42378-016: power system expansion and efficiency ... · power system expansion and efficiency...

87
Environmental Monitoring Report Project No: 42378-016 Loan No-BAN: 3087 July 2018 Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation in DESCO Area January – June 2018 Prepared by: Dhaka Electric Supply Company Ltd. (DESCO) for the Asian Development Bank for People’s Republic of Bangladesh.

Upload: others

Post on 19-Mar-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Environmental Monitoring Report

Project No: 42378-016 Loan No-BAN: 3087 July 2018

Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation in DESCO Area

January – June 2018 Prepared by: Dhaka Electric Supply Company Ltd. (DESCO) for the Asian Development Bank for People’s Republic of Bangladesh.

Page 2: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation
Page 4: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation
Page 5: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

3rd Environmental Monitoring Report

on

Augmentation and Rehabilitation of Distribution System in

DESCO Area

Period: January 2018 to June 2018

Page 6: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation
Page 7: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

i

Table of Content

List of Tables ............................................................................................. iii

List of Figures ............................................................................................ iv

Unit of Measurement ................................................................................... v

Abbreviations and Acronyms ..................................................................... vii

Executive Summary ................................................................................... ix

1. Introduction .......................................................................................... 1

1.1 Background ......................................................................................... 1

1.2 Objectives ........................................................................................... 1

1.2.1 Main Objective .............................................................................. 1

1.2.2 Specific Objectives ......................................................................... 1

1.3 Project Locations .................................................................................. 2

1.4 Scope of Studies .................................................................................. 5

1.5 Monitoring Law and Policy Standard ........................................................ 6

1.5.1 Compliance with National Environmental Laws ................................... 6

1.5.2 Bangladesh Government Regulation and Compliance Monitoring ........... 7

1.5.3 Compliance with DoE’s Guidelines .................................................... 9

1.5.4 ADB Loan Covenants with the DESCO ............................................. 10

2. Approach and Methodology ................................................................. 12

2.1 Overall Approach ................................................................................ 12

2.2 Study Mobilization .............................................................................. 12

2.3 Study Team Mobilization ...................................................................... 12

2.4 Methodology ...................................................................................... 13

2.4.1 Physical Environment ................................................................... 13

2.4.2 Biological Environment ................................................................. 14

3. Monitoring Results .............................................................................. 16

3.1 Introduction....................................................................................... 16

3.2 Physical Environment .......................................................................... 16

3.2.1 Ambient Air Quality...................................................................... 16

3.2.2 Noise Level ................................................................................. 18

3.2.3 Waste Management and Sanitation System ..................................... 20

3.2.4 Soil Quality ................................................................................. 20

3.3 Ecosystem and Biodiversity Conservation ............................................... 41

Page 8: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

ii

4. Institutional Arrangement and Grivence Redress Mechanism .............. 46

4.1 Institutional Arrangement .................................................................... 46

4.2 Grivence Redress Mechanism ............................................................... 46

5. Specific Environmental Management Plan............................................ 48

6. Conclusions and Recommendations ..................................................... 52

6.1 Conclusions ....................................................................................... 52

6.2 Recomendations ................................................................................. 52

Reference ................................................................................................. 54

Appendix-A: Field Photos .......................................................................... 56

Appendix-B: Monitoring Checklist ............................................................. 58

Appendix-C: Contract Agreement between DESCO and Simens India ......... 64

Appendix-D: Map of the Study Area ........................................................... 68

Appendix-E: Environmental Clearence Certificate ...................................... 70

Page 9: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

iii

List of Tables

Table 1.1: Proposed Twenty Four 33/11kv Substations in DESCO Area .................. 4

Table 1.2: Selected IESCs and Parameters ...................................................... 10

Table 2.1: The Composition of the Main Team .................................................. 12

Table 2.2: The Composition of the Multidisciplinary Field Team ........................... 12

Table 3.1: Test Results of Air Quality Monitoring of DESCO Project Area ............... 17

Table 3.2: The Measured Average Noise Level of the Project Sites during the Field

Visit ........................................................................................................... 19

Table 3.3: Standards of Noise Levels for Different Zones of Bangladesh ............... 19

Table 3.4: Laboratory Test Summary Sheet for Agragaon .................................. 21

Table 3.5: Laboratory Test Summary Sheet for Mirpur-6 ................................... 22

Table 3.6: Laboratory Test Summary Sheet for ADA ......................................... 23

Table 3.7: Laboratory Test Summary Sheet for Baunia ...................................... 24

Table 3.8: Laboratory Test Summary Sheet for Mirpur DoHS (Augmentation) ....... 25

Table 3.9: Laboratory Test Summary Sheet for Uttar Khan (Promy) .................... 26

Table 3.10: Laboratory Test Summary Sheet for Merul Badda ............................ 28

Table 3.11: Laboratory Test Summary Sheet for Satarkul, Vatara ....................... 29

Table 3.12: Laboratory Test Summary Sheet for Kalshi, Senpara ........................ 30

Table 3.13: Laboratory Test Summary Sheet for Diabari, Uttara ......................... 31

Table 3.14: Laboratory Test Summary Sheet for Swarnali Abason, Barua ............. 32

Table 3.15: Laboratory Test Summary Sheet for Lake City Concord, Khilkhet ....... 33

Table 3.16: Laboratory Test Summary Sheet for Mirpur DOHS-2 ........................ 34

Table 3.17: Laboratory Test Summary Sheet for Swadesh Properties, Satarkul ..... 35

Table 3.18: Laboratory Test Summary Sheet for Tongi-3/Uttara Sector-14 ........... 36

Table 3.19: Laboratory Test Summary Sheet for Tongi -1, BSCIC I/A,Tongi ,Gazipur)

................................................................................................................. 38

Table 3.20: Laboratory Test Summary Sheet for Tongi -2, Cherag Ali Besides Tongi

S & D Division ............................................................................................. 39

Table 3.21: Laboratory Test Summary Sheet for Tongi BSCIC’S, Near BPDB’s 80 MW

Power Station, Tongi .................................................................................... 40

Table 3.22: Matrix of Monitoring Results ......................................................... 42

Table 3.23: Implementation Plan for Non Compliance Issues .............................. 43

Table 5.1: Specific Environmental Management Plan (SEMP) .............................. 48

Page 10: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

iv

List of Figures

Figure 1.1: Map of Proposed 24 (Twenty Four) 33/11kv Substations in DESCO Area 3

Figure 3.1: Photographs of Air Quality Monitoring at Different Locations of DESCO

Project Area ................................................................................................ 17

Figure 3.2: Project Area at Uttara, Section-14 .................................................. 41

Figure 4.1: Institutional Arrangement of DESCO for Compliance and Monitoring .... 46

Page 11: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

v

Unit of Measurement

1 Bigha = 33 Decimals

1 Katha = 1.65 Decimals

1 acre = 0.404686 Hectare

Page 12: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

vi

Page 13: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

vii

Abbreviations and Acronyms

ADB Asian Development Bank

BOD Biological Oxygen Demand

CEGIS Center for Environmental and Geographic Information Services

DESCO Dhaka Electric Supply Company Limited

DO Dissolved Oxygen

DoE Department of Environment

DBH Diameter at Breast Height

ECR Environmental Conservation Rule

ERF Extracting area Rehabilitation Fund

EIA Environmental Impact Assessment

EMP Environmental Management Plan

EPC Engineering, Procurement and Construction

GoB Government of Bangladesh

IESCs Important Environmental and Social Components

IUCN International Union for Conservation of Nature

SDG Sustainable Development Goal

ToR Terms of Reference

Page 14: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

viii

Page 15: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

ix

Executive Summary

This Environmental Monitoring is conducted based on ADB safeguard’s policy, the laws and

policies of Bangladesh Govt and Loan covenants between ADB and Bangladesh Govt. For

environmental monitoring, variables and indicators are selected interms of project

description, activities during project implementation, probable impacted indicators of physical

and biological environment.

This is the 3rd phase of environmental monitoring commenced (January 2018 to June 2018)

through monthly field visit by the consulatant. In this stage, there are twenty one (21)

substations whereas the constructions work is ongoing and this study cover all these

substations. The monitoring team visited and observe all construction activites and consulted

with relevant stakeholders according to the prepared checklist on physical (i.e. air quality,

waste management, noise and soil quality), ecosystem and biodiversity (i.e. terristrial

vegetation, flora and fauna) status at the construction sites applying both qualitative and

quantitative approaches.

Based on the selected parameters of air quality, the results of the air quality were checked

whether it is satisfactory or not regarding the national air quality standard. Besides, how this

construction activities are related with the air quality has been observed through regular field

visit.

The noise levels were measured during day time at different project sites. Noise showed the

minimum level at the entrance. On the contrary, the noise reading near the construction

zone was un-steady due to different construction activities. The impact of this noise level is

considered as insignificant as it is more like temporary. The provision of soild waste is

maintaining by the EPC contractor as the risks for solid waste disposal is in satisfactory

condition.

The concentration of PM10, PM2.5 and SPM of DESCO project area is higher than the

Bangladesh standard limit. From the above data, we have found data the amount of PM10,

PM2.5 and SPM are maximum which are 227, 128 and 287 µg/m3 accordingly. On the other

hand, concentration of SO2, NOx and CO have found within the Bangladesh standard limit.

The air pollution levels have been compared with the Bangladesh Ambient Air Quality

Standard as adopted in 2005.

During field visit, no significant internal and external sources of air pollution was observed in

the project sites that would deteriorate air quality. Due to vehicular movements, digging of

the earth and loose earth materials (e.g. soil, sand), some dust particles were observed in

the project area. Heavy construction machineries were used to carry out pile work which

caused scanty amount of SOx and NOx which is negligible.

The compliance status of noise quality and waste management have been addressed

through air quality measurement, field observation and consultation with relevant

stakeholders. However, it is found that due to the construction, there is no significant

negative impact on health of community people, but the labors working for construction can

be impacted for heavy sound produced the pilling works. In this regard, availability and use

of earmuff has been suggested as the Corrective Action Plan (CAP) and shared with PMU

for further improvement.

Page 16: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

x

The construction activities were found in various stages at different sites during the visits.

There were no ecological resources in the all the substations, except Uttara section-14 and

Mirpur DOHS. Mirpur DOHS, which was situated, near the ditch, the construction materials

and wastes were being drained into the ditch. This might have some negative impacts on

aquatic life forms and their ecosystems. There is a suggestion to make plan for alternative

drainage to avoid the negative impact on fish habitat near the Mirpur DoHs Substation. Most

of the cases, compliance status achieved significantly but for the non compliance issues

several corrective action plans suggested and shared with implementing agency. The status

of non compliance issues will be addressed in the next phase of environmental monitoring.

Page 17: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

1

1. Introduction

1.1 Background

1. Bangladesh Govt. has set their goal in providing access to affordable and reliable

electricity for all by 2021. In this respect, The People’s Republic of Bangladesh has scaled

up its priority to strengthen the electricity production, transmission, and distribution for overall

growth and development of the country.

2. For the enhancing the electricity distribution and meeting the increasing demand,

Dhaka Electric Supply Company Limited (DESCO) has taken initiatives to expand its

infrastructure in the distribution system with the construction of the new line, substations,

and renovation of existing substations. This project titled : Augmentation and Rehabilitation

of Distribution System in DESCO Area has already been obtained the site and

environmental clearance certificate from DoE . The Simmens India entrusted as the EPC

contractor to implement this project. In this project, CEGIS is working as environmental

consult5ant to monitor the compliance status based on Bangladesh National Environmental

Policy Standards, ADB’s Environmental conservation rules and ADB and Bangladesh loan

covenant.

3. In relation to 2nd environmental monitoring, this 3rd monitoring has been held (from

January 2018 to June 2018) and the compliance status has been checked based the

prepared checklist on physical and biological environment.

4. With the monthly field visit and following the mixed approach this environmental

monitoring hjas been completed (upto june 2018). The status of non compliance issues

addressed in this EMR and provide to upgrade the status by expert judgement mentioning

the Corrective Action Plan.

