6-8 may, 2008 toronto, canada developing a flood warning system: a case study mohammad karamouz...
TRANSCRIPT
6-8 May, 2008
Toronto, Canada
Developing a Flood Warning System: A Case Study
Mohammad KaramouzProfessor, School of Civil Engineering, University of Tehran, Tehran, Iran
Azadeh AhmadiPh.D. Candidate, School of Civil engineering, University of Tehran, Tehran, Iran
Ali MoridiPh.D, School of Civil Engineering, Amirkabir University (Tehran Polytechnic), Tehran, Iran
Sina Rassaei Kashuk Graduate M.Sc. Student, School of Civil engineering, University of Tehran, Tehran, Iran
Developing a Flood Warning System: A Case Study2
6-8 May, 2008
Toronto, Canada
Contents
Conclusion6
Flood Warning Algorithm5
Study Area3
Introduction1
Methodology2
Simulation Models .4
Developing a Flood Warning System: A Case Study3
6-8 May, 2008
Toronto, Canada
Introduction Flood is a natural disaster which can cause extensive damages
and loss of life.
But with appropriate and sound decision making and flood management, the level of damage could be highly decreased and the flood could also be controlled and used as a vital source of water supply.
Developing a Flood Warning System: A Case Study4
6-8 May, 2008
Toronto, Canada
Introduction
Four levels for providing Early Flood warning could be defined as follows:
First Level: 4 to 6 months before the flood seasons (January through
April) based on a Long Term Precipitation and flood forecasting using
Climate Signals and Statistical Downscaling of GCM outputs.
Second Level: 1 to 2 months before the beginning of flood seasons
based on short term models such as an ANN or ARMAX models.
Third Level: Before reaching the probable time of flood occurrance (say
February) based on Ensembled forecasts and utilizing any new
information in December to January.
Forth Level: The start of heavy precipitation that could lead to major
floods
Flood Monitoring and warning Algorithm will be activated
Developing a Flood Warning System: A Case Study5
6-8 May, 2008
Toronto, Canada
Introduction
The simplest and easiest flood warning systems in the developing countries are conventional systems. These systems are equipped
with simple gages at critical points.
In its basic form, they report the data to the system analyst that uses the real time hydro-meteorologic data to estimate flood
events through predetermined tables and algorithms.
The predictions can include the return period of the flood, the peak discharge of the flood and the time for the flood hydrograph
reaches the reservoir, considering the time of concentration of each sub-basins.
Developing a Flood Warning System: A Case Study6
6-8 May, 2008
Toronto, Canada
Introduction
Real time flood warning system
Developing a Flood Warning System: A Case Study7
6-8 May, 2008
Toronto, Canada
IntroductionThree groups of instruments are needed for developing a flood
warning system as follows: The measuring instruments: These instruments are set up in
the meteorologic and hydrologic stations and they collect the hydro-metrological data, manually or automatically.
The hardware instruments: This group of instruments includes computers, data transfer tools, receiver and amplifier centers.
The software instruments: Data banks, data processors, the flood prediction models (including rainfall-runoff and flood routing models), visualization models and user interfaces are included in this group.
Developing a Flood Warning System: A Case Study8
6-8 May, 2008
Toronto, Canada
Methodology In this study, a flood warning system is developed based on
available climatic and hydrometric stations in the study area.
Thresholds of the observed cumulative precipitation in the upstream climatic stations and observed flood discharge in hydrometric stations provide early warnings to the area downstream of the reservoir.
These thresholds in different time steps are determined using the rainfall- runoff simulation model (HEC-HMS software), flood routing model (HEC-RAS software) and time distribution of the precipitation in the study area.
Developing a Flood Warning System: A Case Study9
6-8 May, 2008
Toronto, Canada
Methodology
The values of rainfall and runoff thresholds for flood warning are recommended for the existing and proposed stations.
Different warning levels are set up considering the reservoir storage and the water levels downstream of the reservoir
obtained from the simulation model.
Developing a Flood Warning System: A Case Study10
6-8 May, 2008
Toronto, Canada
Study Area
Persian Gulf
Iran
Developing a Flood Warning System: A Case Study11
6-8 May, 2008
Toronto, Canada
Study Area
The Kajoo watershed located in the southeastern part of Iran
is considered as the study area.
The area of this watershed is about 6800 Km2 and its mean
precipitation is about 218 millimeters.
Kajoo River is the main river of this watershed and is 254 km
long.
This river runs from the north to the south of the watershed
and entering the Gouatr bay in the Oman Sea.
Developing a Flood Warning System: A Case Study12
6-8 May, 2008
Toronto, Canada
Study Area The Kajoo River basin has steep areas and is subject to frequent
flash floods in the winter and during the Monsoon season in the summer.
