement 

    Site Assessmene Action 

    NOTICE ANDication  of  Pros and ownerspublic  in  resmental review 

    bers of the puterested  in hie preserved audy Checklistogical Resournt  adverse  enntified in the W

    on

    sure 

    ion Special‐

    dous 

    Building 

    nt and 

    D COMMENT oject  Receivin of propertiessponse  to  thas appropriat

    ublic were  intistoric  resouras part of  the t under Sectiorces). No othenvironmental Western SoM

    A

    Applicable: Tremoval of trevacant buildin

    Applicable: Tdemolition of

    Not Applicabby San Franci22A (Maher O

    ng  Environms within 300 fhe  notice  wete for CEQA a

    terested  in  lerces and one project. Thes

    on 1  (Land Uer comments impacts  asso

    Ma PEIR. 

    Applicability 

    The project invees and demolng. 

     

    The project inclf a pre‐1970s b

    ble: This is supisco Health CoOrdinance). 

    mental  Reviewfeet of the proere  taken  intanalysis.  

    earning more member of  tse  issues  rais

    Use and Landwere receiveociated with 

    volves lition of a 

    TtsqlvdM

    ludes building. 

    TtcbsadfwapM

    perseded ode Article 

    N

    w” was maileoject site. Oveto  considerat

    about the prthe public  intsed by  the pud Use Plannined. The propothe  issues  id

    1144-Case N

    Com

    The project spto conduct prespecial‐status qualified bat blarge trees arevacant buildindemolished (PMeasure 8). 

    The project spto ensure that containing polbiphenyls (PCsuch as fluoreare removed adisposed, andfluorescent ligwhich could care similarly rproperly dispoMitigation Me

    Not Applicabl

    ed  on  July  5erall, concerntion  and  inc

    roject with twterested  in wublic are addng) and Sectioosed project wdentified  by  t

    1150 Harrison No. 2016-00173

    mpliance 

    ponsor has agre‐constructionbat surveys bybiologist whene to be removengs are to be Project Mitigat

     

    ponsor has agrany equipmenlychlorinated 

    CBs) or mercurscent light baland properly d that any ght tube fixturcontain mercurremoved intacosed of (Projeceasure 8).  

    le 

    5,  2017  to  adjns and issues rcorporated  in

    wo members whether PDR dressed  in  theon 3 (Culturawould not resthe  public  be

    Street 38ENV

    10

    reed n y a n ed or 

    tion 

    reed nt 

    ry, llasts, 

    es, ry, t and ct 

    jacent raised n  the 

    of the space e CPE al and sult in eyond 

  • Certificate  

    CONCLUAs summ

    1. Thth

    2. Thp

    3. Thth

    4. Thinse

    5. ThP

    TherePublic

                     7  The CPE Planning De

    of Determinatio

    SION arized above 

    he proposed he Western So

    he  proposed roject or the p

    he proposed hat were not i

    he proposed nformation thevere than we

    he project spEIR to mitiga

    efore, no  furthc Resources C

                           Initial  Study Chepartment, 1650 M

    on

    and further d

    project is conoMa Commun

    project wouproject site th

    project woulidentified in t

    project woulhat was not knere already an

    ponsor will unate project‐rela

    her environmCode Section 2

                       hecklist  is  availaMission Street, S

    discussed in t

    nsistent with tnity Plan; 

    uld  not  resultat were not id

    ld not  result the Western S

    d not result innown at the tinalyzed and d

    ndertake feasated significa

    mental  review21083.3 and C

    able  for  review uite 400, San Fra

    the project‐sp

    the developm

    t  in  effects  ondentified as si

    in potentiallSoMa PEIR; 

    n significant ime the Westedisclosed in th

    sible mitigatioant impacts. 

    w  shall be  reqCEQA Guidel

    online  at  http://ancisco, in Case F

    pecific initial s

    ment density e

    n  the  environignificant effe

    ly  significant 

    effects, whichern SoMa PEIhe PEIR; and 

    on measures 

    quired  for  thelines Section 1

    /sf‐planning.org/File No. 2016‐001

    1144-Case N

    study7: 

    established fo

    nment  that  aects in the We

    off‐site or  cu

    h, as a result IR was certifi

    specified  in 

    e proposed p15183. 

