21cn legacy interconnection working group 17 th december 2004 auditorium city place, gatwick
TRANSCRIPT
21CN Legacy Interconnection Working Group
17th December 2004
Auditorium
City Place, Gatwick
Agenda
The purpose of the Working Group meeting today is to discuss the maintenance of existing legacy interconnect services during the establishment of the 21CN network.
To this purpose ,after previous discussions and feedback from industry, BT will present a proposal setting out the commercial arrangements arising from the physical changes to the network.
In addition BT will set out a proposal for the future architecture/routing arrangements for discussion and to obtain industry’s feedback
Agenda
Introductions Purpose of meeting BT’s commercial proposal Operational Issues Contractual aspects and timescales Discussion
LEGACY INTERCONNECTION IN 21CN17 DECEMBER 2004
ANTHONY SHEPPARDSENIOR PORTFOLIO STRATEGY MANAGER
FORWARD LOOKING STATEMENTS - CAUTION ADVISED
Certain statements in this presentation are forward-looking and are made in reliance on the safe harbour provisions of the US Private Securities Litigation Reform Act of 1995. These statements include, without limitation, those concerning: BT's plans for transformation of its networks; benefits to customers of the 21CN programme; key milestones and expected timetable for delivery of 21CN; and the benefits in relation to, for example interconnect, convergence and broadband
Although BT believes that the expectations reflected in these forward-looking statements are reasonable, it can give no assurance that these expectations will prove to have been correct. Because these statements involve risks and uncertainties, actual outcomes may differ materially from those expressed or implied by these forward-looking statements
Factors that could cause differences between actual outcomes and those implied by the forward-looking statements include, but are not limited to: material adverse changes in economic and financial markets conditions in the markets served by BT; supplier arrangements; future regulatory actions and conditions in BT’s operating areas; technological innovations; developments in the convergence of technologies and the anticipated benefits and advantages of new technologies, products and services, including broadband, not being realised
AGENDA
BACKGROUND & GENERAL PRINCIPLES
COMMERCIAL PRINCIPLES
COMMERCIAL PROPOSALS
What is 21CN and why is change beneficial for the industry?
•21CN represents a multi-billion pound capital investment by BT for the benefit of the industry and the industry's customers
•21CN is the enabling infrastructure for growth and opportunity for the industry
•21CN will enable compelling new products and services for all operators to market to their customers.
•BT is committed to working closely and openly with industry to ensure that the benefits are maximised for operators, the economy and society.
For discussion purposes.No implementation assurances
Subject to Contract
BT’s Approach to Interconnect Portfolio
•Continue to provide any-any voice connectivity in consultation with customers
•Work with customers to ensure appropriate inter-operability of new services, for example through access to “network hooks”
•Provide new forms of Interconnect for the new IP world
•Discharge its regulatory obligations in a professional manner
•Minimise inconvenience to customers during the implementation of 21CN
•Support reasonable ongoing requirements for TDM interconnect until 2010
For discussion purposes.No implementation assurances
Subject to Contract
Principles
• An equitable, but affordable commercial agreement.
• BT will not indemnify altnets from investment risk due to obsolescence (e.g. Dial IP over the coming years)
• Recognise Ofcom’s policy of encouraging infrastructure build-out.
• Recognise the re-arrangement process is years long and the interconnect picture will be changing between offer and implementation.
Interconnect at DLEs
0
5
10
15
20
25
30
Operators I/X Links (000)
CSI
ISI via NGS sites
ISI (Non-NGS sites)
IEC (from non-NGSsites)ISI (all)
For discussion purposes.No implementation assurances
Subject to Contract
Key Migration Issues for Customers
BT closes switches -
•Customer traffic must be rearranged
•Value of POCs at non-NGS sites
•ISI users at DLE-only sites face biggest disruption
•FRIACO at DLEs expected to die due to broadband penetration
•How will SIA Systems Alteration clause be applied?
•Under existing contractual terms, the change process is designed for BAU rather than large tranche one-offs
•What happens to DLE conveyance rate?For discussion purposes.
