440-00-baa-emm-ege-001_reva-erection procedure.pdf

Upload: utku-can-kilic

Post on 06-Jul-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    1/134

    Project:

    Title:

    Rev: A

    Date: 10.12.2010

    Isolated Phase Bus Duct

    10/20 BAA10 - Erection Procedure

    KainzApproved:

    Svoboda

    EGE Document No: -

    For Approval

    Samsun ElektrikÜretim Sanayi ve Ticaret A.Ş.

    Prepared: Petyrek

    Reviewed:

    KKS Document No: 440-00-BAA-EMM-EGE-001

    Purpose of issue:

    This document contains proprietary information and is to be used solely for the Project and the purpose for which it is furnished.

    It may not be disclosed to others for a different use without written permission

    SAMSUN COMBINED CYCLE POWER PLANT 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    2/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  1 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Erection and Test Instruction 

    SAMSUN CCPP  EGE  440‐00‐BAA‐EMM‐001 

    Power Plant  Producer  No 

    System/Component:  10/20 BAA10  Index: ‐

    Instruction Title:  Isolated Phase Bus Duct (IPB) 

    Type and Scope  Pages:133  Appendices: ‐

    Contents 

    1.  Scope of Erection and Test 

    2.  Preconditions 

    3.  Time Schedule and Staff Planning 

    4.  Required Tools, Materials and Welding Instructions 5.  Execution 

    6.  Field Quality Plan 

    7.  Documentation for Erection 

    Prepared  by  Verified  by  Released  by 

    Department: EGE Alu  EGE Alu  EGE Alu 

    Name: Petyrek  Svoboda  Kainz 

    Date: 2010‐10‐14  2010‐10‐14  2010‐10‐14 

    Copies to: 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    3/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  2 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    SHEET OF THE REVISION 

    Rev  Section/Page 

    A  Added Cover Sheet 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    4/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  3 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    1.  TYPE  AND

     SCOPE

     OF 

     WORK   8 

    1.1  Instruction for erection of IPB  8 

    1.2  Instruction for tests after completion of IPB erection  9 

    1.3  Scope of Supply for IPB Erection  9 

    1.3.1  Check of completeness of supply  9 

    1.4  Completion of works  9 

    1.5  Exclusion of works  9 

    1.5.1  Components excluded from IPB erection  10 

    1.5.2  Storage of IPB at site before erection  10 

    1.5.3  Cabling of IPB components  10 

    1.6  Supervision of IPB erection  10 

    1.6.1  General rules for reporting of Supervision  10 

    1.6.2  Content of weekly report  11 

    2.  PRECONDITIONS  12 

    2.1  Structural preconditions and space requirement  12 

    2.2  Main components and structural preconditions  13 

    2.3  Precondition for IPB supervision  13 

    2.4  Procedure of

     protocol

     “Ready

     for

     Erection

     (RFE)“  15 

    3.  TIME SCHEDULE  AND STAFF  PLANNING  16 

    3.1  Time scheduling, general  16 

    3.2  Observations for preparation of project‐specific time schedule  16 

    3.3  Proposal for erection team  16 

    3.4  Proposal for erection time schedule  17 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    5/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  4 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    4.  REQUIRED TOOLS,  MATERIALS  AND GENERAL WELDING INSTRUCTION   18 

    4.1  Erection tools, made available by Erection Company  18 

    4.2  Special tools supplied with IPB  18 

    4.3  Consumables and spares supplied with IPB per Unit  19 

    4.3.1  Consumables  19 

    4.3.2  Spare parts for erection per Unit  19 

    4.4  Welding  21 

    4.4.1  Welding 

    of 

    aluminium  21 

    4.4.1.2.1  Designation of site welds  21 

    4.4.1.2.2  Methods of welding  21 

    4.4.1.2.3  Designation on package of welding wire  22 

    4.4.1.3.1  Preparation of welding  22 

    4.4.1.3.2  Execution of welding  22 

    4.4.1.3.3  After‐treatment

     of

     weld  23 

    4.4.2  Welding of steel  59 

    5.  EXECUTION   AND TESTS  66 

    5.1  Erection Procedures  66 

    5.1.1  Preparatory work  66 

    5.1.2  Transport at Site  66 

    5.1.3  Check of measurements to be executed on site by civil  66 

    5.1.3.1  Permissible tolerances inside and outside of buildings  66 

    5.1.4  Check of clearance of the IPB route  67 

    5.1.5  Erection of IPB steel structures in scope of IPB supplier  67 

    5.1.6  Erection of enclosure supports  69 

    5.1.7  Erection of component connections  69 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    6/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  5 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    5.1.7.1 Connection to Generator  69 

    5.1.7.2  Connection to generator circuit‐breaker type HECS  70 

    5.1.7.3  Connection to Unit Auxiliary transformer  70 

    5.1.7.4  Connection to GSU transformer  71 

    5.1.7.5  Securing and sealing of IPB components  71 

    5.1.7.6  Removal and re‐installing of inspection covers  72 

    5.1.8  Handling of shipping units  73 

    5.1.8.1  General  73 

    5.1.8.2  Designation of shipping units  73 

    5.1.8.3  Erection of shipping units  74 

    5.1.9  Welding between shipping units  76 

    5.1.9.1  Installation and welding of conductor connections  76 

    5.1.9.1.1  Rigid conductor connections  76 

    5.1.9.1.1.1  Connection L16  76 

    5.1.9.1.1.2  Connection L24  76 

    5.1.9.1.1.3  Connection L15  78 

    5.1.9.1.2  Flexible conductor connection  78 

    5.1.9.1.2.1  Connection L43  79 

    5.1.9.2  Installation and welding of enclosure connection  79 

    5.1.9.2.1  Connection H13  80 

    5.1.9.2.2  Connection H22  81 

    5.1.9.2.3  Connection H32  82 

    5.1.9.2.4  Electrically continuous connection at UAT  84 

    5.1.10  Erection of equipments  86 

    5.1.10.1  Instruction for Cabling (Labels at IPB enclosure and components)  86 

    5.1.10.2 Temporary Earthing Device  86 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    7/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  6 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    5.1.11  Installation of enclosure short‐circuiting connections  87 

    5.1.12  Grounding system  87 

    5.1.12.1  Installation of grounding connections  87 

    5.1.13  Installation of building wall penetration  88 

    5.1.14  Installation of bushings and compensators  89 

    5.1.14.1 Installation of silicone bushing  89 

    5.1.14.2  Fastening by use of steel band and special tensioning tool  90 

    5.1.14.2.1  Employing of steel band  90 

    5.1.14.2.2  Special tensioning tool for the inner diameter  91 

    5.1.14.2.3  Special tensioning tool for the outer diameter  92 

    5.1.14.3  Installation of rubber compensators of IPB enclosure  92 

    5.1.15  Installation of current transformers (CT)  94 

    5.1.15.1  Transport and general instructions  94 

    5.1.15.2  Installation of

     current

     transformers

     at

     UAT  94 

    5.1.16  N/A  94 

    5.1.17  Installation of removable conductor and grounding connections  94 

    5.1.17.1  General instruction  94 

    5.1.17.2  Installation  /  Treatment of Cu ‐ Cu and Al ‐ Al contact connections  96 

    5.1.17.3  Installation of silver plated Cu and silver plated Al contact connections  96 

    5.1.17.4  Tightening torque

     of

     removable

     bolted

     current

     carrying

     connections  97 

    5.1.17.5  Tightening torque for threaded bushes within cast‐resin post insulators  97 

    5.1.17.6  Legend for treatment and preparation for current carrying connections  98 

    5.1.18  Installation of air pressurisation equipment  100 

    5.1.19  Installation of condensate system  101 

    5.1.20  Installation of heat‐sensitive stickers at bolted conductor connections  101 

    5.1.21  Cleaning of support insulators by installing auxiliary supports  101 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    8/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  7 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    5.1.22  Repair or final painting of IPB enclosure and conductor  103 