    /community‐plan1738ENV. 

    1150 Harrison No. 2016-00173

    or the project s

    are  peculiar  testern SoMa P

    umulative  im

    of substantiaed, would be

    the Western 

    project pursua

    n‐exemptions  or

    Street 38ENV

    11

    site in 

    to  the PEIR; 

    mpacts 

    al new e more 

    SoMa 

    ant  to 

    r  at  the 

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 1

    EXHIBIT 1: MITIGATION MONITORING AND REPORTING PROGRAM

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    MITIGATION MEASURES

    Project Mitigation Measure 1: Protect Historical Resources from Adjacent Construction Activities (Implementing Western SoMa PEIR Mitigation Measure M-CP-7a)

    The project sponsor shall consult with Planning Department environmental planning/preservation staff to determine whether adjacent or nearby buildings constitute historical resources that could be adversely affected by construction‐generated vibration. For purposes of this measure, nearby historic buildings shall include those within 100 feet of a construction site if pile driving would be used; otherwise, it shall include historic buildings within 25 feet, if heavy equipment would be used. (No measures need be applied if no heavy equipment would be employed.) If one or more historical resources is identified that could be adversely affected, the project sponsor shall incorporate into construction specifications for the proposed project a requirement that the construction contractor(s) use all feasible means to avoid damage to adjacent and nearby historic buildings. Such methods may include maintaining a safe distance between the construction site and the historic buildings (as identified by the Planning Department preservation staff),

    Project sponsor and construction contractor(s) under the direction of the Environmental Review Officer (ERO).

    Prior to and during demolition and construction activities.

    Planning Department Preservation Technical Specialist to review monitoring reports provided by Project sponsor and/or contractor.

    Considered complete upon end of construction and documentation by a qualified historic preservation profession at the direction of preservation staff that all identified protection methods were undertaken.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 2

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    using construction techniques that reduce vibration, appropriate excavation shoring methods to prevent movement of adjacent structures, and providing adequate security to minimize risks of vandalism and fire.

    Project Mitigation Measure 2: Construction Monitoring Program for Historical Resources (Implementing Western SoMa PEIR Mitigation Measure M-CP-7b)

    For those historical resources identified in Mitigation Measure M‐CP‐7a, and where heavy equipment would be used, the project sponsor shall undertake a monitoring program to minimize damage to adjacent historic buildings and to ensure that any such damage is documented and repaired. The monitoring program, which shall apply within 100 feet where pile driving would be used and within 25 feet otherwise, shall include the following components. Prior to the start of any ground‐disturbing activity, the project sponsor shall engage a historic architect or qualified historic preservation professional to undertake a pre‐construction survey of historical resource(s) identified by the San Francisco Planning Department within 125 feet of planned construction to document and photograph the buildings’ existing conditions. Based on the construction and condition of the resource(s), the consultant shall also establish a maximum vibration level that shall not be exceeded at each building, based on existing condition, character‐defining features, soils conditions, and anticipated construction practices (a common standard is

    Project sponsor, construction contractor(s), and qualified historic preservation professional under the direction of the ERO.

    Prior to and during ground‐disturbing, demolition, or construction activities.

    The project sponsor and construction contractor(s) at the direction of preservation staff shall monitor vibration levels during ground‐disturbing, demolition, or construction activities and report to Planning Department Preservation Technical Specialist.

    In the event that vibration levels exceed the maximum limit established by the historic preservation professional and preservation staff, construction shall be halted and alternative construction techniques shall be implemented to the extent feasible.