1.2 Objectives

1.2.1 Main Objective

5. The main objective of the environmental monitoring is to observe how EMP is

compiled in relation with national and international standard in pre-construction, construction

and operation phase of the project.

1.2.2 Specific Objectives

6. The specific objectives of the environmental monitoring are to:

Analyze the water and air quality in pre and construction phase of the project

Analyze noise in three stages of the project

Explore land characteristics in the project sites

Analyze the waste management system of concerned authority or EPC

Contractor

7. The environmental compliance monitoring would include:

Analysis of Environmental Laws and Policies of Bangladesh

Page 18: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

2

Description of Environmental Management, and Monitoring Plan described in the

EIA in line with ADB’s requirements.

1.3 Project Locations

8. Following figure 1.1 and table 1.1 shows the locations of proposed 24 (twenty four)

33/11kV Substations in DESCO area. An A3 size map is shown in the Appendix D. Here it is

noted that this environmental monitoring consider the construction activities of twenty one

(21) substation where the construction works are ongoing.

Page 19: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

3

Figure 1.1: Map of Proposed 24 (Twenty Four) 33/11kv Substations in DESCO Area

9. In the EIA report the sub-stations area and locations were mentioned clearly. But in

the meantime the DESCO authority has changed /shifted some of the sub-station area due

to land availability. The final list of the proposed sub-stations area mentioned in the Table

1.1.

Page 20: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

4

Table 1.1: Proposed Twenty Four 33/11kv Substations in DESCO Area

Sl. No.

Name of the substations

Address Remarks

1 Kazipara Switching Station

740/B, West Kazipara,Mirpur

(Beside the mosque of west Kazipara Bus station)

-

2 Mazar Road

Plot: J-82, J-10

Eastern Housing

Mirpur,Dhaka

Relocated:

Mazar Road shifted to Eastern Housing. It is fallow land and suitable for housing and any kind of infrastructure.

3 Kalshi (Shenpara)

Bijoy Rakeen City

Plot: 1/2, Block: D, Section: 15, Mirpur, Dhaka.

From Mirpur Road

Beside Police Staff College and Behind Institute of Science Trade & Technology. (At the end of Piling work.)

4 Mirpur DOHS-2

Road#33, Plot#837, Mirpur 14, Dhaka.

On the Right after entering in DOHS

5 Lake City Concord

Mouza: Joarsahara, Ward No: 17, Khikhet, Dhaka

Area of Land: 11.8 Katha1.

6 Satarkul-2

Sun Valley Abason, Swadesh Properties Ltd.

Plot#11, Block#E

Road#7, Sector#2

Mauza: Satarkul

Thana: Badda

Area of Land: 16.0 Katha

Before United City

7 Satarkul-1

Road# 317,Plot#4, Sect#03,

Dag:1100,1105,1106

United City

Mauza: Satarkul

Thana: Badda

Area of Land: 1.0 bigha2

8 Barua

Plot# 13,Road# 11, Block#A,Sector#1, Swarnali Properties Mauza: Borua,

Thana: Dakshinkhan.

Area of Land: 20 Katha.

9 Gulshan-03 BRAC university, Merul Badda, Dhaka

Relocated:

Gulshan-03 shifted to Merul Badda

10 Basundhara Block G

AIUB New campus Relocated:

Basundhara shifted to AIUB

11 Sholahati

Uttara Third Phase (Sector-15, Block-G, Commercial Plot)

Besides Rajuk Apartment Project

Enter through sector-12, Cross khalpar and Grid. Turn Left from Diabari Golchokkor (first Golchokkor)

12 Mohakhali DoHS Mohakhali DoHs, Dhaka Cantonment, The proposed location is located

1 1 katha = 1.6 decimals

2 1 bigha = 33 decimals

Page 21: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

5

Sl. No.

Name of the substations

Address Remarks

Dhaka at Mohakhali DoHS, beside the British American Tobacco industry.

13 Uttarkhan (Promy)

Promy Agro Foods Ltd., Moinertek

Mauza: Gobindapur,

C.S.-305,306. R.S.-538

Area of Land :

22-23 Katha

14 Tilargati, Tongi Sataish

S.A.R.S-01, S.A-129, R.S-251, Mauza-Kakil 27, Tilargati, Tongi.

West from S&D, Near Uttara Proborton City & Sangbadik Bari, Tilargati, Sataish,Tongi.

15 Agargaon New Colony, Behind BCS Computer City,With Probin Hitoishi Hospital, Opposite to the Agargaon S&D.

Existing 33/11 KV substation

16 Mirpur DOHS At the end of R#10 , DOHS, Mirpur-12.

Existing 33/11 KV substation

17 Mirpur-06 Near Al-Markajul Mosque & Market of Section-06, Original Mirpur-10.

Existing 33/11 KV substation

18 Tongi-01 BSCIC I/A, Tongi, Gazipur Existing 33/11 KV substation

19 Tongi-02 Cherag Ali, Beside Tongi S&D Division.

Existing 33/11 KV substation

20 Civil Aviation (CAAB)

Left from Jashimuddin, Beside Airport Boundary & Sector#1)

Kurmitola, Uttara, Dhaka

Existing 33/11 KV substation

21 ADA Beside Civil Aviation Quarters’, Kaola.

Existing 33/11 KV substation

22 Sector – 14,Uttara

Existing DESCO’s Sub-store

23 Tongi (BSCIC) Near BPDB’s 80 MW Power Station, Tongi.

Existing 33/11 KV substation

24 Baunia Mouza: Faridabad, Airport, Uttara, Dhaka

Existing 33/11 KV substation

Source: PD office, May, 2018.

1.4 Scope of Studies

10. In line with the aforementioned objectives the scope of the services should cover the

following:

i. Monitoring ambient air quality of the project site and its adjoining area before

construction stage;

ii. Review of environmental management and environmental monitoring plan

suggested in the EIA report in line with the action plan proposed by ADB;

iii. Upgrade (if required) the environmental monitoring framework and work plan

specifying the indicators, method, location, time, frequency of monitoring

provided in the EIA that shall be followed by the EPC contractor;

Page 22: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

6

iv. Monthly monitoring of construction activities to see their compliance with national

environmental and social regulations, and ADB’s performance standards on

social and environmental sustainability;

v. Physical observation (monthly) to assess that all mitigation measures are carried

out or in place in conformity with the EMP and action plan;

vi. Monthly monitoring of implementation of environmental monitoring activities as

specified in the environmental monitoring plan;

vii. Monthly monitoring of different activities of EPC contractor regarding analysis of

air quality, water quality, soil texture and quality, soil and land erosion, noise

measurement, waste management, etc in connection with the environmental

monitoring plan;

viii. Monthly monitoring of socio-economic issues like community safeguard due to

pollution, hazards and employment opportunity;

ix. Suggestion of pollution prevention and mitigation measures to ensure

environmental safeguard, to ensure compliance with national environmental and

social regulations;

x. Keep close liaison with the project implementation office (Project Director), and

EPC contractor;

xi. Provide an interim monitoring report at the end of every three (3) months in line

with the reporting requirement of DESCO/ ADB satisfying equator principles;

xii. Provide a monitoring report at the end of every six (6) months in line with the

reporting requirement of ADB satisfying equator principles.

1.5 Monitoring Law and Policy Standard

11. The Environment Conservation Rules place construction of power plant into the Red

category. The site clearances based on IEE and Environmental Clearance Certificate have

been obtained from Department of Environment (DoE). As per the Bangladesh Govt. policy

standard, environmental compliance monitoring is one of the important part need to be

initiated following the Environmental compliance monitoring guidelines by DoE and the

agreement between ADB and Bangladesh Govt (based on the ADB loan covenants).

DESCO has taken initiatives to expand its infrastructure of the distribution system through

construction of new lines, installation of new substations and rehabilitation of existing

substation in order to provide new connections to the incoming consumers. In this regard,

during carrying out the EIA study for the proposed twenty four 33/11kV Substations, EMP

was prepared following the national guidelines of Bangladesh and policies of Asian

Development Bank. Now, the purpose of the environmental monitoring is to monitor whether

the construction activities are performed or not considering the EMP prepared in the EIA

stage.

1.5.1 Compliance with National Environmental Laws

12. The environmental legislation of GOB gives importance to reduce the negative

impacts of infrastructure development projects, and give priority for the enhancement of

positive impacts due to the project implementation. It conforms the National Environmental

Policy 1992 based on the Agenda 21 of Rio Conference and subsequent enactments of the

Page 23: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

7

Bangladesh Environmental Conservation Act (BECA) 1995 and Bangladesh Environmental

Conservation Rules (BECR) 1997.

National Environmental Laws Compliance Requirement Performance of DESCO

Bangladesh Environmental

Conservation Act (BECA) 1995

and Bangladesh Environmental

Conservation Rules (BECR)

1997

The Construction of Twenty

Four 33/11kv Substations in

DESCO Area requires

environmental clearance

certificate (EC)

The environmental clearance (valid for 1 year) for the project was obtained from the DoE on 25.06.15. The processing for renewal is ongoing as per the Government rules.

3 sites under this project have been relocated that require Environmental clearance certificate. The completion of EIA for these relocated sites is in under process.

1.5.2 Bangladesh Government Regulation and Compliance Monitoring

13. The Bangladesh Environment Conservation Act of 1995 (ECA, 1995) is the key

legislation in relation to environment protection in Bangladesh. This Act is promulgated for

environment conservation, standards, development, pollution control, and abatement. It has

repealed the Environment Pollution Control Ordinance of 1977. The Act has been amended

in 2000, 2002, 2007 and 2010.

14. The main objectives of the Act are:

Conservation and improvement of the environment; and

Control and mitigation of pollution of the environment.

15. The main strategies of the Act can be summarized as:

Declaration of ecologically critical areas and restriction on the operations and

processes, which can or cannot be carried/initiated in the ecologically critical

areas;

Regulations in respect of vehicles emitting smoke harmful for the environment;

Environmental clearance;

Regulation of the industries and other development activities’ discharge permits;

Promulgation of standards for quality of air, water, noise and soil for different

areas for different purposes;

Promulgation of a standard limit for discharging and emitting waste; and

Formulation and declaration of environmental guidelines.

16. The ECA, 1995 specified that no industrial unit or project shall be established or

undertaken without obtaining Environmental Clearance from Director General in a manner

prescribed by the Rules. The project promoter must obtain Environmental Clearance from

the Director General of Department of Environment (DoE). An appeal procedure does exist

for those promoters who fail to obtain clearance. Failure to comply with any part of this Act

Page 24: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

8

may result in punishment of imprisonment or fine or both. The DoE executes the Act under

the leadership of the Director General.

17. The Bangladesh Environment Conservation Act (Amendment), 2000 focuses on:

(1) ascertaining responsibility for Compensation in cases of damage to ecosystems, (2)

increased provision of punitive measures both for fines and imprisonment and (3) fixing

authority on cognizance of offences.

18. The Bangladesh Environment Conservation Act (Amendment), 2002 elaborates

on: (1) restriction on polluting automobiles, (2) restriction on the sale and production of

environmentally harmful items like polythene bags, (3) assistance from law enforcement

agencies for environmental actions, (4) break up of punitive measures and (5) authority to try

environmental cases.

19. The Bangladesh Environment Conservation Act (Amendment), 2010 introduces

new rules & restriction on: a) Ensure proper management of hazardous wastes to prevent

environmental pollution and Health Risk, b) No remarked water body cannot be filled

up/changed; in case of national interest; it can be done after getting clearance from the

respective department; and c) Emitter of any activities/incident will be bound to control

emission of environmental pollutants that exceeds the existing emission standards (d)

Government may declare any ecosystem as “Ecologically critical area” if it appears to be

degraded or expected to be degraded and take all precaution measures to protect that

ecosystem. In addition, government shall stop any ongoing activities and will not allow any

new developments in the ecosystem after declaration of “Ecologically Critical Area”.