The base time of the flood hydrograph is short and the peak of the flood events is high. This seasonal river has no base flow
most of the year. The arid climate of this region makes the inhabitants to move
near the river and take the risk of extensive damages and loss of life due to frequent flood occurrences.
Because of the limited carrying capacity of the Kajoo River main channel, yearly floods cause damages in the agricultural fields
and in the nearby rural areas.
Developing a Flood Warning System: A Case Study13
6-8 May, 2008
Toronto, Canada
Study Area
Kajoo Watershed
Developing a Flood Warning System: A Case Study14
6-8 May, 2008
Toronto, Canada
Study Area Zirdan reservoir located in the middle of the Kajoo river
watershed will have considerable effects on flood mitigation.
The analysis of cross sections show that the river is too narrow downstream of the reservoir where the carrying capacity of the
main river is too low.
Therefore the downstream floodplain is too wide and flood control options are needed.
In the past fifteen years there have been seven considerable floods in this region, which occurred in the years of 1991, 1992,
1995, 1997, 2005, and 2007.
Developing a Flood Warning System: A Case Study15
6-8 May, 2008
Toronto, Canada
Simulation models
Rainfall-Runoff model
A rainfall-runoff model has been developed using HEC-HMS software.
Sub-basins of the study area have been characterized and modeled in HEC- HMS software
using the SCS method. The hydrograph of the January 1, 2005 flood has
been used for model calibration.
Developing a Flood Warning System: A Case Study16
6-8 May, 2008
Toronto, Canada
Rainfall-Runoff model The SCS curve method has been used for runoff estimation
and an average curve number (CN) of 85 has been estimated for the watershed.
Observed and predicted flood hydrographs for
January 2005
Developing a Flood Warning System: A Case Study17
6-8 May, 2008
Toronto, Canada
Flood routing in the Zirdan dam The height of the dam is 53 m and the height of the spillway
is about 43m. The maximum discharge of the spillway is about 9634 cms. The reservoir storage at the crust elevation is about 433 MCM
and at the spillway elevation is about 207 MCM. The hydrological storage routing method is used for flood
routing in the reservoir.
0
500
1000
1500
2000
2500
3000
3500
0 20 40 60 80 100 120 140t (Min)
Q (
CM
S)
2 2
5 5
10 10
Outflow Inflow
Developing a Flood Warning System: A Case Study18
6-8 May, 2008
Toronto, Canada
Hydraulic simulation model
The HEC-RAS model is used for flood flow routing along the river, downstream of the Zirdan dam.
From hydraulic simulation of the river, the safe discharge of the river downstream of the Zirdan dam is calculated.
The Safe discharge is the maximum discharge downstream the dam which do not cause damages.
The safe discharge is obtained based on land use of the floodplain and hydraulic simulation of flood along the river.
Developing a Flood Warning System: A Case Study19
6-8 May, 2008
Toronto, Canada
Hydraulic simulation model
River section at Km-70 of the river near Taradan
Village
(Based on Survey of 2002)
River section at Km-6 of the river near Polan
Village
(Based on Survey of 2002)
Developing a Flood Warning System: A Case Study20
6-8 May, 2008
Toronto, Canada
Hydraulic simulation model
Flood Plan of Kajoo River at 9th and 10th sections (30.4 to 46 Km from end reach) near Oraki village for floods with 25, 50, 100 and 200 years return period
Developing a Flood Warning System: A Case Study21
6-8 May, 2008
Toronto, Canada
Flood Warning Algorithm
1 .Determination of proposed stations
2 .Determination of the rainfall and runoff
thresholds 3 .Reservoir management
Developing a Flood Warning System: A Case Study22
6-8 May, 2008
Toronto, Canada
Determination of proposed stations
The investigation of the location of existing stations in the study area
shows that the existing stations are not sufficient for flood warning
purposes.
The estimation of runoff, playing an important role in the
determination of warning thresholds, has been calculated using the
developed rainfall-runoff model in the study area.
One of the considered criteria to locate new hydrometric stations is
the proportion of each sub-basin to the inflow of the Zirdan dam.
First hydrometric station should be constructed after joining the 5
sub-basins named Ahooran, Miani 1 and 2, Kenari and Chanef. This
station covers about 48% of the runoff of the study area.
