7x24 nor cal om best practices presentation rev4 9-1-2011

Upload: sathiaram-ram

Post on 03-Jun-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    1/41

    Presented by:

    Terry Rodgers, CPE, CPMP

    Vice President, Sustainable Operations

    Primary Integration Solutions, Inc.

    [email protected]

    DATA CENTER O&M BEST

    PRACTICES

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    2/41

    www.primaryintegration.com

    Data Center O&M Best PracticesPerspectives

    Designing for Maintainability

    Commissioning, Construction, Startup & TestingO&M Staffing and Organization

    Operations & Maintenance Processes

    Existing Facilities

    Agenda

    2

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    3/41

    www.primaryintegration.com

    Data Center O&M Best Practices

    As the robustness & complexity of critical facilities has increased for

    improved fault-tolerance and concurrent maintenance, the importanceof equally robust O&M practices has become apparent.

    As much as 75% or more impact events where critical missions

    have been compromised are associated with human Activity.

    3

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    4/41

    www.primaryintegration.com 4

    A&E Programming, engineer & design, submittals & RFIs, CA

    6 to 9 months of intense effort then some minor CA support

    GC & Contractors Propose, purchase, construct, punch/commission9 to 15 months with minor follow-up effort

    Mfgrs & Vendors Submittals/shop dwgs, assemble, startup & commission3 to 6 months and a 12 month warranty + SLAs

    CxA Design, construction, startup, acceptance, training & documentation9 to 15 months plus 10 month pre-warranty return effort

    Owner Design, construct, commission, transition, sustained operations15 months design/construction, 12 months transition, 24 yearsoperations

    Perspectives

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    5/41

    www.primaryintegration.com 5

    The A&Es, GC & Contractors, Manufacturers and Vendors, andCommissioning Agents completion date (i.e., project close-out)

    is the Owners start date (i.e., Day-1 of mission critical operations)

    Dont let Sustainable Operations be an after-thought!

    Perspectives

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    6/41

    www.primaryintegration.com

    Designing for Maintainability

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    7/41

    www.primaryintegration.com

    Include facility O&M considerations in the programming phase

    Define facility O&M needs and expectations in the Basis-of-Design

    Specify the associated O&M deliverables in the Construction Documents

    Designing for Maintainability

    7

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    8/41

    www.primaryintegration.com

    Include O&M considerations in the programming phase via the Owners Project Requirements(OPR) document

    O&M Organization, Reporting Structure, & Budget

    O&M Staffing (24x7 Coverage, Trades, Quals, etc.)

    In-House, Outsourced, SLA, or a combination

    Training Program (Day-1, New Hire, & Recurring)

    O&M Programs & Processes

    CMMS (new or expand existing)

    Asset Management System (inventory control)

    Configuration Management System

    Comprehensive As-Built Documentation & Doc Control

    Facilities Management space-planning (offices, command center, shops, etc.)

    Designing for Maintainability

    8

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    9/41

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    10/41

    www.primaryintegration.com

    CDs (Drwgs & Specs) should define O&M deliverables as part of the overall construction project

    Equipment, System, & Space naming and color conventions

    Signage, Bar-coding, RFID, etc.

    A vs. B plants (mechanical & electrical) should be easily differentiated

    Color code systems (mechanical, electrical, controls, critical vs. non-critical, etc.)

    Valve and switch tagging

    Drawings should include Valve and Switch schedules (tables)

    Specifications should dictate size, material, location, ease-of-view, etc.

    Maintenance and access requirements

    Shown on drawings, permanently identified in field

    Access panels with labels where covered/closed-in

    Heavy equipment transport including truck/forklift routes, overhead rigging, pick-points

    Emergency lighting (response vs. egress)

    Storage and spare parts requirements

    Designing for Maintainability

    10

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    11/41

    www.primaryintegration.com

    Most (if not all) Data Centers are designed with the expectation they will be expanded or modifiedduring their lifespan

    The design must accommodate this expectation

    Appropriate means to isolate infrastructure between production from expansion

    Avoid loss of redundancy schemes during construction

    These situationsincrease the risk of impact events occurring and are when quality O&M

    processes are most important

    O&M staff well trained and practiced at reconfiguring systems and isolating equipment and

    distribution paths

    Updated and accurate as-built docs and operating procedures

    Critical work authorization review and approval processes

    Routine means to test/verify isolation points (valve leak tests, breaker tests, etc.)

