23 rd may 2013

26
By: Rakesh Verma CTO and Vice President Samsung Heavy Industries India Pvt. Ltd. 23 rd May 2013 India Drilling & Exploration Conference (IDEC) 2013 Does Project incubation define Project success?

Upload: van

Post on 17-Jan-2016

25 views

Category:

Documents


0 download

DESCRIPTION

India Drilling & Exploration Conference (IDEC) 2013. Does Project incubation define Project success?. 23 rd May 2013. By: Rakesh Verma CTO and Vice President Samsung Heavy Industries India Pvt. Ltd. Introduction. FPSOs a popular choice in recent years. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: 23 rd  May 2013

By:

Rakesh Verma

CTO and Vice President

Samsung Heavy Industries India Pvt. Ltd.

23rd May 2013

India Drilling & Exploration Conference (IDEC) 2013

Does Project incubation define Project success?

Page 2: 23 rd  May 2013

Introduction

• FPSOs a popular choice in recent years.

• Majority of FPSO projects incur significant project delays and budget

overruns.

• Conceptual / Tendering phase a bone of contention

Page 3: 23 rd  May 2013

Objective

• To show the challenges of current Conceptual / Tendering phase practices

and how this can affect the success of a FPSO project.

• To highlight the strategic roadmap to better results

Page 4: 23 rd  May 2013

Outline

• Challenges

• Key drivers

• Current practices

• Impacts and challenges

• Way forward

Page 5: 23 rd  May 2013

Decade 10-20 Challenges

History shows that FPSO projects have a turbulent past.

Data Source: IPA

Page 6: 23 rd  May 2013

Decade 10-20 Challenges

• Cost and schedule overruns regularly surfacing.

• Successfully executing a FPSO topsides project on time and budget is a

serious challenge.

• Most FPSO projects, and in particular Lease FPSO’s, are fast track projects.

• Consequently few FPSO lease companies make healthy profits.

• Many leased FPSO’s struggle to meet expected delivery schedule,

production regularity and production rate.

Page 7: 23 rd  May 2013

KEY DRIVERS TO THE CHALLENGES

Page 8: 23 rd  May 2013

Market Trends

• Increasing size & complexity (Brazil main driver)

• Field specific solutions

• HT & HP wells

• Heavy Oil

• Salt and CO2 issues

• Deep waters

• Harsh environment

• Local content at design and construction phase

Page 9: 23 rd  May 2013

Why the hurry?

• The Operator Company have invested a lot of money in Seismic activities

and expensive drilling programs.

• First oil as quickly as possible in order to start return of investment.

Page 10: 23 rd  May 2013

CURRENT PRACTICES

Page 11: 23 rd  May 2013

Current tendering practices

• Field Operator spending long time on preparing, however first oil date does

not change.

• Functional specifications.

• Short bidding period.

• Pushing risk over to the contractors.

• FPSOs high profile developments, with senior management “attention”.

Schedule commitments made independent of project realities.

• Consequently definition stages are arbitrarily shortened. Insufficient time to

complete definition deliverables.

Page 12: 23 rd  May 2013

IMPACTS AND CHALLENGES

Page 13: 23 rd  May 2013

Skimped Engineering Definition and its peril

Data Source: IPA

Page 14: 23 rd  May 2013

Impact of tendering practices

• FPSO projects are more likely to have upsets…

• Hence need a more matured conceptual design and a balanced tendering

process

Data Source: IPA

Page 15: 23 rd  May 2013

Increasing the odds

OperatorOperator Topsides ProviderTopsides Provider

• Each contractor different philosophy

• 3 different layout

• Redundancy philosophy

• Options

Contractor 1Contractor 1

Contractor 2Contractor 2

Contractor 3Contractor 3

Page 16: 23 rd  May 2013

A very basic Tender / FEED Layout

Higher level of detailing needed during tender phase.

FEED Stage Layout

FEED Stage Layout

Detailed Engineering Data Layout

Detailed Engineering Data Layout

HP Compression Module Layout comparison for one of Samsung’s past projects.

Page 17: 23 rd  May 2013

Chain reaction

Slippage of Engineering Deliverables adds to Project costs.

Late engineering and its link to cost growth

Data Source: IPA

Page 18: 23 rd  May 2013

Chain reaction

• Cost growth in Engineering leads to growth in Fabrication.

• 50 % growth in Engineering leads to 20% Hull/Topsides fabrication

growth.

Data Source: IPA

Page 19: 23 rd  May 2013

WAY FORWARD…..

Page 20: 23 rd  May 2013

Working together

• Lease contractors pick a strategic partners for various key supplies.

• Specialists companies can often come up with better, more robust and

cost efficient solutions that give added value for client.

• Early involvement in order to allow sub-contractors sufficient time to

make quality bid and reduce risk for both parties

• Balanced contracts (Back to back)

Page 21: 23 rd  May 2013

Project definition phase utilization

• Front loading effort in the project definition and tendering phase will provide

a mature and predictable basis for weight and cost estimate.

• The design status at authorization may have a significant effect on project

cost, schedule:

Basis for equipment design and bulk material quantity

Key element of an accurate cost estimate

• Late changes to process design after start of detailed design are costly and

a threat to delivery schedule.

Page 22: 23 rd  May 2013

The bid workflow (typical)

ProcessSimulations

Material Selection

Process andMechanicalDatasheets

PFD / P&ID's

Equipmentquotations and

leadtime

EquipmentSizing

Weight Estimate

E&IMTO

Valve list

Layout

MEL

Valve quotationsand leadtime

Valve RFQ

Pipe Routing

Structural SteelDesign

Bulk MTOFabrication Prices

Fabrication RFQModule Price

Cost HoursHours Estimate

ManagementCost/logistics etc

E&I Quotes

Example: Typical time needed for above process 8-10 weeks

Example: Typical time given 4-6 weeks

Page 23: 23 rd  May 2013

Conceptual Engineering

Detail EngineeringFabrication

Contract award

Tender phase as far as possible towards detail engineering phase.

Topside Module EPC Project execution strategy

Page 24: 23 rd  May 2013

Potential risks

• Poor quality information from suppliers/sub contractors.

• Large number of clarifications and deviations

Example: “A process guarantee is given provided the proper use of

chemical injection program”

• Delivery schedule uncertainties.

• Variation Orders with significant cost growth.

Page 25: 23 rd  May 2013

Way Forward

• Front loaded in project definition phase (Owner)

• Matured Conceptual design (Owner)

• Participation by key stakeholders during Concept finalization (Owner)

• Early involvement of potential Contractors….Design competition (Owner)

• Inject incentives and risk sharing measures (Owner)

• Focus on Life Cycle cost (Owner / Bidder)

• Pick a few strategic partners & develop long term relation (Bidder)

Page 26: 23 rd  May 2013

Thank you !Thank you !