 Advanced Planning in Supply Chains -Illustrating the Concepts Using an SAP APO Case Study

7 Global Available-to-Promise (global ATP)

Page 2: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 2/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 2

Page 3: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 3/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 3

Page 4: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 4/28

7.1 ATP: Basics and Literature

•  ATP quantities

• Time series of quantities available for new orders• In the Frutado case (MTS): Quantities of a certain finished product

•  ATP quantities consider:

• Current inventory

•  Already released production or purchase orders

• Planned but not yet released production or purchase orders

• Reservations for already promised customer orders

 Advanced Planning in Supply Chains 4

Page 5: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 5/28

7.1 ATP: Basics and Literature

• Calculation of the Available-to-Promise Quantities

 Advanced Planning in Supply Chains 5

  1 2 3 4

0  2

()  3 5 3 3

()  2 5

()  3 8 6 9

()  3 6 6 9

 ()  3 3 3

Table 7.1 Calculation of ATP quantities for 0  = 1 

Page 6: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 6/28

7.1 ATP: Basics and Literature

• Cumulated ATP quantities  

• Total available quantity of a product for a certain date t

•  ATP quantities   

•  Available quantity of a supply on a certain date t for new orders

(used in availability check!)

• Relationship between   and  

•    = ∑   =  

•    =   − 

 Advanced Planning in Supply Chains 6

Page 7: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 7/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 7

Page 8: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 8/28

7.2.1 Planning Tasks

• Order Promising:

• Decision on acceptance and delivery date of newly arrived orders• Refusal of some orders is possible

• Modes of Order Promising

• Real-time Order Promising (instant processing of new orders,

often used in MTS-Case)

• Batch Order Promising (processing of new order in certain timeintervals)

• Demand Supply Matching

• In case of short ATP quantities:

• Decision on late deliveries, substitution or even cancellation of

orders

• Substitution e.g. alternative product, alternative location (DC),

alternative Production Process Model (PPM)

 Advanced Planning in Supply Chains 8

Page 9: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 9/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 9

Page 10: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 10/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 10

Page 11: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 11/28

7.3.1 Introduction to SAP APO Global ATP

• Information Flows between SAP APO and the ERP

 Advanced Planning in Supply Chains 11

Figure 7.1 

Page 12: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 12/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 12

Page 13: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 13/28

7.3.2 Customization of Order Promising at the Frutado

Company

• Parameters for Global ATP

 Advanced Planning in Supply Chains 13

Figure 7.2 

Page 14: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 14/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 14

Page 15: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 15/28

7.3.3 Basic Global ATP Model and Implementation for

Frutado

 Advanced Planning in Supply Chains 15

 Availability Check

• Check for sufficient ATP quantities

• Order requirements are matched with ATP time series

• Based on ATP quantities of requested location-product

• Procedure• Check for sufficient ATP not later than material availability deadline

(latest date at which order must be shipped to hold confirmed delivery date)

• Search for new possible confirmed date in case of shortage

Page 16: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 16/28

7.3.3 Basic Global ATP Model and Implementation for

Frutado

•  Availability Check

 Advanced Planning in Supply Chains 16

Figure 7.3:

Calculation of the

material availability

deadline and logic of the

product availability check

Page 17: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 17/28

7.3.3 Basic Global ATP Model and Implementation for

Frutado

 Advanced Planning in Supply Chains 17

Rules-Based ATP Check

• Method for availability check with additional measures in shortagesituations

• Order of possible measures to be specified, e.g.

1. alternative products as substitutes,

2. alternative sourcing locations,

3. alternative PPM

4. etc.

