7/17/2019 2742-PLAN3 http://slidepdf.com/reader/full/2742-plan3 1/40 Job : 62742-202 Plan : 3 IBC9.7 DESIGN CRITERIA:  A. Code: 2010 CBC, Wind: C, 85 mph, Category: D B. Maximum 19% moisture content prior to Installation of Finish Material 4X Members: No. 2 or Better 6X, 8X Beams and Headers: No.1 or Better 2X Joists and Rafters: No. 2 or Better Plates and Blocking: Standard Grade or Better Studs: Stud Grade or Better Mud Sills: Pressure Treated Utility Grade or Better PRIMARY ROOF LOADING Pitch 4.0:12 K = Increase for pitch 1.05 Truss(24" OC) x K 2.53 Plywood(7/16") x K 1.37 1/2" Gyp. Board 2.20 Conc. Tile x K 10.54 Sprinkler 1.00 Misc.(Insul.,Elect.,ETC) 2.36 Snow Load 0.00 Live Load 20.00 Dead Load 20.00 PRIMARY FLOOR LOADING 14" TJI/210 @ 19.2" O/C 1.94 Plywood(5/8") 1.85 1/2" Gyp. Board 2.20 Carpet 1.00 None Covering 0.00 Sprinkler 1.00 Misc.(Insul.,Elect.,ETC) 7.00 Partition 0.00 Live Load 40.00 Dead Load 15.00

Upload: thai-phong

Post on 06-Jan-2016

9 views

Category:

Documents


0 download

DESCRIPTION

calculation a wood building with u.s standard

TRANSCRIPT

Page 1: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 1/40

Job : 62742-202

Plan : 3

IBC9.7

DESIGN CRITERIA:

 A. Code: 2010 CBC, Wind: C, 85 mph, Category: D

B. Maximum 19% moisture content

prior to Installation of Finish Material

4X Members: No. 2 or Better 

6X, 8X Beams and Headers: No.1 or Better 

2X Joists and Rafters: No. 2 or Better 

Plates and Blocking: Standard Grade or Better 

Studs: Stud Grade or Better 

Mud Sills: Pressure Treated Utility Grade or Better 

PRIMARY ROOF LOADING

Pitch 4.0:12

K = Increase for pitch 1.05

Truss(24" OC) x K 2.53

Plywood(7/16") x K 1.37

1/2" Gyp. Board 2.20Conc. Tile x K 10.54

Sprinkler 1.00

Misc.(Insul.,Elect.,ETC) 2.36

Snow Load 0.00

Live Load 20.00

Dead Load 20.00

PRIMARY FLOOR LOADING

14" TJI/210 @ 19.2" O/C 1.94

Plywood(5/8") 1.851/2" Gyp. Board 2.20

Carpet 1.00

None Covering 0.00

Sprinkler 1.00

Misc.(Insul.,Elect.,ETC) 7.00

Partition 0.00

Live Load 40.00

Dead Load 15.00

Page 2: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 2/40

Beam ID: GT#1 Girder Truss @ Rear of the Family RoomLoads (Downward +)Beam Weight 30.0 PLF from 0.0' to 20.0'

Primary Roof  720 PLF=36.0'x(20+20)/2 @ 0.00' to 20.00'

20.00'

Dow n (DL+LL/Max.) 6924/6924 6924/69

Up (DL+LL/Max.) 0/0 0/0

*** TRUSS DESIGNED BY OTHERS ***

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: GT#2 Girder Truss Over the GarageLoads (Downward +)Beam Weight 40.0 PLF from 0.0' to 20.8'

Primary Roof  200 PLF=10.0'x(20+20)/2 @ 0.00' to 20.75'

20.75'

Dow n (DL+LL/Max.) 2490/2490 2490/24

Up (DL+LL/Max.) 0/0 0/0

*** TRUSS DESIGNED BY OTHERS ***

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: GT#3 Girder Truss Over the Bed #2Loads (Downward +)Beam Weight 40.0 PLF @ 0.0' to 33.8'

Primary Roof  200 PLF=10.0'x(20+20)/2 @ 0.00' to 33.75'

33.75'

Dow n (DL+LL/Max.) 4050/4050 4050/40

Up (DL+LL/Max.) 0/0 0/0

*** TRUSS DESIGNED BY OTHERS ***

Job : 62742-202

Plan : 3

IBC9.7

Page 3: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 3/40

Beam ID: GT#4 Girder Truss Over the Family Room @ ELEV.CLoads (Downward +)Beam Weight 30.0 PLF from 0.0' to 19.5'

Primary Roof  200 PLF=10.0'x(20+20)/2 @ 0.00' to 19.50'

19.50'

Dow n (DL+LL/Max.) 2243/2243 2242/2242Up (DL+LL/Max.) 0/0 0/0

*** TRUSS DESIGNED BY OTHERS ***

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: GT#5 Girder Truss Over the Family Room @ OPT.Loads (Downward +)Beam Weight 30.0 PLF from 0.0' to 14.8'

Primary Roof  200 PLF=10.0'x(20+20)/2 @ 0.00' to 14.75'

14.75'

Dow n (DL+LL/Max.) 1696/1696 1696/1696

Up (DL+LL/Max.) 0/0 0/0

*** TRUSS DESIGNED BY OTHERS ***

Job : 62742-202

Plan : 3

IBC9.7

Page 4: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 4/40

Beam ID: 1(Drop) Header @ Rear of the Bed #4Loads (Downward +)Beam Weight 20.0 PLF @ 0.0' to 6.5'

Primary Roof  720 PLF=36.0'x(20+20)/2 @ 0.00' to 6.50'

Exterior Wall 15 PLF= 1.0'x15.0 @ 0.00' to 6.50'

 6.50'

Reactions(DL+LL/Max. Load Combination)

Down 2454/2454 2454/2454

Up 0/0 0/0

Use DFL NO2 4 x 10(Fb= 900 Fv=180)

Critical Shear =2202 LB @ 0.33' 1.5xShear/(FvxA)=0.453

Fv=225 A= 32.38

Crit ical Moment =3987 LBxFT @ 3.25' Ratio=0.718

Fb= 1335 S= 49.91

Critical Deflection = -0.082 INCH @ 3.25'

2202

Shear Diagram:DL RF_L

3987

Moment Diagram:DL RF_L

-0.082

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 2(Drop) Header @ Rear of the Bed #4Loads (Downward +)Beam Weight 20.0 PLF from 0.0' to 4.3'

Primary Roof  720 PLF=36.0'x(20+20)/2 @ 0.00' to 4.25'

Exterior Wall150 PLF=10.0'x15.0 @ 0.00' to 4.25'

Primary Floor  523 PLF=19.0'x(15+40)/2 @ 0.00' to 4.25'

 4.25'

Reactions(DL+LL/Max. Load Combination)

Down 3002/2608 3002/2608

Up 0/0 0/0

Use DFL NO2 4 x 8(Fb= 900 Fv=180)

Critical Shear =1886 LB @ 0.33' 1.5xShear/(FvxA)=0.619

Fv=180 A= 25.38

Crit ical Moment =2375 LBxFT @ 2.17' Ratio=0.798

Fb= 1165 S= 30.66

Critical Deflection = -0.058 INCH @ 2.08'

1886

Shear Diagram:DL FL_L

2375

Moment Diagram:DL FL_L

-0.058

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 5: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 5/40

Beam ID: 3(Drop) Header @ Rear of the Dining RoomLoads (Downward +)Beam Weight 20.0 PLF @ 0.0' to 6.5'

Primary Floor  523 PLF=19.0'x(15+40)/2 @ 0.00' to 6.50'

Exterior Wall 60 PLF= 4.0'x15.0 @ 0.00' to 6.50'

 6.50'

Reactions(DL+LL/Max. Load Combination)

Down 1958/1958 1958/1958

Up 0/0 0/0

Use DFL NO2 4 x 10(Fb= 900 Fv=180)

Critical Shear =1757 LB @ 0.33' 1.5xShear/(FvxA)=0.452

Fv=180 A= 32.38

Crit ical Moment =3182 LBxFT @ 3.25' Ratio=0.715

Fb= 1071 S= 49.91

Critical Deflection = -0.041 INCH @ 3.25'

1757

Shear Diagram:DL FL_L

3182

Moment Diagram:DL FL_L

-0.041

Deflection Diagram:LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 4 Header @ Rear of the KitchenLoads (Downward +)Beam Weight 20.0 PLF from 0.0' to 6.3'

Exterior Wall 165 PLF=11.0'x15.0 @ 0.00' to 6.25'

Primary Floor 523 PLF=19.0'x(15+40)/2 @ 0.00' to 6.25'

Primary Roof  700 PLF=35.0'x(20+20)/2 @ 0.00' to 6.25'

 6.25'

Reactions(DL+LL/Max. Load Combination)

Down 4398/3828 4398/3828

Up 0/0 0/0

Use DFL NO2 4 x 12(Fb= 900 Fv=180)w/Left:2-2x4 trim./stud Right:2-2x4 trim./stud

Critical Shear =-2952 LB @ 5.92' 1.5xShear/(FvxA)=0.625

Fv=180 A= 39.38

Crit ical Moment =5163 LBxFT @ 3.17' Ratio=0.848

Fb= 990 S= 73.83

Critical Deflection = -0.073 INCH @ 3.08'

-2952Shear Diagram:DL FL_L

5163

Moment Diagram:DL FL_L

-0.073

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 6: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 6/40

Beam ID: 4C Header @ Rear of the Kitchen @CLoads (Downward +)Beam Weight 20.0 PLF from 0.0' to 6.3'

Exterior Wall 165 PLF=11.0'x15.0 @ 0.00' to 6.25'

Primary Floor  536 PLF=19.5'x(15+40)/2 @ 0.00' to 6.25'

Primary Roof  700 PLF=35.0'x(20+20)/2 @ 0.00' to 4.00'

Primary Roof  180 PLF= 9.0'x(20+20)/2 @ 4.00' to 6.25'