20. The Bangladesh Environment Conservation Rules, 1997 is the first set of rules,

promulgated under the ECA 95 (so far there have been three amendments to this set of

rules – February and August 2002 and April 2003). The Environment Conservation Rules of

1997 has provided categorization of industries and projects and identified types of

environmental assessments needed against respective categories of industries or projects.

21. Among other things, these rules set (i) the National Environmental Quality Standards

for ambient air, various types of water, industrial effluent, emission, noise, vehicular exhaust

etc., (ii) the requirement for and procedures to obtain environmental clearance, and (iii) the

requirement for IEE and EIA’s according to categories of industrial and other development

interventions.

22. The proposed project, according to the DoE, was under the “Red” category accrding

to the Environmental Conservation Rules, 1997 but recent amendment in 2018 made this

project as orange B category.

23. Noise Pollution (Control) Rules, 2006 gives the authority to all the Union Councils,

Paurasabhas, City Corporations, City Development Authority (i.e. RAJUK, CDA, KDA, RDA

etc.) to mark off the areas under their jurisdiction as silent, residential, mixed, commercial or

industrial. They should also put signs to mark those areas. The act also describes the

approved standard limit of sound in the added schedule 1 and 2. In the schedule 1, silent

area means area up-to a radius of 100 meters around hospitals or educational institutions or

special institutions/ establishments identified/to be identified by the government. In the silent

area, it is prohibited to use any kind of horns of vehicles, audio signals and loudspeakers.

According to this act, daytime is counted from 6am to 9pm whereas nighttime is counted

from 9pm to 6am.

Page 25: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

9

24. The Motor Vehicle Ordinance, 1983 stated to impose a penalty of maximum two

hundred taka for those vehicles that are emitting smokes that poses health hazard in the

public places. It also restricts the passenger from smoking in public service vehicles and in

any other vehicles with notice of not smoking. This ordinance is enforced occasionally but a

regular enforcement would be helpful to reduce air pollution in big cities including Dhaka.

However, it is to be noted that amount of the penalty is very low which may be revised as

well.

25. The Environment Court Act, 2000 provides for the establishment of environment

courts and matters incidental thereto. This act also provides the jurisdictions of environment

court, penalty for violating court’s order, trial procedure in special magistrate’s court, power

of entry and search, procedure for investigation, procedure and power of environment court,

authority of environment court to inspect, appeal procedure and formation of environment

appeal court.

1.5.3 Compliance with DoE’s Guidelines

26. As mentioned above, the project activities fall under the ‘red’ category according to

the Environment Conservation Rules, 1997. For projects under this category, it is mandatory

to carry out IEE and subsequently EIA including Environmental Management Plan (EMP)

and where necessary develop a Resettlement Plan for getting environmental clearance from

the DoE. The DoE has issued EIA Guidelines for Industries and addresses the IEE and EIA

for several industrial sectors and activities. Each Project Proponent shall conduct an IEE or

EIA and is expected to consult and follow the DoE guidelines. The provisions of the

environment legislations and the EIA guidelines of the DoE have been reviewed under this

study. The DoE has issued application procedure for obtaining site/environmental clearance.

27. Environmental quality standards for air quality, noise, odor, sewage discharge,

industrial effluents, and industrial project emissions for Bangladesh

28. The Environment Conservation Act, 1995 and the Environment Conservation Rules,

1997 are the main legislative base in Bangladesh for protection and conservation of natural

environment. The Environment Conservation Rules (1997) place activities of power plant

into the Red category during the time of EIA study but the with the amendment held in 2018

made all substations project as orange B category. In this study, all compliance addressed

regarding the policy standard set during the EIA stage and monitoring of this project

completed following this way.

29. However, the Safeguard Policy Statement (SPS) of Asian Development Bank has

also been reviewed since ADB is financing the project in partnership with the GoB. As per

the ADB categorization, the sub-station construction activities are under the category B

considering the significance of the project’s potential environmental impacts. Therefore, the

EMP is prepared based on the combination of both the national and the ADB.

30. The environmental standards are determined in the Environmental Conservation

Rules. The standards for air, water, sound, odor and other components of the environment is

started to monitor in accordance with the standards specified in Schedules - 2, 3, 4, 5, 6, 7

and 8. The Bangladesh standards, in general, are less stringent compared to the developed

countries. This is in view to promote and encourage industrialization in the country. The

Bangladesh standards are not for any specific period of time. There is no provision for partial

Page 26: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

10

compliance too. For this reason, monitoring is based on the national standards unless there

is absence of clear standards; only then ADB’s standard is being considered.

31. Following IESCs and parameters are selected for monitoring in DESCO’s 24 sub-

station areas which have presented in Table 1.2.

Table 1.2: Selected IESCs and Parameters

IESCs Parameters

Air Suspended Particulate Maters (SPM), Sulphur dioxide, Carbon Monoxide,

Oxides Nitrogen

Waste Waste generation and proper waste disposal

Noise dBa unit at both day and night time

Water (if any) DO, PH, BOD, Arsenic whether water is usable for irrigation or by fisheries

Biodiversity Habitat conversion and fragmentation

Health & Safety Risk of electrocution, safety measures within the construction site, emergency

plan.

Resettlement livelihood challenges, restoration process, compensation process, whether any

complaints from affected people

32. The results of the monitoring are needed to compare the established benchmarks/

baseline and compliance status and help to identify the areas where adverse environmental

and social adverse impacts are still occurring. It would be helpful to formulate the corrective

actions accordingly and in a timely manner.

1.5.4 ADB Loan Covenants with the DESCO

33. According to the Loan Covenant Article (II), section 2.01, DESCO should carry out

the project, with the due diligence and efficiency and in conformity with sound administrative,

financial, engineering, environmental and power sector practices. For the execution of

project following criteria should be followed.

Implementation arrangement

34. DESCO should ensure the project implementation in accordance with the detailed

arrangements set forth in the PAM. Besides, it is the responsibility of DESCO to ensure their

project management staff who have the qualification to undertake necessary tasks of

procurement, construction, supervision, inspection, and testing of equipment, payments to

contractors, monitoring, environmental and social safeguards due diligence and reporting of

progress relevant to the components under their responsibility.

Environment

35. DESCO should ensure that the preparation, design, construction, implementation,

operation, and decommissioning of the project and all project facilities comply with;

All applicable laws and regulations of the relating to environment, health and

safety

The environmental safeguard (i.e. Air quality, noise quality, soil quality and waste

management, and conservation of ecological resources)

Page 27: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Introduction

11

All measures and requirements set forth in the respective IEE and EMP and any

corrective or preventive actions set forth in a safeguard monitoring report

Project Reviews

The project progress would be reviewed by the ADB with necessary midcourse

corrections

The Assistance should be provided by the Executing Agency (i.e. DESCO).

36. The environmental monitoring will assess the compliance that has been suggested

under the Bangladesh Govt. laws, policies and national standards (i.e. air, noise and water

quality) and ADB loan covenants. As there is no involuntary resettlement and ethnic minority

issues, therefore, this monitoring assess the environmental issues in accordance with the

Govt. laws and ADB loan covenants like the above mentioned ways.

Page 28: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

12

2. Approach and Methodology

2.1 Overall Approach

37. The objective of the Environmental Compliance Monitoring is to identify

environmental issues following the compliance regarding the EMP, National Environmental

Acts, Laws and Policy, ADB’s Environmental Standard and terms of Bangtladesh and ADB

loan covenants. During this environmental monitoring, mixed approach has been followed

and collected both quantive and qualitative data to understand the compliance status of

physical and biological environment regardiung the project implementation.

2.2 Study Mobilization

38. Based on a comprehensive checklist this study has been mobilized and consider the

compliance status due to the project implementation. A multidisciplinary team having with

relevant expertise has been selected to conduct this study.

2.3 Study Team Mobilization

39. In line with the 2nd environmental monitoring, the study team has been mobilized to

conduct the 3rd environmental monitoring. A group of highly skilled professionals mobilized

for conducting field observation and collecting both quantitative and qualitative data.

Initiatives have been taken for accomplishment of the study within the expected time-frame

based on the formulated action plan.

40. The consultant (CEGIS) continued the whole works through overall supervision of the

Project Director, and close liaison with DESCO offices (both field and central offices).

Besides, the team Leader supervised and visited the study area to complete the study based

on the study objectives. The progress of the study was reviewed in weekly progress review

meeting. Each report and deliverable was reviewed carefully by the team members and

Team Leader and finally, checked by technical and linguistic editors.

Table 2.1: The Composition of the Main Team

Sl. No. Name of Professional Position Assigned

1 Engr. Jalal Ahmed Chawdhury Environmental Expert/ Transmission Line/ Power Plant Expert

2 Dr. Dilruba Ahmed Sociologist

3 Subrata Kumar Mondal Economist

41. As per commitment the following multidisciplinary team was mobilized for collecting

data from the field.

Table 2.2: The Composition of the Multidisciplinary Field Team

Sl. No. Name of Professional Position Assigned

1 Amith Dutta Anthropologist

2 Rifat Jahan Sadia Water Resource Engineer

3 Tanvir Ahmed Ecologist

Page 29: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Approach and Methodology

13

2.4 Methodology

2.4.1 Physical Environment

Ambient Air Quality

42. Air quality is an indicator of purity of air for respiration process of human being plants,

and animals. Poor air quality can affect human health and deteriorate surrounding

environment. Air quality was monitored through visual inspection as potential pollution

sources were from external air contamination. CEGIS engaged “Development Solutions

Consultant Limited “as 3rd party to conduct air quality test in the project sites.

43. To assess the baseline condition of the project areas, ambient air quality monitoring

was conducted for 8 hours at different project sites and then the average value of ambient

air quality has been used for the DESCO project area. The parameters were SPM, PM2.5,

PM10, Carbon Monoxide (CO), Oxides of Nitrogen (NOx), and SO2. LATA Envirotech APM

250 with Combined PM10 Sampler was used for the measurement of particulate matters and

for gaseous pollutants LATA Envirotech LES 411 was used. To monitor carbon monoxide

(CO) HTC CO-01 meter was used and value is expressed in ppm. The air quality monitoring

results provided by the Development Solutions Consultant Limited are not only been

presented but also have been compared with the national standards.

Noise level

44. Noise level is an important parameter as excessive noise may create disturbance to

local communities, ecosystem and workers at worksite due to project activities. Short-term

noise exposure can be overcome with rest, but if exposure is sustained, it may result in

irreversible long-term damage. Hearing loss in the workplace can lead to safety risks if

workers are unable to hear alarms or critical communications from other workers. Noise level

was perceived from individual acoustics of monitoring team. Noise monitoring is important

for any big construction activity as excessive noise may create disturbance to the wild life,

indigenous species, fragile ecosystems, communal stability in case of sudden intrusion and

workers due to construction activities and subsequent increased traffic movement.

45. Thus, ambient noise level has been monitored monthly at nearby sensitive receptors

around the construction site (including substation site) of this project. Each time, noise level

has been recorded using portable noise level meter for a two minutes time span at 5 minutes

interval depending on the site condition. Noise level has been recorded at day time only as

the construction works held only at day light hour. A probable increase in noise level in the

same area may provide the tools for assessment of impact on environment.

Waste Management

46. Infrastructure work for any development, usually generate variable quantities and

types of waste materials which have the potential to cause adverse environmental impacts

during generation, storage, transport and disposal. For this reason, the project aims to

implement waste management procedures immediately after the commencement of the civil

works in order to maintain minimal potential impacts to the environment. The project sites

were observed visually during sites visit to investigate concerns related to waste disposal.

Page 30: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Approach and Methodology

14

Soil Quality

47. Sub-soil investigation is very important for proper planning and designing of the

structure which confirm the safety and stability of the structure. Thus, National Survey

Organization has been performed the sub –soil investigation for the construction of proposed

design, supply installation and commissioning of 24 nos 33/11kv Sub-stations. National

Survey Organization has executed Standard Penetration test (SPT), different field and

laboratory tests for investigation of sub-soil. They have evaluated bearing capacity of soils at

different layers. A number of bore holes have been drilled at a particular depth depending on

the project sites. We have been reviewed and incorporated the sub-soil investigation report’s

data for understanding the soil condition of the project sites which are provided by Siemens

Bangladesh Ltd.