    5.2  Test Procedure  104 

    5.2.1  Tests to be executed after completion of IPB erection  104 

    5.2.2  General Checks after Completion of Erection  104 

    5.2.3  Acceptance of IPB by Owner  104 

    5.2.4  Test description  105 

    5.2.4.1  Insulation Test between Enclosure and Insulated Enclosure Supports  105 

    5.2.4.2  High‐Voltage Test  105 

    5.2.4.2.1  AC High‐Voltage Test  105 

    5.2.4.2.2  DC High‐Voltage Test  106 

    5.2.4.3  Leakage Test  107 

    5.2.5  N/A  108 

    5.2.6  N/A  108 

    5.2.7  Blank forms

     for

     Test

     Results  108 

    5.2.7.1  Insulation Test between Enclosure and IPB Supports  109 

    5.2.7.2  AC High‐Voltage Test  110 

    5.2.7.3  DC High‐Voltage Test  111 

    5.2.7.4  Leakage Test  112 

    6.  FIELD QUALITY PLAN (FQP)  113 

    6.1 Clearance and ready for erection of IPB route  114 

    6.2 Erection of steel structures in scope of IPB supplier  115 

    6.3 Erection of enclosure supports  116 

    6.4 Erection of shipping units  117 

    6.5 Welding between shipping units  118 

    6.6 Erection of enclosure contact flanges  119 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    9/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  8 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    6.10 Installation of enclosure short‐circuiting connections  120 

    6.11 Installation of grounding connections  121 

    6.12 Installation of cast resin bushing with flat Cu‐conductor  122 

    6.13 Installation of silicone bushing  123 

    6.15 Installation of rubber compensators of IPB enclosure  124 

    6.16 Installation of current transformers  125 

    6.20 Installation of wall penetrations  126 

    6.24 Installation of temperature monitoring system  127 

    6.26 Current‐carrying component connection  128 

    6.27 Torque and sealing of IPB  129 

    6.29 Checks of installed cubicles and boxes  130 

    6.30 Checks after completed erection of IPB  131 

    6.31 Tests after completed erection of IPB  132 

    7.  DOCUMENTATION FOR

     ERECTION  133 

    1. 

    Type and

     Scope

     of 

     Work

     

    The instruction describes the work to  be executed at site for erection and test of IPB. 

    1.1  Instruction  for  erection of  IPB 

    The procedure of erection for 

    •  supports 

    •  shipping units 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    10/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  9 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    •  connection elements for conductors and enclosures 

    •  component connections 

    •  cubicles related to IPB 

    •  pressurizing equipment 

    is described in a work sequence in Chapter 5.1 

    1.2  Instruction  for  tests after  completion of  IPB erection 

    The procedure of tests after completion of IPB erection is described in Chapter 5.2. 

    1.3  Scope of  Supply  for  IPB Erection 

    The scope of supply is summarized in the following documents 

    for parts manufactured  by IPB supplier: 

    see chapter 7, IPB Layout and List of Layout Modules 

    for equipment within scope of IPB supply: 

    see the shipping documents (Packing list) 

    1.3.1  Check of  completeness of  supply 

    The completeness of supply shall  be checked against the packing lists of the IPB manufacturer  by the 

    erection company. The check shall  be executed  before start of erection and in the presence of the IPB 

    supervisor. 

    The result of completeness check shall  be included in one of the first weekly reports (if applicable) of IPB 

    supervisor. (see FQP 6.1) 

    1.4  Completion of  works 

    The completion of works (works as per chapter 5.1 and 5.2.) is finalized  by hand over of document “Erection 

    Clearance Certificate (ECC)” issued  by Site management (SM). 

    1.5  Exclusion of  works 

    General: 

    The erection work is limited to IPB and associated equipment which is in scope of IPB supplier. 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    11/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  10 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    1.5.1  Components excluded  from IPB erection 

    The erection instruction of the following components with interface to IPB is not part 

    of this instruction and excluded of works: 

    •  Generator (including the generator terminals to IPB) 

    •  GSU transformer 

    •  Generator circuit‐ breaker 

    •  Unit auxiliary transformer 

    Note: 

    It has to  be coordinated  between SM, generator and IPB erection that the generator terminals are installed only 

    after installation of slip‐on current transformers. 

    1.5.2  Storage of  IPB at  site before erection 

    Storage at Site is determined  by the shipping documents “PACKING LIST” 

    1.5.3  Cabling  of  IPB components 

    Cabling of IPB components is excluded of work. 

    1.6  Supervision of  IPB erection 

    The IPB erection is guided  by a Supervisor (SV) ordered  by the technical department of Customer. 

    The supervision is executed  by order of the  before mentioned technical department. 

    In the following the reporting via agreed weekly reports is described. 

    1.6.1  General rules  for  reporting  of  Supervision 

    The report shall describe a  brief status of IPB erection progress at site and shall  be written  by the assigned IPB 

    Supervisor. 

    The report shall reflect one completed erection week and shall  be issued in time. 

    The language of report shall  be in English. 

    In case of detected problems during IPB erection then an immediate feedback shall  be given to the Customers site management (SM), the technical department of Customer and the IPB manufacturer. 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    12/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  11 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    1.6.2  Content  of  weekly report  

    The weekly report shall indicate the erection week the completed tasks and an outlook of tasks for the coming 

    week.  Subsequent reports shall  be  based upon the previous one retaining all entries of the same.  The  blank 

    form of reports will  be handed over to the SV. The  blank form compiles all possible tasks to  be executed for IPB 

    erection. Tasks not to  be executed are marked “not applicable” or abbreviated ‐ n.a. 

    The report has to  be received  by addressed technical department latest on Monday following the reported 

    erection week. The report shall  be signed  by SM previous to transmission. 

    The project‐specific version of weekly report will  be handed over as  blank form electronically  by IPB 

    manufacturer to Supervisor to facilitate an electronic fill‐up and subsequent E‐mail transmission. 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    13/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  12 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    2.  Preconditions 

    2.1  Structural  preconditions and space requirement  

    The following preconditions must  be fulfilled for erection of IPB: 

    •  the turbine  building, the transformer foundations and the structural steel, in scope of civil, 

    for IPB support fastening must have  been completed, 

    •  all embedded anchor plates, anchor rails and anchor holes requested for the IPB support 

    fastening must  be available; where such measures have not  been specified, fixing  by means 

    of dowels to the skeleton structure shall  be employed, 

    •  steel platforms/girders provided  by civil works in the turbine  building to support the IPB must  be installed, 

    •  all necessary ceiling and wall openings must  be completed to allow installation of sleeves 

    and cover plates (included in scope of IPB supply). 

    Space for erection must  be available for 

    •  Generator connection 

    •  Generator

     Circuit

    ‐ breaker

     

    •  Unit Auxiliary Transformer  branch feeder 

    •  GSU Transformer connection 

    •  IPB  between generator and circuit‐ breaker 

    •  IPB  between circuit‐ breaker and GSU Transformer 

    In order to allow measurement and erection of components and shipping units a hoist and lifting devices must 

     be available for IPB erection. 

    Note: 

    The weights per transport units are given in “List of Layout Modules “(see chapter 7) to calculate the required 

    lifting equipment. Erection platforms, mobile cranes or man lifts are required in the outdoor area. Temporary supports may  be required during erection in order to support shipping units during welding. The 

    procedure is described in chapter 5.1.7.1 

    For the erection of steel constructions related to IPB a mobile crane must  be available (crane, chain‐ropes,  jacks) 

    with minimal carrying capacity of app. 5 t, an erection platform or scaffolding with floor height app. 0,5 m 

     below  bottom line of IPB and adequate fasteners. 

    Accident prevention measures 

    Refer to project specific safety instructions (PI) 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    14/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  13 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Fire prevention measures 

    •  keep flammable materials (cleaning solvents, plastics, wood ) away from locations at 

    which cutting‐off by means of abrasive wheel, grinding or welding work is performed 

    •  in closed area provide adequate ventilation at locations where welding is carried out 

    •  endangered adjacent components and structures shall be protected to prevent fire 

    •  fire extinguishers shall be available during welding 

    2.2 

     Main 

    components 

    and 

    structural 

     preconditions 

    Prior to start of IPB erection measurements are executed  by site management. 

    Measurement protocols for components shall  be handed over to the Erection Company of IPB and the IPB 

    Supervisor. 

    Note: Permissible civil tolerances for IPB erection are indicated in chapter 5.1.2.1 

    In addition to the structural precondition the following main components should have  been installed already. 

    •  Generator 

    •  Generator circuit‐ breaker 

    •  GSU transformer 

    •  Unit Auxiliary transformer 

    In abnormal cases and due to time schedule it may  be required to start IPB erection without main components 

    installed  but with measuring points indicated  by civil. 

    2.3  Precondition  for  IPB supervision 

    A  blank format of “Call for Supervisor” (see chapter 2.3.1) shall  be completed  by Site Management (SM) and to  be sent to EGE Ltd. 3 weeks  before start of work of IPB supervisor at site. By calling the supervisor to Site the 

    following preconditions and measures are fulfilled or are guarantied  by SM: 

    •  Precondition according to Chapter 2.1 and Chapter 2.2 

    •  Complete supply of IPB according to Packing list Coli Nos. 