Point Load(P1) From left of BM GT#3 @ 3.75

:Point Load Location

P1

 3.75'

 6.25'

Reactions(DL+LL/Max. Load Combination)

Down 5851/5130 5912/5201

Up 0/0 0/0

Use GLB 24F V4 3 1/8 x 10 1/2(Fb=2400/1850 Fv=265)w/Left:4x4 post Right:4x4 post

Critical Shear =-4015 LB @ 5.92' 1.5xShear/(FvxA)=0.693

Fv=265 A= 32.81

Critical Moment =10546 LBxFT @ 3.75' Ratio=0.735

Fb= 3000 S= 57.42

Critical Deflection = -0.143 INCH @ 3.17'

-4015Shear Diagram:DL FL_L

10546

Moment Diagram:DL 0.75xFL 0.75xRl

-0.143

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 5 Flush Bm @ Left of the STAIRLoads (Downward +)Beam Weight 20.0 PLF from 0.0' to 5.3'

Primary Floor  289 PLF=10.5'x(15+40)/2 @ 0.00' to 5.25' 5.25'

Reactions(DL+LL/Max. Load Combination)

Down 810/810 810/810

Up 0/0 0/0

Use TIMBERSTRAND 1 3/4x14 1.5E(Fb=2325 Fv=310)

Critical Shear =708 LB @ 0.33' 1.5xShear/(FvxA)=0.140

Fv=310 A= 24.50

Crit ical Moment =1063 LBxFT @ 2.67' Ratio=0.097

Fb= 2292 S= 57.17

Critical Deflection = -0.006 INCH @ 2.67'

708

Shear Diagram:DL FL_L

1063

Moment Diagram:DL FL_L

-0.006

Deflection Diagram:LL

Job : 62742-202

Plan : 3

IBC9.7

Page 7: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 7/40

Beam ID: 6 Flush Bm @ Left of the STAIRLoads (Downward +)Beam Weight 30.0 PLF from 0.0' to 14.5'

Point Load(P1) From left of BM 5 @ 3.75

Primary Floor  413 PLF=15.0'x(15+40)/2 @ 0.00' to 3.50'

Primary Floor  88 PLF= 3.2'x(15+40)/2 @ 3.50' to 14.50'

:Point Load Location

P1

 3.75'

14.50'

Reactions(DL+LL/Max. Load Combination)Down 2455/2455 1202/1202

Up 0/0 0/0

Use TIMBERSTRAND 1 3/4x14 1.5E(Fb=2325 Fv=310)w/Left:2-2x4 trim./stud

Critical Shear =2308 LB @ 0.33' 1.5xShear/(FvxA)=0.456

Fv=310 A= 24.50

Crit ical Moment =6124 LBxFT @ 4.33' Ratio=0.561

Fb= 2292 S= 57.17

Critical Deflection =-0.231 Inch @ 6.75' L/480=0.362

2308

Shear Diagram:DL FL_L

6124

Moment Diagram:DL FL_L

-0.231

Deflection Diagram:LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 7 Flush Bm @ Rear of the STAIRLoads (Downward +)Beam Weight 30.0 PLF from 0.0' to 13.5'

Primary Floor  921 PLF=33.5'x(15+40)/2 @ 0.00' to 9.25'

Primary Floor  523 PLF=19.0'x(15+40)/2 @ 9.25' to 13.50'

Point Load(P1) From left of BM 6 @ 9.25

:Point Load Location

P1

 9.25'

13.50'

Reactions(DL+LL/Max. Load Combination)

Down 6597/6597 6363/6363

Up 0/0 0/0

Use PARALLAM 5 1/4 x 14(Fb=2800 Fv=285)w/Left:2-2x6 trim./stud Right:2-2x6 trim./stud

Critical Shear =6296 LB @ 0.33' 1.5xShear/(FvxA)=0.451

Fv=285 A= 73.50

Critical Moment =24032 LBxFT @ 7.25' Ratio=0.611

Fb= 2752 S= 171.50Critical Deflection =-0.221 Inch @ 6.83' L/480=0.338

6296

Shear Diagram:DL FL_L

24032

Moment Diagram:DL FL_L

-0.221

Deflection Diagram:LL

Job : 62742-202

Plan : 3

IBC9.7

Page 8: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 8/40

Beam ID: 7.1 Flush Bm @ Rear of the KitchenLoads (Downward +)Beam Weight 30.0 PLF from 0.0' to 13.8'

Primary Floor  578 PLF=21.0'x(15+40)/2 @ 0.00' to 13.75'

Point Load(P1) From left of BM 6 @ 3.00

:Point Load Location

P1

 3.00'

13.75'

Reactions(DL+LL/Max. Load Combination)

Down 5982/5982 4623/4623Up 0/0 0/0

Use TIMBERSTRAND 3 1/2x14 1.5E(Fb=2325 Fv=310)w/Left:4x4 post Right:2-2x4 trim./stud

Critical Shear =5784 LB @ 0.33' 1.5xShear/(FvxA)=0.571

Fv=310 A= 49.00

Critical Moment =17933 LBxFT @ 6.00' Ratio=0.821

Fb= 2292 S= 114.33

Critical Deflection =-0.348 Inch @ 6.67' L/480=0.344

5784

Shear Diagram:DL FL_L

17933

Moment Diagram:DL FL_L

-0.348

Deflection Diagram:LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 8 Top Flush Bm Over the GarageLoads (Downward +)Beam Weight 40.0 PLF from 0.0' to 20.8'

Exterior Wall 135 PLF= 9.0'x15.0 @ 0.00' to 20.75'

Primary Roof  440 PLF=22.0'x(20+20)/2 @ 0.00' to 20.75'

Primary Roof  210 PLF=10.5'x(20+20)/2 @ 0.00' to 20.75'

Primary Floor  55 PLF= 2.0'x(15+40)/2 @ 0.00' to 20.75'

Shear Wall W= 751 S= 1080 H= 9.0' @ 5.0' L= 4.0' 3(A)

Point Load(P1) From right of BM GT#1 @ 0.00

Point Load(P2) From right of BM 6 @ 0.00

:Point Load Location :Edge of Shear Panel

P1P2

20.75'

Reactions(DL+LL/Max. Load Combination)

Down 15621/16121 8060/8890

Up 0/0 0/0

Use PARALLAM 5 1/4 x 18(Fb=2800 Fv=285)w/Left:Design trim./post Right:2-2x6 trim./stud

Critical Shear =7400 LB @ 0.33' 1.5xShear/(FvxA)=0.330

Fv=356 A= 94.50Critical Moment =39660 LBxFT @ 10.33' Ratio=0.502

Fb= 3346 S= 283.50

Critical Deflection =-0.635 Inch @10.33' L/280=0.889

7400

Shear Diagram:DL RF_L

39660

Moment Diagram:DL RF_L

-0.635

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 9: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 9/40

Beam ID: 8 Top Flush Bm Over the GarageLoads (Downward +)Beam Weight 40.0 PLF from 0.0' to 20.8'

Exterior Wall 135 PLF= 9.0'x15.0 @ 0.00' to 20.75'

Primary Roof  440 PLF=22.0'x(20+20)/2 @ 0.00' to 20.75'

Primary Roof  210 PLF=10.5'x(20+20)/2 @ 0.00' to 20.75'

Primary Floor  55 PLF= 2.0'x(15+40)/2 @ 0.00' to 20.75'

Shear Wall W= 751 S= 1080 H= 9.0' @ 5.0' L= 4.0' 3(A)

Point Load(P1) From right of BM GT#1 @ 0.00

Point Load(P2) From right of BM 6 @ 0.00

:Point Load Location :Edge of Shear Panel

P1P2

20.75'

Reactions(DL+LL/Max. Load Combination)

Down 15621/16121 8060/8890

Up 0/0 0/0

Use GLB 24F V4 5 1/8 x 18(Fb=2400/1850 Fv=265)w/Left:Design trim./post Right:2-2x6 trim./stud

Critical Shear =7400 LB @ 0.33' 1.5xShear/(FvxA)=0.363

Fv=331 A= 92.25

Critical Moment =39660 LBxFT @ 10.33' Ratio=0.620

Fb= 2772 S= 276.75Critical Deflection =-0.723 Inch @10.33' L/280=0.889

7400

Shear Diagram:DL RF_L

39660

Moment Diagram:DL RF_L

-0.723

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 10: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 10/40

Beam ID: 8C Flush Bm Over the GarageLoads (Downward +)Beam Weight 40.0 PLF from 0.0' to 20.8'

Exterior Wall 135 PLF= 9.0'x15.0 @ 0.00' to 20.75'

Primary Roof  400 PLF=20.0'x(20+20)/2 @ 0.00' to 13.75'

Primary Roof  210 PLF=10.5'x(20+20)/2 @ 0.00' to 20.75'

Primary Floor  55 PLF= 2.0'x(15+40)/2 @ 0.00' to 20.75'

Shear Wall W= 751 S= 1080 H= 9.0' @ 5.0' L= 4.0' 3(A)

Primary Roof  200 PLF=10.0'x(20+20)/2 @13.75' to 20.75'

Point Load(P1) From right of BM GT#4 @13.75

Point Load(P2) From left of BM GT#1 @ 0.00

Point Load(P3) From right of BM 6 @ 0.00

:Point Load Location :Edge of Shear Panel

P1

13.75'

P2P3

20.75'

Reactions(DL+LL/Max. Load Combination)

Down 15774/16272 8036/8889

Up 0/0 0/0

Use GLB 24F V4 5 1/8 x 18(Fb=2400/1850 Fv=265)w/Left:Design trim./post Right:2-2x6 trim./stud

Critical Shear =7538 LB @ 0.33' 1.5xShear/(FvxA)=0.370

Fv=331 A= 92.25Critical Moment =42831 LBxFT @ 11.00' Ratio=0.671

Fb= 2769 S= 276.75

Critical Deflection =-0.773 Inch @10.42' L/280=0.889

7538

Shear Diagram:DL RF_L

42831

Moment Diagram:DL RF_L

-0.773

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 9(Drop) Header @ Front of the GarageLoads (Downward +)Beam Weight 30.0 PLF from 0.0' to 16.3'

