4 n k srivastava

Upload: nashok689039

Post on 03-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 4 N K Srivastava

    1/31

    FOCUS ON COAL AND

    ASH HANDLING PLANTBYN.K.SRIVASTAVA

    22nd MAY,2012

  • 7/28/2019 4 N K Srivastava

    2/31

    CAPACITY ADDITION ANNOUNCED

    Announced Capacity

    920.7 Gigawatt 914 Projects

  • 7/28/2019 4 N K Srivastava

    3/31

    CONTINUED

    Fuel Projects Capacity (MW)Coal 571 683,402

    Under Construction 124 116,761

    Under Implementation 111 113,044

    Under Planning 336 453,597

    Gas 112 111,366

    Under Construction 20 10,259

    Under Implementation 18 8,465

    Under Planning 74 92,642Hydro 220 86,246

    Under Construction 48 13,417

    Under Implementation 30 8,377

    Under Planning 142 64,452

    Nuclear 11 39,700

    Under Construction 3 4,800

    Under Planning 8 34,900

    Total 11 39,700Under Construction 195 145,237

    Under Implementation 159 129,886

    Under Planning 560 645,591

    Grand Total 914 920,714

  • 7/28/2019 4 N K Srivastava

    4/31

    Key Clearances

    Project StatusUnder

    Construction

    Under

    Implementation

    Under

    Planning

    Grand

    Total

    Cap (MW) 145,237 129,886 645,591 920,714

    Total 195 159 560 914

    Land 181 126 71 378

    Water 181 114 74 369

    Environment 183 128 86 397

    Financial 169 60 12 241

    Equipment 183 58 13 254

  • 7/28/2019 4 N K Srivastava

    5/31

    Environment Clearance Pipeline

    Announced Capacity

    417 Gigawatt 370 Projects

  • 7/28/2019 4 N K Srivastava

    6/31

    Fuel Continues to Be the Biggest Issue

    Plant Type Projects Capacity

    Linkage 255 283,099

    Captive 47 62220

    Imported 30 47,500

    Linkage+Imported 26 35,532

    Captive+Imported 5 5,770

    Captive+linkage 32 36,360

    Captive+Linkage+Imported 1 600

    Not Finalized 175 212,321Grand Total 571 683,402

    Fuel Pipeline for the Coal Sector

    203 Projects have applied for

    Linkage but is pending

  • 7/28/2019 4 N K Srivastava

    7/31

    MAJOR PLAYERS

    Coal Companies (CIL)

    Railways Power Generation Companies

    CHP Equipment suppliers and contractors

  • 7/28/2019 4 N K Srivastava

    8/31

    Major Issues

    Coal quality

    Coal Transportation Coal stock

    Competent contractors

  • 7/28/2019 4 N K Srivastava

    9/31

    Coal Quality

    very variable

    ash content system capacity, component life

    moisture & fines flowability in hoppers, chutes,

    housekeeping

    oversize quantity delays in unloading ,

    additional handling

    stones and trash delays in unloading, removal

    facilities, damage to equipment

  • 7/28/2019 4 N K Srivastava

    10/31

    Coal transportation

    Bunching of rakes

  • 7/28/2019 4 N K Srivastava

    11/31

    Coal stock

    Actual delivery less than requirement

    Imported coal

    - handling

    - blending with domestic coal

  • 7/28/2019 4 N K Srivastava

    12/31

    CHP /AHP suppliers- Issues

    Limited numbers/Bunching of Orders. Shortage of skilled Manpower/Capabilities

    Core competency in executing Civil works

    Good Civil sub contractors. Fabrication works execution.

    Standardisation by Utilities

    Steel procurement/Availability of fronts Skewed Cash Flow strategies

    Interface issues with main plant& other

    Vendors

  • 7/28/2019 4 N K Srivastava

    13/31

    Trends in manufacturing capacities of key CHPand AHP players

    CHP manufacturing companies have augmentedtheir in-house manufacturing capacities to meetthe new challenges of capacity additionprogramme of XII and XIII th Plan.

    Need for a good AHP player is there . Manycompanies are trying to enter in the fray.

  • 7/28/2019 4 N K Srivastava

    14/31

    Key Technology Developments

    L&T:

    Wagon Shifters and Pushers :

    Developed for reducing the space requirements inouthaul side of Wagon Tippler Complex and to

    reduce the unloading time. Revolutionary

    development considering paucity of free hold land.

    Wagon Tipplers: Development to meet the latest requirements of

    RDSO G-33 specification, which has come into

    force from 1st December 2010.

  • 7/28/2019 4 N K Srivastava

    15/31

    Hydraulic Drives for Conveyors . Low / zerorunning maintenance cost.

    Stacker Reclaimer bucket wheel & slew drives.These will increase the efficiencies over theelectro mechanical drives, lower maintenance,reduction in overall machine weight.

    Permanent Deck sheets for floor slab castings

    against the conventional shuttering, leads tofaster construction.