2.4.2 Biological Environment

48. Proposed substation sites are situated in urban area, so urban ecosystem as well as

vegetation and wildlife are major components for this environmental monitoring.

Terrestrial Vegetation

49. Project site specific data (i.e. Cocos, Psidium, Cynodon, Scorpia, Croton, Leucas,

Cyperus, Chan grass) were collected through visual observation and use of GPS, noise

meter, iPAD etc. instrument for proper ecological monitoring. In addition, local people were

interviewed for getting data. Monitoring of intercultural operation was done quarterly through

consultation with stakeholders and local people.

Flora and Fauna

50. Flora and Fauna of all sites observed through regular field visit. The impact of project

implementation (i.e. land development; vegetation clearing, Labor and vehicle movement) on

small mammals, amphibians, reptiles and local urban birds have been identified through in

depth observation and consultation relevant stakeholders according to the prepared

checklist.

Page 31: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Approach and Methodology

15

Page 32: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

16

3. Monitoring Results

3.1 Introduction

51. For the commencement of the project implementation, Dhaka Electric Supply

Company Limited (DESCO) has made a Contract Agreement with Simens India in

consortium with the Siemens Bangladesh to Design, Supply, and Install & Commission 24

(twenty four) 33/11kV Substations in Turnkey Basis in DESCO area under the Dhaka and

Gazipur districts against Bid No. IFB 01/2016, Package-C1 of Lot-3 under ADB Loan No.:

3087- BAN: under “Power System Expansion and Efficiency Improvement Investment

Program” (Trench 2). After getting the Topographical Survey report they have started their

construction. Presently, there are twenty one (21) substations where the construction work is

ongoing. The environmental monitoring (3rd Phase) has been completed based on the

construction actitivites of these substations and impact due to the project implementation. All

activities3 related to the construction observed and findings of social safeguard monitoring

compiled following the ADB social safeguard policy and ADB –Bangladesh loan covenants.

3.2 Physical Environment

3.2.1 Ambient Air Quality

52. Ambient air quality data at the project site were measured to ascertain the current

quality of air. The aim was to develop the baseline air quality data and to compare the same

with the air quality data during project activities to check if there is any high air pollution

developed due to the construction activities and to design adequate mitigation measures, as

applicable.

53. The major air pollutants in Greater Dhaka City are nitrogen oxides (NOx), sulphur

dioxide (SO2), suspended particles matters (SPM), PM10 and PM2.5 (particulate matter with

diameter of 10 and 2.5 microns or smaller), carbon monoxide (CO), carbon dioxide (CO2)

etc. Motor vehicles, construction activities, uncontrolled emission from hundreds of brick

fields around the city, etc. are the major source of these pollutants particularly the PMs.

Dispersal of these pollutants greatly depends upon factors like prevailing wind direction and

other weather conditions, atmospheric stability, height of the source.

54. The air quality test for this project has been done during January, 2018 which is

winter season and in winter the pollutant level particularly PMs level increases to a great

extant where as in summer the heavy shower cleans the air to a great extant. CEGIS

engaged “Development Solutions Consultant Limited “as 3rd party to conduct air quality test

in the project sites the test was carried out for 24 hours except CO for 8hrs at and around

the project sites (Figure 3.1) from 15 January to 25 January 2018. The parameters were

SPM, PM2.5, PM10, Carbon Monoxide (CO), Oxides of Nitrogen (NOx), and SO2. The

weather was mostly sunny during the test period.. The average values of ambient air quality

result has been shown in Table 3.1. The air quality analysis of Tongi area is in progress and

will be presented in the next report.

3 Piling, Electrical Works (i.e. Earth work),Transformer Foundation, RCC Works, Fellow Casting

Page 33: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

17

Figure 3.1: Photographs of Air Quality Monitoring at Different Locations of DESCO Project Area

Table 3.1: Test Results of Air Quality Monitoring of DESCO Project Area

Para

mete

r

Un

it

Co

ncen

trati

on

Pre

sen

t o

f D

ES

CO

pro

ject

are

a

Ban

gla

desh

Sta

nd

ard

**

IFC

/Wo

rld

Ban

k

Sta

nd

ard

Du

rati

on

(h

ou

rs)

Weath

er

Co

nd

itio

n

Meth

od

of

An

aly

sis

PM10 µg/m3 243 150 150 24

Sunny

Gravimetric

PM2.5 µg/m3 137 65 75 24 Gravimetric

SPM µg/m3 302 200 160 24 Gravimetric

SO2 µg/m3 53.2 365 125 24 West- Geake

NOx µg/m3 38.9 100 - Annual Jacob and Hochheiser

CO* ppm 001 9 10 (WHO) 8 CO Meter

Source: DSCL Laboratory, January 2018

Note:

* CO concentrations and standards are 8-hourly only.

** The Bangladesh National Ambient Air Quality Standards have been taken from the Environmental

Conservation Rules, 1997 which was amended on 19thJuly 2005 vide S.R.O. No. 220-Law/2005

Note:

PM2.5 – Fine Particulate Matter.

PM10 -Respirable Dust Content

SPM – Suspended Particulate Matters

SO2 – Sulphur Di-oxide

NOX— Oxides of Nitrogen.

CO – Carbon Monoxide

Page 34: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

18

It is evident from the test result that only PMs(SPM, PM10 & PM2.5) are above

the Bangladesh standard limit. The reason being as explained above. Other

pollutants are well below the standard

The concentration of PM10, PM2.5 and SPM of DESCO project area is higher

than the Bangladesh standard limit. From the above data, we have found that

the amount of PM10, PM2.5 and SPM are maximum which are 243 ,137 and 302

µg/m3 respectively . On the other hand, concentration of SO2, NOx and CO*

have found within the Bangladesh standard limit. The air pollution levels have

been compared with the Bangladesh Ambient Air Quality Standard as adopted in

2005.

During field visit, no significant internal and external sources of air pollution was

observed in the project sites that would deteriorate air quality. Due to vehicular

movements, digging of the earth and loose earth materials (e.g. soil, sand), some

dust particles were observed in the project area. Heavy construction machineries

were used to carry out pile work which caused scanty amount of SOx and NOx

which is negligible.

During field visit it was also found that the EPC contractor is spraying water once

in a day in the construction site to maintain the air quality within the standard.

However, the constructional activities do not cause air pollution of the project

sites. The overall air condition of Dhaka city is comparatively polluted for which

the air qualities of the adjacent project sites are deteriorated.

3.2.2 Noise Level

55. The noise produced during pilling, vehicular movement and other construction

activities made a considerable impact on the human settlement around the project area. The

disturbance hinders public concentration to continue their activities during construction. Due

to the construction of boundary walls, the noise wouldn’t be produced beyond the boundary;

therefore, a short term effect due to noise pollution is considered as the negligible impact for

the community people around the project area.

56. During this visit, it was noticed that most of the workers were not comfortable in using

earmuffs. The contractors were suggested to provide earmuffs to all workers. The labours

are exposed approximately eight hours per day to the loud noise which can cause acute

damage to their hearing system, leading to hearing loss.

57. Though the project sites are within developing residential area where no

considerable human settlement around the project site has yet been set up that could be

affected by noise pollution.

58. Vehicular movements around the project sites were relatively moderate. Hence,

noise generation from external sources was insignificant. The average noise level of the

project sites are shown in the table 3.2 below along with the standards of noise levels for

different zones of Bangladesh. According to the following table it is found that the noise

level of Uttra sector 14 is higher than the other project sites. The average noise level of all

sites is negligible regarding the noise pollution aspect and it is not creating severe problems

for the locality near to the project area.

Page 35: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

19

Table 3.2: The Measured Average Noise Level of the Project Sites during the Field

Visit

Sl. No. Name of the substations Average Noise Level (dB)

1 Kazipara Switching Station 60

2 Kalshi (Shenpara) 58

3 Mirpur DOHS-2 50

4 Lake City Concord 61

5 Satarkul-1 63

6 Barua 62

7 Gulshan-03 63

8 Basundhara Block G 61

9 Sholahati 64

10 Uttarkhan (Promy) 65

11 Agargaon 56

12 Mirpur DOHS 65

13 Mirpur-06 64

14 Civil Aviation (CAAB) 50

15 ADA 58

16 Sector – 14,Uttara 66

17 Baunia 50

18 Tongi-01 50

19 Tongi-02 55

20 Tongi (BSCIC) 52

21 Tilargati, Tongi Sataish 50

Source: CEGIS, EMR, January to June, 2018

Table 3.3: Standards of Noise Levels for Different Zones of Bangladesh

Serial No.

Category of areas

Standards determined at dBa unit

Day Night

1 Silent zone 45 35

2 Residential area 50 40

3 Mixed area (mainly residential area, simultaneously used for commercial and industrial purposes)

60 50

4 Commercial area 70 60

5 Industrial area 75 70

Source: E.C.R. ’97

Page 36: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

20

3.2.3 Waste Management and Sanitation System

59. Waste management system at project sites was relatively good. Most of the sites

were good in terms of prevalent solid wastes. Dustbins were present at the project areas for

cooking and other organic disposals. Workers should be more encouraged and guided

properly to use dustbins as they show less interest to use them properly. It has been advised

accordingly to improve the waste management system.

60. There were separate arrangements of sanitation facilities for officials and daily

workers in the project sites. No form of water stagnation was observed during the monitoring

period within the project sides.

3.2.4 Soil Quality

61. Soil is an important component of environment management as well as proper

planning and designing of the structure. We have been reviewed and incorporated the sub-

soil investigation report’s data for understanding the soil condition of the project sites which

are provided by Siemens Bangladesh Ltd in the following table (3.4 to 3.20)

Page 37: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

21

Table 3.4: Laboratory Test Summary Sheet for Agragaon

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D7 D6 D8 D12 UD-1 D2 D3 D7 D8 D9 D11

Depth (ft) 8 10 15 35 30 40 60 8 10 15 35 40 45 55

Natural moisture content 25 26

Specific gravity 2.666 2.656

Particle Size

Gravel

Sand 20 57 62 12 51 53

Fines<0.075 mm 80 43 38 88 49 47

Unconfined

Compression

Test

qu,UD, (Psi) 25.75 24.55

Starin (%) 6.50 6.50

Wrt Density,pcf 119.25 119.45

Dry Density,pcf 95.75 95.85

Atterbag limit

Liquid Limit 49 47

Plastic Limit 25 25

Plasticity index 23 22

Direct Shear

Test

Ø (Degree) 30.30 31.75 32.10 30.25 31.50 32.15

C (tsf) 0 0 0 0 0 0

Consolidation

Test

Comp. Index,Cc 0.1090 0.1092

Initial Void Ratio

e0

0.3473 0.3470

Page 38: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

22

Table 3.5: Laboratory Test Summary Sheet for Mirpur-6

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D6 D7 D8 D9 D11 UD-1 D2 D5 D8 D9 D10 D12

Depth (ft) 8 10 30 35 40 45 55 8 10 25 40 45 50 60

Natural moisture content 28 27

Specific gravity 266 269

Particle Size

Gravel

Sand 14 54 52 10 55 54

Fines<0.075 mm 86 46 48 90 45 46

Unconfined

Compression Test

qu,UD, (Psi) 19.95

Starin (%) 6.50

Wrt Density,pcf 118.75

Dry Density,pcf 95.50

Atterbag limit

Liquid Limit 48 47

Plastic Limit 25 24

Plasticity index 23 23

Direct Shear Test Ø (Degree) 30.28 31.25 33.50 31.25 31.75 32.55

C (tsf) 0 0 0 0 0 0

Consolidation Test Comp. Index,Cc 0.1088 0.1090

Initial Void Ratio e0 0.3469 0.3471

Page 39: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

23

Table 3.6: Laboratory Test Summary Sheet for ADA

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D7 D6 D8 D12 UD-1 D2 D3 D7 D8 D9 D11