Exterior Wall 165 PLF=11.0'x15.0 @ 0.00' to 16.25'

Primary Roof  200 PLF=10.0'x(20+20)/2 @ 0.00' to 16.25'

Primary Floor  605 PLF=22.0'x(15+40)/2 @ 0.00' to 16.25'

Shear Wall W= 1141 S= 1102 H= 9.0' @14.0' L= 4.0' 10(A)

:Edge of Shear Panel

16.25'

Reactions(DL+LL/Max. Load Combination)

Down 8043/8053 8043/11679

Up 0/0 0/-4041

Use GLB 24F V4 5 1/8 x 15(Fb=2400/1850 Fv=265)w/Left:2-2x6 trim./stud Right:Design trim./post

Critical Shear =-6934 LB @15.92' 1.5xShear/(FvxA)=0.511

Fv=265 A= 76.88

Critical Moment =29372 LBxFT @ 8.08' Ratio=0.794

Fb= 2310 S= 192.19

Critical Deflection =-0.599 Inch @ 8.17' L/280=0.696

-6934Shear Diagram:DL FL_L

29372

Moment Diagram:DL FL_L

-0.599

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 11: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 11/40

Beam ID: 10(Drop) Header @ Front of the GarageLoads (Downward +)Beam Weight 20.0 PLF from 0.0' to 8.3'

Primary Roof  420 PLF=21.0'x(20+20)/2 @ 0.00' to 2.00'

Primary Roof  180 PLF= 9.0'x(20+20)/2 @ 2.00' to 8.25'

Exterior Wall 30 PLF= 2.0'x15.0 @ 0.00' to 8.25'

Point Load(P1) From right of BM GT#2 @ 2.00

:Point Load Location

P1

 2.00'

 8.25'

Reactions(DL+LL/Max. Load Combination)

Down 3257/3257 1611/1611

Up 0/0 0/0

Use DFL NO1 6 x 8(Fb=1200 Fv=170)

Critical Shear =3100 LB @ 0.33' 1.5xShear/(FvxA)=0.531

Fv=213 A= 41.25

Crit ical Moment =5574 LBxFT @ 2.00' Ratio=0.869

Fb= 1492 S= 51.56

Critical Deflection =-0.199 Inch @ 3.83' L/240=0.412

3100

Shear Diagram:DL RF_L

5574

Moment Diagram:DL RF_L

-0.199

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 11 HDR Bm @ Front of the GarageLoads (Downward +)Beam Weight 30.0 PLF @ 0.0' to 16.3'

Primary Floor  28 PLF= 1.0'x(15+40)/2 @ 0.00' to 16.25'

Exterior Wall 135 PLF= 9.0'x15.0 @ 0.00' to 16.25'

Primary Roof  40 PLF= 2.0'x(20+20)/2 @ 0.00' to 16.25'

16.25'

Reactions(DL+LL/Max. Load Combination)

Down 1889/1808 1889/1808

Up 0/0 0/0

Use DFL NO1 6 x 10(Fb=1350 Fv=170)

Critical Shear =1500 LB @ 0.33' 1.5xShear/(FvxA)=0.281

Fv=153 A= 52.25

Crit ical Moment =6354 LBxFT @ 8.17' Ratio=0.759

Fb= 1215 S= 82.73

Critical Deflection =-0.580 Inch @ 8.08' L/280=0.696

1500

Shear Diagram:DL

6354

Moment Diagram:DL

-0.580

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 12: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 12/40

Beam ID: 12(Drop) Drop Bm @ Front of the Porch @ ELEV.BLoads (Downward +)Beam Weight 30.0 PLF from 0.0' to 14.8'

Primary Roof  140 PLF= 7.0'x(20+20)/2 @ 0.00' to 14.75'

Exterior Wall 15 PLF= 1.0'x15.0 @ 0.00' to 14.75'

14.75'

Reactions(DL+LL/Max. Load Combination)

Down 1364/1364 1364/1364

Up 0/0 0/0

Use DFL NO1 6 x 12(Fb=1350 Fv=170)

Critical Shear =1303 LB @ 0.33' 1.5xShear/(FvxA)=0.145

Fv=213 A= 63.25

Crit ical Moment =5031 LBxFT @ 7.42' Ratio=0.301

Fb= 1654 S= 121.23

Critical Deflection =-0.177 Inch @ 7.42' L/240=0.738

1303

Shear Diagram:DL RF_L

5031

Moment Diagram:DL RF_L

-0.177

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 13(Drop) Header @ Rear of the Bed #2 @ ELEV.CLoads (Downward +)Beam Weight 20.0 PLF @ 0.0' to 4.3'

Primary Roof  180 PLF= 9.0'x(20+20)/2 @ 0.00' to 3.50'

Primary Roof  700 PLF=35.0'x(20+20)/2 @ 3.50' to 4.25'

Exterior Wall 30 PLF= 2.0'x15.0 @ 0.00' to 4.25'

Point Load(P1)From left of BM GT#3 @ 3.50

:Point Load Location

P1

 3.50'

 4.25'

Reactions(DL+LL/Max. Load Combination)

Down 1238/1238 4180/4180

Up 0/0 0/0

Use DFL NO2 4 x 10(Fb= 900 Fv=180)w/ Right:2-2x4 trim./stud

Critical Shear =-3930 LB @ 3.92' 1.5xShear/(FvxA)=0.809

Fv=225 A= 32.38

Crit ical Moment =2924 LBxFT @ 3.50' Ratio=0.524

Fb= 1340 S= 49.91

Critical Deflection = -0.021 INCH @ 2.33'

-3930Shear Diagram:DL RF_L

2924

Moment Diagram:DL RF_L

-0.021

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 13: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 13/40

Beam ID: 14(Drop) Header @ Rear of the Bed #2Loads (Downward +)Beam Weight 20.0 PLF from 0.0' to 4.3'

Primary Floor  523 PLF=19.0'x(15+40)/2 @ 0.00' to 4.25'

Exterior Wall 60 PLF= 4.0'x15.0 @ 0.00' to 4.25'

Point Load(P1) From left of BM 13 @ 0.00

Point Load(P2) From right of BM 13 @ 4.25

:Point Load Location

P1 P2

 4.25'

Reactions(DL+LL/Max. Load Combination)

Down 2518/2190 5460/4818

Up 0/0 0/0

Use DFL NO2 4 x 6(Fb= 900 Fv=180)w/ Right:2-2x4 trim./stud

Critical Shear =1079 LB @ 0.33' 1.5xShear/(FvxA)=0.467

Fv=180 A= 19.25

Crit ical Moment =1360 LBxFT @ 2.17' Ratio=0.793

Fb= 1166 S= 17.65

Critical Deflection = -0.036 INCH @ 2.08'

1079

Shear Diagram:DL FL_L

1360

Moment Diagram:DL FL_L

-0.036

Deflection Diagram:LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 16 Header @ Rear of the Bed #4Loads (Downward +)Beam Weight 20.0 PLF from 0.0' to 5.5'

Exterior Wall 150 PLF=10.0'x15.0 @ 0.00' to 5.50'

Primary Floor  523 PLF=19.0'x(15+40)/2 @ 0.00' to 5.50'

Point Load(P1) From left of BM 13 @ 0.50

Point Load(P2)From right of BM 13 @ 5.00

Primary Roof  200 PLF=10.0'x(20+20)/2 @ 0.00' to 0.50'

Primary Roof  720 PLF=36.0'x(20+20)/2 @ 5.00' to 5.50'

:Point Load Location

P1

 0.50'

P2

 5.00'

 5.50'

Reactions(DL+LL/Max. Load Combination)

Down 3521/3091 6165/5449

Up 0/0 0/0

Use DFL NO2 4 x 12(Fb= 900 Fv=180)w/ Right:4x4 post

Critical Shear =-5040 LB @ 5.17' 1.5xShear/(FvxA)=0.853

Fv=225 A= 39.38

Crit ical Moment =3454 LBxFT @ 3.00' Ratio=0.567

Fb= 990 S= 73.83Critical Deflection = -0.035 INCH @ 2.83'

-5040Shear Diagram:DL 0.75xFL 0.75xRl

3454

Moment Diagram:DL FL_L

-0.035

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 14: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 14/40

Beam ID: 15(Drop) Header @ Left of the Living Room 2 OPT.Loads (Downward +)Beam Weight 20.0 PLF @ 0.0' to 2.8'

Point Load(P1) From left of BM 7 @ 1.00

Exterior Wall 30 PLF= 2.0'x15.0 @ 0.00' to 2.75'

Primary Floor  55 PLF= 2.0'x(15+40)/2 @ 0.00' to 2.75'

:Point Load Location

P1

 1.00'

 2.75'

Reactions(DL+LL/Max. Load Combination)Down 4553/4553 2663/2663

Up 0/0 0/0

Use GLB 24F V4 3 1/8 x 12(Fb=2400/1850 Fv=265)w/Left:2-2x4 trim./stud

Critical Shear =4518 LB @ 0.33' 1.5xShear/(FvxA)=0.682

Fv=265 A= 37.50

Crit ical Moment =4500 LBxFT @ 1.00' Ratio=0.303

Fb= 2374 S= 75.00

Critical Deflection = -0.004 INCH @ 1.25'

4518

Shear Diagram:DL FL_L

4500

Moment Diagram:DL FL_L

-0.004

Deflection Diagram:LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 16 Header @ Rear of the Porch @ PLAN 3CLoads (Downward +)Beam Weight 20.0 PLF from 0.0' to 5.5'

Exterior Wall 150 PLF=10.0'x15.0 @ 0.00' to 5.50'

Primary Floor  523 PLF=19.0'x(15+40)/2 @ 0.00' to 5.50'