    Considered complete upon end of construction.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 3

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    0.2 inch per second, peak particle velocity). To ensure that vibration levels do not exceed the established standard, the project sponsor shall monitor vibration levels at each structure and shall prohibit vibratory construction activities that generate vibration levels in excess of the standard.

    Should vibration levels be observed in excess of the standard, construction shall be halted and alternative construction techniques put in practice, to the extent feasible. (For example, pre‐drilled piles could be substituted for driven piles, if feasible based on soils conditions; smaller, lighter equipment might be able to be used in some cases.) The consultant shall conduct regular periodic inspections of each building during ground‐disturbing activity on the project site. Should damage to either building occur, the building(s) shall be remediated to its pre‐construction condition at the conclusion of ground‐disturbing activity on the site.

    Project Mitigation Measure 3: Procedures for Archeological Testing (Implementing Western SoMa PEIR Mitigation Measure M-CP-4b)

    Based on a reasonable presumption that archeological resources may be present within the project site, the following measures shall be undertaken to avoid any potentially significant adverse effect from the proposed project on buried or submerged historical resources. The project sponsor shall retain the services of an archaeological

    Project sponsor/ archeological consultant at the direction of the ERO.

    Prior to and during soil disturbing activities

    Project sponsor to retain a qualified archeological consultant who shall report to the ERO.

    Qualified archeological consultant will scope archeological testing program with ERO.

    Considered complete when ERO approves archeological testing plan scope.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 4

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    consultant from the rotational Department Qualified Archaeological Consultants List (QACL) maintained by the Planning Department archaeologist. The project sponsor shall contact the Department archeologist to obtain the names and contact information for the next three archeological consultants on the QACL. The archeological consultant shall undertake an archeological testing program as specified herein. In addition, the consultant shall be available to conduct an archeological monitoring and/or data recovery program if required pursuant to this measure. The archeological consultant’s work shall be conducted in accordance with this measure at the direction of the Environmental Review Officer (ERO). All plans and reports prepared by the consultant as specified herein shall be submitted first and directly to the ERO for review and comment, and shall be considered draft reports subject to revision until final approval by the ERO. Archeological monitoring and/or data recovery programs required by this measure could suspend construction of the project for up to a maximum of four weeks. At the direction of the ERO, the suspension of construction can be extended beyond four weeks only if such a suspension is the only feasible means to reduce to a less than significant level potential effects on a significant archeological resource as defined in CEQA Guidelines Sect. 15064.5 (a) and (c). Consultation with Descendant Communities: On discovery of an archeological site1 associated with descendant Native

    Project sponsor’s qualified

    In the event that an

    Consult with descendant communities to determine

    Considered complete after

    1 By the term “archeological site” is intended here to minimally include any archeological deposit, feature, burial, or evidence of burial.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 5

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    Americans, the Overseas Chinese, or other potentially interested descendant group an appropriate representative2 of the descendant group and the ERO shall be contacted. The representative of the descendant group shall be given the opportunity to monitor archeological field investigations of the site and to offer recommendations to the ERO regarding appropriate archeological treatment of the site, of recovered data from the site, and, if applicable, any interpretative treatment of the associated archeological site. A copy of the Final Archaeological Resources Report shall be provided to the representative of the descendant group. Archeological Testing Program. The archeological consultant shall prepare and submit to the ERO for review and approval an archeological testing plan (ATP). The archeological testing program shall be conducted in accordance with the approved ATP. The ATP shall identify the property types of the expected archeological resource(s) that potentially could be adversely affected by the proposed project, the testing method to be used, and the locations recommended for testing. The purpose of the archeological testing program will be to determine to the extent possible the presence or absence of archeological resources and to identify and to evaluate whether any archeological resource

    archeological consultant Archeological consultant at the direction of the ERO.

    archeological site is uncovered during the construction period Prior to soil disturbing activities.

    appropriate treatment of archeological finds and report findings as appropriate Submittal of draft ATP to ERO for review and approval. Distribution of the ATP by the archeological consultant.