    Designing for Maintainability

    11

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    12/41

    www.primaryintegration.com

    Specifications should include defining close-out documentation As-Built (vs. redlines) and exact content and formats

    Redlines maintained throughout construction

    Formal Record Drawings (As-Built) in hardcopy & electronic

    Field verified for accuracy prior to acceptance

    O&M Training details, deliverables, content, effort, and quality

    Systems Operations & Maintenance Manuals (vs. Manufacturers O&M manuals)

    Designing for Maintainability

    12

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    13/41

    www.primaryintegration.com

    Systems Operations & Maintenance Manuals (SOMMs) should be organized by category(HVAC, FP, Security, BMS, etc.), system, & sub-system

    Include for each system:

    Descriptive narrative

    Single-line diagrams (one for each operating mode and/or configuration)

    Sequences-of-Operations, setpoints, alarm thresholds, safeties, etc. BMS points lists (DIs, DOs, AIs, AOs, etc.)

    Standard Operating Procedures (Normal, Maint., Emergency, Recovery, etc.)

    Approved submittals

    Commissioning scripts including baseline data

    Spare Part Lists (including on-site inventory)

    Warranties

    Service Level Agreements

    Designing for Maintainability

    13

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    14/41

    www.primaryintegration.com

    Specifications should define O&M Training Curriculum, Scope, & Content Venues (classroom, shop, on-the-job)

    Instructor qualifications

    Duration and times (i.e., shift coverage)

    Testing and/or certifications

    Safety considerations (OSHA, Arc Flash, PPE, etc.)

    Operating procedures (normal, maintenance, emergency, & recovery modes)

    Equipment level, Systems level, and Integrated Systems level scenarios

    Maintenance procedures (inspections, preventive, predictive, corrective, replacement, etc.)

    NOTE: Commissioning affords excellent training opportunities

    Designing for Maintainability

    14

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    15/41

    www.primaryintegration.com

    Commissioning, Construction, Startup & Testing

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    16/41

    www.primaryintegration.com

    The overarching goal is to deliver the site, staff, and processes totally constructed andprovisioned on Day-1 to support 24x7 mission uptime for the life of the facility.

    Commissioning Process Design Phase

    Commissioning Process Strategy

    Use the Commissioning Process to Provision for O&M

    Transition from Construction to Production

    ASHRAE Guideline 0-2005 The Commissioning Process is an excellent reference and

    user-friendly guide geared towards new construction. A sister guideline is currently

    being developed for commissioning existing facilities.

    Commissioning, Construction, Startup & Testing

    16

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    17/41

    www.primaryintegration.com

    Commissioning process (Cx is not a procedure) Design Phase

    Ensure the OPR captures construction QC, performance validation, and facility O&M

    considerations

    Ensure the BOD complies with the OPR and defines high-level requirements

    Ensure the CDs comply with the BOD and include clear and concise specifications

    Ensure the CDs capture the requirements and effort associated with Commissioning

    (including documentation & training)

    Develop the Commissioning Plan to ensure the built product can be operated,

    maintained, and tested to validate performance

    Commissioning, Construction, Startup & Testing

    17

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    18/41

    www.primaryintegration.com

    Commissioning Process Strategy Identify issues and discrepancies as early as possible so they can be resolved with least

    impact on schedule, resources, and costs

    Factory Witness Tests identify issues prior to shipment

    Field Component Verification identifies issues upon receipt and ensure proper

    storage & care prior to installation Systems Construction Verification (progress inspections) identify issues prior to

    start-up and functional testing

    Site Acceptance Testing identifies issues at the component, equipment, and system

    level before testing interfaces

    Integrated Systems Testing identifies issues at system interfaces and facility-widelevel prior to going live.