Point Load(P1) From left of BM 13 @ 0.50

Point Load(P2) From right of BM 13 @ 5.00

Primary Roof  200 PLF=10.0'x(20+20)/2 @ 0.00' to 0.50'

Primary Roof  720 PLF=36.0'x(20+20)/2 @ 5.00' to 5.50'

:Point Load Location

P1

 0.50'

P2

 5.00'

 5.50'

Reactions(DL+LL/Max. Load Combination)

Down 3521/3091 6165/5449

Up 0/0 0/0

Use DFL NO2 4 x 12(Fb= 900 Fv=180)w/ Right:4x4 post

Critical Shear =-5040 LB @ 5.17' 1.5xShear/(FvxA)=0.853

Fv=225 A= 39.38

Crit ical Moment =3454 LBxFT @ 3.00' Ratio=0.567Fb= 990 S= 73.83

Critical Deflection = -0.035 INCH @ 2.83'

-5040Shear Diagram:DL 0.75xFL 0.75xRl

3454

Moment Diagram:DL FL_L

-0.035

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 15: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 15/40

Beam ID: 17 Header @ Rear of the Porch @ PLAN 3CLoads (Downward +)Beam Weight 20.0 PLF from 0.0' to 5.5'

Exterior Wall 150 PLF=10.0'x15.0 @ 0.00' to 5.50'

Primary Floor  523 PLF=19.0'x(15+40)/2 @ 0.00' to 5.50'

Primary Roof  720 PLF=36.0'x(20+20)/2 @ 0.00' to 5.50'

 5.50'

Reactions(DL+LL/Max. Load Combination)

Down 3884/3376 3884/3376Up 0/0 0/0

Use DFL NO2 4 x 10(Fb= 900 Fv=180)w/Left:2-2x4 trim./stud Right:2-2x4 trim./stud

Critical Shear =-2544 LB @ 5.17' 1.5xShear/(FvxA)=0.655

Fv=180 A= 32.38

Crit ical Moment =3980 LBxFT @ 2.75' Ratio=0.886

Fb= 1080 S= 49.91

Critical Deflection = -0.079 INCH @ 2.75'

-2544Shear Diagram:DL FL_L

3980

Moment Diagram:DL FL_L

-0.079

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 18(Drop) Header @ Rear of the Patio @ OPT.Loads (Downward +)Beam Weight 20.0 PLF @ 0.0' to 12.3'

Primary Roof  720 PLF=36.0'x(20+20)/2 @ 0.00' to 12.25'

Exterior Wall150 PLF=10.0'x15.0 @ 0.00' to 12.25'

Primary Floor  536 PLF=19.5'x(15+40)/2 @ 0.00' to 12.25'

12.25'

Reactions(DL+LL/Max. Load Combination)

Down 8691/7553 8691/7553

Up 0/0 0/0

Use GLB 24F V4 3 1/8 x 15(Fb=2400/1850 Fv=265)w/Left:Design trim./post Right:Design trim./post

Critical Shear =6175 LB @ 0.33' 1.5xShear/(FvxA)=0.746

Fv=265 A= 46.88

Critical Moment =20000 LBxFT @ 6.17' Ratio=1.023

Fb= 2003 S= 117.19

Critical Deflection =-0.454 Inch @ 6.08' L/280=0.525

6175

Shear Diagram:DL FL_L

20000

Moment Diagram:DL FL_L

-0.454

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 16: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 16/40

Beam ID: 19(Drop) Drop Bm @ Front of the PatioLoads (Downward +)Beam Weight 20.0 PLF @ 0.0' to 11.3'

Primary Roof  200 PLF=10.0'x(20+20)/2 @ 0.00' to 11.25'11.25'

Reactions(DL+LL/Max. Load Combination)

Down 1238/1238 1238/1238

Up 0/0 0/0

Use DFL NO1 6 x 8(Fb=1200 Fv=170)

Critical Shear =1164 LB @ 0.33' 1.5xShear/(FvxA)=0.199

Fv=213 A= 41.25

Crit ical Moment =3480 LBxFT @ 5.67' Ratio=0.544

Fb= 1489 S= 51.56

Critical Deflection =-0.256 Inch @ 5.67' L/240=0.563

1164

Shear Diagram:DL RF_L

3480

Moment Diagram:DL RF_L

-0.256

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Beam ID: 20 Drop Bm @ Left of the PatioLoads (Downward +)Beam Weight 20.0 PLF @ 0.0' to 7.3'

Primary Roof  200 PLF=10.0'x(20+20)/2 @ 0.00' to 5.50'

Primary Roof 340 PLF=17.0'x(20+20)/2 @ 5.50' to 7.25'

Point Load(P1) From left of BM GT#5 @ 5.50

:Point Load Location

P1

 5.50'

 7.25'

Reactions(DL+LL/Max. Load Combination)

Down 1237/1237 2300/2300

Up 0/0 0/0

Use DFL NO1 6 x 8(Fb=1200 Fv=170)

Critical Shear =-2180 LB @ 6.92' 1.5xShear/(FvxA)=0.373

Fv=213 A= 41.25

Crit ical Moment =3473 LBxFT @ 5.50' Ratio=0.539

Fb= 1500 S= 51.56

Critical Deflection = -0.099 INCH @ 3.83'

-2180Shear Diagram:DL RF_L

3473

Moment Diagram:DL RF_L

-0.099

Deflection Diagram:DL LL

Job : 62742-202

Plan : 3

IBC9.7

Page 17: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 17/40

Page 18: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 18/40

Page 19: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 19/40

GOUVIS ENGINEERING CONSULTING GROUPLATERAL ANALYSIS

2010 CBC

POURING MONO

SHEET : L - 1

 JOB NO. : 62742

CLIENT : Pardee Homes

PLAN NO. : 3

DATE : 8/21/2012(Ver

Y DIRECTION SECTION 1Y

BLDG DIMENSION (FT): BASE HT=0.5, SLOPE ROOF HT=25.0, GABLE MEAN ROOF HT=23.0, L=56.0, B=48.0FLOOR HT (FT):  1-FLR=9.0, 2-FLR=19.3WIND PARAMETERS:  WIND SPEED=85 MPH, WIND EXPOSURE=CCOEFFICIENTS: Kd=0.85, Kzt=1.00, G=0.85, GCpi=  0.18, =1.00INTERPOLATION: L/B  YES, h/L  YES,  YES, qh=14.47WIND HEIGHT (FT): 15 20 25 30 UPLIFT (AVE.)WALL PRESSURE P (PSF): 14.81 15.38 15.84 16.24 9.37ROOF: 48.00(WW)/17.00/18.43, 48.00(LW)/17.00/18.43; OVERHANGS: 48.00/2.00WIND LOAD ROOF (PLF): MINIMUM LOAD=(10*5.75*1.00)+70.51=128.01WIND LOAD FLOOR (PLF): 1-FLR=150.68 MAX TOTAL=278.69Ry= 6.5, SITE CLASS: D, SDS=2FaSs/3=2x1.00x1.50/3=1.000, SD1=2FvS1/3=2x1.50x0.60/3=0.600, SDC=D, k=1.0000V=SDSIW/1.4Ry=(1.000)(1.00)W/(1.4*6.5)= 0.1099WROOF: DL ROOF = 20.0x36.0 = 720.00 PLF

DL EXT WALL = 15.0[2.0(19.25-14.63)] = 138.75 PLFDL INT WALL = 10.0[2.0(19.25-14.63)] = 92.50 PLFSHEAR = 0.1099(720.00+138.75+92.50) = 0.1099(951.25) = 104.53 PLF 

1-FLR: DL FLOOR = 15.0x34.0 = 510.00 PLFDL EXT WALL = 15.0[2.0(14.63-10.00)+2.0(9.00-4.50)] = 273.75 PLFDL INT WALL = 10.0[2.0(14.63-10.00)+1.0(9.00-4.50)] = 137.50 PLFSHEAR = 0.1099(510.00+273.75+137.50) = 0.1099(921.25) = 101.24 PLF 

TOTAL SEISMIC LOAD = 104.53+101.24 = 205.77 PLF REDISTRIB.: 951.3x19.3+921.3x9.0 = 26602.8SHEAR ROOF = 205.77 x 951.25 x 19.25 / 26602.81 = 141.64 PLF (141.64 PLF)SHEAR 1-FLR = 205.77 x 921.25 x 9.00 / 26602.81 = 64.13 PLF (131.61 PLF)

ROOF : 141.64 PLF SEISMIC GOVERN (DIAPH.ONLY)1-FLR: 278.69 PLF WIND GOVERN

ROOF DIAPHRAGM V = 141.64 = 141.64 PLFMAX SHEAR = 141.64 x 48.00 / (2 x 34.00) = 99.98 PLFUSE: 15/32" CDX RATED UNBLKED 32/16 W/8d COMMON NAILS AT 6", 6", 12" O.C.CHORD FORCE = 141.64 x 48.00 x 48.00 / (8 x 34.00) = 1199.75 LBSUSE 8 - 16d SINKER NAILS MINIMUM BETWEEN SPLICE POINTS1-FLR DIAPHRAGM V = 150.68 PLF ALIGNMAX SHEAR = 150.68 x 48.00 / (2 x 34.00) = 106.36 PLFUSE: 23/32" CDX RATED UNBLKED W/10d COMMON NAILS AT 6", 6", 12" O.C.CHORD FORCE = 150.68 x 48.00 x 48.00 / (8 x 34.00) = 1276.33 LBS