Depth (ft) 8 10 15 35 30 40 60 8 10 15 35 40 45 55

Natural moisture content 25 26

Specific gravity 2.666 2.656

Particle Size

Gravel

Sand 20 57 62 12 51 53

Fines<0.075 mm 80 43 38 88 49 47

Unconfined

Compression

Test

qu,UD, (Psi) 25.75 24.55

Starin (%) 6.50 6.50

Wrt Density,pcf 119.25 119.45

Dry Density,pcf 95.75 95.85

Atterbag limit

Liquid Limit 49 47

Plastic Limit 25 25

Plasticity index 25 22

Direct Shear

Test

Ø (Degree) 30.30 31.75 32.10 30.25 31.50 32.15

C (tsf) 0 0 0 0 0 0

Consolidation

Test

Comp. Index,Cc 0.1090 0.1092

Initial Void Ratio

e0

0.3472 0.3471

Page 40: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

24

Table 3.7: Laboratory Test Summary Sheet for Baunia

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D6 D7 D8 D13

UD-1 D2 D3 D7 D8 D9 D12

Depth (ft) 12 10 15 30 35 40 65 12 10 15 35 40 45 60

Natural moisture content 28 27

Specific gravity 2.666 2.656

Particle Size

Gravel

Sand 16 52 56 12 51 53

Fines<0.075 mm 84 48 44 88 49 47

Unconfined

Compression

Test

qu,UD, (Psi) 21.25 20.85

Starin (%) 6.50 6.50

Wrt Density,pcf 119.25 119.45

Dry Density,pcf 95.75 95.85

Atterbag limit

Liquid Limit 48 47

Plastic Limit 25 25

Plasticity index 23 22

Direct Shear

Test

Ø (Degree) 30.45 31.85 32.25 30.25 31.50 32.15

C (tsf) 0 0 0 0 0 0

Consolidation

Test

Comp. Index,Cc 0.3492 0.3489

Initial Void Ratio e0 0.1073 0.1070

Page 41: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

25

Table 3.8: Laboratory Test Summary Sheet for Mirpur DoHS (Augmentation)

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D6 D6 D7 D12 UD-1 D3 D7 D7 D8 D11

Depth (ft) 8 10 15 30 30 35 60 8 15 35 35 40 55

Natural moisture content 26 27

Specific gravity

Particle Size

Gravel

Sand 13 19 56 18 17 52

Fines<0.075 mm 87 81 44 82 83 48

Unconfined

Compression Test

qu,UD, (Psi) 25.75 24.55

Starin (%) 6.50 6.50

Wrt Density,pcf 119.25 119.45

Dry Density,pcf 95.75 95.85

Atterbag limit

Liquid Limit 49 48

Plastic Limit 25 25

Plasticity index 24 23

Direct Shear Test Ø (Degree) 30.25 31.30 30.45 31.55

C (tsf) 0 0 0

Consolidation Test Comp. Index,Cc 0.1091 0.1089

Initial Void Ratio e0 0.3471 0.3470

Page 42: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

26

Table 3.9: Laboratory Test Summary Sheet for Uttar Khan (Promy)

Bore Hole BH-1 BH-2 BH-3 BH-4 BH-5

Sample No.

UD

-1

D3

D7

D8

D18

UD

-1

D3

D8

D10

D12

UD

-1

D2

D10

D12

D18

UD

-1

D3

D9

D10

D17

UD

-1

D2

D13

D19

Depth (ft)

8

15

35

40

90

8

15

40

50

60

8

10

50

60

90

8

15

45

50

85

8

10

65

95

Natural moisture content

28

27

28

27

27

Specific gravity

2.6

56

2.6

90

2.6

90

2.6

66

2.6

65

Particle Size

Gravel

Sand

16

20

57

11

51

53

14

51

54

18

52

56

14

51

57

Fines<0.075 mm

84

80

43

89

49

47

86

49

46

82

48

44

86

49

43

Unconfined

Compression

Test

qu,UD, (Psi)

21.1

5

19.7

5

20.3

5

21.6

5

20.9

5

Starin (%)

6.5

0

6.5

0

6.5

0

6.5

0

6.5

0

Wrt Density,pcf

119.2

5

118.7

5

119.5

0

119.2

5

119.6

5

Dry Density,pcf

95.7

5

46

95.5

0

95.6

5

95.7

5

69.2

5

Page 43: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

27

Bore Hole BH-1 BH-2 BH-3 BH-4 BH-5

Sample No.

UD

-1

D3

D7

D8

D18

UD

-1

D3

D8

D10

D12

UD

-1

D2

D10

D12

D18

UD

-1

D3

D9

D10

D17

UD

-1

D2

D13

D19

Atterbag limit

Liquid Limit 24

48

47

46

48

Plastic Limit

22

25

25

24

25

Plasticity index

23

22

22

23

Direct Shear Test Ø (Degree)

30.8

8

31.2

5

33.5

0

31.1

5

30.5

31.2

5

C (tsf) 0

0

0

0

0

0

Consolidation

Test

Comp. Index,Cc

0.3

470

0.3

471

0.3

473

0.3

469

0.3

474

Initial Void Ratio

e0

0.1

088

0.1

089

0.1

09

0.1

092

0.1

091

Page 44: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

28

Table 3.10: Laboratory Test Summary Sheet for Merul Badda B

ore

Hole

Sam

ple

No.

Depth

(ft)

Wet

Un

it W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compressio

n Test

Consolidatio

n Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex

(Cc)

Void

(e0)

Ø0

Cohessio

n (

kg/m

3 )

0

Ø0

Cohessio

n (

kg/m

3 )

0

San

d(%

)

Silt

(%)

Cla

y (

%)

S.P

. G

ravity

1 D-03 4.50 1944.25 1518.21 30 34 20 14 0.30 7.40 0.14 0.730 27 73 2.62

D-09 13.50 26 NP NP NP 37.49 0 80 20 2.68

2 D-03 4.50 1938.12 1510.50 27 39 23 16 0.98 8 0.19 0.775 39 61 2.64

D-09 13.50 25 NP NP NP 40.24 0 89 11 2.70

3 D-03 4.50 1940.75 1512.10 28 38 2 15 0.90 7.80 0.18 0.760 38 62 2.63

D-09 13.50 27 NP NP NP 39.89 0 85 15 2.69

4 D-03 4.50 1938.20 1510.27 27 39 24 15 0.93 7.90 0.18 0.765 40 60 2.64

D-09 13.50 26 NP NP NP 38.73 0 83 17 2.68

5 D-03 4.50 1941.24 1515.15 29 37 21 16 0.88 7.70 0.16 0.750 37 63 2.63

D-09 13.50 27 NP NP NP 41.97 0 92 8 2.70

Page 45: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

29

Table 3.11: Laboratory Test Summary Sheet for Satarkul, Vatara B

ore

Hole

Sam

ple

No.

Depth

(ft)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex

(Cc)

Void

(e0)

Ø0

Cohessio

n (

kg/m

3 )

0

Ø0

Cohessio

n (

kg/m

3 )

0

San

d(%

)

Silt

(%)

Cla

y (

%)

S.P

. G

ravity

1 D-10 15 28 NP NP NP 40 35 25 2.63

D-14 21 26 NP NP NP 40.12 0 87 13 2.68

2 D-10 15 27 NP NP NP 43 32 25 2.64

D-14 21 26 NP NP NP 40.24 0 88 12 2.69

3 D-10 15 28 NP NP NP 41 30 29 2.62

D-14 21 25 NP NP NP 41.50 0 90 10 2.70

4 D-11 16.50 26 NP NP NP 45 35 20 2.65

D-14 21 24 NP NP NP 41.75 0 92 8 2.70

5 D-11 16.50 28 NP NP NP 399 33 28 2.62

D-14 21 25 NP NP NP 40..49 0 89 11 2.69

6 D-11 16.50 27 NP NP NP 41 32 27 2.63

D-14 21 24 NP NP NP 40.89 0 90 10 2.69

Page 46: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

30

Table 3.12: Laboratory Test Summary Sheet for Kalshi, Senpara B

ore

Hole

Sam

ple

No.

Depth

(ft)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear

Test

Direct

Shear Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohessio

n (

kg/m

3 )

0

Ø0

Cohessio

n (

kg/m

3 )

0

San

d(%

)

Silt

(%)

Cla

y (

%)

S.P

. G

ravity

1 D-03 7.50 1944.70 1518.60 31 35 20 15 0.50 7.50 0.14 0.735 29 71 2.62

D-09 12 27 NP NP NP 40.89 0 83 17 2.69

2 D-03 7.50 1516.15 30 36 20 16 0.60 8 0.16 0.745 34 66 2.63

D-09 12 27 NP NP NP 40.73 0 81 19 2..68

3 D-03 9 1943 31 36 21 15 0.48 7.45 0.15 0.730

D-09 13.50 26 NP NP NP 40.97 0 85 15 2.69

4 D-03 9 1942.19 30 25 21 14 0.45 7.40 0.14 0.725 29 71 2.63

D-09 13.50 28 NP NP NP 39.73 0 80 20 2.68

5 D-03 9 1940.12 28 37 22 15 0.62 8.20 0.16 0.750 35 65 2.64

D-09 13.50 26 NP NP NP 39.50 0 78 22 2.68

Page 47: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

31

Table 3.13: Laboratory Test Summary Sheet for Diabari, Uttara B

ore

Hole

Sam

ple

No.

Depth

(ft)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohessio

n (

kg/m

3 )

0

Ø0

Cohessio

n (

kg/m

3 )

0

San

d(%

)

Silt

(%)

Cla

y (

%)

S.P

. G

ravity

1 D-02 3 1938.60 1513.35 28 37 22 15 0.85 8 0.19 0.760 35 65 2.64

D-20 30 27 16.22 0.60 82 18 2.66

2 D-02 3 1942.47 1517.30 30 35 20 15 0.48 7.50 0.14 0.725 28 72 2.62

D-20 30 27

3 D-02 3 1941.70 1516.75 29 36 20 16 0.60 7.70 0.16 0.750 30 70 2.63

D-20 30 28 14.14 0.46 75 25 2.65

4 D-02 3 1940.25 1515.15 29 37 21 16 0.72 7.90 0.18 0.765 32 68 2.64

D-20 30 26 17.25 0.68 85 15 2.67

5 D-02 3 1939.10 1514.50 28 37 22 15 0.89 8.10 0.20 0.780 38 62 2.65

D-21 31.50 25 NP NP NP 41.89 0 90 10 2.69

Page 48: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

32

Table 3.14: Laboratory Test Summary Sheet for Swarnali Abason, Barua B

ore

Hole

Sam

ple

No.

Depth

(ft)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct

Shear Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohessio

n (

kg/m

3 )

0

Ø0

Cohessio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-10 15 27 NP NP NP 29 31 40 2.63

D-16 24 25 NP NP NP 41.50 0 93 7 2.70

2 D-10 15 28 NP NP NP 25 30 45 2.62

D-16 24 26 NP NP NP 40.49 0 90 10 2.68

3 D-10 15 27 NP NP NP 24 29 47 2.62

D-16 24 25 NP NP NP 40.73 0 91 9 2.69

4 D-10 15 31 NP NP NP 24 27 49 2.61

D-16 24 25 NP NP NP 39.50 0 89 11 2.68

5 D-10 15 30 NP NP NP 26 30 44 2.62

D-16 24 26 NP NP NP 39.12 0 88 12 2.68

6 D-10 15 33 NP NP NP 22 35 43 2.61

D-16 24 25 NP NP NP 40.24 0 90 10 2.69

Page 49: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

33

Table 3.15: Laboratory Test Summary Sheet for Lake City Concord, Khilkhet B

ore

Hole

Sam

ple

No.