Developing a Flood Warning System: A Case Study23
6-8 May, 2008
Toronto, Canada
Determination of proposed stations
5 7 . 5 5 8 5 8 . 5 5 9 5 9 . 5 6 0 6 0 . 5 6 1 6 1 . 5
2 6
2 6 . 5
2 7
2 7 . 5
2 8
2 8 . 5
2 9
2 9 . 5
123
4
5
6
7
8 9
1 0
1 1
1 2
1 3
1 4
1 5
1 6
1 7
1 8
1 9
2 0
2 1
2 2
5 7 . 5 5 8 5 8 . 5 5 9 5 9 . 5 6 0 6 0 . 5 6 1 6 1 . 5
2 6
2 6 . 5
2 7
2 7 . 5
2 8
2 8 . 5
2 9
2 9 . 5
Ghasreghand
The storm centers in the study area are identified (one is located at Ghasre-Ghand
city) through meteorological studies of the region. Since there is a hydrologic
station near this storm center, Ghasre-Ghand station located 20 km downstream of
the city, it is considered as one of the stations in the flood warning system.
Developing a Flood Warning System: A Case Study24
6-8 May, 2008
Toronto, Canada
Determination of the rainfall and runoff thresholds
In order to determine the critical threshold of cumulative rainfall
in meteorologic stations, precipitations with different return periods
have been simulated.
The precipitation that causes a flood peak more than the carrying
capacity of the river, after the reservoir routing in the Zirdan dam, is
considered as the critical threshold of rainfall.
As most of the sub-basins in the study area do not have
meteorologic station, the isohyets analysis has been used for
estimation of each sub-basin's rainfall.
Developing a Flood Warning System: A Case Study25
6-8 May, 2008
Toronto, Canada
Determination of the rainfall and runoff thresholdsThe safe discharge is considered based on the importance of the project,
economic aspects and the acceptable risk level downstream of the
reservoir using a hydraulic simulation of the river for different scenarios.
In this study, the 25-year return period flood, with a maximum discharge
of about 2500 cms has been considered as the safe carrying capacity of the
river. the output discharge peak of the reservoir with a 5-years return
period is around 2500 cms.
0
500
1000
1500
2000
2500
3000
3500
0 20 40 60 80 100 120 140t (Min)
Q (
CM
S)
2 2
5 5
10 10
Outflow Inflow
Developing a Flood Warning System: A Case Study26
6-8 May, 2008
Toronto, Canada
Determination of the rainfall and runoff thresholds
According to the rainfall- runoff model, reservoir and river routing
models, the critical cumulative rainfall is 43, 42, and 41 mm for Ahooran,
Chanef, and Ghasre-Ghand climatic stations, respectively. This values
cause the flood with 5year return period.
In order to cross check the flood forecasting results, the control points
are considered based on hydrometric stations. The critical discharge in
Dirak and Ghasre-Ghand hydrometric stations are 540 and 960 CMS,
respectively.
The time of concentration (tc) in each sub-basin and the traveling time of
the flood flow in the river is used to determined the pre-warning time of the
reservoir and the downstream river.
Developing a Flood Warning System: A Case Study27
6-8 May, 2008
Toronto, Canada
Determination of the rainfall and runoff thresholds
The rainfall pattern includes the dimensionless temporal distribution of
cumulative rainfall at meteorological stations which is determined based
on the schemes of the historical storms in the region.
Thus, the pre-warning times of the reservoir are 13, 12, and 6hr for
Ahooran, Chanef, and Ghasre-Ghand climatic stations, respectively.
These values are based on
time of concentration (tc)
of each sub-basin.
0
10
20
30
40
50
60
70
80
90
100
0 10 20 30 40 50 60 70 80 90 100
زمان)درصد(
د(صدرن)رابا
Time)%(
Pre
cipi
tatio
n)%
(
Developing a Flood Warning System: A Case Study28
6-8 May, 2008
Toronto, Canada
Flood warning system algorithm
.
Defining New StationsNew Weather station: 60 53 Lon. , 26 37 Lat. (Ahooran Station: R5)New Weather station: 60 34 Lon., 26 39 Lat. (Chanef Station: R1)New Weather Station: 60 44 Lon., 26 28 Lat. (Dirak Station: H3)
Monitoring and checking Equipment and Stations
Are they all up and running?
Rep
airm
ent
Reservoir Water Level Control
What month are we currently in?