USE 8 - 16d SINKER NAILS MINIMUM BETWEEN SPLICE POINTS

Page 20: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 20/40

GOUVIS ENGINEERING CONSULTING GROUPLATERAL ANALYSIS

2010 CBC

POURING MONO

SHEET : L - 2

 JOB NO. : 62742

CLIENT : Pardee Homes

PLAN NO. : 3

DATE : 8/21/2012(Ver

Y DIRECTION SECTION 2Y

BLDG DIMENSION (FT): BASE HT=0.5, SLOPE ROOF HT=22.5, GABLE MEAN ROOF HT=21.5, L=56.0, B=48.0FLOOR HT (FT):  1-FLR=9.0, 2-FLR=19.3WIND PARAMETERS:  WIND SPEED=85 MPH, WIND EXPOSURE=CCOEFFICIENTS: Kd=0.85, Kzt=1.00, G=0.85, GCpi=  0.18, =1.00INTERPOLATION: L/B  YES, h/L  YES,  YES, qh=14.47WIND HEIGHT (FT): 15 20 25 UPLIFT (AVE.)WALL PRESSURE P (PSF): 14.81 15.38 15.84 6.51ROOF: 20.00(WW)/10.50/18.43; OVERHANGS: 30.50/1.00GABLE: 20.50(LW)/10.50WIND LOAD ROOF (PLF): +Y/+GCpi=51.61(R)  +Y/-GCpi=54.78(R)  -Y/+GCpi=74.86(R)  -Y/-GCpi=71.69(R)WIND LOAD FLOOR (PLF): 1-FLR=92.58(R) MAX TOTAL=167.44Ry= 6.5, SITE CLASS: D, SDS=2FaSs/3=2x1.00x1.50/3=1.000, SD1=2FvS1/3=2x1.50x0.60/3=0.600, SDC=D, k=1.0000V=SDSIW/1.4Ry=(1.000)(1.00)W/(1.4*6.5)= 0.1099WROOF: DL ROOF = 20.0x21.8 = 435.00 PLF

DL EXT WALL = 15.0[2.0(19.25-14.63)] = 138.75 PLFDL INT WALL = 10.0[1.0(19.25-14.63)] = 46.25 PLFSHEAR = 0.1099(435.00+138.75+46.25) = 0.1099(620.00) = 68.13 PLF 

1-FLR: DL FLOOR = 15.0x21.8 = 326.25 PLFDL EXT WALL = 15.0[2.0(14.63-10.00)+2.0(9.00-4.50)] = 273.75 PLFDL INT WALL = 10.0[1.0(14.63-10.00)+0.0(9.00-4.50)] = 46.25 PLF

SHEAR = 0.1099(326.25+273.75+46.25) = 0.1099(646.25) = 71.02 PLF TOTAL SEISMIC LOAD = 68.13+71.02 = 139.15 PLF REDISTRIB.: 620.0x19.3+646.3x9.0 = 17751.3SHEAR ROOF = 139.15 x 620.00 x 19.25 / 17751.25 = 93.56 PLF (93.56 PLF)SHEAR 1-FLR = 139.15 x 646.25 x 9.00 / 17751.25 = 45.59 PLF (92.32 PLF)

ROOF : 93.56 PLF SEISMIC GOVERN (DIAPH.ONLY)1-FLR: 167.44 PLF WIND GOVERN

ROOF DIAPHRAGM V = 93.56 = 93.56 PLFMAX SHEAR = 93.56 x 20.00 / (2 x 21.75) = 43.01 PLFUSE: 15/32" CDX RATED UNBLKED 32/16 W/8d COMMON NAILS AT 6", 6", 12" O.C.CHORD FORCE = 93.56 x 20.00 x 20.00 / (8 x 21.75) = 215.07 LBSSPLICE W/ MINI (5)16d SINKER NAILS EACH SIDE OF SPLICE @ 8 IN. O.C. (STANDARD CONSTRUCTION)1-FLR DIAPHRAGM V = 92.58 PLF ALIGNMAX SHEAR = 92.58 x 30.50 / (2 x 21.75) = 64.91 PLFUSE: 23/32" CDX RATED UNBLKED W/10d COMMON NAILS AT 6", 6", 12" O.C.

CHORD FORCE = 92.58 x 30.50 x 30.50 / (8 x 21.75) = 494.94 LBSSPLICE W/ MINI (5)16d SINKER NAILS EACH SIDE OF SPLICE @ 8 IN. O.C. (STANDARD CONSTRUCTION)

Page 21: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 21/40

GOUVIS ENGINEERING CONSULTING GROUPLATERAL ANALYSIS

2010 CBC

POURING MONO

SHEET : L - 3

 JOB NO. : 62742

CLIENT : Pardee Homes

PLAN NO. : 3

DATE : 8/21/2012(Ver

X DIRECTION SECTION 1X

BLDG DIMENSION (FT): BASE HT=0.5, SLOPE ROOF HT=25.0, GABLE MEAN ROOF HT=23.0, L=48.0, B=56.0FLOOR HT (FT):  1-FLR=9.0, 2-FLR=19.3WIND PARAMETERS:  WIND SPEED=85 MPH, WIND EXPOSURE=CCOEFFICIENTS: Kd=0.85, Kzt=1.00, G=0.85, GCpi=  0.18, =1.00INTERPOLATION: L/B  YES, h/L  YES,  YES, qh=14.47WIND HEIGHT (FT): 15 20 25 30 UPLIFT (AVE.)WALL PRESSURE P (PSF): 15.22 15.79 16.25 16.65 6.05OVERHANGS: 34.00/2.003.00/2.00GABLE: 34.00(LW)/24.00WIND LOAD ROOF (PLF): +X/+GCpi=105.23  +X/-GCpi=85.70  -X/+GCpi=99.53  -X/-GCpi=119.06WIND LOAD FLOOR (PLF): 1-FLR=154.83 MAX TOTAL=273.89Rx= 6.5, SITE CLASS: D, SDS=2FaSs/3=2x1.00x1.50/3=1.000, SD1=2FvS1/3=2x1.50x0.60/3=0.600, SDC=D, k=1.0000V=SDSIW/1.4Rx=(1.000)(1.00)W/(1.4*6.5)= 0.1099WROOF: DL ROOF = 20.0x49.0 = 980.00 PLF

DL EXT WALL = 15.0[2.0(19.25-14.63)] = 138.75 PLFDL INT WALL = 10.0[2.0(19.25-14.63)] = 92.50 PLFSHEAR = 0.1099(980.00+138.75+92.50) = 0.1099(1211.25) = 133.10 PLF 

1-FLR: DL FLOOR = 15.0x48.0 = 720.00 PLFDL EXT WALL = 15.0[2.0(14.63-10.00)+2.0(9.00-4.50)] = 273.75 PLFDL INT WALL = 10.0[2.0(14.63-10.00)+1.5(9.00-4.50)] = 160.00 PLF

SHEAR = 0.1099(720.00+273.75+160.00) = 0.1099(1153.75) = 126.79 PLF TOTAL SEISMIC LOAD = 133.10+126.79 = 259.89 PLF REDISTRIB.: 1211.3x19.3+1153.8x9.0 = 33700.3SHEAR ROOF = 259.89 x 1211.25 x 19.25 / 33700.31 = 179.81 PLF (179.81 PLF)SHEAR 1-FLR = 259.89 x 1153.75 x 9.00 / 33700.31 = 80.08 PLF (164.82 PLF)

ROOF : 179.81 PLF SEISMIC GOVERN (DIAPH.ONLY)1-FLR: 273.89 PLF WIND GOVERN

ROOF DIAPHRAGM V = 179.81 = 179.81 PLFMAX SHEAR = 179.81 x 34.25 / (2 x 48.00) = 64.15 PLFUSE: 15/32" CDX RATED UNBLKED 32/16 W/8d COMMON NAILS AT 6", 6", 12" O.C.CHORD FORCE = 179.81 x 34.25 x 34.25 / (8 x 48.00) = 549.30 LBSSPLICE W/ MINI (5)16d SINKER NAILS EACH SIDE OF SPLICE @ 8 IN. O.C. (STANDARD CONSTRUCTION)1-FLR DIAPHRAGM V = 164.82 PLF ALIGNMAX SHEAR = 164.82 x 34.25 / (2 x 48.00) = 58.80 PLFUSE: 23/32" CDX RATED UNBLKED W/10d COMMON NAILS AT 6", 6", 12" O.C.

CHORD FORCE = 164.82 x 34.25 x 34.25 / (8 x 48.00) = 503.50 LBSSPLICE W/ MINI (5)16d SINKER NAILS EACH SIDE OF SPLICE @ 8 IN. O.C. (STANDARD CONSTRUCTION)

Page 22: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 22/40

GOUVIS ENGINEERING CONSULTING GROUPLATERAL ANALYSIS

2010 CBC

POURING MONO

SHEET : L - 4

 JOB NO. : 62742

CLIENT : Pardee Homes

PLAN NO. : 3

DATE : 8/21/2012(Ver

X DIRECTION SECTION 2X

BLDG DIMENSION (FT): BASE HT=0.5, SLOPE ROOF HT=22.5, GABLE MEAN ROOF HT=21.5, L=48.0, B=56.0FLOOR HT (FT):  1-FLR=9.0, 2-FLR=19.3WIND PARAMETERS:  WIND SPEED=85 MPH, WIND EXPOSURE=CCOEFFICIENTS: Kd=0.85, Kzt=1.00, G=0.85, GCpi=  0.18, =1.00INTERPOLATION: L/B  YES, h/L  YES,  YES, qh=14.47WIND HEIGHT (FT): 15 20 25 UPLIFT (AVE.)WALL PRESSURE P (PSF): 15.22 15.79 16.25 6.59ROOF: 21.75(WW)/10.25/18.43, 21.75(LW)/10.25/18.43; OVERHANGS: 21.75/2.00WIND LOAD ROOF (PLF): MINIMUM LOAD=(10*3.25*1.00)+72.41=104.91WIND LOAD FLOOR (PLF): 1-FLR=154.83 MAX TOTAL=259.74Rx= 6.5, SITE CLASS: D, SDS=2FaSs/3=2x1.00x1.50/3=1.000, SD1=2FvS1/3=2x1.50x0.60/3=0.600, SDC=D, k=1.0000V=SDSIW/1.4Rx=(1.000)(1.00)W/(1.4*6.5)= 0.1099WROOF: DL ROOF = 20.0x22.5 = 450.00 PLF