No implementation assurancesSubject to Contract
BACKGROUND & GENERAL PRINCIPLES
COMMERCIAL PRINCIPLES
COMMERCIAL PROPOSALS
Contractual Principles & Issues
• SIA Systems Alterations Clause
• BT meets reasonable agreed costs of network engineering alterations to Operator network
• Connection Charge rebate applies if Capacity is ceased (SIA, Ann. A, App. B, 4)
• But current contract terms ineffective for large one-off network changes
• We need –
• upfront agreement on criteria for Operator cost reimbursement
• early agreement on terms & process for dealing with complex alterations
• to provide certainty for both BT and our customers
For discussion purposes.No implementation assurances
Subject to Contract
Backhaul from Closing DLEs
• All backhaul Connection costs met by BT
• Ongoing backhaul circuit costs met by BT for 6 months
• Applies to ISI Voice only at all closing DLE switches
• CSI: BT will simply re-point or cease circuits as agreed with customer
• Signalling aspects:
• IUP traffic backhauled to NGS
• ISUP circuits may be extended to Metro Node on same terms by agreement, if required
• FRIACO
• Decline in demand needs to be managed collectively by industry
• Need to consolidate off DLEs?
• Your views invited
For discussion purposes.No implementation assurances
Subject to Contract
Conveyance Charges for Re-located DLE Circuits
• Local Call Termination will continue to be charged for 6 months
• smooth impact of loss of competitive model based on legacy architecture
• Applies to ISI Voice at all closing switches
• Dial IP
• Residual demand needs to be managed collectively by industry to meet remaining end users’ requirements
• Need to consolidate off DLEs?
• Specialist ad hoc group?
• Your views invited
Views and Comments please!
Is there a better way of doing this?
Annex A: Can I install Capacity after Notice of a Switch Closure?
BT proposals
• From date Notice given under SIA:• New POCs for new customers or orders for new transmission systems/IEC access at customer’s risk (BT will not meet any costs of rearrangement or backhaul); Local Call Termination not available after DLE closure;
• Customers may bring into use spare capacity on existing ISI transmission systems already installed before Notice given and qualify for BT proposals on backhaul and Local Call Termination.
• From 7 months before Closure Date:• No new POCs accepted;
• No new capacity or IECs to be ordered;
• Customers may bring into use spare capacity on existing ISI transmission systems already installed before Notice given and qualify for BT proposals on backhaul and Local Call Termination.
• From Closure Date:• No expansion of capacity allowed under SIA;
• Installed capacity on existing ISI transmission systems brought into use will no longer qualify for BT proposals on backhaul and Local Call Termination
21CN
Metro node(ISUP)
Today
NGS(IUP / ISUP)
PoC
PoC
IEC
IEC (ISUP)
IEC(IUP/ISUP)
IEC (ISUP)
Annex B: Proposed Architecture
Conc
DLE
NGS
MSAN
Newinterconnect:
IP or ISUP4. If required,
operators with IECs to closing DLE have IEC redirected to NGS, if IUP is retained
3. If required, operators with PoC at closing DLE provided with IEC to NGS, if IUP is retained
1. IUP not available on 21CN
2. IUP continues to be available on NGS until withdrawal. Anticipated at the end of 21CN implementation
For discussion purposes.No implementation assurances
Subject to Contract
Maintenance of Legacy Interconnect - Operational Issues
Mark Ward Head of Interconnect and Numbering Services BT Wholesale - Network Design and Implementation
Typical Existing Architecture
CPSwitch
NGS
Conc
DLE
DLE
Conc
T
X
M
T
X
M
DLE
Conc
T
X
M
TDM I/C
IUP/UK-ISUP IEC
DLE SITE DLE SITE
NGS SITENote - 90% all ISI Capacity passes through an NGS site.
Example of Future Architecture
Signaling
GatewayCall
Server
21 CN
Voice / Data
Sig
Metro Node
TDM
IP
CPs
TDMGateway
Interim Arrangements
Signaling
Gateway
CallServer
TDMGateway
21 CN
Voice / Data
Sig
Metro Node
NGS
TDM
CPSwitch
IUP/UK-ISUP
UK-ISUP
Process
Tied to agreement on Commercials and new System Alteration Process (SAN)
Intend to provide SANs in tranches - 1year at a time (?)
Detailed discussions and agreement with Technical Account Managers on transfer method required.
Detailed programme with dates fully agreed .