    •  Storage of IPB Components according to Chapter  1.4.2 

    •  Measurement Protocols (see Chapter  2.2) 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    15/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  14 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    2.3.1   Format  of  Call  for  Supervisor  

    To  EGE s.r.o.  From:  Site Management 

    Dep. Alu  Project: 

    Fax: + 420 387 764  – 605 or 606  Name: 

    E‐mail: [email protected] , 

    [email protected] 

    Number of pages:  Date: 

    Please complete this form, fix date of start of work of Supervisor and 

    send to above given address  back 3 weeks  before requested arrival of Supervisor at site. 

    Yes  No  RFE 

    Generator was installed in final position 

    Generator circuit‐ breaker (if applicable) was installed in final position 

    Generator transformer was installed in final position 

    Unit aux. transformer (if applicable) was installed in final position 

    Exciter transformer (if applicable) was installed in final position 

    Power control centre (if applicable and required for IPB support) was installed in final position 

    Steel constructions and all necessary supports in scope of civil are installed in 

    final position 

    Welder machine for steel and for aluminium, scaffolding, mobile crane are 

    available 

    Erection team and welder with qualification for steel and aluminium are 

    available 

    Office working place available including telephone and access to internet 

    Supervisor available at site  beginning with date: 

    Note: RFE protocols shall  be handed over to IPB supervisor at arrival at site 

    Remarks: 

    Date: 

    Name: 

    Signature: 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    16/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  15 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    2.4 

    Procedure of 

      protocol

     “Ready

      for 

     Erection

     (RFE)“ 

     

    By issue of RFE the Erection Company receives the release for start of IPB erection and takes over the 

    corresponding erection area. 

    The take over of erection area  by Erection Company includes: 

    •  the check of the measuring protocols against the erection drawings and the check of 

    permissible deviations 

    •  the acceptance of erection area with respect to cleanliness and free of damages 

    •  the responsibility with respect to health and safety regulations 

    •  the responsibility with respect to protection of equipments 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    17/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  16 

    _______________________________________________________________________  __________ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    3. 

    Time Schedule

     and

     Staff 

     Planning 

     

    3.1  Time scheduling,  general 

    The following proposed time schedule is subject to  be further detailed  by the IPB Erection Company and 

    coordinated with Site Management (SM) during IPB kick‐off meeting at site. The IPB supervisor shall take part 

    and assist in the kick‐off meeting. 

    3.2  Observations  for   preparation of   project ‐specific time schedule 

    The following shall  be observed and coordinated with SM during preparation of project specific time schedule. The sequence of IPB erection might  be driven  by the requirement of  back‐energizing. It is meant the 

    transformer connection has priority to  be finished/connected. 

    The non‐availability of crane of turbine hall due to restricted movement of the same. The sequence of 

    installation of connected components as a precondition of IPB erection. It might  be necessary to  be changed 

    with respect to transport of IPB into  building, like for example the generator circuit‐ breaker. 

    3.3  Proposal  for  erection team 

    1  Team manager – Foreman (English speaking!) 

    1‐2 Welders with qualification for Aluminium and for Steel 

    1‐2  Welder’s helper 

    2  Fitters 

    2  Skill workers 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    18/134

    CCPP BRAZI 860 MW  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  17 

    ______________________________________________________________________________ 

    435‐10‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    3.4  Proposal  for  erection time schedule  Week  1  2  3  4  5  6  7  8  9 

    1 Key dates 2 Check and control of measuring protocols and erection area 

    3 Organization of storage of small materials near to erection area  Iiiiii  

    4 Organization of scaffolding in erection area  iiiiii  

    5 Transport and installation of IPB steel support structures and‐consoles  iiiiii  

    6 Transport of shipping units to erection area  Iiiiii  

    7 Installation of IPB enclosure to components  iiiicc iiiiiii 

    8 Lifting and alignment of shipping units  between Line side cubicle and transformer  iiiiiii iiiiiii 

    9 Final alignment and erection of shipping units  iiiicc iiiiiii 

    10 Erection of Line side cubicle connection  Iiiiii 

    11 Erection of Short Circuit Device SCD (if applicable)  iiiiii 

    12 Installation of  branches to unit aux.‐and generator transformer  iiiiii 

    13 Welding of conductor and inside cleaning of IPB  iiiic 

    14 Welding of enclosure  iiiiii  iiiiiii 

    15 Welding of grounding  brackets and enclosure short circuit plates  iiiiii  iiiiiii 

    16 Welding of enclosure saddles  iiiiii  iiiiiii 

    17 Installation of pressurization system / dehydration system  Iiiiii 

    18 Installation of IPB wall penetrations (if applicable)  Iiiiii 

    19 Installation of sun shade (if applicable)  iiiiii 

    20 Cleaning of insulators  iiiiii 

    21 Insulation test  iiiiii 

    22 Installation of grounding links  iiiiii 

    23 High Voltage test  Iiiiii 

    24 Installation of flexible  bolted links of components  iiiicc iii 

    25 Installation of inspection covers and rubber compensators  I  i 

    26 Air leakage test  Ii I 

    27 Repair and /or final painting  iiiiii  

    28 Erection of next unit 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    19/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  18 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    4.  Required Tools,  Materials and General Welding  Instruction 

    4.1 

    Erection 

    tools, 

    made 

    available 

    by 

    Erection 

    Company 

    •  Electric driven tool (drilling machines, screw driving machines) 

    •  Welding equipment including welding  gas (excluded welding wire; for list of recommended 

    equipment see chapter 4.4.1.5) 

    •  Abrasive wheel cutting‐off machines, grinding machines 

    •  Hoists 

    •  Measuring and marking devices 

    •  Open ended spanners M10÷M36 

    •  Ring spanners M10÷M36 

    •  Ratchet wrenches M10÷M36 

    •  Torque wrench (range 30 – 120 N/m) 

    •  Test equipments according to chapter 5.2 

    Note: Erection

     company

     has

     to

      be

     able

     to

     pass

     all

     tests

     according

     to

     the

     chapter:

     5.2.4.

     Erection

     

    Co. have to  be able provide appropriate testing equipment, pressure gauge, High voltage 

    tester, tool, pressure compressor as well. 

    4.2  Special tools supplied with IPB 

    •  Tensioning tool for steel  band (Band‐IT), for silicon  bushing D58 ‐ if applicable 

    •  Tensioning tool for steel  band (Band‐IT), for rubber compensator 

    •  Special insulated spanners for SCD 

    •  Rivet players 

    •  Gun for silicon cartridges 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    20/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  19 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    4.3  Consumables and spares supplied with IPB  per  Unit  

    4.3.1  Consumables 

    1.  Detergents (Ethyl alcohol) 

    2.  Lubricants (Molykote 1000) 

    3.  Contact grease (Alvania R3) 

    4.  Primer coat of dull  black finish (for repaint) 

    5.  Final coat according to project specific colour (for repaint) 

    6.  Al Welding wires and Fe welding electrodes 

    7. 

    Templates of

     flexible

     expansion

     links

     (see

     chapter

     5.1.6

     for

     detailed

     use)

     

    8.  Shim‐plates for insulators (see chapter 5.1.8 for detailed use) 

    9.  Aluminium sheets (for test/practise welding at site, identified in packing list) 

    ‐ The sheets are duly marked “for test welding at site“ and the specific material code. 

    10.  FE shim‐plates for saddles 

    11.  Glue 

    12.  0,5 m of enclosure and conductor (for adaptation purpose, if needed) 

    13.  Cleaning rags 

    14.  Sealing paint (signal red colour) 

    15.  Emery paper 

    16.  Adhesive label 

    17.  Synthetic sponge 

    18.  Silicon Zn coat (for repaint/repair) 

    4.3.2  Spare  parts  for  erection  per  Unit  

    1.  Insulator (for IPB conductor support) 

    2.  O‐Ring D120 (for insulator) 

    3.  Cu‐expansion link (310 and / or 410 mm) 

    4.  Al‐expansion link 

    5.  Al‐flat  bar (100 x 15 x 1000 mm) 6.  Insulating tubes (for IPB enclosure support) 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    21/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  20 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    7.  Sleeve (for IPB enclosure moveable support) 

    8.  Sleeve (for IPB enclosure fixedsupport) 

    Note 1: 

    The erection spares are generally marked in the packing list  by Pos No 8.9.., where the “9” identifies the 

    spare. 