DL EXT WALL = 15.0[2.0(19.25-14.63)] = 138.75 PLFSHEAR = 0.1099(450.00+138.75) = 0.1099(588.75) = 64.70 PLF 

1-FLR: DL ROOF = 20.0x10.5 = 210.00 PLFDL FLOOR = 15.0x20.5 = 307.50 PLFDL EXT WALL = 15.0[2.0(14.63-10.00)+2.0(9.00-4.50)] = 273.75 PLFSHEAR = 0.1099(210.00+307.50+273.75) = 0.1099(791.25) = 86.95 PLF 

TOTAL SEISMIC LOAD = 64.70+86.95 = 151.65 PLF 

REDISTRIB.: 588.8x19.3+791.3x9.0 = 18454.7SHEAR ROOF = 151.65 x 588.75 x 19.25 / 18454.69 = 93.13 PLF (93.13 PLF)SHEAR 1-FLR = 151.65 x 791.25 x 9.00 / 18454.69 = 58.52 PLF (113.04 PLF)

ROOF : 104.91 PLF WIND GOVERN (DIAPH.ONLY)1-FLR: 259.74 PLF WIND GOVERN

ROOF DIAPHRAGM V = 104.91 = 104.91 PLFMAX SHEAR = 104.91 x 21.75 / (2 x 20.50) = 55.65 PLFUSE: 15/32" CDX RATED UNBLKED 32/16 W/8d COMMON NAILS AT 6", 6", 12" O.C.CHORD FORCE = 104.91 x 21.75 x 21.75 / (8 x 20.50) = 302.61 LBSSPLICE W/ MINI (5)16d SINKER NAILS EACH SIDE OF SPLICE @ 8 IN. O.C. (STANDARD CONSTRUCTION)1-FLR DIAPHRAGM V = 154.83 PLF ALIGNMAX SHEAR = 154.83 x 21.75 / (2 x 31.00) = 54.31 PLFUSE: 23/32" CDX RATED UNBLKED W/10d COMMON NAILS AT 6", 6", 12" O.C.CHORD FORCE = 154.83 x 21.75 x 21.75 / (8 x 31.00) = 295.34 LBSSPLICE W/ MINI (5)16d SINKER NAILS EACH SIDE OF SPLICE @ 8 IN. O.C. (STANDARD CONSTRUCTION)

Page 23: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 23/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 3072 Seismic: 3399

1Y_ROOF

wind

seismic

 128.0

 141.6

| 48.0

1 @Left of Elevation 2ND Floor Exterior Wall(Y Dir.)

Wind 3072(Uplift on Roof=7.4 PSF)Seismic 3597= 3399+ 198

1.5 2.5 5.8 2.5 2.3 4.5 8.0

 A

 2.8 2.5 1.8

 9.0

Strap(E)

 0.0

 A

11.3

B

19.0

 2010

27.0

  741

 A

34.034.0

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate spliceTotal Wall Length = 34.00(FT) Total Panel Length = 8.00(FT)Shear Diaphragm = 3597/ 34.00 = 106(PLF) = 1.00Use (9 A35) or (6 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) = 3597/ 8.00= 450(PLF)(Flexible ) Max. Drag = 2010(LB)

Use TYPE 3

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.192" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'

OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 3953(LB) C= 4200(LB) (2)CS14/(2)2x4 ****

Right Side : T= 3953(LB) C= 4200(LB) (2)CS14/(2)2x4 ****

Use (2)CS14/(2)2x4 on both ends

**** Plywood shear wall to be nailed to all studs receiving holdowns

Page 24: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 24/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 749 Seismic: 936

2Y_ROOF

wind

seismic

  74.9

  93.6

| 20.0

2 @Left of Family Room 2ND Floor Exterior Wall(Y Dir.)

Wind 749(Uplift on Roof=8.5 PSF)Seismic 1045= 936+ 109

0.5 4.5 3.8 2.5 4.0

 A

 1.0 2.5 1.5

 9.0

Strap(E)

 0.0

 A

11.2

  580

15.3

  258

 A

20.320.3

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceTotal Wall Length = 20.25(FT) Total Panel Length = 4.00(FT)Shear Diaphragm = 1045/ 20.25 = 52(PLF) = 1.00Use (3 A35) or (2 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) = 1045/ 4.00= 261(PLF)(Flexible ,SW V_allow(Seismic) Ajusted for H/W Ratio) Max. Drag = 580(LB)

Use TYPE 2

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.052" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'Roof_P 210.0= 20 *21.0/2 FROM 0.0' TO 20.3'

OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 2220(LB) C= 2676(LB) (2)CS16/(2)2x4 ****

Right Side : T= 2220(LB) C= 2676(LB) (2)CS16/(2)2x4 ****

Use (2)CS16/(2)2x4 on both ends

**** Plywood shear wall to be nailed to all studs receiving holdowns

Page 25: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 25/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 749 Seismic: 936

2Y_ROOF

wind

seismic

  74.9

  93.6

| 20.0

3 @Right of Family Room 2ND Floor Exterior Wall(Y Dir.)

Wind 749(Uplift on Roof=8.5 PSF)Seismic 1056= 936+ 120

1.5 2.5 1 .0 4.0

 A

 2.5 5.0 2.5 1.5

 9.0

Strap(E)

 0.0

 A

 5.0

  257

 9.0

  592

 A

20.5

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceTotal Wall Length = 20.50(FT) Total Panel Length = 4.00(FT)Shear Diaphragm = 1056/ 20.50 = 51(PLF) = 1.00Use (3 A35) or (2 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) = 1056/ 4.00= 264(PLF)(Flexible ,SW V_allow(Seismic) Ajusted for H/W Ratio) Max. Drag = 592(LB)

Use TYPE 2

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.063" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'Roof_P 210.0= 20 *21.0/2 FROM 0.0' TO 20.5'

OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 2247(LB) C= 2702(LB) (2)CS16/(2)2x4 ****

Right Side : T= 2247(LB) C= 2702(LB) (2)CS16/(2)2x4 ****

Use (2)CS16/(2)2x4 on both ends

**** Plywood shear wall to be nailed to all studs receiving holdowns

Page 26: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 26/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 3072 Seismic: 3399

1Y_ROOF

wind

seismic

 128.0

 141.6

| 48.0

4 @Right of Elevation 2ND Floor Exterior Wall(Y Dir.)

Wind 3072(Uplift on Roof=8.5 PSF)Seismic 3603= 3399+ 204

1.0 2.5 2.8 2.3 2.8 2.3 0.5 7.5

 A

 5.5 2.5 3.5

 9.0

Strap(E)

 0.0

 A

10.9

B

14.0

 1529

21.5

 1256

22.1

 AB

33.033.0

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate spliceTotal Wall Length = 33.00(FT) Total Panel Length = 7.50(FT)Shear Diaphragm = 3603/ 33.00 = 109(PLF) = 1.00Use (9 A35) or (7 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) = 3603/ 7.50= 480(PLF)(Flexible ) Max. Drag = 1529(LB)

Use TYPE 3

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.296" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'

OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 4267(LB) C= 4498(LB) (2)CS14/(2)2x4 ****

Right Side : T= 4267(LB) C= 4498(LB) (2)CS14/(2)2x4 ****

Use (2)CS14/(2)2x4 on both ends

**** Plywood shear wall to be nailed to all studs receiving holdowns

Page 27: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 27/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 3616 Seismic: 1539

1Y_1_FL

wind

seismic

 150.7

  64.1

| 48.0

Load 1 @ 0.0' Start 0.0' to 34.0'(100%)

5 @Left of Elevation 1ST Floor 1-Pour Exterior Wall(Y Dir.)

Wind 6689Seismic 5521= 5334+ 187

1.5 2.8 9.5

 A

 5.0 2.0 2.5 5.5

B

 3.0 1.5

 9.0

Strap(E) HD Panel Edge on the above Story MIN. 4x Post E.N. @ 3" O/C May Needed

 0.0

 A

 4.2

  855

13.7

 1470

15.1

 AB

23.3

  441

28.8

  905

 A

33.333.3

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate spliceTotal Wall Length = 33.25(FT) Total Panel Length = 15.00(FT)

Shear Diaphragm = 6689/ 33.25 = 201(PLF) = 1.00Use (16 A35) or (12 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(W) = 6689/15.00= 446(PLF)(Flexible ) Max. Drag = 1470(LB)

Use TYPE 3

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.747" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'

Load 1 @ 0.0' Start 0.0' to 34.0'(100%)OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 3407(LB) C= 4230(LB) STHD14/4x4

  T= 3351(LB) C= 4230(LB) ** STHD10/4x4Right Side : T= 3459(LB) C= 4230(LB) STHD14/4x4

  T= 3342(LB) C= 4230(LB) ** STHD10/4x4

Use STHD14/4x4 on both ends or Use STHD10/4x4** on both ends

w/(3)5/8" x 12" Anchor Bo lt (@ 40" O.C. Max.)Panel B Left Side : T= 2741(LB) C= 4414(LB) STHD10/4x4

Right Side : T= 6304(LB) C= 4328(LB) HDU8/4x4(I) w/DBL BLK'G

Use STHD10/4x4 @ L. & HDU8/4x4(I) @ R.w/(2)5/8" x 12" Anchor Bo lt (@ 40" O.C. Max.)

For Grade Beam, Add (1)#4 Top & Bottom, 4' Past Panel Each End

** w/ Dead loads of adjacent element, use detail for connection of S.W. to trimmer 

(I) Holdown inside of panel

Page 28: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 28/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 3616 Seismic: 1539

1Y_1_FL

wind

seismic

 150.7

  64.1

| 48.0

Load 1 @ 0.0' Start 0.0' to 34.0'(100%)

5XA @Left of Elevation 1ST Floor 1-Pour Exterior Wall(Y Dir.)