Depth

(ft)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression Test

Consolidation

Test

Triaxial

Shear Test

Direct

Shear Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohessio

n (

kg/m

3 )

0

Ø0

Cohessio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-04 6 29 NP NP NP 28 30 42 2.62

D-08 12 28 NP NP NP 36.89 0 81 19 2.68

2 D-04 6 30 NP NP NP 25 31 44 2.62

D-08 12 27 NP NP NP 37.73 0 83 17 2.69

3 D-04 6 32 NP NP NP 22 29 49 2.61

D-08 12 27 NP NP NP 37.97 0 85 15 2.69

4 D-04 6 32 NP NP NP 20 28 52 2.61

D-08 12 28 NP NP NP 37.49 0 82 18 2.68

5 D-04 6 28 NP NP NP 20 33 47 2.63

D-08 12 25 NP NP NP 40.85 0 90 10 2.70

6 D-04 6 29 NP NP NP 21 35 44 2.62

D-08 12 26 NP NP NP 39.90 0 88 12 2.69

Page 50: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

34

Table 3.16: Laboratory Test Summary Sheet for Mirpur DOHS-2 B

ore

Hole

Sam

ple

No.

Depth

(ft)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohessio

n (

kg/m

3 )

0

Ø0

Cohessio

n (

kg/m

3 )

0

San

d(%

)

Silt

(%)

Cla

y (

%)

S.P

. G

ravity

1 D-02 3 1939.40 15114.60 26 39 24 15 1.20 8.50 0.24 0.800 38 62 2.64

D-14 21 24 NP NP NP 32.25 1.47 35 65 2.69

2 D-02 3 1938.50 1510.30 25 40 24 16 1.35 8.80 0.26 0.815 40 60 2.65

D-16 24 24 NP NP NP 31.30 1.40 30 70 2.68

3 D-02 3 1940.10 1514.90 27 38 23 15 1.15 8.60 0.25 0.810 37 63 2.36

D-16 24 25 NP NP NP 31.62 1.38 32 68 2.68

4 D-02 3 1941.25 1515.21 28 37 22 15 0.95 8.10 0.225 0.780 35 65 2.62

D-16 24 26 NP NP NP 32.56 1.51 38 62 2.70

5 D-02 3 1940.75 1514.65 27 37 21 16 1 8.20 0.23 0.790 36 64 2.63

D-16 24 26 NP NP NP 32.10 1.40 34 66 2.69

6 D-02 3 1939.20 1513.45 28 38 23 15 1.08 8.30 0.23 0.785 37 63 2.63

D-16 24 26 NP NP NP 31.94 1.33 30 70 2.68

Page 51: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

35

Table 3.17: Laboratory Test Summary Sheet for Swadesh Properties, Satarkul B

ore

Hole

Sam

ple

No.

Depth

(ft)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Un

it W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohessio

n (

kg/m

3 )

0

Ø0

Cohessio

n (

kg/m

3 )

0

San

d(%

)

Silt

(%)

Cla

y (

%)

S.P

. G

ravity

1 D-05 7.50 1940.47 1515.11 30 36 21 15 0.80 8 0.19 0.785 32 68 2.63

D-10 15 28 NP NP NP 31.42 0 30 70 2.68

2 D-05 7.50 1939.97 1514.45 30 35 20 16 0.82 8.10 0.19 0.790 35 65 2.64

D-10 15 NP NP NP 35.73 0 41 59 2.69

3 D-05 7.50 1942.19 1518.13 32 34 20 14 0.50 7.50 0.15 0.745 28 72 2.62

D-10 27 NP NP NP 34.97 0 36 64 2.68

4 D-06 9 1941.21 1517.75 31 35 21 14 0.60 7.70 0.16 0.750 30 70 2.63

D-10 15 28 NP NP NP 34.45 0 34 66 2.68

5 D-05 7.50 1944.15 1521.15 33 34 19 15 0.35 7.40 0.14 0.730 25 75 2.62

D-9 13.50 28 NP NP NP 35.97 0 30 70 2.68

6 D-05 7.50 1944.80 1521.78 33 33 18 15 0.37 7.50 0.14 0.735 20 80 2.62

D-10 15 27 NP NP NP 30.73 0 26 74 2.68

7 D-06 9 1939.15 1515.15 30 37 22 15 0.70 8 0.19 0.790 31 69 2.63

D-24 36 27 NP NP NP 41.89 0 90 10 2.70

Page 52: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

36

Table 3.18: Laboratory Test Summary Sheet for Tongi-3/Uttara Sector-14

Bore Hole BH-1 BH-2 BH-3 BH-4 BH-5

Sample No.

UD

-1

D2

D6

D5

D11

UD

-1

D2

D5

D7

D12

UD

-1

D2

D4

D6

D12

UD

-1

D3

D6

D7

D12

UD

-1

D3

D7

D7

D12

Depth (ft)

8

10

30

25

55

8

10

25

35

60

8

10

20

30

60

8

15

30

35

60

8

15

35

35

60

Natural moisture content 2 8

2 7

2 8

2 7

2 7

2 7

Specific gravity

2.6

6

2.6

9

2.6

9

2.6

7

2.6

7

Particle Size

Gravel

Sand

14

54

52

10

55

54

21

52

58

20

52

57

9

54

58

Fines<0.075 mm 8 6

4 6

4 8

9 0

4 5

4 6

7 9

4 8

4 2

8 0

4 8

4 3

9 1

4 6

4 2

Unconfined

Compression Test

qu,UD, (Psi)

21.2

5

19.9

5

20.2

5

21.5

5

20.7

5

Starin (%)

6.5

0

6.5

0

6.5

0

6.5

0

6.5

0

Wrt Density,pcf

119.2

5

118.7

5

119.5

0

119.2

5

119.6

5

Dry Density,pcf

95.7

5

95.5

0

95.6

5

95.7

5

96.2

5

Atterbag limit Liquid Limit

48

47

46

47

48

Plastic Limit 2 5

2 4

2 4

2 5

2 5

Page 53: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

37

Bore Hole BH-1 BH-2 BH-3 BH-4 BH-5

Sample No.

UD

-1

D2

D6

D5

D11

UD

-1

D2

D5

D7

D12

UD

-1

D2

D4

D6

D12

UD

-1

D3

D6

D7

D12

UD

-1

D3

D7

D7

D12

Plasticity index 2 3

2 3

2 2

2 2

2 3

Direct Shear Test Ø (Degree)

32.1

0

31.2

5

32.4

5

30.8

8

32.4

5

C (tsf) 0

0

0

0

0

Consolidation Test

Comp. Index,Cc

0.3

469

0.3

471

0.3

468

0.3

470

0.3

472

Initial Void Ratio e0

0.1

088

0.1

090

0.1

093

0.1

089

0.1

031

Page 54: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

38

Table 3.19: Laboratory Test Summary Sheet for Tongi -1, BSCIC I/A,Tongi ,Gazipur)

Bore Hole BH-4 BH-5 BH-6

Sample No. UD-1 D3 D6 D7 D12 UD-1 D3 D7 D7 D12 UD-1 D3 D7 D3 D13

Depth (ft) 8 15 30 35 60 8 15 35 35 60 8 15 35 65 65

Natural moisture content 27 27 27

Specific gravity 2.67 2.67 2.67

Particle Size

Gravel

Sand 20 52 57 9 54 58 20 24 55

Fines<0.075 mm 80 48 43 91 46 42 80 76 45

Unconfined

Compression

Test

qu,UD, (Psi) 21.55 22.25 20.85

Starin (%) 6.50 6.30 6.50

Wrt Density,pcf 119.25 119.95 119.55

Dry Density,pcf 95.75 96.35 95.65

Atterbag limit

Liquid Limit 47 48 47

Plastic Limit 25 25 25

Plasticity index 22 23 22

Direct Shear

Test

Ø (Degree) 30.88 32.45 32.75

C (tsf) 0 0 0

Consolidation

Test

Comp. Index,Cc 0.1089 0.1091 0.1092

Initial Void Ratio

e0 0.3470 0.3472 0.3474

Page 55: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

39

Table 3.20: Laboratory Test Summary Sheet for Tongi -2, Cherag Ali Besides Tongi S & D Division

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D6 D7 D8 D13 UD-1 D2 D3 D7 D8 D9 D12

Depth (ft) 8 10 15 30 35 40 65 8 10 15 35 40 45 60

Natural Moisture Content 28 27

Specific Gravity 2.666 2.656

Particle Size

Gravel 51 53

Sand 16 52 56 12 49 47

Fines<0.075 mm 84 48 44 88

Unconfined

Compression

Test

qu,UD, (Psi) 21.25 20.85

Starin (%) 6.50 6.50

Wrt Density,pcf 139.25 119.45

Dry Density,pcf 95.75 95.85

Atterbag limit

Liquid Limit 48 47

Plastic Limit 25 25

Plasticity index 23 22

Direct Shear

Test

Ø (Degree) 30.45 31.85 52.25 30.25 31.50 32

15

C (tsf) 0 0 0 0 0 0

Consolidation

Test

Comp. Index,Cc 0.347 0.347

Initial Void Ratio

e0 0.109 0.109

Page 56: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

40

Table 3.21: Laboratory Test Summary Sheet for Tongi BSCIC’S, Near BPDB’s 80 MW Power Station, Tongi

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D7 D6 D8 D11 UD-1 D2 D7 D8 D9 D12

Depth (ft) 8 10 15 35 30 40 55 8 8 15 35 40 45

Natural moisture content 28 27

Specific gravity 2.666 2.656

Particle Size

Gravel

Sand 16 54 59 12 51 53

Fines<0.075 mm 84 46 41 88 49 47

Unconfined

Compression Test

qu,UD, (Psi) 20.25 19.350

Starin (%) 6.50 6.50

Wrt Density,pcf 119.25 119.45

Dry Density,pcf 95.75 95.85

Atterbag limit

Liquid Limit 48 47

Plastic Limit 25 25

Plasticity index 23 22

Direct Shear Test Ø (Degree) 30.30 31.75 32.10 30.25 31.25 32.15

C (tsf) 0 0 0 0 0 0

Consolidation Test Comp. Index,Cc 0.1091 .1093

Initial Void Ratio e0 0.3471 0.33474

Page 57: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

41

3.3 Ecosystem and Biodiversity Conservation

62. This report mainly deals with the ecological resources might have a chance of being

afflicted due to the construction activities of 21 substations. The construction activities were

found in various stages at different sites during the visits. There were no ecological

resources in the all the substations, except Uttara section-14 and Mirpur DOHS. Most of the

substations sites were developed and paved by infrastructures of DESCO already. At Uttara

14 section, the main floristic composition was found with some fruit trees. Therefore, these

trees were being used by avifauna for resting and roosting behaviors.

Figure 3.2: Project Area at Uttara, Section-14

63. Clearing those vegetables might have some impacts of the existing wildlife there. As

the area of substation is very small in size, the existing surrounding nature can support the

wildlife without applying any mitigation measures.

64. On the other hand, Mirpur DOHS, which was situated, near the ditch, the

construction materials and wastes were being drained into the ditch. This might have some

negative impacts on aquatic life forms and their ecosystems. For instance, increase of

turbidity can reduce the light penetration in the water body and ultimately low food

production for fishes. The draining of construction wastes are not a problem in all the sites

as some sites have good facilities to drain out in drainage system. Among the all sites, some

of them were covered by seasonally grown grasses (small and tall). Most importantly, there

were no threatening species in the substation sites at all.

65. In case of faunal species, except some avifauna, there were no potential wildlife

habitats, those needs to be taken care of. Therefore, very minimal changes of ecological

resources have been observed during visits of all the substations. In a nutshell, there wasn’t

any significant impacts been found on existing wildlife and vegetation during the construction

periods of 21 substations.

66. It is better to mention here that during the night, no construction activities were

performed. Therefore, noise and light was not hampering the wildlife during night anyway.

The monitoring indicators regarding ecological resources and their complaince status are

presented in Appendix B.