• Rules-Based ATP check follows this specified sequence

Page 18: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 18/28

7.3.3 Basic Global ATP Model and Implementation for

Frutado

• Sequence for the Rules-Based Search

 Advanced Planning in Supply Chains 18

Figure 7.4 

PPM

Page 19: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 19/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 19

Page 20: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 20/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 20

Page 21: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 21/28

7.3.5 Processing the Results

• Overlapping functions in the Global ATP und Deployment modules

• Demand Supply Matching performed by the Deployment module fora batch of already promised orders

• Real-Time Order Promising performed by Global ATP for new orders

 Advanced Planning in Supply Chains 21

Page 22: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 22/28

7 Global Available-to-Promise (global ATP)

7.1 ATP: Basics and Literature

7.2 Planning Tasks and Data for Frutado

7.2.1 Planning Tasks

7.2.2 Data

7.3 Modeling the Frutado Planning Tasks and Implementation in Global ATP

7.3.1 Introduction to SAP APO Global ATP

7.3.2 Customization of Order Promising at the Frutado Company

7.3.3 Basic Global ATP Model and Implementation for Frutado

7.3.4 Extensions

7.3.5 Processing the Results

7.4 Global ATP Learning Units

Contents

 Advanced Planning in Supply Chains 22

Page 23: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 23/28

7.4 Global ATP Learning Units

•  Availability Check: Confirmation I

 Advanced Planning in Supply Chains 23

Figure 7.5: SAP-Screenshot Confirmation situation in scenario I

Page 24: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 24/28

7.4 Global ATP Learning Units

•  Availability Check: Overview I

 Advanced Planning in Supply Chains 24

Figure 7.6: SAP-Screenshot  Availability situation in scenario I

Page 25: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 25/28

7.4 Global ATP Learning Units

•  Availability Check: Confirmation II

 Advanced Planning in Supply Chains 25

Figure 7.7: SAP-Screenshot Confirmation situation in scenario II

Page 26: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 26/28

7.4 Global ATP Learning Units

•  Availability Check: Confirmation III

 Advanced Planning in Supply Chains 26

Figure 7.8: SAP-Screenshot Confirmation situation in scenario III

Page 27: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 27/28

7 Global Available-to-Promise - Bibliography

• Ball, M. O.; Chen, C.-Y.; Zhao, Z.-Y. (2004) Available-to-promise, in: D.

Simchi-Levi; S. D. Wu; Z.-J. Shen (Eds.) Handbook of Quantitative

Supply Chain Analysis – Modeling in the E-Business Era, chap. 11,

Kluwer Academic, 447–483

• Dickersbach, J. (2009) Supply Chain Management with APO, Springer,

Heidelberg

• Fleischmann, B. (2008) Distribution and transportation planning, in: H.Stadtler; C. Kilger (Eds.) Supply Chain Management and Advanced

Planning, Springer, Berlin et al., 231–246

• Fleischmann, B.; Meyr, H. (2004) Customer orientation in advanced

planning systems, in: H. Dyckhoff; R. Lackes; et al. (Eds.) Supply chain

management and reverse logistics, Springer, Heidelberg, 297–321

• Kilger, C.; Meyr, H. (2008) Demand fulfillment and ATP, in: H. Stadtler;

C. Kilger (Eds.) Supply Chain Management and Advanced Planning,

Springer, Berlin et al., 181–198

 Advanced Planning in Supply Chains 27

Page 28: 7. Global Available-To-Promise Version 1.0

7/18/2019 7. Global Available-To-Promise Version 1.0

http://slidepdf.com/reader/full/7-global-available-to-promise-version-10 28/28

7 Global Available-to-Promise - Bibliography

• Meyr, H. (2008) Clustering methods for rationing limited resources, in: L.

Mönch; G. Pankratz (Eds.) Intelligente Systeme zur

Entscheidungsunterstützung. Konferenzband zur Teilkonferenz der

Multikonferenz Wirtschaftsinformatik München, 26.02.2008-28.02.2008,

SCS Publishing House e.V., San Diego et al., S. 19–31

• Meyr, H. (2009) Customer segmentation, allocation planning and order

promising in make-to-stock production, OR Spectrum, vol. 31, 229–256• Pibernik, R. (2005) Advanced available-to-promise: Classification,

selected methods and requirements for operations and inventory

management, International Journal of Production Economics, vol. 93,

239–252

• Pibernik, R.; Yadav, P. (2009) Inventory reservation and real-time orderpromising in a make-to-stock system, OR Spectrum, vol. 31, 281–307

• Schwendinger, J. (1979) Master production scheduling’s available-to-

promise, in: APICS Conference Procedings, 316–330

Advanced Planning in Supply Chains 28