5.04 shortcomings and proposed improvements to the asset … · 2017. 11. 23. · – software:...

21
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities Sharon Mushabe Eskom Holdings SOC Ltd Paper Number 5.04 Session Number 5 15 November 2017 Shortcomings And Proposed Improvements To The Current Practice Used By Eskom Transmission To Determine Asset Health Index Of Overhead Transmission Lines

Upload: others

Post on 25-Jan-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Sharon MushabeEskom Holdings SOC Ltd

    Paper Number 5.04

    Session Number 5

    15 November 2017

    Shortcomings And Proposed

    Improvements To The Current Practice

    Used By Eskom Transmission To

    Determine Asset Health Index Of

    Overhead Transmission Lines

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Content

    • Overview of the Asset Profile• Description of the Transmission Line Health Index• Challenges and Shortcomings• Recommendations

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities3

    • 358 overhead transmission lines in 10 grids• 85000+ towers• 32 500+ km (route length)• 275 000+ km of conductor (excl. Earthwire and

    OPGW)

    Transmission Line Asset Profile 1

    1 Profile at the end of the 2016/2017 financial year

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities4

    Free State has the most

    kilometers of Overhead

    transmission line to cover

    East Grid has the most

    number of lines

    Transmission Line Asset Profile

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Eskom Transmission Line Teams

    • Design Team– Full detail designs for HVAC up to 765 kV and HVDC up to 800

    kV

    – Team of over 70 engineers, technologists and technicians – Facilities include tower test station and corona cage test – Software: PLSCADD, SolidWorks, FALLS, ATP

    • Maintenance Team– Maintenance teams in 10 grids/operating units– Live line teams

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Eskom Maintenance Strategy

    • Currently, the strategy is a time based inspection and assessment approach

    • Eskom Transmission is moving towards adopting a condition based approach

    • The condition based approach includes determining the asset health of the overhead line

    • Part of this approach required a health index to be defined

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Transmission Line Health Index (ideal)

    • Two asset classes for Overhead Transmission lines are defined,

    namely: Steel Structures and

    Overhead Conductor systems.

    • Failure mode and effects analysis (FMEA) is compiled.

    • Condition monitoring task and activity schedule is created

    based on results.

    • End-of-life criteria are developed for various

    components of the asset class.

    7

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities8

    Abbreviated Transmission Line Health Index

    The following abbreviated Health Measures were applied

    when conducting this survey:

    – A line will be rated as a whole and not per individual structure, span etc.

    – Overall ratings of components based on visual inspection reports.

    – Fibre Optic systems will be excluded from the line ratings.– The age of the line is based on the earliest recorded date on

    TxSiS.

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Health Index rating

    Health index

    Condition Description Requirements

    85 - 100Very Good

    (A)

    Some ageing or minor deterioration of a limited number of components

    Normal maintenance

    70 - 85Good

    (B)Significant deterioration of some components

    Normal maintenance

    50 - 70Fair

    (C)

    Widespread significant deterioration or serious deterioration of specific components

    Increase diagnostic testing, possible remedial work or replacement needed depending on criticality

    30 - 50Poor

    (D)Widespread serious deterioration

    Start planning process to replace or rebuild considering risk and consequences of failure

    0 - 30Very Poor

    (E)Extensive serious deterioration

    At end-of-life, immediately assess risk; replace or rebuild based on assessment

    9

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Transmission Line Health Index

    10

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Challenges and Shortcomings

    • Type and Frequency of Inspections

    • Data Capturing

    • Data Storage

    • Sampling and Testing

    • Resources

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Type and Frequency of Inspections

    • Fast aerial inspection at least once year on each line– Purpose to the pick up serious defects that could result in

    failure in

    • Detailed aerial inspection every four years on each line.– Visual inspection with multi-spectural camera of line

    hardware, conductors, spacers, insulators with the use of

    helicopter

    • Both inspections neglect the foundations as well as sections of tower that are not visible from the air

    • Pole top inspection – Similar to detail aerial inspection but with inspectors physically

    on the tower

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Data Capturing

    • Detailed aerial inspections captures the defects at each tower.– Defects are supported with photos and videos. – No assignment of a condition rating for each component.– No information is given for towers that have no defects. – Reports vary from operator to operator.

    • No measurements, tests or samples are performed to determine remaining life of the assets.

    • Inspection checksheet or report is ambiguous and leads to various interpretations.

    • Operators are not clear on what to look for during a visual inspection nor how to identify all signs of deterioration on

    transmission lines.

    • Budget constraints limiting number of hours flown by helicopter.

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Data Storage

    • Accurate records of as-built infrastructure is needed. • Records of all the major components/assemblies including

    material, type, size, manufacturer and installation year must be

    stored.

    • Data must be updated after each inspection cycle and following changes due to maintenance and construction activities.

    • No central storage facility of inspection photos, reports and/or investigations.

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Sampling and Testing

    • Samples are required to be taken for various tests. – Conductor and Earthwire samples are required for tensile

    tests, tensile ductility tests, wrapping tests, zinc coating

    measurements and torsional ductility tests.

    – Hardware samples are required for corrosion examinations. – Insulator strings are required for pollution conductivity

    testing.

    • Some cases network constraints prevent outages for significant periods to allow teams to acquire the samples.

    • Some lines more than one conductor sample is required to give a suitable representation of the line.

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Tests or Inspections

    • Conductor clearance measurements• Corrosion and wear on tower

    members and hardware

    • IR and UV scanning • Tower footing resistance

    measurements

    • Line impedance measurements

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Resources

    • Field operators are responsible for collecting the data while analysis of the data is performed by the relevant engineering

    department.

    • Movement of staff from grid to grid means that local knowledge of lines diminishes as new staff move in and out.

    • Testing facilities, labs, equipment and tools are required to run tests on samples.

    Advancements in technology

    • The maintenance strategy includes the use of multi-spectral cameras and hand-held tough books that are linked to the plant

    management system.

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    UAV’s and Line Robots

    • The use of unmanned aerial vehicles and line robots for overhead line inspections is still being reviewed.

    • Integrating vibration sensors on towers are still being investigated. • These interventions all require trained and skilled personnel to

    operate and produce quality reports.

    Power Line Robot: Developed by Eskom and UKZN (image from: www.powerlinerobot.com)

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Recommendations

    • Detailed and complete asset registry is required – (including manufacturer, material type, installation year, etc)

    • Revision of the inspection check sheet such that the data can be captured accurately without ambiguity.

    • Review of the frequency of inspections to complete an audit that can be used to compile a complete health index.

    • System is under development that allows operators to capture data in the field, integrate seamlessly with the current plant

    management systems and be available online for all the relevant

    stakeholders.

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Recommendations

    • Develop a training program for line audits so that the operators are:

    – Fully knowledgeable of the components on the transmission lines

    – Can identify defects and accurately comment on the condition of the transmission line

    – Equipped and trained to use and interpret the results

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Acknowledgements

    • Team within the following Eskom departments:– Transmission Grid Supervisors, Operators and

    Engineers

    – Research, Testing and Development– Line Engineering Services – Asset Investment Planning, and– Asset Management Execution