6.1_adapting the integrated grid economic framework to microgrids_roark_epri/snl microgrid
TRANSCRIPT
1© 2016 Electric Power Research Institute, Inc. All rights reserved. © 2016 Electric Power Research Institute, Inc. All rights reserved.
Symposium on Secure and Resilient Microgrids
August, 2016Baltimore, MD
Jeffrey D. RoarkTechnical Executive
Power Delivery & Utilization
Adapting the Integrated Grid Economic Framework
to Microgrids
2© 2016 Electric Power Research Institute, Inc. All rights reserved.
The dynamic power system of the future requires an
end-to-end integrated approach.
AnIntegrated
Grid
EPRI’s Integrated Grid Initiative
30020027333002004878
At EPRI.com, search for the complete number: 300200xxxx
3© 2016 Electric Power Research Institute, Inc. All rights reserved.
What do we mean by “Benefit-Cost Framework”?
Benefit-CostAnalysisProcess
Phenomena
Net Costs& Benefits
Cost & Benefit
Components∆ Fuel
∆ O&M
∆ RevenueRequirements
∆ Customer Costs
∆ InterruptionCost
Costs,Investments
Impacts &Phenomena
∆ Loss kWh
∆ Load kWh
∆ Gen kWh
∆ Ancillary Services
∆ T&DInvestment
A CBA “Framework” can be expressed in termsof impacts & phenomena to be included,
or in terms of cost and benefit components.A framework also specifies the perspective or point of view.
ProposedProject
Base/Comparison
Case
Costs,Investments
Phenomena
4© 2016 Electric Power Research Institute, Inc. All rights reserved.
Types of Benefit-Cost Analysis
Economic
Analysis
Financial
Analysis
Regulated-UtilityPlanningAnalysis
Special Case
The distinctions are mattersof perspective: To whom do the costs and benefits apply?
5© 2016 Electric Power Research Institute, Inc. All rights reserved.
EPRI’s Benefit-Cost Framework
SocietalImpacts
Customer Impacts
Bulk System Impacts
Distribution System Impacts
• Net Capital Cost Changes• Net Fuel/O&M Changes
(Avoided less Incurred)
• Net Capital Cost Changes• Net O&M Cost Changes
(Avoided less Incurred) Change inUtility Cost
(The Utility-Cost Function)
• Reduced/Increased Emissions
• General Economic Effects
Monetization Protocols
DirectCustomer Benefits
Net Societal Benefits• Reliability Improvement
• Resiliency Improvement• Customer Equipment Cost
Monetization Protocols
Societal Benefits
6© 2016 Electric Power Research Institute, Inc. All rights reserved.
Steps to Apply Cost-Benefit Framework
Formulate Question
Define Scenarios and Assumptions
Evaluate Scenarios Using Benefit - Cost
Framework
Compare Scenarios and Identify “Best”
OptionThe economic and technical questions
for the framework are not pre-configured.
7© 2016 Electric Power Research Institute, Inc. All rights reserved.
Challenges to Developing a Microgrid BCA Framework
Policy & Regulatory Challenges:• Ownership of microgrids, resources• Transactions within microgrid • Price/rate at point of interconnection
Economic Challenges: • DG technologies still costly
and lifetimes uncertain• Business model still undeveloped• New value streams
Technical Challenges:• Interconnection• Bi-directional power flows• Fault current contribution • Variable protection conditions
8© 2016 Electric Power Research Institute, Inc. All rights reserved.
Challenges to Developing a Microgrid BCA Framework
Stakeholders in Microgrids: Distribution utility Microgrid owner/developer Internal customers External customers Surrounding market Community Society
9© 2016 Electric Power Research Institute, Inc. All rights reserved.
Analysis is complicated by the variety of possible business/ownership arrangements.
3rd Party, or Utility?
One customeror mini-utility?
Non-utility3rd Party
Premium reliability/resilience district, regulated rates
PublicUtility
One Customer, multiple facilities,
regulated rate @ POI
OneCustomer
Mini-utility w/internal customers,
behind meter @ POIinternally unregulated
Mini-utility
POI = Point of Interconnection
Additional dimensions:• Existing loads, or green/brownfield?• Existing infrastructure? • Critical loads? Commercial loads?• Incidental (non-microgrid) Loads?• Surrounding system: Market or Integrated?• Rate structure at POI: Real-time, TOU, or Static Rate• Internal customers: retail access?
Provides continuityof essential services
for local area.
10© 2016 Electric Power Research Institute, Inc. All rights reserved.
A complex project can be examined in stages, addressing a series of Benefit-Cost Analysis (BCA) questions.
Layer 1: Base w/o MicrogridExisting system: customers, loads,existing DER, and service levels.
Cost of DERcapital, O&M, fuel
IncrementalBenefits of
Energy-Producing DER
Layer 2: Energy-Producing DERoptimized with surrounding
system’s marginal cost
IncrementalReliability &Resilience
Benefits
Cost of Controlsand Capacity
controllers, sensors,installation, O&M
Layer 3: Complete MicrogridControls & Equipment
+ Capacity-Producing DER,Optimized with System
Change inOperating
Cost
Ownership & Operating
Changes
Layer 4: Business Arrangements
Ownership, Pricing at POI,Operating Objectives
Stacking of “Layers” for DER and Microgrid Analysis
BCA Q1: What is the net value of the energy-producing DER?
BCA Q3: Does the total value of the microgrid outweigh its cost?
BCA Q2: Does the value of incremental reliability/resiliency outweigh its incremental cost?
Avoided Energy $Avoided Capacity $
Avoided/Incurred Emissions $Avoided/Incurred Upgrades $
(Reliability unchanged)
∆ reliability∆ resiliency
Avoided Energy $Avoided Capacity $
Avoided/Incurred Emissions $Avoided/Incurred Upgrades $
∆ Op costs∆ Emissions∆ other costs
11© 2016 Electric Power Research Institute, Inc. All rights reserved.
Other Comments and Issues Microgrid value proposition is resilience + reliability.
View as a bet or insurance against low-probability events.– Value of Reliability (short-term interruptions)
ICE* value is generic, indicative (longer-term interruptions)
Value is specific to customers involved
– Value of Resilience
EPRI has work underway to help establish the value of resilience.
New survey instruments may help value both reliability & resilience
– Cases should evaluate backup generation as an alternative.
A microgrid is not required for DER to exist or produce benefits– Does the DER in the microgrid offset other DER elsewhere?
– Is the incremental cost of the DER the cost of location/concentration?
* ICE = DOE’s Interruption Cost Estimator @ icecalculator.com
12© 2016 Electric Power Research Institute, Inc. All rights reserved.
Microgrid Cost Evaluation
A crisp benefit/cost ratio may not always be practical, owing at least to the resilience value question.
Evaluation of microgrid costs under a range of assumptions may provide decision-makers with sufficient information.
Costs can be estimated across ranges of important assumptions, providing a parametriclook at the incremental cost of resilience.
13© 2016 Electric Power Research Institute, Inc. All rights reserved.
Questions &Discussion
Together…Shaping the Future of Electricity
Jeffrey D. RoarkTechnical ExecutiveElectric Power Research Institute