Routes moved off closing DLEs approx. 6 months in advance of DLE closure (prevents dependency and any late running problems as previously experienced)
Transfer Scenario examples
1.Capacity no longer required - Cease
2. Capacity available at NGS - Cease & data-change
3. Capacity provided via NGS site - Re-jumper at NGS
4. Capacity provided via non-NGS site - provide Backhaul
5. UK-ISUP - direct MGW connection available if required.
6. Route Consolidation possibilities.
7. CSI - BT termination transferred as agreed
Example of detailed Transfer Scenario
The following is an example of work in progress to define a range of transfer
scenarios for discussion with individual CPs.
DLE 1Figure 1 - Option ‘A’ - Transfer Using CP to NGS Route Spare Capacity
Interconnect Scenario Before Transfer
DLE1 SITE
NGS SITE
DLE2 SITE
IEC
14 E1s
3 E1s
10 E1s (BH use 6 E1s)
4 E1s
12 E1s
CP
NGS
DLE 2 21CN
MGW
MSAN
MSAN
METRONODE
DLE 1
DLE1 SITE
NGS SITE
DLE2 SITE
IEC
18 E1s
3 E1s
10 E1s (BH use 6 E1s)
4 E1s
15 E1s
CP
NGS
DLE 2
Figure 2 - Option ‘A’ - Transfer Using CP to NGS Route Spare Capacity Preliminary DLE to NGS Route Enhancement
21CN
MGW
MSAN
MSAN
METRONODE
DLE 1
DLE1 SITE
NGS SITE
DLE2 SITE
IEC
18 E1s
3 E1s
10 E1s (BH use 6 E1s)
4 E1s
15 E1s
CP
AAR
AAR
NGS
DLE 2
Figure 3 - Option ‘A’ - Transfer Using CP to NGS Route Spare Capacity DLE 1 Transfer - Stage 1
21CN
MGW
MSAN
MSAN
METRONODE
NGS
DLE 1
DLE1 SITE
NGS SITE
DLE2 SITE
18 E1s
3 E1s
10 E1s (BH use 10 E1s)
4 E1s
15 E1s
CP
AAR
AAR
DLE 2
Figure 4 - Option ‘A’ - Transfer Using CP to NGS Route Spare Capacity DLE 1 Transfer - Stage 2
21CN
MGW
MSAN
MSAN
METRONODE
DLE 1
DLE1 SITE
NGS SITE
DLE2 SITE
18 E1s
3 E1s
10 E1s (BH use 10 E1s)
4 E1s
15 E1s
CP
NGS
DLE 2
Figure 5 - Option ‘A’ - Transfer Using CP to NGS Route Spare Capacity DLE 1 Transfer - Stage 3
21CN
MGW
MSAN
MSAN
METRONODE
DLE 1
DLE1 SITE
NGS SITE
DLE2 SITE
18 E1s
3 E1s
4 E1s
15 E1s
CP
NGS
CombinedRoute
10 E1s
DLE 2
Figure 6 - Option ‘A’ - Transfer Using CP to NGS Route Spare Capacity DLE 2 Transfer - Stage 1
Circuitsgrown ontoNGS Route
Combined Route14 E1s (BH use = 13 E1s)
Used for DLE 1 and DLE 2 traffic
21CN
MGW
MSAN
MSAN
METRONODE
DLE 1
DLE1 SITE
DLE 2
NGS SITE
DLE2 SITE
18 E1s
3 E1s
4 E1s
15 E1s
CP
NGS
CombinedRoute
10 E1s
AAR
AAR
Figure 7 - Option ‘A’ - Transfer Using CP to NGS Route Spare Capacity DLE 2 Transfer - Stage 2
Combined Route14 E1s (BH use = 13 E1s)
Used for DLE 1 and DLE 2 traffic
21CN
MGW
MSAN
MSAN
METRONODE
DLE 1
DLE1 SITE
DLE 2
NGS SITE
DLE2 SITE
18 E1s
Combined Route14 E1s (BH use = 13 E1s)
Used for DLE 1 and DLE 2 traffic
4 E1s
15 E1s
CP
NGS
CombinedRoute
10 E1s
Figure 8 - Option ‘A’ - Transfer Using CP to NGS Route Spare Capacity DLE 2 Transfer - Stage 3
21CN
MGW
MSAN
MSAN
METRONODE
Information Provision
Metro Node list on NIPP - still subject to revision - detailed address info via NISCC.
DLE closure timetable as soon as reasonably stable
Detailed per CP information per DLE provided with SAN
Completed Transfer of BT number ranges to NGN advised probably via NIPP.
Any Questions or Comments ?