Wind 6689Seismic 5524= 5334+ 190

1.8 2.3 9.8

 A

 5.3 4.0

B

 2.3 4.3 9.8

 9.0

Strap(E) HD Panel Edge on the above Story MIN. 4x Post E.N. @ 3" O/C May Needed

 0.0

 A

 4.0

  682

13.7

 2400

15.3

BC

19.0

 1505

23.0

 2769

C

26.7

B

32.3

 A

39.339.3

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate spliceC: Simpson ST6236(3230 LB) ALT (22) # 16d sinker per top plate spliceTotal Wall Length = 39.25(FT) Total Panel Length = 13.75(FT)Shear Diaphragm = 6689/ 39.25 = 170(PLF) = 1.00

Use (16 A35) or (12 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(W) = 6689/13.75= 486(PLF)(Flexible ,SW V_allow(Seismic) Ajusted for H/W Ratio) Max. Drag = 2769(LB)

Use TYPE 3

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.965" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'

Load 1 @ 0.0' Start 0.0' to 34.0'(100%)OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 3719(LB) C= 4669(LB) STHD14/4x4

Right Side : T= 3812(LB) C= 4603(LB) STHD14/4x4

Use STHD14/4x4 on both endsw/(4)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)

Panel B Left Side : T= 8042(LB) C= 9203(LB) HDQ8/(3)2x4(I) w/DBL BLK'G ****

Right Side : T= 4832(LB) C= 5003(LB) HDU8/4x4(I) w/DBL BLK'GUse HDQ8/(3)2x4(I) @ L. & HDU8/4x4(I) @ R.w/(2)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)

For Grade Beam, Add (1)#4 Top & Bottom, 4' Past Panel Each End

(I) Holdown inside of panel

**** Plywood shear wall to be nailed to all studs receiving holdowns

Page 29: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 29/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 1412 Seismic: 695

2Y_1_FL

wind

seismic

  92.6

  45.6

| 30.5

Load 2 @ 0.0' Start 0.0' to 20.3'(100%)

Load 3 (30%)

6 @Left of Garage 1ST Floor 1-Pour Exterior Wall(Y Dir.)

Wind 2385Seismic 2413= 2259+ 154

7.3 8.0

 A

 5.5

 9.0

Strap(E) Panel Edge on the above Story MIN. 4x Post E.N. @ 3" O/C May Needed

 0.0

 A

 7.2

  843

15.2

  640

 A

20.720.7

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceTotal Wall Length = 20.75(FT) Total Panel Length = 8.00(FT)Shear Diaphragm = 2413/ 20.75 = 116(PLF) = 1.00Use (6 A35) or (5 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) = 2413/ 8.00= 302(PLF)(Flexible ) Max. Drag = 843(LB)

Use TYPE 2

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.744" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'

Load 2 @ 0.0' Start 0.0' to 20.3'(100%)Load 3 (30%)OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 3257(LB) C= 3048(LB) STHD10/4x4

Right Side : T= 3233(LB) C= 5493(LB) STHD10/4x4

Use STHD10/4x4 on both endsw/(2)5/8" x 12" Anchor Bo lt (@ 48" O.C. Max.)

Page 30: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 30/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 3616 Seismic: 1539

1Y_1_FL

wind

seismic

 150.7

  64.1

| 48.0

Wind: 0 Seismic: 695

2Y_1_FL

wind

seismic

  0.0

  45.6

| 30.5

Load 4 @ 0.0' Start 0.0' to 33.3'(100%)

Load 3 (70%)

7 @Right of Elevation 1ST Floor 1-Pour Exterior Wall(Y Dir.)

Wind 7213Seismic 7425= 7074+ 352

7.3 4.0 10.3

 A

 6.5 9.0 3.0 8.0

B

 8.5

 9.0

Strap(E) HD Panel Edge on the above Story MIN. 4x Post E.N. @ 3" O/C May Needed

 0.0

 A

 9.1

B

11.3

 1479

21.5

 1345

22.7

 AB

40.0

 1087

48.0

 1117

 A

56.5

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate spliceTotal Wall Length = 56.50(FT) Total Panel Length = 18.25(FT)Shear Diaphragm = 7425/ 56.50 = 131(PLF) = 1.00Use (18 A35) or (13 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) =4498/ 9.00= 500(PLF)(Up_Floor ) Max. Drag = 1479(LB)

Use TYPE 4

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.442" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'

Load 4 @ 0.0' Start 0.0' to 33.3'(100%)Load 3 (70%)OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 6718(LB) C= 4062(LB) HDU8/4x4(I) w/DBL BLK'G

Right Side : T= 6653(LB) C= 8495(LB) HDU8/4x6(I) w/DBL BLK'G

Use HDU8/4x4(I) @ L. & HDU8/4x6(I) @ R.w/(4)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)

For Grade Beam, Add (1)#4 Top & Bottom, 4' Past Panel Each EndPanel B Left Side : T= 3554(LB) C= 3800(LB) STHD14/4x4

Right Side : T= 3554(LB) C= 3800(LB) STHD14/4x4

Use STHD14/4x4 on both endsw/(3)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)

Page 31: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 31/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 2039 Seismic: 3079

1X_ROOF

wind

seismic

 119.1

 179.8

| 34.3

8 @Rear of Elevation 2ND Floor Exterior Wall(X Dir.)

Wind 2039(Uplift on Roof=7.4 PSF)Seismic 3334= 3079+ 254

4.0 4.5 0.5 10.0

 A

 6.5 0.3 6.5 9.5 4.5 1.5

 9.0

Strap(E)

 0.0

 A

 9.0

  628

19.0

 2007

B

30.7

 A

47.8

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate spliceTotal Wall Length = 47.75(FT) Total Panel Length = 10.00(FT)Shear Diaphragm = 3334/ 47.75 = 70(PLF) = 1.00Use (8 A35) or (6 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) = 3334/10.00= 333(PLF)(Flexible ) Max. Drag = 2007(LB)

Use TYPE 2

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.053" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'Roof_P 350.0= 20 *35.0/2 FROM 0.0' TO 47.8'

OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 1982(LB) C= 3324(LB) (2)CS16/(2)2x4 ****

Right Side : T= 1982(LB) C= 3324(LB) (2)CS16/(2)2x4 ****  T= 1462(LB) C= 3324(LB) ** CS16/4x4

Use (2)CS16/(2)2x4 on both ends or Use (2)CS16/(2)2x4 @ L. & CS16/4x4** @ R.

** w/ Dead loads of adjacent element, use detail for connection of S.W. to trimmer 

**** Plywood shear wall to be nailed to all studs receiving holdowns

Page 32: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 32/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 2039 Seismic: 3079

1X_ROOF

wind

seismic

 119.1

 179.8

| 34.3

Wind: 1141 Seismic: 1013

2X_ROOF

wind

seismic

 104.9

  93.1

| 21.8

9 @Front of Bed #3 2ND Floor Exterior Wall(X Dir.)

Wind 3180(Uplift on Roof=7.4 PSF)Seismic 4411= 4092+ 319

4.0

 A

 4.5 4.0

B

 0.5 2.5 24.3 2.5 5.8

C

 9.0

Strap(E) Blocked Opening Use on BOT(/TOP) of Opening See Detail on PlansTYPE 3

0.0 12.5

 1418

B

15.0

 A

40.9

B

42.2

 1316

48.0

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate splice

See Detail Information on Next Page

Page 33: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 33/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

9Total Wall Length = 48.00(FT) Total Panel Length = 13.75(FT)Shear Diaphragm = 4411/ 48.00 = 92(PLF) = 1.00Use (11 A35) or (8 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S)=436(PLF)(on Opening A & B ) Max. Drag= 1418(LB)

Use TYPE 3

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 0.939" <= 0.02 x 108.0 = 2.160"

Dead Loads:Wall 135.0= 15 * 9.0'Roof_P 350.0= 20 *35.0/2 FROM 0.0' TO 47.3'

OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 576(LB) C= 2423(LB) CS16/2x4

Right Side : T= 0(LB) C= 0(LB) No Sign. Uplift()Use CS16/2x4 @ L.

Blocked! Force @ Edge of Opening is 982(LB)Panel B Left Side : T= 0(LB) C= 0(LB) No Sign. Uplift()

Right Side : T= 576(LB) C= 2423(LB) CS16/2x4

Use CS16/2x4 @ R.

Panel C Left Side : T= 2412(LB) C= 3275(LB) (2)CS16/(2)2x4 ****Right Side : T= 2517(LB) C= 3041(LB) (2)CS16/(2)2x4 ****

Use (2)CS16/(2)2x4 on both ends

**** Plywood shear wall to be nailed to all studs receiving holdowns

Page 34: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 34/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 1141 Seismic: 1013

2X_ROOF

wind

seismic

 104.9

  93.1

| 21.8

10 @Front of Elevation 2ND Floor Exterior Wall(X Dir.)

Wind 1141(Uplift on Roof=7.4 PSF)Seismic 1118= 1013+ 105

5.3 4.3 0.3 4.5 1.3 4.0

 A

 9.0

Strap(E)

 0.0

 A

15.5

  907

19.5Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceTotal Wall Length = 19.50(FT) Total Panel Length = 4.00(FT)Shear Diaphragm = 1141/ 19.50 = 59(PLF) = 1.00Use (3 A35) or (2 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) = 1118/ 4.00= 279(PLF)(Flexible ,SW V_allow(Seismic) Ajusted for H/W Ratio) Max. Drag = 907(LB)

Use TYPE 2

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.146" <= 0.02 x 108.0 = 2.160"Dead Loads:

Wall 135.0= 15 * 9.0'OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 2607(LB) C= 2769(LB) (2)CS16/(2)2x4 ****

Right Side : T= 2607(LB) C= 2769(LB) (2)CS16/(2)2x4 ****

Use (2)CS16/(2)2x4 on both ends

**** Plywood shear wall to be nailed to all studs receiving holdowns

Page 35: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 35/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 2651 Seismic: 1371

1X_1_FL

wind

seismic

 154.8

  80.1

| 34.3

Load 8 @ 0.0' Start 0.0' to 47.8'(100%)

11 @Rear of Elevation 1ST Floor 1-Pour Exterior Wall(X Dir.)