    Key Technology Developments

  • 7/28/2019 4 N K Srivastava

    16/31

    Key Technology Developments

    Flow dividing concept in the junction towers, forefficient blending

    Increased belt speed up to 4.8 m/sec.

    HT and LT cables are routed through conveyorgalleries, instead of cable trestles

    Single CHP for both phases of the power plant e.g.

    Adani Tiroda,etc.-High capacity CHP 3000-5000TPH Rapid unloading system for small Track Hopper

  • 7/28/2019 4 N K Srivastava

    17/31

    Recently executed projects, their highlights

    and learning's

    Utilities are switching for Wagon Tipplers, toaddress latest RDSO guidelines and ensure

    minimum unloading rate of 25 tips / hr. Reduced Engineering approval time for all the

    customers Ensure faster availability of customers inputs to

    be done by utilities.

  • 7/28/2019 4 N K Srivastava

    18/31

    Recently executed projects, their highlights

    and learning's In recent times, most of the utilities are including the

    Bunker TPs in the scope of CHP Contractor to avoid thedelays in overall plant completion, e.g. Malwa CHP, DBPower CHP.

    Overall CHP execution time has come down. CHPs arenow being executed in 20 months e.g. Mahan CHP.

    Tuticorin Coal Handling Plant for NTPL (2 x 500 MW) -port based power plant, includes marine piles, 2.2 km of

    off Shore Conveyor with Hydraulic conveyor drives for12 conveyors.

  • 7/28/2019 4 N K Srivastava

    19/31

    TRENDS IN MANUFACTURING

    CAPACITIES

    -NO CLEAR TRENDS SEEN IN EXPANSION OF

    MANUFACTURING CAPACITY IN INDUSTRY

    -PLAYERS ARE GENERALLY STICKING TO CORE

    AREAS

  • 7/28/2019 4 N K Srivastava

    20/31

    KEY TECHNOLOGY DEVELOPMENT

    - HIGH CONCENTRATION SLURRY DISPOSAL

    SYSTEM

    - DRY BOTTOM ASH SYSTEM

  • 7/28/2019 4 N K Srivastava

    21/31

    LEARNINGS FROM PROJECTS UNDER

    EXECUTION-

    -DELAYS IN ASH HANDLING SYSTEM:

    DELAY DUE TO EXECUTION OF CIVIL &

    STRUCTURAL WORKS.

    COLLABORATORS FULL FLEDGED NON

    INVOLVEMENT.DELAY IN PLACEMENT OF ORDERS FOR

    BOUGHTOUT ITEMS.

    NONAVAILABILITY OF EXPERIENCED & SKILLED

    MANPOWER FOR PROJECT EXECUTION.

    NON STANDARDISATION OF SYSTEM.

    FINANCIAL CAPABILITIES OF CONTRACTORS.

  • 7/28/2019 4 N K Srivastava

    22/31

  • 7/28/2019 4 N K Srivastava

    23/31

  • 7/28/2019 4 N K Srivastava

    24/31

  • 7/28/2019 4 N K Srivastava

    25/31

  • 7/28/2019 4 N K Srivastava

    26/31

    THANK YOU

  • 7/28/2019 4 N K Srivastava

    27/31

    KEY TECHNOLOGICAL

    DEVELOPMENTS

    - LATEST HIGH CAPACITY WAGON TIPPLERS

    (CONFORMING TO RDSO G33 Rev.1)

    -HIGH CAPACITY CHPs (3000TPH-5000TPH)

    - HYDRAULIC DRIVE IN PLACE OF ELECTRO-

    MECHANICAL DRIVE FOR MAJOR EQUIPMENTS

    LIKE TIPPLER, STACKER CUM RECLAIMER

  • 7/28/2019 4 N K Srivastava

    28/31

    TRENDS IN MANUFACTURING

    CAPACITIES

    - HAVE GENERALLY INVESTED IN EXPANDING

    MANUFACTURING CAPACITIES TO CATER TO

    HIGHER PRODUCTION VOLUME REQUIRED FORUPCOMING PROJECTS

    - HAVE GONE IN FOR COLLABORATION/

    ASSOCIATION/ JOINT VENTURES WITH VARIOUS

    FOREIGN PARTIES TO EXPAND THEIR RANGE

  • 7/28/2019 4 N K Srivastava

    29/31

    RECENTLY EXECUTED PROJECTRECENTLY EXECUTED PROJECT-- HIGHLIGHT &HIGHLIGHT &

    LEARNINGLEARNING

    --HIGH CAPACITY PLANT OPERATING SUCCESSFULLY.HIGH CAPACITY PLANT OPERATING SUCCESSFULLY.

    --CAN PLAN FOR HIGHER CAPACITY CHP.CAN PLAN FOR HIGHER CAPACITY CHP.

    -- GENERAL SHORTAGE OF SKILLED MANPOWERGENERAL SHORTAGE OF SKILLED MANPOWER

  • 7/28/2019 4 N K Srivastava

    30/31

  • 7/28/2019 4 N K Srivastava

    31/31