Page 58: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

42

Table 3.22: Matrix of Monitoring Results

Environmental

and social

components

Potential

impacts

Monitoring

Measures Status

Corrective Action

Plan (CAP)

Ambient air

quality

Emission of

fugitive dusts due

to construction

activities can

accelerate the air

pollution.

Spraying water in the

construction site to

control fugitive dusts

Water

spraying is

carried out

once in a

day

- Water should be

sprayed twice in a

day for controlling

fugitive dusts.

- Loose soil can be

covered by

polythine or

sacks.

Construction

materials (sand/soil)

to be kept covered

Not

complied at

any site

- Construction

materials

(sand/soil) should

be covered by

polythene or

mulches during

dry weather

Introducing vehicle

speed limit N/A

Using new/good

engine quality

machines/vehicles to

avoid incomplete

combustion.

Complied in

all sites

Noise level

Disturbance to

local

communities,

ecosystem and

workers at

worksite due to

construction

activities of the

proposed project

site.

Using modern

machineries for

production of low

noise

Complied in

all sites

Providing hearing

protection for the

workers

Complied in

all sites.

The

contractor

has

mentioned

that they

arrange tool

box training

for the

workers

every day.

Waste

management

An inefficient

municipal solid

waste

engagement

system may

Earmarking specific

sites for waste

disposal

Complied in

all sites

Page 59: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

43

Environmental

and social

components

Potential

impacts

Monitoring

Measures Status

Corrective Action

Plan (CAP)

create serious

negative impacts

like spread of

infectious

diseases, land

and water,

pollution,

obstruction of

drains and loss

of bio diversity.

Conservation of

Ecosystem and

Biodiversity

Increase of

turbidity can

reduce the light

penetration in the

water body and

food production

for fishes will be

hampered

Alternative drainange

can be created

Complied

70%

Alternative drainage

should be initiated at

Mirpur DoHs for

avoiding the risk for

fish habitat ofnearby

ditch.

Source: CEGIS, EMR, January to June, 2018

67. During the monitoring it is found that here have some non compliance issues which

would be complied in the next phase of monitoring. The implementation plan has been

suggested through the consutation with the EPC contractor and PMU. In this following table

3.9 provides a implementation with action plan of such non compliance found during this

phase of monitoring. Based on this implementation plan, implementation performance would

be reported in the next monitoring report.

Table 3.23: Implementation Plan for Non Compliance Issues

Corrective Action

Plans Action Plan

Implementing

Period

Responsible

Agency Remarks

Water can be sprayed twice in a day for controlling fugitive dusts.

Consulted

with PMU and

ensured to

monitor the

status which

would be

incorporated

in the next

monitoring

report

At the next

pahse, the

result will be

incorporated

EPC contractor

and PMU

- Due to the

project

activities, it is

suggested to

spray water

twice in a day

for controlling

fugitive dusts.

- If the next

monitoring

result shows

unsatisfactory

result

frequency of

water spraying

will be

increased to

Page 60: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

44

Corrective Action

Plans Action Plan

Implementing

Period

Responsible

Agency Remarks

comply (100%)

within the next

phase of the

monitoring.

Loose soil can be

covered by

Polythine or sacks.

The EPC

contractor will

consider the

mitigation and

will cover

loose soil by

polythine or

sacks.

At the

construction

phase, this

non

compliance

issue will be

complied and

incorporated

in the next

phase of the

monitoring

EPC Contractor

and PMU

PMU ensured that

all will be complied

(100%) in the next

phase of the

monitoring

Construction

materials (sand/soil)

should have to kept

covered by

polythene or

mulches during dry

weather so that

strong wind cannot

blow away.

The EPC

contractor will

consider the

mitigation and

will cover

loose soil by

polythine or

sacks.

It will be

compiled at

the

construction

phase

EPC contractor

and PMU

PMU ensured that

all will be complied

(100%) in the next

phase of the

monitoring and

would be reported

at the next report.

Providing hearing

protection

equipment (air

plug/air muffler) for

the workers who are

directly exposed to

high noise level.

Consulted

with PMU and

EPC

contractor for

ensuring this

compliance.

It will be

compiled at

the

construction

phase before

the next phase

of monitoring

EPC contractor

PMU ensured that

all will be complied

(100%) in the next

phase of the

monitoring and the

performance of

non compliance

issue will be

reported in the

next report.

Facilitate garbage

bin for solid waste

disposal.

Construction wastes

need to be collected

and disposed in a

particular site inside

the project

boundary.

It would be

provided

before the

next phase of

the

monitoring

Would be

arranged at

the

construction

phase and

taken it

granted as it

comply and

incorporated

in the next

monitoring

report.

EPC contractor

The performance

of this non

compliance issue

will be reported in

the next monitoring

report.

Alternative Drainage

would be created for

avoiding the

EPC

Contarctor

has been

After the

completion of

construction

EPC contractor

and PMU

PMU will ensure

the compliance

status.

Page 61: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Monitoring Results

45

Corrective Action

Plans Action Plan

Implementing

Period

Responsible

Agency Remarks

negative impacts for

fishes at nearby

ditch

informed and

noted the

point for

alternative

drainage

Source: Monitoring field visit and consultation with PMU

Page 62: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

46

4. Institutional Arrangement and Grivence Redress

Mechanism

4.1 Institutional Arrangement

68. The organogram (provided by the DESCO) is responsible to monitor environmental

compliance and monitoring during the project construction. The assistant engineer

(electrical), assistant manager, and sub assistant engineer are working under the

supervision of the deputy project director for monitoring of augmentation, rehabilitation of

distribution system in DESCO area. The project director is responsible to supervise and

guide the whole work following the prepared checklist on the compliance status. The

following figure 4.1 shows the institutional arrangement those who are responsible to ensure

monitoring and compliance in accordance with Govt. laws, rules regulations and ADB’s loan

covenants.

Project Director

Deputy project

Director

Assistant EngineerAssistant Engineer

Sub assistant

Engineer

Manager

Sub assistant

Engineer

Figure 4.1: Institutional Arrangement of DESCO for Compliance and Monitoring

4.2 Grivence Redress Mechanism

69. At this stage, There is no Grievence redress comitee to address the grivence redress

but the EA will assist the grivence redress mechanism through their institutional

arrangement. As there is no construction activities, no sign provided at the project office to

accept peoples complain as well as redress the grivences. The subdivisional engineer will

work as the field officer and would be responsible to arrange consultation for peoples

awareness at the respective project sites.

70. Presently, With the starting of construction activities, a sub assistant engineer is

playing key role to understand the people problems (if any related to the project activity) and

visited three sites. In addition, phone number attached in each station to get compliant and

emergency response during the construction activities.

Page 63: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Institutional Arrangement and Grivence Redress Mechanism

47

Page 64: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

48

5. Specific Environmental Management Plan

71. The site specific Environmental Management plan is suggested by the EPC

contractor (i.e. Simmens India). At this stage, it is found that they have that plan to guide

their works for these three substations locations. In their plan, Simmens have the plans to

manage environmental issues during the construction phase of the project. Based on the

following table 5.1, Simmens India started the construction work at the three locations

whereas the construction activities continued based on this specific environmental

management plan.

Table 5.1: Specific Environmental Management Plan (SEMP)

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

1.

Top soil

Ensure the topsoil excavated from the proposed construction site not be dumped or stockpiled anywhere.

We will label all uneven land and excavated topsoil will immediately spread in between site working area.

Confirm the sediment-laden runoff must be prevented from entering into nearby water courses, if erosion occurs from stockpiles due to their location in drainage paths.

Stockpiles will be planed and located such way (away from water courses) so that sediment-laden cannot runoff into nearby water courses.

2.

Fauna (Wildlife)

Make sure that project workers and employees should not disturb, catch, fish, hunt, kill, trade and consumption of birds and wild animals available in natural environment around the project site.

We will provide official instruction (written, verbal and signboard) to all workers and employees to do not disturb wildlife. Also from management sites we will keep monitoring it throughout projects.

Establish and enforce daily site clean-up procedures, including maintenance of adequate disposal facilities for construction debris.

One clear system under waste management will be established for daily clean of construction area.

3.

Solid Waste

Establish daily cleaning through adequate collection and storage of solid waste produces at project site because of various activities throughout the work site, construction yard and labour camp.

Sufficient number of workers will be trained on cleaning to maintain cleaning activities of site areas. Besides this separate waste bin with color code and labeling would be provided to collect and segregate different types of waste.

Ensure adequately safe handling and transportation, with no dropping from waste carrier, of the solid wastes to the disposal sites.

Under waste management training all site personnel and assigned cleaner would be instructed and trained on handling and transporting of waste. Standard tools will also provide to carry and transport waste.

Establish an order that under no

circumstances dispose any materials in environmentally

Buckets, places and area will be placed or allocated far away from any environmentally sensitive’s area.

Page 65: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Specific Environmental Management Plan

49

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

sensitive area (example: designated forest area, area of endanger/rear flora, natural drainage course).

Proper barricade will be provided along with billboard or signage to restricted waste and create awareness.

4.

Drainage Congestion

Confirm an effective system for smooth draining of storm and rain water, and resulting no water logging (for rain and flood water in the monsoon).

Proper drainage system includes rain water drain, water pits sloping in the surface will be constructed/provided for smooth draining of storm and rain water and ensuring no water logging during monsoon.

Ensure no congestion in the

drain(s) resulting blockage of water passing.

To avoid blockage drain would be clean periodically.

5.

Noise level

Control sound pollution from construction equipment and machineries installed in the construction site.

Sound level for several heavy equipment and machineries and generator will be measured individual during their operation and record will be maintained properly.

Maintain noise levels associated with all machineries and equipment at or below 90 decibel (db), in particular for nearby community facilities.

Air plug will provide all site personnel who are working near the noisy area.

Fully avoid use of hydraulic

horns to project vehicles.

Hydraulic horn (if any exist) of each and every project vehicle will be replaced by non-hydraulic horn.

Control sound pollution from

generation.

We will ensure Installation of soundless generator. If not, generators will be placed in the closed room having barricaded from all sides, which will restrict sound level.

Regulate use of horns of

project vehicles as much as minimum, especially in night.

Strict instruction will be given to the flagman and drivers of project vehicles (motor cycle, car, truck, etc.) for use of horns as much as minimum.

6.

Air quality & Dust

Ensure use of dust-masks by all personnel in areas prone to dust emissions throughout the period of construction.

Proper dust mask will be provided and monitored by site management and EHS officer in the construction area.

Ensure minimum dust emission

in places where earth and cement works is done.

We will prepare and maintain proper HIRA (Hazard Identification & Risk Assessments) and implement SWMS (Standard work method system) to ensure minimum dust emission during earth and cement work. Also regular water will be sprayed all over those area to restrict dust emission.

7. Setting of Ensure health facilities for the

workers and employees at camp Standard camp along with proper sanitation and fresh drinking water

Page 66: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Specific Environmental Management Plan

50

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

construction camp

site. and safe area will be provided to ensure proper health facilities for workers.

Ensure safe disposal of wastewater from the labor camp and causing no pollution of nearby ponds and watercourses.

Proper drainage system including a temporary septic tank will be setup to avoid any pollution of nearby ponds and watercourses.

Confirm maintenance of all camp facilities in a safe clean and/or appropriate condition throughout the constructed period.

A routine cleaning would be ensured to maintain safe, clean and appropriate labor camp.

Ensure hygienic toilet facility (with constant water supply system) at residence of the workers in the camp area.

At least one water closet toilet will be constructed and provided to each 25 workers.

Ensure hygienic urinal facility (with constant water supply system) at residence of the workers in the camp area and its usage.

At least one urinal facility will be constructed and provided to each 25 workers.

Confirm appropriate usage of

the toilet and urinal facilities for all workers and personnel.

Signage and billboard will be provided to create awareness and also site management will strictly monitor of using it.

Ensure safe water supply system for bath, cook and other essential use in camp and their usage by workers.

Tube well, submergible pump (if necessary) will be provided to ensure safe water supply.