    Note 2: 

    All  bolting elements are supplied with 5 % erection spares, not identified in the packing list as given in Note 

    1. 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    22/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  21 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    4.4  Welding  

    4.4.1  Welding  of  aluminium 

    4.4.1.1  Welder  qualification  for  aluminium 

    The IPB is designed for site welding procedures in accordance with EN 287, Part 2, or relevant ASME rule 

    IX. QW 400. The welder has to  be qualified  by certification to the  before mentioned regulations. 

    Each individual site welding has to follow the Welding Procedure Specification (WPS) given in Chapter 

    4.4.1.5 

    4.4.1.2  General instructions 

    The welding methods shall  be executed according to WPS. 

    (WIG and MIG methods shall  be executed as indicated in WPS) 

    4.4.1.2.1  Designation of  site welds 

    The individual welds which shall  be executed at site are designated in the erection drawings  by the 

    following symbol.

     

    Individual welding has to follow the indicated weld  joint number of WPS. 

    4.4.1.2.2 

     Methods 

    of  

    welding  

    WIG and MIG method shall  be executed at site. The respective method is indicated in the WPS. 

    1. WIG: Wolfram gas–shielded welding 

    The electrode (Wolfram) and the supplementary material (Aluminium) are independent. The method is 

    used for welds up to material thickness of 2 – 5 mm (IPB enclosure). 

    2. MIG: Metal gas‐shielded welding 

    The electrode is simultaneously the supplementary material. 

    Both, the electrode and the supplementary material are of aluminium. The method is used for welds up to 

    material thickness of 3 – 15 mm (IPB conductor, short‐circuit connections). 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    23/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  22 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    4.4.1.2.3  Designation on  package of  welding  wire 

    The designation on the package shield indicates the chemical composition of welding wire, 

    or the material number and colour designation according to EN 573. 

    Chemical composition of 

    welding wire according to 

    DIN 1732 

    Designation of welding wire 

    according to EN 573 

    Colour designation 

    according to EN 573 

    SG Al 99,5 Ti  EN AW‐1450  Green frame 

    SG Al Mg5  EN AW‐5356  Red frame 

    SG AlSi5  EN AW‐4043A  Yellow frame The designation of welding wire is valid for all diameters of welding wire and for  both methods of welding 

    procedures WIG and MIG. 

    4.4.1.3  Preparation, execution and after ‐treatment  

    4.4.1.3.1  Preparation of  welding  

    The welding area must  be cleaned (including paint removal) prior to welding. Cleaning (brushed or 

    scraped) has to  be executed with a distance of approximately 50 mm to  both sides of welding axis. Note: 

    Prescribed preheating temperature according to corresponding WPS has to  be observed and followed. The 

    preheating is mainly assigned to welding of current‐carrying connections like: 

    •  conductor connections 

    •  grounding contacts 

    •  short‐circuiting connections 

    Generaly: the Al material over 8,0 mm thickness has to  be preheated. 

    Recommended method of manufacturer for preheating: 

    A required preheating shall  be executed  by means of flame of Butane or other suitable gas  burner. The 

    electrical preheating is possible as well. 

    4.4.1.3.2  Execution of  welding  

    Welding has to follow the corresponding Weld  Joint Number of WPS. The corresponding Weld  Joint 

    Number related to a weld is stated in the erection drawings (refer to chapter 4.4.1.4 for WPS of aluminium). 

    Note: 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    24/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  23 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Prescribed preheating temperature according to WPS has to  be observed. 

    4.4.1.3.3   After ‐treatment  of  weld 

    The weld surface has to  be  brushed and welding slag has to  be removed. After cool down of weld the area 

    must  be painted. 

    Note: 

    Each executed weld shall  be stamped with the individual certification number of corresponding welder. 

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    25/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  24 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    4.4.1.4  Overview of  WPS  for  aluminium welding  

    4.4.1.5  Welding  Procedure Specification (WPS)  for  aluminium 

    Following are assembled all WPS needed for project specific site welding. 

    Drawing WPS No.:

    Layout 384  

    440-00-BAA-EDA-EGE-001

    Connection to Generator 34 318 554

    440-00-BAA-EDA-EGE-002

    Connection to GSU Transformer 34 200 318 319 554

    440-00-BAA-EDA-EGE-003

    Connection to UA Transformer 113 114 225 273 418 700

    440-00-BAA-EDA-EGE-004

    Pressure Device 112

    440-00-BAA-EDA-EGE-007

    Connection to Generator Circuit Breaker 19 23 141

    440-00-BAA-EDA-EGE-005

    Bus Connection Pieces 13 520 553 554 694

    440-00-BAA-EDA-EGE-009

    Enclosure Connection Pieces 19 22 23 105 155 449440-00-BAA-EDA-EGE-010

    Isolated Enclosure Support – Fixed 415

    440-00-BAA-EDA-EGE-011

    Isolated Enclosure Support – Moveable  415

    440-00-BAA-EDA-EGE-012

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    26/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  25 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS Valid from: 30.08.2010Weld Joint No.: 13 Weld Form acc : Aluminium weldings Page: 1/1 Revision: 16

    BASIS DATAIssued by for WPS: EN ISO 15609-1Testing laboratory for WPQR: EN ISO 15614-2

    EGE LtdIO ŠKOLA Welding Ltd

    BASIC MATERIAL – PARENT METALSpecification-sort, quality (Metal sheet) T1 and T2 /Thickness of the welded material – t1 and t2 (mm)

    T1: Plate: Al 99,5 ( EN 573:EN AW EAl 99,5) / t1: 12T2: Plate: Al 99,5 ( EN 573:EN AW EAl 99,5) / t2: 12

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical marking

    Storage conditions / Cleaning method / Color label / SymbolEN ISO 18273: SAL99,5 Ti: SAl 1450Standard conditions / Special cleaning not required / Green / Alloy: 1450

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN ISO 14175 / 15 - 20

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding techniqueWelding / Weld type / Double or single pass

    Design throat thickness (mm): s / Root protection

    Weld length: L (mm) / Covering surfaceRoot gab:b, Depth of root face:c (mm)

    Welding position

    Welding method

    Weld indication in drawings / Weld preparation

    Semi-automatic inert gas shielded welding / 131:MIG:EN ISO 4063Manual / BW - butt weld – II weld / Singles = 5 for II weld / nb – backing free welding EN ISO 9606-2

    L = In whole lengths welded part T1 and T2 / Convex for II weldb 3, c = 12 for II weldPF: vertical position up or PA: flat position or PD horizontal overheadposition: EN ISO 6947ss - unilateral welding: EN ISO 9606-2EN 22553 / EN ISO 9692-3

    PREHEAT / POSTWELD HEAD TREATMENTPreheat for t1 and t2 (°C) / Post heating / Fuel gasesHeating rate / Cooling rate / Post weld heat treatment

    80 - 100 for t1 and t2 / No / Propane-butane or oxy-acetyleneContinuous / Air / No

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)

    Wire feed rate / Flashing currentInverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant)

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de control

    Implement for cleaning for weld

    EN ISO 10042: Acceptance level: D / 100 %Wire brush or chisel, grinding machine for aluminium

    QUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P BW 21 S t„x“ PF ss nb / for „x“ ≥ 6

    WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLE

    Bead (No.)∅ of filler material

    (mm)

    Current

    (A)

    Voltage

    (V)

    Current kind

     polarity

    Wire feed rate

    (m/min)

    Welding speed

    (cm/min)

    Quantity wire

    (kg/m)

    1, 2 1,6 165 – 245 21 – 24 =/+(DC) 4,0 - 6,0 18 - 20 0,09-0,1WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    PRODUCTION PROCESSclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection

    SUPERVISIONElaborated by: Ing. Pavel KálalTitle: International and European Welding Engineer: EN ISO 14731

    Department: Technology Welding: Welding coordination

    Issued on: 14.06.2001

    Welding Procedure Qualification Repord: WPQR 19/2009 

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENTThe technical documentation is the property of EGE, spol. s r.o. and is subject to protection under copyright law as a useful work.

    Reproduction, distribution, use, display and communication to third parties without the explicit consent of EGE, spol. s r.o. is illegal and prohibited.