    Commissioning, Construction, Startup & Testing

    18

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    19/41

    www.primaryintegration.com

    Use the Commissioning Process to provision for O&M Use the Commissioning design review process to ensure the OPR, BOD, and CDs capture

    O&M needs

    O&M staff participation in commissioning (FWTs, inspections, and testing) affords in-depth

    ops training and establishes contacts with the EOR, mfgrs/vendors, and contractors

    Submittals, Field Component Verification, equipment startup forms, and completed test

    scripts can capture and document data for input to the CMMS, AMS, & CMS and spare

    parts collection & inventory

    Functional Tests and Integrated Systems Tests set the original baseline for performance

    Commissioning, Construction, Startup & Testing

    19

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    20/41

    www.primaryintegration.com

    Use the Commissioning Process to provision for O&M The Commissioning Process includes ensuring the built facility is thoroughly documented

    System Operations & Maintenance Manuals should be developed concurrently with the

    construction phase

    SOMMs are a compilation of data and documents from:

    OPR, BOD, and CDs

    Record Drawings (As-Builts)

    Approved Submittals

    Final Commissioning Report & completed test scripts

    Warranties, SLAs, etc.

    Commissioning, Construction, Startup & Testing

    20

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    21/41

    www.primaryintegration.com

    Use the Commissioning Process to provision for O&M Training Start with a comprehensive Training Plan

    Develop a Training Program that is site and client specific

    Embed training in the construction and acceptance testing phases

    Utilize the site SOMMs to support and supplement training materials

    Design training to match O&M staff position descriptions

    Integrate project specific technical training with Corporate policy & procedures training

    Training material should be editable so it can be updated and kept current

    Training delivery should be recorded for future use (new-hires, remedial training, periodic

    re-training, and refresher training prior to infrequently performed activities)

    Commissioning, Construction, Startup & Testing

    21

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    22/41

    www.primaryintegration.com

    O&M Staffing and Organization

    Remember the following should be addressed during the programming

    phase and should influence how the facility is designed and built!

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    23/41

    www.primaryintegration.com

    Use an Enterprise reporting structure Critical Facilities O&M should be a department within the IT division

    Fundamentally eliminate the silos

    Recognize the mutual support and dependence of IT and Facilities on each other

    Combined goals drives collaboration and planning (sink or swim together)

    Eliminate competition for resources (staff & $$$)

    Combine NOC and Facilities Command Center operations into an Enterprise

    Command & Control Center

    Formalize and communicate load vs. capacity tracking, trending, and management

    O&M Staffing & Organization

    23

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    24/41

    www.primaryintegration.com

    Staff the O&M department to meet site specific needs Start with a site specific O&M Job Analysis (dont confuse jobs with positions)

    Compile list of Jobs (tasks) required to O&M the site infrastructure

    Differentiate between operations and maintenance tasks

    Develop Job Descriptions that group tasks and assess what requisite skills and

    knowledge are required

    Identify all that pertain to critical facilities

    Consider what qualifications, certifications, or other credentials are necessary where

    appropriate

    Decide how critical vs. non-critical aspects will be structured Decide how operations vs. maintenance aspects will be structured

    O&M Staffing & Organization

    24

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    25/41

    www.primaryintegration.com

    Staff the O&M department to meet site specific needs - continued Develop Position Descriptions

    Position Descriptions describe the jobs and associated tasks, duties and

    responsibilities expected for a specific staff position

    Assemble with the following considerations:

    Combined O&M or separate Operations from Maintenance

    Jack-of-all-trades or Trade-specific (mechanic, electrician, controls tech, etc.)