Ensure no accident from fire at

camp, residence/quarter. Fire extinguisher will be setup in camp and other important areas.

Ensure immediate

troubleshooting and maintenance of facilities.

Maintenance of all facilities will be done in time as scheduled for keeping the things in a safe, clean and appropriate condition throughout the constructed period.

Page 67: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Specific Environmental Management Plan

51

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

i. 12 Cutting Trees4

Avoid tree cutting as many as possible.

SIEMENS will not involve in any kinds of cutting trees and activities which will cause of it.

Confirm replantation of double number of trees against tree cutting.

N/A

Ensure additionally replantation of 107

5 numbers of trees

along the access road slopes. N/A

Strictly prohibit collection of any kind of construction material from within the natural habitat.

No materials for construction, cook, fire, etc. will be collected from within the natural habitat.

When removing vegetation from right of ways, workspaces etc. featheredge the cut to ensure that line of site and cover (both security and thermal protection) issues are addressed.

N/A

13. Natural Habitat6

Prohibit disposal of construction

waste within the natural habitat.

It will be strictly monitored and

controlled by supervising and raising

awareness through training and

meeting.

Restrict any disturbance to

water resource within the

natural habitats.

All site personnel will be clearly

instructed to avoid any disturbance

to water resources within the natural

habitats.

Prevent human disturbance and

ecosystem impacts on sensitive

areas adjacent to projects by

using temporary fencing or flag

off area to restrict travel to

construction zones, RoW and

workplace.

Temporary fencing or flag will be

provided to avoid any disturbance of

human by traveling or moving inside

construction zones, RoW and

workplace. Also at least one security

guard will be placed to ensure

unauthorized personnel movement

on sites and maintain site security

during project execution.

4 1) The species shall be identified in consultation with officials of forest department and/or local

community, giving due importance to local flora, preferably same species as cut.

2) Recommended to plant mixed species in case of both avenue or cluster plantation.

3) Plantation must follow availability of water during dry season.

4) Plants must be protected at initial stage of growth. 5 The EIA/EMP report suggested for planting 107 trees along the access road slops commonly for

each of six specific substations. 6 1) The species shall be identified in consultation with officials of forest department and/or local

community, giving due importance to local flora, preferably same species as cut.

2) Recommended to plant mixed species in case of both avenue or cluster plantation. 3) Plantation must follow availability of water during dry season.

3) Plants must be protected at initial stage of growth.

Page 68: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

52

6. Conclusions and Recommendations

6.1 Conclusions

72. This monitoring was conducted twenty one (21) substations and explored the

compliance status based on ADB safeguard policy, EMP provided in the EIA, Bangladesh

Govt and ADB loan covenant. it ur proposed locations have been identified and existing

physical, biological and social conditions observed to get an insight about the base situation.

In this stage of environmental monitoring, the environmental management system and action

plan, occupational health and safety, workers’ wellbeing, biodiversity and sustainable

management of natural resources have been observed through monthly field visit for

particular project area following selected indicators mentioned in the checklist. Thus, a

comprehensive environmental monitoring result has been compiled and suggested the

corrective action plan for further improvement on non compliance status. Finally, an

implementation plan based on Corrective Action Plan (CAP) has been recommended in this

environmental report.

6.2 Recomendations

73. For the effective compliance staus, following recommendations are proposed by the

study team to be followed during the construction phase of these projects:

Though construction materials like sand and soil were not covered with polythene

at all project sites. This might cause dust pollution in dry condition. Thus, it is

required to cover the construction materials properly.

The noise level should be limited during the construction expecially the pilling

stage of the project implementation.

Earmuff should be available in adequate numbers for all labors working during

construction.

Separate Dustbins for both disposal and non disposal waste should be set within

the project during implementatiion.

The use of PPE should be ensured through regular monitoring by the monitoring

team of PMU to avoid the risks for further accidental case.

More awareness is to be created among the workers and community dwellers

regarding the health and safety risks associated with the construction phase of

the project.

One paramedic doctors, and an ambulance need to be made available for the

labors in case of any injury and accident.

Feedbacks from the labors taken to understand their problems during the weekly

toolbox meetings on health and safety, as well as the other governing

environmental and social issues should be initiated.

Page 69: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Conclusions and Recommendations

53

.

Page 70: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

54

Reference

ADB (2009). Safeguard Policy Statement, Policy Paper

Page 71: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Reference

55

Page 72: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

56

Appendix-A: Field Photos

Safety Measures and Instrument at Mirpur Substation

Working Environment during Project Implementation

Page 73: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-A

57

Construction Activity at Agargaon Substation Area

Construction Activity at Mirpur 6

Page 74: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

58

Appendix-B: Monitoring Checklist

Category Description of

potential impact Measures/Indicators

Compliance Status

Co

mp

lied

No

t C

om

plied

Rem

ark

s

Monitoring Component: Physical Environment

Noise Level

Disturbance to local communities, ecosystem and workers at worksite due to construction activities of the proposed plant site.

Use modern low noise producing machineries. Partially Complied 70%

Rest of the percentage would be complied and incorporated with the next monitoring report.

Switching off machines which are not in use. ✓

Develop temporary corrugated/Tarja fencing around the project boundary

Provide hearing protection for the workers ✓

Follow mandatory regulations in case of night shift operations. Not Applicable

Maintainng noise level 45 dBA at the residential area and 55 dBA at day light hour

Partially Complied 70%

Rest of the percentage would be complied and incorporated with the next monitoring report.

Maximize the offset distance between noisy plant items and nearby sensitive receivers

Not Applicable

Employ effective silencing measures for equipment and other abatement techniques to minimize construction site noise.

Ensure that all equipment is in good repair and operated in the correct manner.

Consult with local people /residents and building owners to address community concerns

Page 75: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-B

59

Category Description of

potential impact Measures/Indicators

Compliance Status

Co

mp

lied

No

t C

om

plied

Rem

ark

s

Air Quality

Emission of particulate matter, SOx and NOx due to construction activity and from construction machineries.

Water spraying system to control fugitive dusts ✓

Restricting excavation activities such as top soil removal during period of high winds

Locating stockpiles away from the sensitive receptors ✓

Carrying out progressive rehabilitation of cleared land ✓

Locating contractor’s compounds away from residential areas ✓

restricting the burning of waste ✓

minimize exhaust emissions from construction equipment through the regular maintenance of all construction machinery and vehicles

Construction materials (sand/soil) to be kept covered with polythene ✓

Provide broad fence/ barrier to restrict wind current ✓

Introduce vehicle speed limit Not applicable

Use good engine quality machines/vehicles ✓

Ensure that emissions from on-road and off-road vehicles should

comply with Schedule 6 (Standards for emissions from motor vehicles) of ECR 1997

Soil Characteristics

The soils of the project areas have clay loam/ silty loam to loamy texture. The area under the project would be filled up with external soils having sandy materials. Then the existing soil might turn into sandy soil in the proposed Sub-station sites.

Topsoil that is to be removed should be stockpiled for site rehabilitation and landscaping works.

Soil-erosion and sedimentation-control measures should be undertaken in stages to minimize the area of unstable or unprotected soil surfaces

Not applicable

Wherever possible, vegetation is to be left undisturbed and retained as soil cover. If vegetation cover is not available, spread mulches over the surface to reduce dust and rainfall impact.

Not applicable for the project site

Undertake the progressive revegetation of excavated areas as quickly as possible. Revegetation may include grassing or planting the area with trees or shrubs. The selection of species should be compatible with the local conditions and use requirements.

Partially 60%

Rest of the percentage would be complied and incorporated with the next monitoring report.

Page 76: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-B

60

Category Description of

potential impact Measures/Indicators

Compliance Status

Co

mp

lied

No

t C

om

plied

Rem

ark

s

All fuel storage areas and refueling vehicles are to be provided with spill –containment kits

An emergency Spill Contingency plan shall be prepared by the contractor as part of the SEMP

Proper deposition of loose soil and construction materials to avoid water logging

Waste Management

An efficient municipal solid waste management system may create serious negative impacts like infectious diseases, land and water, pollution, obstruction of drains and loss of bio diversity.

Specific sites for waste disposal ✓

Quantification of solid wastes Not Applicable

Sanitation system

Location of backfilling stockpile in safe area ✓

Measures to control odor problems

Excavated material unsuitable for fill should be disposed in an environmentally safe manner.

Ensure that the waste management measures (collection, sorting, and disposal) are correctly implemented on the project site

Ensure that correctly signed waste containers are available at convenient locations for the disposal of wastes

Partially 50%

Rest of the percentage would be complied and incorporated with the next monitoring report.

Dispose of all used oil and fuel filters in a secure landfill, unless they can be recycled

Ensure that an adequately sized area is made available for the safe storage of wastes prior to collection

Ensure that all on-site wastes are suitably contained and prevented from escaping into

Partially 60%

Rest of the percentage would be complied and incorporated with the next monitoring

Page 77: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-B

61

Category Description of

potential impact Measures/Indicators

Compliance Status

Co

mp

lied

No

t C

om

plied

Rem

ark

s

report.

Neighboring fields, properties, and waterways, and that the waste contained does not contaminate soil, surface, or groundwater, or create unpleasant odors for neighbors or workers

Ensure the site is regularly cleaned and waste material appropriately removed, i.e., to a landfill in accordance with regulations

Monitoring Component: Biological Environment

Ecosystem and Biodiversity Conservation

Bird’s habitat loss, damages of herbs, shrubs and degradation of ecosystem and biodiversities due to construction works.

No disturbance on wildlife movement ✓

Limiting the use of night light ✓

No plantation of non-native species ✓

The removal of vegetation shall be restricted to the development

footprint, which should encompass areas that are already relatively disturbed in preference to clearing vegetation

Any additional clearing for construction will compound the impacts,

so ancillary facilities outside the footprint shall be avoided ✓

The construction footprint shall be clearly demarcated. The clearing boundaries are to be shown to machinery operators with the instruction that machinery is not allowed to operate outside the boundaries. The area is then cleared to minimize disturbance to adjacent areas

The boundary will be fenced and the area cleared in such a way that

the footprint shall not be extended during clearing works. ✓

If the area is to be revegetated, preference should be given to

naturally occurring species that are recognized as non-invasive species.

Not yet started related initiative

Page 78: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-B

62

Category Description of

potential impact Measures/Indicators

Compliance Status

Co

mp

lied

No

t C

om

plied

Rem

ark

s

Ecosystem and Biodiversity Conservation

Bird’s habitat loss,

damages of herbs,

shrubs and degradation

of ecosystem and

biodiversities due to

construction works.

No disturbance on wildlife movement Partially 70%

The alternative drainage have been suggested for Mirpur DoHs Substation, will be implemented after the completion of construction actitivity.

Limiting the use of night light ✓

No plantation of non-native species ✓

The removal of vegetation shall be restricted to the development

footprint, which should encompass areas that are already relatively disturbed in preference to clearing vegetation

Any additional clearing for construction will compound the impacts,

so ancillary facilities outside the footprint shall be avoided ✓

The construction footprint shall be clearly demarcated. The clearing boundaries are to be shown to machinery operators with the instruction that machinery is not allowed to operate outside the boundaries. The area is then cleared to minimize disturbance to adjacent areas

The boundary will be fenced and the area cleared in such a way that

the footprint shall not be extended during clearing works. ✓

If the area is to be revegetated, preference should be given to

naturally occurring species that are recognized as non-invasive species.

Not yet started related initiative

Legend:

Complied = ✓ Partially complied= (--)✓ Not complied= ✓

Page 79: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

63

Page 80: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

64

Appendix-C: Contract Agreement between DESCO and Simens

India

Page 81: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-C

65

Page 82: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-C

66

Page 83: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-C

67

Page 84: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-D: Map of the Study Area

Page 85: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation
Page 86: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

70

Appendix-E: Environmental Clearence Certificate

Page 87: 42378-016: Power System Expansion and Efficiency ... · Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Output C1 and C2: Augmentation and Rehabilitation

Appendix-E

71