    Archeological consultant undertake activities specified in ATP and immediately notify ERO of any encountered archeological resource.

    Final Archeological Resources Report is approved and provide to descendant groups. Considered complete upon completion of the archeological testing program outlined in the ATP.

    2 An “appropriate representative” of the descendant group is here defined to mean, in the case of Native Americans, any individual listed in the current Native American Contact List for the City and County of San Francisco maintained by the California Native American Heritage Commission and in the case of the Overseas Chinese, the Chinese Historical Society of America. An appropriate representative of other descendant groups should be determined in consultation with the Department archeologist.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 6

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    encountered on the site constitutes an historical resource under CEQA. At the completion of the archeological testing program, the archeological consultant shall submit a written report of the findings to the ERO. If based on the archeological testing program the archeological consultant finds that significant archeological resources may be present, the ERO in consultation with the archeological consultant shall determine if additional measures are warranted. Additional measures that may be undertaken include additional archeological testing, archeological monitoring, and/or an archeological data recovery program. No archeological data recovery shall be undertaken without the prior approval of the ERO or the Planning Department archeologist. If the ERO determines that a significant archeological resource is present and that the resource could be adversely affected by the proposed project, at the discretion of the project sponsor either:

    A) The proposed project shall be re‐designed so as to avoid any adverse effect on the significant archeological resource; or

    B) A data recovery program shall be implemented, unless the ERO determines that the archeological resource is of greater interpretive than research significance and that interpretive use of the resource is feasible.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 7

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    Archeological Monitoring Program. If the ERO in consultation with the archeological consultant determines that an archeological monitoring program shall be implemented the archeological monitoring program shall minimally include the following provisions:

    The archeological consultant, project sponsor, and ERO shall meet and consult on the scope of the AMP reasonably prior to any project‐related soils disturbing activities commencing. The ERO in consultation with the archeological consultant shall determine what project activities shall be archeologically monitored. In most cases, any soils‐ disturbing activities, such as demolition, foundation removal, excavation, grading, utilities installation, foundation work, driving of piles (foundation, shoring, etc.), site remediation, etc., shall require archeological monitoring because of the risk these activities pose to potential archaeological resources and to their depositional context;

    The archeological consultant shall advise all project contractors to be on the alert for evidence of the presence of the expected resource(s), of how to identify the evidence of the expected resource(s), and of the appropriate protocol in the event of apparent discovery of an archeological resource;

    Project sponsor/ archeological consultant at the direction of the ERO.

    During soils‐ disturbing activities.

    Project sponsor/archeological consultant shall meet and consult with ERO on scope of AMP. Archeological consultant to monitor soils‐disturbing activities specified in AMP and immediately notify ERO of any encountered archeological resource.

    Considered complete upon completion of archeological monitoring plan as outlined in the AMP.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 8

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    The archeological monitor(s) shall be present on the project site according to a schedule agreed upon by the archeological consultant and the ERO until the ERO has, in consultation with project archeological consultant, determined that project construction activities could have no effects on significant archeological deposits;

    The archeological monitor shall record and be authorized to collect soil samples and artifactual/ecofactual material as warranted for analysis;

    If an intact archeological deposit is encountered, all soils‐disturbing activities in the vicinity of the deposit shall cease. The archeological monitor shall be empowered to temporarily redirect demolition/excavation/pile driving/construction activities and equipment until the deposit is evaluated. The archeological consultant shall immediately notify the ERO of the encountered archeological deposit. The archeological consultant shall make a reasonable effort to assess the identity, integrity, and significance of the encountered archeological deposit, and present the findings of this assessment to the ERO.