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    27/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  26 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS Valid from: 27.05.2010Weld Joint No.: 19 Weld Form acc: Aluminium weldings Page: 1/1 Revision: 18

    BASIS DATAIssued by for WPS: EN ISO 15609-1

    Testing laboratory for WPQR: EN ISO 15614-2

    EGE Ltd

    IO ŠKOLA Welding LtdBASIC MATERIAL – PARENT METALSpecification-sort, quality (Metal sheet) T1 and T2 /

    Thickness of the welded material – t1 and t2 (mm)T1: Tube: Al 99,5 ( EN 573:EN AW EAl 99,5) / t1: 5T2: Plate: Al 99,5 ( EN 573:EN AW EAl 99,5) / t2: 5

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical markingStorage conditions / Cleaning method / Color label / Symbol

    EN ISO 18273: SAL99,5 Ti: SAl 1450Standard conditions / Special cleaning not required / Green / Alloy: 1450

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN 439 / 15 - 20

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding techniqueWelding / Weld type / Lap width: l (mm)

    Design throat thickness (mm): s / Weld length: L (mm)Weld distance b: (mm) / Covering surface

    Welding position

    Weld indication in drawings / Weld preparation

    Semi-automatic inert gas shielded welding / 131: MIG:EN ISO 4063Manual / FW - fillet weld / l = 75 ± 50s = 3,5 for fillet weld / L = Peripheral weld for T2b 2 for Fillet weld / Convex for fillet weld

    PF: vertical position up or PB: flat position or PD horizontal overheadposition or PC: horizontal position: EN ISO 6947EN 22553 / EN ISO 9692-3

    PREHEAT / POSTWELD HEAD TREATMENTPreheat for t1 and t2 (°C)

    Post heating / Fuel gases

    Heating rate / Cooling rate / Post weld heat treatment

    No for t1 and t2 for atmospheric air or temperature of room > 050 – 80 for t1 and t2 for atmospheric air or temperature of room ≤ 0No / Propane-butane or oxy-acetyleneContinuous / Air / No

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)

    Wire feed rate / Flashing currentInverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant)

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de control

    Implement for cleaning for weldEN ISO 10042: Acceptance level: D / 100 %Wire brush or chisel, grinding machine for aluminium

    QUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P FW 22 S t„x“ PF sl / for „x“ ≥ 3

    WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLE

    Bead (No.)∅ of filler material

    (mm)

    Current

    (A)

    Voltage

    (V)

    Current kind

     polarity

    Wire feed rate

    (m/min)

    Welding speed

    (cm/min)

    Quantity wire

    (kg/m)

    1 Root layer 1,6 165 – 245 21 – 24 =/+(DC) 3,9 - 6,0 22 – 23 0,06 - 0,07WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    PRODUCTION PROCESSclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection

    SUPERVISIONElaborated by: Ing. Pavel KálalTitle: International and European Welding Engineer: EN ISO 14731

    Department: Technology Welding: Welding coordination

    Issued on: 25.01.2001

    Welding Procedure Qualification Repord: WPQR 21/2009

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENTThe technical documentation is the property of EGE, spol. s r.o. and is subject to protection under copyright law as a useful work.

    Reproduction, distribution, use, display and communication to third parties without the explicit consent of EGE, spol. s r.o. is illegal and prohibited.

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    28/134

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    29/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  28 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS Valid from: 30.08.2010Weld Joint No.: 23 Weld Form acc : Aluminium weldings Page: 1/1 Revision: 20

    BASIS DATAIssued by for WPS: EN ISO 15609-1

    Testing laboratory for WPQR: EN ISO 15614-2

    EGE Ltd

    IO ŠKOLA Welding LtdBASIC MATERIAL – PARENT METALSpecification-sort, quality (Metal sheet) T1 and T2 /

    Thickness of the welded material – t1 and t2 (mm)T1: Plate: Al 99,5 ( EN 573:EN AW EAl 99,5) / t1: 5T2: Plate: AlMgSi0,5 ( EN 573:EN AW EAlMgSi) / t2: 5

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical marking

    Storage conditions / Cleaning method / Color label / SymbolEN ISO 18273: SAlSi5: SAl4043(A)Standard conditions / Special cleaning not required / Yellow / Alloy: 4043

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN ISO 14175 / 15 - 20

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding techniqueWelding / Weld type

    Design throat thickness (mm): s / Weld length: L (mm)Weld distance b: (mm) / Covering surface

    Welding position

    Weld indication in drawings / Weld preparation

    Semi-automatic inert gas shielded welding / 131:MIG:EN ISO 4063Manual / FW - fillet welds = 3,5 for fillet weld / L = In whole lengths welded part for T2b 2 for Fillet weld / Convex for fillet weld

    PF: vertical position up or PB: flat position or PD horizontal overheadposition: EN ISO 6947EN 22553 / EN ISO 9692-3

    PREHEAT / POSTWELD HEAD TREATMENTPreheat for t1 and t2 (°C)

    Post heating / Fuel gasesHeating rate / Cooling rate / Post weld heat treatment

    No for t1 and t2 for atmospheric air or temperature of room > 050 – 80 for t1 and t2 for atmospheric air or temperature of room ≤ 0No / Propane-butane or oxy-acetyleneContinuous / Air / No

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)

    Wire feed rate / Flashing currentInverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant)

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de control

    Implement for cleaning for weldEN ISO 10042: Acceptance level: D / 100 %Wire brush or chisel, grinding machine for aluminium

    QUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P FW 23 S t„x“ PF sl / for 2,5 ≤ „x“ ≤ 6

    WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLE

    Bead (No.)∅ of filler

    material (mm)

    Current

    (A)

    Voltage

    (V)

    Current kind

     polarity

    Wire feed rate

    (m/min)

    Welding speed

    (cm/min)

    Quantity wire

    (kg/m)

    1 Root layer 1,6 145 – 220 20 – 24 =/+(DC) 3,9 - 6,0 22 – 25 0,065 - 0,075WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    PRODUCTION PROCESSclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection

    SUPERVISIONElaborated by: Ing. Pavel KálalTitle: International and European Welding Engineer: EN ISO 14731

    Department: Technology Welding: Welding coordination

    Issued on: 25.01.2001

    Welding Procedure Qualification Record: WPQR 09/2007

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENTThe technical documentation is the property of EGE, spol. s r.o. and is subject to protection under copyright law as a useful work.Reproduction, distribution, use, display and communication to third parties without the explicit consent of EGE, spol. s r.o. is illegal and

     prohibited.

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    30/134

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    31/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  30 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS Valid from: 19.10.2010Weld Joint No.: 105 Weld Form acc: Aluminium weldings Page: 1/1 Revision: 11

    BASIS DATAIssued by for WPS: EN ISO 15609-1

    Testing laboratory for WPQR: EN ISO 15614-2

    EGE Ltd

    IO ŠKOLA Welding LtdBASIC MATERIAL – PARENT METALSpecification-sort, quality (Metal sheet) T1 and T2 /

    Thickness of the welded material – t1 and t2 (mm)T1: Plate: Al 99,5 ( EN 573:EN AW EAl 99,5) / t1: 6T2: Plate: AlMgSi0,5 ( EN 573:EN AW EAlMgSi) / t2: 5

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical markingStorage conditions / Cleaning method / Color label / Symbol

    EN ISO 18273: SAlSi5: S Al 4043(A)Standard conditions / Special cleaning not required / Yellow / Alloy: 4043

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN ISO 14175 / 20 - 25 

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding techniqueWelding / Weld type

    Design throat thickness (mm): s / Weld length: L (mm)Weld distance b: (mm) / Covering surface

    Welding position

    Weld indication in drawings / Weld preparation

    Semi-automatic inert gas shielded welding / 131:MIG:EN ISO 4063Manual / FW - fillet welds = 3,5 for fillet weld / L = In whole lengths welded part for T2b 2 for Fillet weld / Convex for fillet weld

    PF: vertical position up or PB: flat position or PD horizontal overheadposition: EN ISO 6947EN 22553 / EN ISO 9692-3

    PREHEAT / POSTWELD HEAD TREATMENTPreheat for t1 and t2 (°C)

    Post heating / Fuel gasesHeating rate / Cooling rate / Post weld heat treatment

    No for t1 and t2 for atmospheric air or temperature of room > 050 – 80 for t1 and t2 for atmospheric air or temperature of room ≤ 0No / Propane-butane or oxy-acetyleneContinuous / Air / No

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)

    Wire feed rate / Flashing currentInverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant)

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de control

    Implement for cleaning for weldEN ISO 10042: Acceptance level: D / 100 %Wire brush or chisel, grinding machine for aluminium

    QUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P FW 23 S t„x“ PF sl / for „x“ ≥ 3

    WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLE

    Bead (No.)∅ of filler

    material (mm)

    Current

    (A)

    Voltage

    (V)

    Current kind

     polarity

    Wire feed rate

    (m/min)

    Welding speed

    (cm/min)

    Quantity wire

    (kg/m)

    1 Root layer 1,6 145 – 220 20 – 24 =/+(DC) 3,9 - 6,0 22 – 25 0,065 - 0,075WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    PRODUCTION PROCESSclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection

    SUPERVISIONElaborated by: Ing. Pavel KálalTitle: International and European Welding Engineer: EN ISO 14731

    Department: Technology Welding

    Issued on: 25.01.2001

    Welding Procedure Qualification Record: WPQR 09/2007

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENTThe technical documentation is the property of EGE, spol. s r.o. and is subject to protection under copyright law as a useful work.