    True 24x7 coverage or Business Day + On-Call for off hours

    Compile a list of duties and responsibilities based on the tasks and associated skills

    and knowledge from the Job descriptions Decide how to staff each position (Direct employees, in-house contractors,

    SLAs, or a combination)

    O&M Staffing & Organization

    25

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    26/41

    www.primaryintegration.com

    Staff the O&M department to meet site specific needs - continued Develop an Organization and Reporting Structure

    Enterprise level organization

    Facilities O&M level organization

    Critical Facilities vs. Non-Critical Facilities

    Operations with shift coverage

    Maintenance broken down by trades

    Electrical (Med Volt, Low Volt, Gensets, UPS, etc.)

    Mechanical (Central Plant, HVAC, Chem Treatment, etc)

    Monitoring & Controls (BMS, EPMS, calibrations, etc.) Vendors, Contractors, SLAs, etc.

    Administration (CMMS, procurement, work approvals, etc.)

    O&M Staffing & Organization

    26

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    27/41

    www.primaryintegration.com

    Operations & Maintenance Processes

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    28/41

    www.primaryintegration.com

    Start with well defined Facilities Management mission Develop a mission or Vision statement

    Create a Strategic Plan with well defined goals and tactical objectives

    Develop programs and processes first, then supporting policies &

    procedures

    Operations & Maintenance Processes

    28

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    29/41

    www.primaryintegration.com

    Establish Operations Program and Processes

    Work authorization process (routine, PM, emergency, etc.)

    Event notification & escalation protocols

    Define Operations Key Performance Indicators (KPIs)

    What defines operational excellence and how is it measured?

    Critical vs. Non-critical boundary and operating protocols

    Practice (dry-runs)

    Double verification

    Mimic boards or other real-time configuration status

    Valve and switch position status tags

    Lock-out/Tag-out and other Safety Programs

    Operations & Maintenance Processes

    29

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    30/41

    www.primaryintegration.com

    Establish Operations Procedures

    Specific to each system

    Normal, maintenance (configuration), emergency, and recovery procedures

    Include pre-requisites and cautions

    Work authorization requirements

    Safety considerations (lock-out/tag-out, PPE, etc.)

    BMS and alarm lock-outs

    Verification of status of redundant or backup systems, etc.

    Operations & Maintenance Processes

    30

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    31/41

    www.primaryintegration.com

    Establish Operations Procedures - Continued

    Provide step-by-step procedure including action to be taken, expected result (alarm,

    indication, action, etc.), and means to collect resulting data (actual alarm, reading, action,

    etc.).

    Embed digital photos of equipment, components, and especially displays and control

    panels

    Annotate with arrows and relate to specific steps, actions, readings, etc.

    Consider using a flowchart format

    Include contingency and direction if expected does not match predicted

    Include completion/closeout checklist to ensure all aspects of system are restored to

    normal operating status (reactivate BMS, remove switch tags, lockouts, notify NOC, etc.)

    Operations & Maintenance Processes

    31

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    32/41

    www.primaryintegration.com

    Establish Maintenance Program and Processes

    Define Maintenance Key Performance Indicators (KPIs)

    What defines maintenance excellence and how is it measured?

    Develop programs to manage assets, configurations, and documentation

    Asset Management System (AMS)

    Bar-code equipment and components

    Computerize inventory, location, and who is authorized to pull stock

    Include shelf-life, PMs (rotate shafts, etc.), and other storage considerations

    Source, vendors, warranties, spec sheets, etc.

    Operations & Maintenance Processes

    32

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    33/41

    www.primaryintegration.com

    Establish Maintenance Processes - Continued

    Configuration Management System (CMS)

    Computerized database of deployed assets & interconnectivity

    Sum loads and capacities to track & alarm at defined thresholds

    Can be integrated with Work Flow processes so asset deployment, relocation, or

    decommissioning automatically generates updates to CMS Can combine both IT, Network, and Facilities infrastructure

    Utilize actual real-time metering (BMS, branch-circuit monitoring, Tivoli, HP Openview,

    etc.) where available

    Use eDiscovery for auto audits where possible

    Set thresholds low enough to ensure redundancy and fail-over strategies remain valid

    Operations & Maintenance Processes

    33

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    34/41

    www.primaryintegration.com

    Establish Maintenance Processes - Continued

    Computerized Maintenance Management System (CMMS)

    Implementation tool for the Maintenance Program

    Include install date, warranty duration, lifespan/replacement date

    Provides input to develop and maintain 5-year & 10-year Capital Plans

    Meet or exceed manufacturer recommendations

    Stagger dates for work load leveling, seasonal considerations, & freeze windows

    Tie to Maintenance Procedures

    Separate daily, weekly, monthly, quarterly, etc

    Develop logical ID convention that facilitates filtering, searching, and reporting ease

    (from design phase!!!)