    Whether or not significant archeological resources are

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 9

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    encountered, the archeological consultant shall submit a written report of the findings of the monitoring program to the ERO. Archeological Data Recovery Program. The archeological data recovery program shall be conducted in accord with an archeological data recovery plan (ADRP). The archeological consultant, project sponsor, and ERO shall meet and consult on the scope of the ADRP prior to preparation of a draft ADRP. The archeological consultant shall submit a draft ADRP to the ERO. The ADRP shall identify how the proposed data recovery program will preserve the significant information the archeological resource is expected to contain. That is, the ADRP will identify what scientific/historical research questions are applicable to the expected resource, what data classes the resource is expected to possess, and how the expected data classes would address the applicable research questions. Data recovery, in general, should be limited to the portions of the historical property that could be adversely affected by the proposed project. Destructive data recovery methods shall not be applied to portions of the archeological resources if nondestructive methods are practical. The scope of the ADRP shall include the following elements:

    Field Methods and Procedures. Descriptions of proposed field strategies, procedures, and

    ERO, archeological consultant, and project sponsor

    In the event that an archeological site is uncovered during the construction period

    Archeological consultant to prepare an ADRP and to undertake the archeological data recovery program in consultation with ERO.

    Considered complete upon completion of archeological data recovery plan as outlined in the ADRP.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 10

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    operations.

    Cataloguing and Laboratory Analysis. Description of selected cataloguing system and artifact analysis procedures.

    Discard and Deaccession Policy. Description of and rationale for field and post‐field discard and deaccession policies.

    Interpretive Program. Consideration of an on‐site/off‐site public interpretive program during the course of the archeological data recovery program.

    Security Measures. Recommended security measures to protect the archeological resource from vandalism, looting, and non‐intentionally damaging activities.

    Final Report. Description of proposed report format and distribution of results.

    Curation. Description of the procedures and recommendations for the curation of any recovered data having potential research value, identification of appropriate curation facilities, and a summary of the accession policies of the curation facilities.

    Human Remains, Associated or Unassociated Funerary Objects. The treatment of human remains and of associated or

    Archeological Consultant, ERO,

    Following discovery of

    Notification of ERO, Coroner and, as warranted, notification

    Considered complete on

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 11

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    unassociated funerary objects discovered during any soils disturbing activity shall comply with applicable State and Federal Laws, including immediate notification of the Coroner of the City and County of San Francisco and in the event of the Coroner’s determination that the human remains are Native American remains, notification of the California State Native American Heritage Commission (NAHC) who shall appoint a Most Likely Descendant (MLD) (Pub. Res. Code Sec. 5097.98). The ERO shall also be immediately notified upon discovery of human remains. The archeological consultant, project sponsor, ERO, and MLD shall have up to but not beyond six days after the discovery to make all reasonable efforts to develop an agreement for the treatment of human remains and associated or unassociated funerary objects with appropriate dignity (CEQA Guidelines. Sec. 15064.5(d)). The agreement should take into consideration the appropriate excavation, removal, recordation, analysis, curation, possession, and final disposition of the human remains and associated or unassociated funerary objects. Nothing in existing State regulations or in this mitigation measure compels the project sponsor and the ERO to accept recommendations of an MLD. The archeological consultant shall retain possession of any Native American human remains and associated or unassociated burial objects until completion of any scientific analyses of the human remains or objects as specified in the treatment agreement if such as agreement has been made or, otherwise, as determined by the archeological consultant and the ERO. If no agreement is reached State regulations shall be followed including the

    and Coroner.

    human remains.

    of NAHC.

    finding by ERO that all State laws regarding human remains/burial objects have been adhered to, consultation with MLD is completed as warranted, and that sufficient opportunity has been provided to the archeological consultant for scientific and historical analysis of remains and funerary objects.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 12