Wind 4690Seismic 5170= 4960+ 210

3.5 5.5 10.0

 A

 6.5 0.3 6.5 3.3 7.8 4.0

B

 0.8

 9.0

Strap(E) HD Panel Edge on the above Story MIN. 4x Post E.N. @ 3" O/C May Needed

 0.0

 A

 9.0

  969

19.0

 1646

23.2

 AB

43.2

  965

47.2

  81

 A

48.048.0

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate spliceTotal Wall Length = 48.00(FT) Total Panel Length = 14.00(FT)

Shear Diaphragm = 5170/ 48.00 = 108(PLF) = 1.00Use (13 A35) or (9 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) = 5170/14.00= 369(PLF)(Flexible ,SW V_allow(Seismic) Ajusted for H/W Ratio) Max. Drag = 1646(LB)

Use TYPE 3

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 2.119" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'Floor_P 146.3= 15 *19.5/2 FROM 0.0' TO 47.8'

Load 8 @ 0.0' Start 0.0' to 47.8'(100%)OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 4124(LB) C= 6920(LB) ** HDU8/4x4(I) w/DBL BLK'G

Right Side : T= 4018(LB) C= 7153(LB) ** HDU8/4x4(I) w/DBL BLK'G

Use HDU8/4x4(I)** on both ends

w/(3)5/8" x 12" Anchor Bol t (@ 40" O.C. Max.)Panel B Left Side : T= 3409(LB) C= 3896(LB) HTT5/4x4(I) w/DBL BLK'G  T= 2043(LB) C= 3896(LB) ** STHD10/4x4

Right Side : T= 3036(LB) C= 4219(LB) HTT5/4x4(I) w/DBL BLK'G  T= 3036(LB) C= 4006(LB) HTT5/4x4(I) w/DBL BLK'G

Use HTT5/4x4(I) on both ends or Use STHD10/4x4** @ L. & HTT5/4x4(I) @ R.w/(2)5/8" x 12" Anchor Bo lt (@ 40" O.C. Max.)

** w/ Dead loads of adjacent element, use detail for connection of S.W. to trimmer 

(I) Holdown inside of panel

Page 36: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 36/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 2632 Seismic: 1361

1X_1_FL

wind

seismic

 154.8

  80.1

| 34.0

Wind: 1684 Seismic: 636

2X_1_FL

wind

seismic

 154.8

  58.5

| 21.8

Load 9 @ 0.0' Start 0.0' to 47.3'(100%)

12 @Rear of Garage 1ST Floor 1-Pour Exterior Wall(X Dir.)

Wind 7496Seismic 6982= 6727+ 254

4.0

 A

 4.5 4.0

B

 0.8 3.5 0.5 4.3 9.5 4.0 10.0

C

 2.0

 9.0

Strap(E) Panel Edge on the above Story MIN. 4x Post E.N. @ 3" O/C May NeededBlocked Opening Use on BOT(/TOP) of Opening See Detail on PlansTYPE 4

0.0 12.5

 1338

B

13.4

 A

28.4

B

34.3

C

35.0

 2250

45.0

  319

 A

47.047.0

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate spliceC: Simpson ST6236(3230 LB) ALT (22) # 16d sinker per top plate splice

See Detail Information on Next Page

Page 37: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 37/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

12Total Wall Length = 47.00(FT) Total Panel Length = 18.00(FT)Shear Diaphragm = 7496/ 47.00 = 159(PLF) = 1.00Use (18 A35) or (13 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(W)=566(PLF)(on Opening A & B ) Max. Drag= 2250(LB)

Use TYPE 4

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 0.985" <= 0.02 x 108.0 = 2.160"

Dead Loads:Wall 135.0= 15 * 9.0'

Load 9 @ 0.0' Start 0.0' to 47.3'(100%)OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 2547(LB) C= 4878(LB) STHD10/4x4

Right Side : T= 0(LB) C= 0(LB) No Sign. Uplift()

Use STHD10/4x4 @ L.w/(2)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)

Blocked! Force @ Edge of Opening is 1274(LB)Panel B Left Side : T= 0(LB) C= 0(LB) No Sign. Uplift()

Right Side : T= 2547(LB) C= 4878(LB) STHD10/4x4Use STHD10/4x4 @ R.

w/(2)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)Panel C Left Side : T= 2959(LB) C= 4184(LB) STHD10/4x4

Right Side : T= 345(LB) C= 3860(LB) No Sign. Uplift(2-2x POST)

Use STHD10/4x4 @ L.

w/(4)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)

Page 38: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 38/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

Wind: 2651 Seismic: 1371

1X_1_FL

wind

seismic

 154.8

  80.1

| 34.3

Wind: 1684 Seismic: 636

2X_1_FL

wind

seismic

 154.8

  58.5

| 21.8

Load 9 @ 0.0' Start 0.0' to 47.3'(100%)

12B @Rear of Garage 1ST Floor 1-Pour Exterior Wall(X Dir.)

Wind 7515Seismic 7000= 6737+ 263

3.5

 A

 5.5 3.5

B

 0.8 3.5 0.5 4.3 9.5 3.0 10.0

C

 3.8

 9.0

Strap(E) Panel Edge on the above Story MIN. 4x Post E.N. @ 3" O/C May NeededBlocked Opening Use on BOT(/TOP) of Opening See Detail on PlansTYPE 4

0.0 12.5

 1127

 A

27.2

B

33.2

C

34.0

 2257

44.0

  590

 A

47.8

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceB: Simpson ST6224(2134 LB) ALT (16) # 16d sinker per top plate spliceC: Simpson ST6236(3230 LB) ALT (22) # 16d sinker per top plate splice

See Detail Information on Next Page

Page 39: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 39/40

Job : 62742-202

Plan : 3

IBC9.7IBC9.7

12BTotal Wall Length = 47.75(FT) Total Panel Length = 17.00(FT)Shear Diaphragm = 7515/ 47.75 = 157(PLF) = 1.00Use (18 A35) or (13 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(W)=526(PLF)(on Opening A & B ) Max. Drag= 2257(LB)

Use TYPE 4

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.019" <= 0.02 x 108.0 = 2.160"

Dead Loads:Wall 135.0= 15 * 9.0'

Load 9 @ 0.0' Start 0.0' to 47.3'(100%)OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 2400(LB) C= 4704(LB) STHD10/4x4

Right Side : T= 0(LB) C= 0(LB) No Sign. Uplift()

Use STHD10/4x4 @ L.w/(2)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)

Blocked! Force @ Edge of Opening is 1447(LB)Panel B Left Side : T= 0(LB) C= 0(LB) No Sign. Uplift()

Right Side : T= 2400(LB) C= 4704(LB) STHD10/4x4Use STHD10/4x4 @ R.

w/(2)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)Panel C Left Side : T= 2882(LB) C= 4421(LB) STHD10/4x4

Right Side : T= 35(LB) C= 4098(LB) No Sign. Uplift(2-2x POST)

Use STHD10/4x4 @ L.

w/(4)5/8" x 12" Anchor Bo lt (@ 32" O.C. Max.)

Page 40: 2742-PLAN3

7/17/2019 2742-PLAN3

http://slidepdf.com/reader/full/2742-plan3 40/40

Job : 62742-202

Plan : 3

Wind: 1684 Seismic: 636

2X_1_FL

wind

seismic

 154.8

  58.5

| 21.8

Load 10 @ 0.0' Start 0.0' to 19.5'(100%)

13 @Front of Elevation 1ST Floor 1-Pour Exterior Wall(X Dir.)

Wind 2825Seismic 1947= 1859+ 88

2.0

 A

16.0 3.0

B

 8.0 1.5

 9.0

Strap(E) HD Panel Edge on the above Story - - - Blocked with the Header(See Plan)

0.0 2.0

  945

 A

18.0

  537

21.0

  880

 A

30.530.5

Drag Force Analysis A: Simpson ST22 (1192 LB) ALT (10) # 16d sinker per top plate spliceTotal Wall Length = 30.50(FT) Total Panel Length = 5.00(FT)Shear Diaphragm = 2825/ 30.50 = 93(PLF) = 1.00Use (7 A35) or (5 LS50) Along Line of Shear Panel or for Framing Clips Spacing See S.W. ScheduleDesign Wall Shear(S) = 1947/ 5.00= 389(PLF)(Flexible ,SW V_allow(Seismic) Ajusted for H/W Ratio) Max. Drag = 945(LB)

Use TYPE 5

Max. Panel Deflect ion: M = (4.0/1.0) x s x 1.4 = 1.987" <= 0.02 x 108.0 = 2.160"Dead Loads:Wall 135.0= 15 * 9.0'Floor_P 161.3= 15 *21.5/2 FROM 0.0' TO 19.8'

Load 10 @ 0.0' Start 0.0' to 19.5'(100%)OVERTURN ANALYSIS UPLIFT(T) DOWN(C)Panel  A Left Side : T= 6520(LB) C= 6977(LB) HDU8/4x4(I) w/DBL BLK'G

Right Side : T= 4882(LB) C= 6977(LB) ** HDU8/4x4(I) w/DBL BLK'G

Blocked with the Header Use HDU8/4x4(I) @ L. & HDU8/4x4(I)** @ R.

w/(2)5/8" x 12" Anchor Bo lt (@ 24" O.C. Max.)For Grade Beam, Add (1)#4 Top & Bottom, 4' Past Panel Each End

Panel B Left Side : T= 5771(LB) C= 6138(LB) ** HDU8/4x4(I) w/DBL BLK'GRight Side : T= 7171(LB) C= 6312(LB) ** HDU8/4x6(I) w/DBL BLK'G

Use HDU8/4x4(I)** @ L. & HDU8/4x6(I)** @ R.w/(2)5/8" x 12" Anchor Bo lt (@ 24" O.C. Max.)

For Grade Beam, Add (1)#4 Top & Bottom, 4' Past Panel Each End