7-1 copyright © 2013 mcgraw-hill education (australia) pty ltd pearson, larson, gray, project...

26
7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

Upload: claire-woods

Post on 24-Dec-2015

220 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-1Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

CHAPTER 7

Project Time Management

Page 2: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-2Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Developing the Project Schedule

• The project schedule is a chart that graphically depicts the sequence, interdependencies and start and finish times of the project.

• The project schedule also depicts the activities to enable the identification of the critical path.

• The project schedule allows for tracking time variances when the project is being executed.

Page 3: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-3Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

From Work Package To Network

Page 4: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-4Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Activity-on-Node (AON) Fundamentals

• A = Sequences

• B = Burst

• C = Merge

• D = Parallel

6–4

Page 5: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-5Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Sequence the Activities

Page 6: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-6Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Add the Durations

Page 7: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-7Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Carry out the Forward PassMaximum of Preceding Activities

Page 8: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-8Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Carry out the Backward Pass Minimum of Succeeding Activities

Page 9: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-9Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Calculate the Slack or Float

Page 10: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-10Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Identify the Critical PathFree slack example

Page 11: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-11Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Identify the Critical Path (cont.)

• The longest path through the activity network that allows for the completion of all project-related activities.

• The shortest expected time in which the entire project can be completed.

• Delays on the critical path will delay completion of the entire project.

Page 12: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-12Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Extended Network Techniquesto Come Closer to Reality

Laddering

• Under the standard finish-to-start relationship, when an activity has a long duration and will delay the start of an activity immediately following it, the activity can be broken into segments.

• The network can be drawn using a laddering approach so the following activity can begin sooner and not delay the work.

Page 13: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-13Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Example of Laddering Using Finish-to-start Relationship

Page 14: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-14Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Extended Network Techniques to Come Close to Reality (Cont.)

Lag

• A lag directs a successor activity to be delayed.

Lead

• A lead allows acceleration of a successor activity.

Page 15: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-15Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Hammock Activities

• An activity that spans a segment of a project.

• Duration of hammock activities is determined after the network plan is drawn.

• Hammock activities are used to aggregate sections of the project to facilitate getting the right amount of detail for specific sections of a project.

6–15

Page 16: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-16Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Common Gantt Chart Relationships

Moving the AON to a Project Schedule

(See following slides)

Page 17: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-17Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Finish-to-Start Relationship (FS)

Page 18: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-18Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Start-to-Start Relationship

Page 19: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-19Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Finish-to-Finish Relationship

Page 20: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-20Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Air Control Project—

Gantt Chart

Page 21: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-21Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Options for Accelerating Project Completion

When resources are not constrained…

• Crashing The most common method for shortening project time is to assign additional staff and equipment (resources) to activities (crashing the project schedule)

• Outsourcing project work

• Scheduling overtime

• Do it twice, fast and then correctly

Page 22: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-22Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Options for Accelerating Project Completion (cont.)

When resources are constrained…

• Fast tracking Sometimes it is possible to rearrange the logic of the project network so that critical activities are done in parallel (concurrently) rather than sequentially

• Critical-chain project management

• Reducing project scope

• Compromising quality

Page 23: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-23Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Options for Accelerating Project Completion (cont.)

When cost is the issue…

• Reduce project scope

• Have the owner take on more responsibility

• Outsource activities or the whole project

• Brainstorm cost-savings options

Page 24: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-24Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Resource Allocation Methods

Page 25: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-25Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Project Scope Integration

Page 26: 7-1 Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e CHAPTER 7 Project Time Management

7-26Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd

Pearson, Larson, Gray, Project Management in Practice, 1e

Key TermsactivityActivity-on-Arrow (AOAActivity-on-Node (AON)burst activityconcurrent engineeringcrashingcritical pathdanglerfast-trackingfree slackGantt charthammock activityheuristicladdering

lag relationshiplagslevellingmerge activityparallel activity parallel/sequence activitiespathresource-constrained projectresource-constrained schedulingresource smoothingsensitivityslack/float (total) splittingtime-constrained project