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    reinternment of the human remains and associated burial objects with appropriate dignity on the property in a location not subject to further subsurface disturbance (Pub. Res. Code Sec. 5097.98). Final Archeological Resources Report. The archeological consultant shall submit a Draft Final Archeological Resources Report (FARR) to the ERO that evaluates the historical significance of any discovered archeological resource and describes the archeological and historical research methods employed in the archeological testing/monitoring/data recovery program(s) undertaken. Information that may put at risk any archeological resource shall be provided in a separate removable insert within the final report. Once approved by the ERO, copies of the FARR shall be distributed as follows: California Archaeological Site Survey Northwest Information Center (NWIC) shall receive one (1) copy and the ERO shall receive a copy of the transmittal of the FARR to the NWIC. The Environmental Planning division of the Planning Department shall receive one bound, one unbound and one unlocked, searchable PDF copy on CD of the FARR along with copies of any formal site recordation forms (CA DPR 523 series) and/or documentation for nomination to the National Register of Historic Places/California Register of Historical Resources. In instances of high public interest in or the high interpretive value of the resource, the ERO may require a

    Archeological consultant at the direction of the ERO. Archeological consultant at the direction of the ERO.

    Following completion of cataloguing, analysis, and interpretation of recovered archeological data. Following completion of FARR and review and approval by ERO.

    Archeological consultant to prepare FARR. Following approval from the ERO, archeological consultant to distribute FARR.

    Considered complete upon review and approval of FARR by ERO. Considered complete upon certification to ERO that copies of FARR have been distributed.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 13

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    different final report content, format, and distribution than that presented above.

    Project Mitigation Measure 4 – Siting of Noise –Generating Uses (Implementing Western SoMa PEIR Mitigation Measure M-NO-1c)

    To ensure that project noise from the mechanical equipment meets the Police Code section 2909 noise requirement, the project sponsor shall undertake the following:

    • For heat pumps and supply fans, the project sponsor shall construct an acoustical barrier/roof parapet along the east edge of the project building that is a minimum of two feet taller than the top of the tallest rooftop mechanical equipment; and

    • For all other rooftop mechanical equipment such as exhaust fans, future tenant equipment, air handling units, or similar equipment, the project sponsor shall incorporate a combination of noise attenuation measures into stationary equipment installed on the project building. Noise attenuation measures can include providing sound enclosures, increasing setback distances from the property plane, providing louvered vent openings, and locating vent openings away from the property plan. The final rooftop mechanical equipment configuration shall demonstrate that noise levels along the property plan to the east are reduced to 58 dBA and

    Project sponsor, architect, acoustical consultant, and construction contractor. Project designer to incorporate mechanical equipment specifications and documentation into construction plans demonstrating compliance with Police Code section 2909 noise requirements.

    Prior to issuance of architectural addendum and at final building inspection.

    Planning Department and Department of Building Inspection to review and approve plans demonstrating compliance with Police Code section 2909.

    Considered complete upon approval of final construction plan set and final building inspection.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 14

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    noise levels along the property plane to the north are reduced to 62 dBA.

    Project Mitigation Measure 5: General Construction Noise Control Measures (Implementing Western SoMa PEIR Mitigation Measure M-NO-2a)

    To ensure that project noise from construction activities is minimized to the maximum extent feasible, the project sponsor shall undertake the following:

    • The project sponsor shall conduct noise monitoring at the beginning of major construction phases (e.g., demolition, excavation) to determine the need and the effectiveness of noise‐attenuation measures.

    • The project sponsor shall require the general contractor to ensure that equipment and trucks used for project construction use the best available noise control techniques (e.g., improved mufflers, equipment redesign, use of intake silencers, ducts, engine enclosures and acoustically attenuating shields or shrouds, wherever feasible).

    • The project sponsor shall require the general contractor to avoid placing stationary noise sources (such as generators and compressors) within noise‐sensitive buffer areas (measured at linear 20 feet) between immediately adjacent

    Project sponsor and construction contractor(s).

    Prior to and during demolition or construction activities.

    The project sponsor and construction contractor(s) shall submit a noise attenuation plan to the Department of Building Inspection and monthly reports to the Planning Department.

    Considered complete upon final monthly report.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 15

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    neighbors. The project sponsor shall construct barriers around such sources and/or the construction site, which could reduce construction noise by as much as 5 dBA. To further reduce noise, the contractor shall locate stationary equipment in pit areas or excavated areas, if feasible.