Water Level Should be below
150 m
February
Max. Allowable Water Level
May: 205 mJun: 183 mJul: 163 mOct: 167 mNov: 164 mDec: 162 mJan: 164 m
Other Months
Discharge in Dirak (H3) Hydrometric Station exceeds of 540 CMS
Ahooran Station (R5)
Cumulative rainfall in 6.5 hrs exceeds
of 15 mm
Cumulative rainfall in 13 hrs exceeds
of 43 mm
Chanef Station (R1)
Cumulative rainfall in 3.5 hrs exceeds
of 11 mm
Cumulative rainfall in 6 hrs exceeds of
16 mm
Flood Warning to dam officials
Public Warning
Discharge in Chandookan (H1) Hydrometric Station exceeds of 960 CMS
Water Level Should be below
94 m
March
Water Level Should be below
137 m
April
Water Level Should be below
155 m
August
Cumulative rainfall in 4 hrs exceeds of
11 mm
Ghasreghand station (R3)
Cumulative rainfall in 2 hrs exceeds of
11 mm
Cumulative rainfall in 3 hrs exceeds of
14 mm
Warning to Downstream installations and villages of
dam
Open All Dam Gages
Operating Rule- Zirdan Reservoir
Cumulative rainfall in 6 hrs exceeds of
41 mm
Cumulative rainfall in 12 hrs exceeds
of 42 mm
0
50
100
150
200
250
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug SepMonth
Vo
lum
e (
MC
M)
Normal Condition
Flood Condition
Developing a Flood Warning System: A Case Study29
6-8 May, 2008
Toronto, Canada
Developing a Flood Warning System: A Case Study30
6-8 May, 2008
Toronto, Canada
Reservoir ManagementThe decreased peak of floods after entering the reservoir is determined
using hydrological flood routing model in the reservoir.
The reservoir flood control volume is calculated based on the flood hydrograph after routing in the reservoir and the carrying capacity of the
downstream river.
Therefore, the needed flood control storage, the extra flood volume and the associated elevation of the reservoir is determined.
.
Developing a Flood Warning System: A Case Study31
6-8 May, 2008
Toronto, Canada
Reservoir Management
.
0
50
100
150
200
250
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Month
Vo
lum
e (M
CM
)
Normal Condition
Flood Condition
Developing a Flood Warning System: A Case Study32
6-8 May, 2008
Toronto, Canada
Flood warning system algorithm
.
Defining New StationsNew Weather station: 60 53 Lon. , 26 37 Lat. (Ahooran Station: R5)New Weather station: 60 34 Lon., 26 39 Lat. (Chanef Station: R1)New Weather Station: 60 44 Lon., 26 28 Lat. (Dirak Station: H3)
Monitoring and checking Equipment and Stations
Are they all up and running?
Rep
airm
ent
Reservoir Water Level Control
What month are we currently in?
Water Level Should be below
150 m
February
Max. Allowable Water Level
May: 205 mJun: 183 mJul: 163 mOct: 167 mNov: 164 mDec: 162 mJan: 164 m
Other Months
Discharge in Dirak (H3) Hydrometric Station exceeds of 540 CMS
Ahooran Station (R5)
Cumulative rainfall in 6.5 hrs exceeds
of 15 mm
Cumulative rainfall in 13 hrs exceeds
of 43 mm
Chanef Station (R1)
Cumulative rainfall in 3.5 hrs exceeds
of 11 mm
Cumulative rainfall in 6 hrs exceeds of
16 mm
Flood Warning to dam officials
Public Warning
Discharge in Chandookan (H1) Hydrometric Station exceeds of 960 CMS
Water Level Should be below
94 m
March
Water Level Should be below
137 m
April
Water Level Should be below
155 m
August
Cumulative rainfall in 4 hrs exceeds of
11 mm
Ghasreghand station (R3)
Cumulative rainfall in 2 hrs exceeds of
11 mm
Cumulative rainfall in 3 hrs exceeds of
14 mm
Warning to Downstream installations and villages of
dam
Open All Dam Gages
Operating Rule- Zirdan Reservoir
Cumulative rainfall in 6 hrs exceeds of
41 mm
Cumulative rainfall in 12 hrs exceeds
of 42 mm
0
50
100
150
200
250
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug SepMonth
Vo
lum
e (
MC
M)
Normal Condition
Flood Condition
Developing a Flood Warning System: A Case Study33
6-8 May, 2008
Toronto, Canada
Conclusion
In this paper, an algorithm for flood warning in the Kajoo watershed has
been developed regarding to the water elevation in the Zirdan dam, the
amount of rainfall in proposed and existing stations, and flow discharge at
hydrologic stations in different time steps.
In the first part of this algorithm, the location of the proposed stations
including Ahoran, Chanef and Dirak have been presented.
In the next part of this algorithm, the critical precipitation and the pre-
warning time for the reservoir from these stations is presented.
The values of discharge at hydrologic stations are also used to determine
the time of flood warning downstream of the reservoir.
Developing a Flood Warning System: A Case Study34
6-8 May, 2008
Toronto, Canada
Conclusion
The flood warning levels will be changed for a different range of
precipitation in each station.
These warnings include flood warning to the Regional Water Authority
and a warning to the dam operation in order to open reservoir gates to an
allowable water level, downstream flood warning and to protect the
downstream floodplain.
6-8 May, 2008
Toronto, Canada
Thank you for your Attention
For more information please contact:
Email: [email protected]
Tel: 0098-21-88555884
Fax:0098-21-88701507