    Reproduction, distribution, use, display and communication to third parties without the explicit consent of EGE, spol. s r.o. is illegal and prohibited.

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    32/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  31 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS  Valid from: 11.05.2007Weld Joint No.: 112  Weld Form acc : Press Air connection  Page: 1/1 Rev.: 5

    BASIS DATAIssued by for WPS: EN ISO 15609-1

    Testing laboratory for WPAR: EN 288-4 

    EGE Ltd

    Czech Welding Institute Ltd BASIC MATERIAL – PARENT METAL Specification-sort, quality (Metal sheet) T1 and T2 /Thickness of the welded material – t1 and t2 (mm)  

    T1: Tube: Al 99,5 ( EN 573:EN AW EAl 99,5: 1450) / t1: 5 T2: Plate: AlMgSi0,5 ( EN 573:EN AW EAlMgSi) / t2: 5 

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical markingStorage conditions / Cleaning method / Color label 

    DIN 1732: SG AlSi5: 3.2245 or EN ISO 18273: SAlSi5:SAl4043(A)Standard conditions / Special cleaning not required / Yellow 

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN 439 / 15 - 20 

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding technique

    Welding / Weld typeDesign throat thickness (mm): s / Weld length: L (mm)Weld distance b: (mm) / Covering surface

    Welding position

    Weld indication in drawings / Weld preparation 

    Semi-automatic inert gas shielded welding / 131:MIG:EN ISO 4063 Manual / FW - fillet welds = 4 for fillet weld / L = Peripheral weld for T2b 2 for Fillet weld / Convex for fillet weld

    PF: vertical position up or PB: flat position or PD horizontal overheadposition: EN ISO 6947EN 22553 / EN ISO 9692-3 

    PREHEAT / POSTWELD HEAD TREATMENTPreheat (°C) / Interpass (°C) / Post heating / Fuel gases

    Heating rate / Cooling rate / Post weld heat treatment 10 - 20 for T1 and T2 / 300 / No / Propane-butane or oxy-acetyleneContinuous / Air / No 

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)Wire feed rate / Flashing current 

    Inverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant) 

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de controlImplement for cleaning for weld  

    EN 30042 or EN ISO 10042: Acceptance level: D / 100 %Wire brush or chisel, grinding machine for aluminium 

    QUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P FW 23 S t„x“ PF sl / for x“ ≥ 3 

    WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLEBead (No.)

    ∅ of fillermaterial (mm)

    Current

    (A)

    Voltage

    (V)

    Current kind

     polarity

    Wire feed rate

    (m/min)

    Welding speed

    (cm/min)

    Quantity

    wire (kg/m)

    Heat input(KJ/mm)

    1 Root layer 1,6 165 – 245 21 – 24 =/+(DC) 3,9 - 6,0 20 – 22 0,07 - 0,08 0,8 - 1,3WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    WELDING PROCEDUREclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection 

    SUPERVISIONElaborated by: Ing. Pavel KálalTitle: International and European Welding Engineer: EN 719

    Department: Technology WeldingIssued on: 05.10.2001

    Welding procedure approval record: WPAR 03/98

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENT

    Handover document stranger only in coordination with EGE.

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    33/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  32 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS Valid from: 21.05.2010Weld Joint No.: 113 Weld Form acc : Aluminium weldings Page: 1/1 Revision: 17

    BASIS DATAIssued by for WPS: EN ISO 15609-1 / Testing laboratory for WPQR: EN ISO 15614-2 EGE Ltd / IO ŠKOLA Welding Ltd

    BASIC MATERIAL – PARENT METALSpecification-sort, quality (Metal sheet) T1 and T2 /Thickness of the welded material – t1 and t2 (mm)

    T1: Tube: Al 99,5 ( EN 573:EN AW EAl 99,5) / t1: 3T2: Plate: AlMgSi0,5 ( EN 573:EN AW EAlMgSi) / t2: 15

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical marking

    Storage conditions / Cleaning method / Color label / SymbolEN ISO 18273: SAlSi5: SAl 4043(A)Standard conditions / Special cleaning not required / Yellow / Alloy: 4043

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN 439 / 15 - 20

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding techniqueWelding / Weld type / Double or single pass

    Design throat thickness (mm): s / Root protection

    Bevel form: u (°) / Welding method

    Weld length: L (mm) / Covering surface

    Root gab:b / Depth of root face:c (mm)Welding position

    Weld indication in drawings / Weld preparation

    Semi-automatic inert gas shielded welding / 131: MIG:EN ISO 4063Manual / BW - butt weld – V weld / Singles = 14 / nb: backing – free welding EN ISO 9606-245 ± according to diameter / ss: unilateral welding EN ISO 9606-2L = In whole lengths welded part for T2 / Convex

    b 2 / c = t2PF: vertical position up or PB: flat position or PD horizontal overheadposition or PC: horizontal position: EN ISO 6947EN 22553 / EN ISO 9692-3

    PREHEAT / POSTWELD HEAD TREATMENTPreheat (°C)

    Interpass (°C) / Post heating / Fuel gases

    Heating rate / Cooling rate / Post weld heat treatment

    No for t1 and 100 – 120 for t2 for atmospheric air or temperature of room > 050 – 80 for t1 and 100 – 120 for t2 for atmospheric air or temperature of room ≤ 0250 / No / Propane-butane or oxy-acetyleneContinuous / Air / No

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)Wire feed rate / Flashing current

    Inverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant)

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de control

    Implement for cleaning for weld

    EN ISO 10042: Acceptance level: D / 100 %

    Wire brush or chisel, grinding machine for aluminiumQUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P BW 23 S t„x“ PF bs nb / for 2 ≤ „x“ ≤ 6 and

    EN ISO 9606-2 131 P BW 23 S t„x“ PF bs nb / for „x“ ≥ 6WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLE

    Bead (No.)∅ of filler

    material (mm)

    Current

    (A)

    Voltage

    (V)

    Current kind

     polarity

    Wire feed rate

    (m/min)

    Welding speed

    (cm/min)

    Quantity wire

    (kg/m)

    1, 2, 3 1,6 165 – 245 22 – 24 =/+(DC) 4,2 - 6,0 9 - 12 0,3 – 0,4WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    Welding position PD, PF, PC:From 2 or 3 strata it can be

    treasure weld strata and side byside

    PRODUCTION PROCESSclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection

    SUPERVISIONElaborated by: Ing. Pavel KálalTitle: International and European Welding Engineer: EN ISO 14731Department: Technology Welding: Welding coordination

    Issued on: 21.04.2004

    Welding Procedure Qualification Record: WPQR 11/2007

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENTThe technical documentation is the property of EGE, spol. s r.o. and is subject to protection under copyright law as a useful work.

    Reproduction, distribution, use, display and communication to third parties without the explicit consent of EGE, spol. s r.o. is illegal and prohibited.

