Gulf House EngineeringJanuary 2010
07-C106 NOVOTEL AL DANA RESORT TOWERS PAGE264 SECTION 15850 AIR HANDLING UNITS
Duct collars shall be provided where ducted connection is required.
The condensate tray located under the coil shall be of one piece construction andshall have sufficient slope for positive and efficient drainage of condensate underall conditions. The trays shall be of 1.2 mm (minimum) hot dipped galvanizedsteel sheet and adequately insulated with fire retardant thermal insulation.
Coils shall be of aluminium fins mechanically bonded to seamless copper tubesand tested with compressed air up to 2000 kPa under water. Face velocitythrough coils shall not exceed 2.25 m/s to prevent moisture carries over.Thenumber of fins shall not exceed 400 per meter and all fins shall be continuous.Coils shall be three rows unless indicated otherwise and be provided with airvents at high points, with drain lines extended to drain pan. The capacity of thecoil shall be based on 6.5 deg C chilled water entering temperature with atemperature difference of 5+_ 1 deg. C.
Coil connections shall be female threaded and compatible with steel pipeconnection.
Unit shall be internally insulated with minimum 25 mm, 32 kg/cubic meter densitythermal and acoustic insulation.
Filter shall be aluminium washable type, 50 mm thickness.
EXECUTION
INSTALLATION
Install unit as per manufacturer’s instruction.
FAN COIL UNIT EXPOSE TYPE
The Fan Coil Unit shall be the factory assembled decorative type, integral fan typewith chilled water-cooling coil and shall be made for exposed mounting. The unitshall be complete with decorative grill.
The Fan Coil Unit shall be of the factory assembled, integral fan type with chilledwater-cooling coil and shall be made with concealed mounting. The capacities of the FCU will be as per the enclosed schedule. And also the unit should haveaccess panel in the lower part of the unit to facilitate all routine maintenanceoperation. The FCU shell also have washable filter, filter shall be 15mmpermanent cleaning aluminum mesh and the drain pan shall be integral and anauxiliary drain pan shall be provided to cover the valve package.
Units shall be ARI rated.
Air Filters: Shall be accessible by dropping down bottom panel of the filter back.Filter shall be 15mm permanent, clearable aluminum mesh.
Valves: The control valve and piping package shall be factory built, installed andtested. Each fan coil units shall be provided at least with one isolating and onebalancing valve at outlet and one isolating at inlet.