    Operations & Maintenance Processes

    34

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    35/41

    www.primaryintegration.com

    Establish Maintenance Processes - Continued

    Types of Maintenance Programs

    Corrective run to failure

    Preventive routine based on frequency or run-hours

    Predictive On-line condition monitoring with thresholds; extrapolate trends to predict

    needs (predict failures) Vibration analysis (snap-shot or continuous via multiplex)

    Thermography (IR Scans) and temperature sensors

    Tribology (lubricant analysis)

    Laser Alignment

    Computerized Balancing Combination of all above

    Input field notes and create equipment histories and review routinely

    Operations & Maintenance Processes

    35

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    36/41

    www.primaryintegration.com

    Establish Maintenance Procedures

    Specific to each system and equipment

    Separate procedure for daily, weekly, monthly, quarterly, etc.

    Include pre-requisites and cautions (similar to Ops procedures)

    Provide step-by-step procedure (similar to Ops procedures)

    Include acceptance criteria, tolerances, settings, etc.

    Include access considerations (ladder, confined space, PPE, key#)

    Include ability to take field notes, comments, technician ID, etc.

    Include completion checklist to ensure all aspects of system are restored to normal

    operating status (reactivate BMS, remove switch tags, lockouts, etc)

    Operations & Maintenance Processes

    36

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    37/41

    www.primaryintegration.com

    Implement BIMS(Building Information Modeling System)

    BIMS products are still relatively new to the industry

    BIMS software uses databases to link electronic data, records, and documents including

    AutoCAD drawings

    BIMS includes virtual 3D models in layers such that you can simulate the construction and

    identify conflicts, fouls, and sequence conflicts

    BIMS can link AutoCAD objects to associated specs, quantities, suppliers/vendors,

    submittals, warranties, inventory, ordering info, maintenance history, and almost any other

    electronic record

    BIMS can link CDs to CMMS, AMS, CMS, etc.

    BIMS implementation, use, and upkeep requires significant pre-planning and resource

    allocation

    Operations & Maintenance Processes

    37

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    38/41

    www.primaryintegration.com

    Existing Facilities

    Build / improve programs to support management, staff, and infrastructure using the

    Sustainable Operations Services (SOS) Methodology

    The SOS Methodology:

    1) Define the requirements and establish acceptance criteria

    2) Evaluate / Assess actual conditions and develop a gap report3) Make recommendations to bridge the gap4) Build the needed program(s) based on client/site-specificBest Practices5) Build the associated processes and procedures6) Train management and staff on the program(s), processes, & procedures7) Implement the program(s), processes, and procedures

    8) Test, verify, audit the results9) Reassess and apply Continuous Process Improvement

    Operations & Maintenance Processes

    38

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    39/41

    www.primaryintegration.com 39

    Data Center O&M Best Practices

    As with Critical Facility design, there are few absolute right and wrong

    solutions. The O&M Best Practice for a given facility depends upon

    many (often conflicting or competing) variables.

    What is most important, is plan ahead, select a solution, and then

    execute in a high quality manner.

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    40/41

    www.primaryintegration.com 40

    Sustainable Operations

    Data Centers will undergo change during their lifespan (expansions,

    infrastructure upgrades, & technology refresh, etc.)

    Industry Best Practices will change and evolve

    Long-term Sustained Operations require programs with integral

    performance measurement and Continuous Process Improvement

  • 8/12/2019 7x24 Nor Cal OM Best Practices Presentation Rev4 9-1-2011

    41/41