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    34/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  33 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS Valid from: 19.10.2010Weld Joint No.: 114 Weld Form acc : Aluminium weldings Page: 1/1 Revision: 19

    BASIS DATAIssued by for WPS: EN ISO 15609-1 / Testing laboratory for WPQR: EN ISO 15614-2 EGE Ltd / IO ŠKOLA Welding Ltd

    BASIC MATERIAL – PARENT METALSpecification-sort, quality (Metal sheet) T1 and T2 /Thickness of the welded material – t1 and t2 (mm)

    T1: Tube: Al 99,5 ( EN 573:EN AW EAl 99,5) / t1: 3T2: Plate: AlMgSi0,5 ( EN 573:EN AW EAlMgSi) / t2: 15

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical markingStorage conditions / Cleaning method / Color label / Symbol

    EN ISO 18273: SAl Si5:SAl 4043(A)Standard conditions / Special cleaning not required / Yellow / Alloy: 4043

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN ISO 14175 / 15 - 20

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding technique

    Welding / Weld type / Double or single passDesign throat thickness (mm): s / Root protection

    Bevel form: u (°) / Welding method

    Weld length: L (mm) / Covering surface

    Root gab:b,Depth of root face:c (mm)Welding position

    Weld indication in drawings / Weld preparation

    Semi-automatic inert gas shielded welding / 131:MIG:EN ISO 4063Manual / BW - butt weld – ½ V weld / Doubles = 7 / nb: backing – free welding EN ISO 9606-245 ± according to diameter / bs - sealing run EN ISO 9606-2L = In whole lengths welded part for T2 / Convex

    b 2 / 1 c 2PF: vertical position up or PB: flat position or PD horizontal overheadposition or PC: horizontal position: EN ISO 6947EN 22553 / EN ISO 9692-3

    PREHEAT / POSTWELD HEAD TREATMENTPreheat (°C)

    Interpass (°C) / Post heating / Fuel gasesHeating rate / Cooling rate / Post weld heat treatment

    No for t1 and 120 – 150 for t2 for atmospheric air or temperature of room > 050–80 for t1 and 120–150 for t2 for atmospheric air or temperature of room ≤ 0250 / No / Propane-butane or oxy-acetyleneContinuous / Air / No

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)Wire feed rate / Flashing current

    Inverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant)

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de control

    Implement for cleaning for weld

    EN ISO 10042: Acceptance level: D / 100 %

    Wire brush or chisel, grinding machine for aluminiumQUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P BW 23 S t„x“ PF bs nb / for 2 ≤ „x“ ≤ 6 and

    EN ISO 9606-2 131 P BW 23 S t„x“ PF bs nb / for „x“ ≥ 7WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLE

    Bead (No.)∅ of filler

    material (mm)

    Current(A)

    Voltage(V)

    Current kind polarity

    Wire feed rate(m/min)

    Welding speed(cm/min)

    Quantity wire(kg/m)

    1, 2 1,6 145 – 240 20 – 24 =/+(DC) 4,0 - 6,0 16 - 20 0,8 – 1,0WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    Welding position PD, PF, PC:From 2 weld strata it can be

    treasure weld strata and side byside

    PRODUCTION PROCESSclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection

    SUPERVISIONElaborated by: Ing. Pavel Kálal

    Title: International and European Welding Engineer: EN ISO 14731Department: Technology Welding: Welding coordination

    Issued on: 05.10.2001

    Welding Procedure Qualification Record: WPQR 11/2007

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENTThe technical documentation is the property of EGE, spol. s r.o. and is subject to protection under copyright law as a useful work.Reproduction, distribution, use, display and communication to third parties without the explicit consent of EGE, spol. s r.o. is illegal and prohibited.

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    35/134

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    36/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  35 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS Valid from: 19.10.2010Weld Joint No.: 155 Weld Form acc : Aluminium weldings Page: 1/1 Revision: 14

    BASIS DATAIssued by for WPS: EN ISO 15609-1 / Testing laboratory for WPQR: EN ISO 15614-2 EGE Ltd / IO ŠKOLA Welding Ltd

    BASIC MATERIAL – PARENT METALSpecification-sort, quality (Metal sheet) T1 and T2 /Thickness of the welded material – t1 and t2 (mm)

    T1: Tube: Al 99,5 ( EN 573:EN AW EAl 99,5) / t1: 3T2: Plate: Al 99,5 ( EN 573:EN AW EAl 99,5) / t2: 4

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical marking

    Storage conditions / Cleaning method / Color label / SymbolEN ISO 18273: SAL99,5 Ti: SAl 1450Standard conditions / Special cleaning not required / Green / Alloy: 1450

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN ISO 14175 / 15 - 20

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding techniqueWelding / Weld type / Lap width: l (mm)

    Design throat thickness (mm): s / Weld length: L (mm)Weld distance b: (mm) / Covering surface

    Welding position

    Weld indication in drawings / Weld preparation

    Semi-automatic inert gas shielded welding / 131:MIG:EN ISO 4063Manual / FW - fillet weld / l = 75 ± 50s = 3 for fillet weld / L = Peripheral weld for T2b 2 for Fillet weld / Convex for fillet weldPF: vertical position up or PB: flat position or PD horizontal overhead

    position or PC: horizontal position: EN ISO 6947EN 22553 / EN ISO 9692-3

    PREHEAT / POSTWELD HEAD TREATMENTPreheat for t1 and t2 (°C)

    Post heating / Fuel gasesHeating rate / Cooling rate / Post weld heat treatment

    No for t1 and t2 for atmospheric air or temperature of room > 050 – 80 for t1 and t2 for atmospheric air or temperature of room ≤ 0No / Propane-butane or oxy-acetyleneContinuous / Air / No

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)Wire feed rate / Flashing current

    Inverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant)

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de controlImplement for cleaning for weld

    EN ISO 10042: Acceptance level: D / 100 %Wire brush or chisel, grinding machine for aluminium

    QUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P FW 21 S t„x“ PF sl / for„x“ ≥ 3

    WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLE

    Bead (No.)∅ of filler

    material (mm)

    Current

    (A)

    Voltage

    (V)

    Current kind

     polarity

    Wire feed rate

    (m/min)

    Welding speed

    (cm/min)

    Quantity wire

    (kg/m)

    1 Root layer 1,6 145 – 200 22 – 27 =/+(DC) 3,9 - 6,0 23 - 27 0,06 – 0,07WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    PRODUCTION PROCESSclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection

    SUPERVISIONElaborated by: Ing. Pavel KálalTitle: International and European Welding Engineer: EN ISO 14731Department: Technology Welding: Welding coordination

    Issued on: 01.04.2004

    Welding Procedure Qualification Record: WPQR 21/2009

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENTThe technical documentation is the property of EGE, spol. s r.o. and is subject to protection under copyright law as a useful work.

    Reproduction, distribution, use, display and communication to third parties without the explicit consent of EGE, spol. s r.o. is illegal and

     prohibited.

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    37/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  36 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS  Valid from: 01.09.2010Weld Joint No.: 200  Weld Form acc : Aluminium weldings  Page: 1/1 Revision: 14

    BASIS DATAIssued by for WPS: EN ISO 15609-1 / Testing laboratory for WPQR: EN ISO 15614-2  EGE Ltd / IO ŠKOLA Welding Ltd 

    BASIC MATERIAL – PARENT METAL Specification-sort, quality (Metal sheet) T1 and T2 /

    Thickness of the welded material – t1 and t2 (mm)  T1: Tube: Al 99,5 ( EN 573:EN AW EAl 99,5) / t1: 5 T2: Plate: AlMgSi0,5 ( EN 573:EN AW EAlMgSi) / t2: 15 

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical markingStorage conditions / Cleaning method / Color label / Symbol 

    EN ISO 18273: SAl Si5:SAl 4043(A)Standard conditions / Special cleaning not required / Yellow / Alloy: 4043 

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN ISO 14175 / 15 - 20 

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding techniqueWelding / Weld type / Double or single pass

    Design throat thickness (mm): s / Root protection

    Bevel form: u (°) / Welding method

    Weld length: L (mm) / Covering surface

    Root gab:b,Depth of root face:c (mm)Welding position

    Weld indication in drawings / Weld preparation 

    Semi-automatic inert gas shielded welding / 131: MIG:EN ISO 4063 Manual / BW - butt weld – ½ V weld / Doubles = 7 / nb: backing – free welding EN ISO 9606-245 ± according to diameter / bs - sealing run EN ISO 9606-2L = In whole lengths welded part for T2 / Convex

    b 2 / 1 c 2PF: vertical position up or PB: flat position or PD horizontal overheadposition or PC: horizontal position: EN ISO 6947EN 22553 / EN ISO 9692-3 

    PREHEAT / POSTWELD HEAD TREATMENTPreheat (°C)

    Interpass (°C) / Post heating / Fuel gasesHeating rate / Cooling rate / Post weld heat treatment 

    No for t1 and 120 – 150 for t2 for atmospheric air or temperature of room > 050–80 for t1 and 120–150 for t2 for atmospheric air or temperature of room ≤ 0250 / No / Propane-butane or oxy-acetyleneContinuous / Air / No 

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)Wire feed rate / Flashing current 

    Inverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant) 

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de control

    Implement for cleaning for weld  EN ISO 10042: Acceptance level: D / 100 %Wire brush or chisel, grinding machine for aluminium 

    QUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P BW 23 S t„x“ PF bs nb / for 3 ≤ „x“ ≤ 6 and

    EN ISO 9606-2 131 P BW 23 S t„x“ PF bs nb / for „x“ ≥ 7 WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLE

    Bead (No.)∅ of filler

    material (mm)

    Current

    (A)

    Voltage

    (V)

    Current kind

     polarity

    Wire feed rate

    (m/min)

    Welding speed

    (cm/min)

    Quantity wire

    (kg/m)

    1, 2 1,6 145 – 240 20 – 24 =/+(DC) 4,0 - 6,0 16 - 20 0,8 – 1,0WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    Welding position PD, PF, PCFrom 2 weld strata it can be

    treasure weld strata and side byside

    PRODUCTION PROCESSclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection 

    SUPERVISIONElaborated by: Ing. Pavel Kálal

    Title: International and European Welding Engineer: EN ISO 14731Department: Technology Welding: Welding coordination

    Issued on: 23.07.2002

    Welding Procedure Qualification Record: WPQR 11/2007 

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENTThe technical documentation is the property of EGE, spol. s r.o. and is subject to protection under copyright law as a useful work.

    Reproduction, distribution, use, display and communication to third parties without the explicit consent of EGE, spol. s r.o. is illegal and prohibited.

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    38/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  37 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS  Valid from: 01.09.2010Weld Joint No.: 225  Weld Form acc : Aluminium weldings  Page: 1/1 Revision: 4

    BASIS DATAIssued by for WPS: EN ISO 15609-1

    Testing laboratory for WPQR: EN ISO 15614-2 

    EGE Ltd

    ŠKOLA Welding Ltd BASIC MATERIAL – PARENT METAL Specification-sort, quality (Metal sheet) T1 and T2 /Thickness of the welded material – t1 and t2 (mm)  

    T1: Tube: Al 99,5 ( EN 573:EN AW EAl 99,5) / t1: 4 T2: Plate: AlMgSi0,5 ( EN 573:EN AW EAlMgSi) / t2: 5 

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical markingStorage conditions / Cleaning method / Color label / Symbol 

    EN ISO 18273: SAlSi5: S Al 4043(A)Standard conditions / Special cleaning not required / Yellow / Alloy: 4043 

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN ISO 14175 / 15 - 20 

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding technique

    Welding / Weld typeDesign throat thickness (mm): s / Weld length: L (mm)Weld distance b: (mm) / Covering surface

    Welding position

    Weld indication in drawings / Weld preparation 

    Semi-automatic inert gas shielded welding / 131:MIG:EN ISO 4063 Manual / FW - fillet welds = 4 for fillet weld / L = In whole lengths welded part T2 b 2 for Fillet weld / Convex for fillet weld

    PF: vertical position up or PB: flat position or PD horizontal overheadposition: EN ISO 6947EN 22553 / EN ISO 9692-3 

    PREHEAT / POSTWELD HEAD TREATMENTPreheat (°C)

    Post heating / Fuel gasesHeating rate / Cooling rate / Post weld heat treatment 

    No for t1 and t2 for atmospheric air or temperature of room > 050 – 80 for t1 and t2 for atmospheric air or temperature of room ≤ 0No / Propane-butane or oxy-acetyleneContinuous / Air / No 

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)

    Wire feed rate / Flashing current Inverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant) 

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de controlImplement for cleaning for weld  

    EN ISO 10042: Acceptance level: D / 100 %Wire brush or chisel, grinding machine for aluminium 

    QUALIFICATION OF WELDERSMinimum qualification of welders EN ISO 9606-2 131 P FW 23 S t„x“ PF sl / for for „x“ ≥ 3 

    WELDING VARIABLE – ESSENTIAL VARIABLE - ADDITIONAL VARIABLE

    Bead (No.)∅ of filler

    material (mm)

    Current(A)

    Voltage(V)

    Current kind polarity

    Wire feed rate(m/min)

    Welding speed(cm/min)

    Quantity wire(kg/m)

    1 Root layer 1,6 165 – 245 21 – 24 =/+(DC) 3,9 - 6,0 18 - 22 0,65 – 0,95WELD - SKETCHES – REMARKS – DETAILS - WELD RUN SEQUENCE

    WELDING PROCEDUREclean weld surface, eventually preheat, stitch, carry out weld, clean weld, remove and correct pertinent imperfection 

    SUPERVISIONElaborated by: Ing. Pavel KálalTitle: International and European Welding Engineer: EN ISO 14731Department: Technology Welding: Welding coordination

    Issued on: 15.11.2002

    Welding Procedure Qualification Record: WPQR 09/2007

    Signature: Common seal:

    Substitutes/Invalidates: 0

    DOKUMENTThe technical documentation is the property of EGE, spol. s r.o. and is subject to protection under copyright law as a useful work.Reproduction, distribution, use, display and communication to third parties without the explicit consent of EGE, spol. s r.o. is illegal and

     prohibited

  • 8/17/2019 440-00-BAA-EMM-EGE-001_RevA-Erection procedure.pdf

    39/134

    SAMSUN CCPP  Isolated Phase Bus Duct (IPB) 

    Erection and Test Instruction  Page:  38 

    ________________________________________________________________________  _  ____ 

    440‐00‐BAA‐EMM‐001  All rights reserved by EGE, spol. s r.o. 2010  

    Welding procedure specification - WPS  Valid from: 08.02.2010Weld Joint No.: 273  Weld Form acc : Aluminium weldings Page: 1/1 Revision: 5

    BASIS DATAIssued by for WPS: EN ISO 15609-1

    Testing laboratory for WPQR: EN ISO 15614-2 

    EGE Ltd

    IO ŠKOLA Welding Ltd BASIC MATERIAL – PARENT METAL Specification-sort, quality (Metal sheet) T1 and T2 /Thickness of the welded material – t1 and t2 (mm)  

    T1: Plate: AlMgSi0,5 ( EN 573:EN AW EAlMgSi) / t1: 5T2: Profil L40x40: AlMgSi0,5 ( EN 573:EN AW EAlMgSi) / t2: 5 

    FILLER MATAL – FILLER WIRE - APPROVED CONSUMABLEStandard, chemical composition, numerical markingStorage conditions / Cleaning method / Color label / Symbol 

    EN ISO 18273: SAlSi5: S Al 4043(A)Standard conditions / Special cleaning not required / Yellow / Alloy: 4043 

    PROTECTIVE GASType of gas / Classification, symbol / Gas flow volume (l/min) Inert / Minimum Ar 99,996 % (Ar 4.6): I1–EN 439 / 15 - 20

    WELDING PROCESS / WELDING POSITIONTechnology of welding / Welding techniqueWelding / Weld type / Double or single pass

    Design throat thickness (mm): s / Root protectionWeld length: L (mm) / Covering surface

    Root gab:b, Depth of root face:c (mm)Welding position

    Welding methodWeld indication in drawings / Weld preparation 

    Semi-automatic inert gas shielded welding / 131:MIG:EN ISO 4063Manual / BW - butt weld – II weld / Singles = 3 for II weld / nb – backing free welding EN ISO 9606-2L = In whole lengths welded part T1 and T2 / Convex for II weldb 2, c = 12 for II weldPF: vertical position up or PA: flat position or PD horizontal overheadposition: EN ISO 6947ss - unilateral welding: EN ISO 9606-2EN 22553 / EN ISO 9692-3 

    PREHEAT / POSTWELD HEAD TREATMENTPreheat (°C)

    Post heating / Fuel gasesHeating rate / Cooling rate / Post weld heat treatment 

    No for t1 and t2 for atmospheric air or temperature of room > 050 – 80 for t1 and t2 for atmospheric air or temperature of room ≤ 0No / Propane-butane or oxy-acetyleneContinuous / Air / No 

    WELDING ACCESSORIESWelding equipment / Current range (A): Duty cycle (ED)Wire feed rate / Flashing current 

    Inverter welding power source / 40 – min. 210 for 100% EDAutomatic / Standard or pulls (a better variant) 

    CONTROL / CLEANINGVisual quality control / Extend of Examination - % de control

    Implement for cleaning for weld  EN ISO 10042: Acceptance level: D / 100 %Wire brush or chisel, grinding machine for aluminium 

    QUALIFICATION OF WELDERSMinimum