    • The project sponsor shall require the general contractor to use impact tools (e.g., jack hammers, pavement breakers, and rock drills) that are hydraulically or electrically powered wherever possible to avoid noise associated with compressed air exhaust from pneumatically powered tools. Where use of pneumatic tools is unavoidable, an exhaust muffler on the compressed air exhaust shall be used, along with external noise jackets on the tools, which could reduce noise levels by as much as 10 dBA.

    • The project sponsor shall require that all construction equipment be in good working order and that mufflers are inspected and determined to be functioning properly. The project sponsor shall require that all construction equipment and engines be operated so as to avoid unnecessary idling.

    • The project sponsor shall include noise control requirements in specifications provided to

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 16

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    construction contractors. Such requirements could include, but not be limited to: performing all work in a manner that minimizes noise to the extent feasible; undertaking the most noisy activities during times of least disturbance to surrounding residents and occupants, as feasible; and selecting haul routes that avoid residential buildings inasmuch as such routes are otherwise feasible.

    • Prior to the issuance of each building permit, along with the submission of construction documents, the sponsor shall submit to the San Francisco Planning Department and Department of Building Inspection (DBI) a list of measures to respond to and track complaints pertaining to construction noise. These measures shall include: (1) a procedure and phone numbers for notifying DBI, the Department of Public Health, and the Police Department (during regular construction hours and off‐hours); (2) a sign posted on‐site describing noise complaint procedures and a complaint hotline number that shall be answered at all times during construction; (3) designation of an on‐site construction complaint and enforcement manager for the project; and (4) notification of neighboring residents and non‐residential building managers within 300 feet of the project construction area at least 30 days in advance of extreme noise‐generating activities

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 17

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    (defined as activities generating noise levels of 90 dBA or greater at 50 feet) about the estimated duration of the activity.

    Project Mitigation Measure 6: Construction Emissions Minimization Plan for Health Risks and Hazards (Implementing Western SoMa PEIR Mitigation Measure M-AQ-7)

    The project sponsor or the project sponsor’s Contractor shall comply with the following:

    A. Engine Requirements.

    1. All off‐road equipment greater than 25 hp and operating for more than 20 total hours over the entire duration of construction activities shall have engines that meet or exceed either U.S. Environmental Protection Agency (USEPA) or California Air Resources Board (ARB) Tier 2 off‐road emission standards, and have been retrofitted with an ARB Level 3 Verified Diesel Emissions Control Strategy. Equipment with engines meeting Tier 4 Interim or Tier 4 Final off‐road emission standards automatically meet this requirement.

    2. Where access to alternative sources of power are available, portable diesel engines shall be prohibited.

    Project sponsor, contractor(s).

    Submit certification statement prior to construction activities requiring the use of off‐road equipment.

    Project sponsor, contractor(s) to submit certification statement to the ERO.

    Considered complete upon submittal of certification statement.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 18

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    3. Diesel engines, whether for off‐road or on‐road equipment, shall not be left idling for more than two minutes, at any location, except as provided in exceptions to the applicable state regulations regarding idling for off‐road and on‐road equipment (e.g., traffic conditions, safe operating conditions). The Contractor shall post legible and visible signs in English, Spanish, and Chinese, in designated queuing areas and at the construction site to remind operators of the two‐minute idling limit.

    4. The Contractor shall instruct construction workers and equipment operators on the maintenance and tuning of construction equipment, and require that such workers and operators properly maintain and tune equipment in accordance with manufacturer specifications.

    B. Waivers.

    1. The Planning Department’s Environmental Review Officer (ERO) or designee may waive the alternative source of power requirement of Subsection (A)(2) if an alternative source of power is limited or infeasible at the project site. If the ERO grants the waiver, the Contractor must submit documentation that

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 19

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    the equipment used for on‐site power generation meets the requirements of Subsection (A)(1).

    2. The ERO may waive the equipment requirements of Subsection (A)(1) if: a particular piece of off‐road equipment with an ARB Level 3 VDECS is technically not feasible; the equipment would not produce desired emissions reduction due to expected operating modes; installation of the equipment would create a safety hazard or impaired visibility for the operator; or, there is a compelling emergency need to use off‐road equipment that is not retrofitted with an ARB Level 3 VDECS. If the ERO grants the waiver, the Contractor must use the next cleanest piece of off‐road equipment, according to the table below.

    Table – Off-Road Equipment Compliance Step-down Schedule

    Engine Emission Standard Emissions Control

    Tier 2 ARB Level 2 VDECS

    Tier 2 ARB Level 1 VDECS

    Tier 2 Alternative Fuel*

    How to use the table: If the ERO determines that the equipment requirements cannot be met, then the project sponsor would need to meet Compliance Alternative 1. If the ERO determines that the Contractor cannot supply off‐road equipment meeting Compliance Alternative 1, then the Contractor must meet Compliance Alternative 2.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 20

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    If the ERO determines that the Contractor cannot supply off‐road equipment meeting Compliance Alternative 2, then the Contractor must meet Compliance Alternative 3. Alternative fuels are not a VDECS.

    C. Construction Emissions Minimization Plan. Before starting on‐site construction activities, the Contractor shall submit a Construction Emissions Minimization Plan (Plan) to the ERO for review and approval. The Plan shall state, in reasonable detail, how the Contractor will meet the requirements of Section A.

    1. The Plan shall include estimates of the construction timeline by phase, with a description of each piece of off‐road equipment required for every construction phase. The description may include, but is not limited to: equipment type, equipment manufacturer, equipment identification number, engine model year, engine certification (Tier rating), horsepower, engine serial number, and expected fuel usage and hours of operation. For VDECS installed, the description may include: technology type, serial number, make, model, manufacturer, ARB verification number level, and installation date and hour meter reading on installation date. For off‐road equipment using alternative

    Project sponsor, contractor(s).

    Prepare and submit a Plan prior to issuance of a permit specified in Section 106A.3.2.6 of the San Francisco Building Code.

    Project sponsor, contractor(s) and the ERO.

    Considered complete upon findings by the ERO that the Plan is complete.

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 21

    MONITORING AND REPORTING PROGRAM

    Adopted Mitigation/Improvement Measures

    Responsibility for

    Implementation

    Mitigation Action and Schedule

    Monitoring and Reporting Responsibility

    Status / Date Completed

    fuels, the description shall also specify the type of alternative fuel being used.

    2. The ERO shall ensure that all applicable requirements of the Plan have been incorporated into the contract specifications. The Plan shall include a certification statement that the Contractor agrees to comply fully with the Plan.

    3. The Contractor shall make the Plan available to the public for review on‐site during working hours. The Contractor shall post at the construction site a legible and visible sign summarizing the Plan. The sign shall also state that the public may ask to inspect the Plan for the project at any time during working hours and shall explain how to request to inspect the Plan. The Contractor shall post at least one copy of the sign in a visible location on each side of the construction site facing a public right‐of‐way.

    D. Monitoring. After start of construction activities, the Contractor shall submit quarterly reports to the ERO documenting compliance with the Plan. After completion of construction activities and prior to receiving a final certificate of occupancy, the project sponsor shall submit to the ERO a final report

    Project sponsor, contractor(s).

    Submit quarterly reports.

    Project sponsor, contractor(s) and the ERO.

    Considered complete upon findings by the ERO that the Plan is being/has been

  • 1 1 4 4 - 1 1 5 0 H A R R I S O N S T R E E T C A S E N O . 2 0 1 6 - 0 0 1 7 3 8 E N V M I T I G A T I O N M O N I T O R I N G A N D R E P O R T I N G P R O G R A M A P R I L 2 0 1 8 22

    MONITORING AND REPORTING PROGRAM

    Adopted Miti